CN205857710U - Air-conditioning formwork support structure - Google Patents
Air-conditioning formwork support structure Download PDFInfo
- Publication number
- CN205857710U CN205857710U CN201620804234.6U CN201620804234U CN205857710U CN 205857710 U CN205857710 U CN 205857710U CN 201620804234 U CN201620804234 U CN 201620804234U CN 205857710 U CN205857710 U CN 205857710U
- Authority
- CN
- China
- Prior art keywords
- conditioning
- air
- cell wall
- stulls
- support structure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000004378 air conditioning Methods 0.000 title claims abstract description 36
- 238000009415 formwork Methods 0.000 title claims abstract description 26
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 15
- 239000010959 steel Substances 0.000 claims abstract description 15
- 210000002421 cell wall Anatomy 0.000 claims description 34
- 230000002093 peripheral effect Effects 0.000 claims description 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims 1
- 238000010276 construction Methods 0.000 description 17
- 230000000875 corresponding effect Effects 0.000 description 11
- 238000005457 optimization Methods 0.000 description 8
- 230000033001 locomotion Effects 0.000 description 4
- 230000000694 effects Effects 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 238000009416 shuttering Methods 0.000 description 2
- 208000031481 Pathologic Constriction Diseases 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 238000006243 chemical reaction Methods 0.000 description 1
- 239000004035 construction material Substances 0.000 description 1
- 230000002596 correlated effect Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 239000012634 fragment Substances 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 210000001215 vagina Anatomy 0.000 description 1
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
The utility model discloses a kind of air-conditioning formwork support structure, including being detachably secured on wall face, be positioned at same level height and the two perpendicular supports being parallel to each other, the upper end being removably fixed in two perpendicular supports respectively and two stulls horizontal-extending to the direction away from described wall face and two diagonal braces, the lower splay end of described two diagonal braces is detachably secured to the lower end of two perpendicular supports respectively, and the upper splay end of described two diagonal braces is detachably secured to the one end in two stulls away from wall face respectively.Air-conditioning formwork support structure is A-frame system, and its good stability, fastness are preferable.Diagonal brace can rotate relative to the fixing point in perpendicular support, facilitates staff to install;Diagonal brace uses sleeve two to terminate screw rod, is adapted to the stull of different length, adapts to the support of different embodiment hollow adjustment mould plate length.Completely disengaging from the pattern of setting up of steel tube fastener formula, independent and exterior wall is attached and sets up gusseted system, and the air-conditioning plate of each floor gap does not the most produce dependence.
Description
Technical field
This utility model relates to the air-conditioning shuttering supporting in a kind of the realm of building construction being supported air-conditioning formwork for placing
Structure.
Background technology
Along with the optimization of engineering construction design, the raising of construction material performance, build board-like component thickness and increasingly reduce.Add
Space utilized require more and more higher, in order to reach the maximum space that uses, great majority can arrange external on exterior wall
Air-conditioning plate.External wall construction all uses big template of assembling at present, can only use secondary construction technology for part primary structural component, i.e. lead
After external wall etc. shape, pour to form air-conditioning plate at wall face secondary, need to set up formwork-support when pouring air-conditioning plate,
Template pours after being placed on formwork-support again, and traditional formwork support structure is to use conventional steel fastener to set up, and one
Individual formwork-support needs to use many steel pipes and some fasteners, the most then add and set up and take-down time and difficulty, unfavorable
In improving efficiency of construction.
Utility model content
For above-mentioned the deficiencies in the prior art, technical problem to be solved in the utility model is: provide a kind of structure letter
The air-conditioning formwork support structure of efficiency set up by list, firm supporting, lifting.
For solving above-mentioned technical problem, the technical scheme that this utility model uses is: provide a kind of air-conditioning template to prop up
Support structure, including being detachably secured on wall face, be positioned at same level height and the two perpendicular supports being parallel to each other, the most removable
Unload and be fixed on the two perpendicular upper ends supportted and two stulls horizontal-extending to the direction away from described wall face and two diagonal braces, described two
The lower splay end of diagonal brace is detachably secured to the lower end of two perpendicular supports respectively, and the upper splay end of described two diagonal braces is the most dismountable fixing
Away from one end of wall face in two stulls.
As optimization, two perpendicular supports are notch to the channel-section steel away from wall face direction, in the upper ends pair of the cell walls of two perpendicular supports
Claim to offer two first installing holes;Two stulls are that downwards and width of rebate is less than the channel-section steel of the perpendicular width of rebate supportted, two to notch
The inner end symmetry of the cell wall of stull offers two second installing holes;The inner end of described two stulls is the most laterally inserted in two perpendicular supports
Upper end, clamping screw sequentially passes through the first installing hole on first cell wall of perpendicular support, corresponding stull is in close proximity to first groove of perpendicular support
The second installing hole on one cell wall of wall, second installing hole of another cell wall of described corresponding stull and described perpendicular support the
Coordinate with nut check after the first installing hole on two cell walls.
As optimization, described two erect support is 6.5# thin-wall channel.
As optimization, described two stulls are 5# thin-wall channel.
As optimization, the lower splay end of described two diagonal braces is detachably secured to first cell wall of described two perpendicular supports respectively
On, the upper splay end of described two diagonal braces is detachably secured to two stulls respectively adjacent on a cell wall of this first cell wall.
As optimization, the lower splay end of described two diagonal braces is detachably secured to second cell wall of described two perpendicular supports respectively
On, the upper splay end of described two diagonal braces is detachably secured to two stulls respectively adjacent on a cell wall of this second cell wall.
As optimization, each diagonal brace all include an inner thread sleeve, respectively with the two ends threaded engagement of inner thread sleeve
Two external thread rods, are installed with a connection journal stirrup, in described company at two external thread rods respectively away from one end of described inner thread sleeve
Connect and on journal stirrup, offer the first connecting hole;In the lower end of described two perpendicular supports corresponding to the first connection of the lower splay end being positioned at two diagonal braces
The position in hole offers the second connecting hole respectively, and the first connecting hole and described second connecting hole that are positioned at splay end under diagonal brace pass through
A connection piece connects and coordinates;Distinguish corresponding to the position of the first connecting hole of the upper splay end being positioned at two diagonal braces in described two stulls
Offer the 3rd connecting hole, be positioned at the first connecting hole of splay end on diagonal brace and described 3rd connecting hole and be connected by a connection piece and join
Close.
As optimization, the outer peripheral face at described inner thread sleeve is provided with gripping handle.
Air-conditioning formwork support structure of the present utility model is A-frame system, and its good stability, fastness are preferable.Tiltedly
Support can rotate relative to the fixing point in perpendicular support, facilitates staff to install;Diagonal brace uses sleeve two to terminate screw rod, is adapted to
The stull of different length, adapts to the support of different embodiment hollow adjustment mould plate length.Completely disengage from steel tube fastener formula sets up mould
Formula, independent and exterior wall is attached and sets up gusseted system, and structural stability is high, and the air-conditioning plate of each floor gap is the most not
Produce and rely on, set up simple and convenient.
Accompanying drawing explanation
Fig. 1 is the structural representation of this utility model air-conditioning formwork support structure one embodiment.
Fig. 2 is the longitudinal sectional drawing of this utility model air-conditioning formwork support structure.
Fig. 3 is the structural representation of diagonal brace in Fig. 1.
Fig. 4 and Fig. 5 is the structural representation of template length adjustment mechanism in Fig. 1.
Detailed description of the invention
Below in conjunction with the accompanying drawing in this utility model embodiment, the technical scheme in this utility model embodiment is carried out
Clearly and completely describe, it is clear that described embodiment is only a part of embodiment of this utility model rather than whole
Embodiment.Based on the embodiment in this utility model, those of ordinary skill in the art are not under making creative work premise
The every other embodiment obtained, broadly falls into the scope of this utility model protection.
Referring to Fig. 1 to Fig. 5, air-conditioning formwork support structure of the present utility model, including being fixed on wall face, be positioned at together
One level height and be parallel to each other two erect support 1, be removably fixed in the upper ends of two perpendicular supports 1 respectively and to away from described wall face
Horizontal-extending two stull 2 and two diagonal braces 3 in direction, the lower splay end of described two diagonal braces 3 is detachably secured to two respectively and erects
The lower end of support 1, the upper splay end of described two diagonal braces 3 is detachably secured to the one end in two stulls 2 away from wall face respectively.Described
The upper splay end of diagonal brace 3, centered by fixing point, rotates in the face being perpendicular to exterior wall around this fixing point, same, the declivity of diagonal brace 3
End can also rotate in the face being perpendicular to exterior wall around this fixing point centered by fixing point.
In the present embodiment, two perpendicular supports 1 are the thin-wall channel of 6.5#, adopt and are bolted on exterior wall, are fixed on exterior wall
After on face, notch is towards away from the direction away from wall face, and the present embodiment is outside each perpendicular support 1 all uses two bolts to be fixed on
On wall.On the upper end cell wall of two perpendicular supports 1, symmetry offers two first installing holes, for installing the stull 2 of correspondence, each perpendicular support
The lower end of the external groove sidevall (following first cell wall, away from a cell wall of another perpendicular support 1) of 1 offers the second connecting hole, uses
Lower splay end in dismountable connection diagonal brace 3.
Two stulls 2 are that downwards and width of rebate is less than the channel-section steel of the perpendicular width of rebate supportting 1 to notch, and the present embodiment is the light of 5#
Type channel-section steel, on the cell wall of the inner end (near one end of exterior wall) of two stulls 2, symmetry offers two second installing holes;Described two is horizontal
The inner end of support 2 is the most laterally inserted in the upper end slot intracavity of two perpendicular supports 1, and clamping screw 4 sequentially passes through 1 first groove of corresponding perpendicular support
The first installing hole on wall, corresponding stull 2 be in close proximity to the second installing hole on one of them cell wall of 1 first cell wall of perpendicular support,
Second installing hole of another cell wall of described corresponding stull 2 and described correspondence erect the first installation on 1 second cell wall of support
Kong Houyu nut check coordinates.In certain embodiments, described stull 2 can also use other be detachably fitted to erect
The upper end of support 1, illustrates the most one by one.External groove sidevall (away from a cell wall of another stull 2) in each stull 2
Position, one end away from exterior wall offers the 3rd connecting hole, for dismountable upper splay end connecting corresponding diagonal brace 3.
In the present embodiment, each diagonal brace 3 all include an inner thread sleeve 31, respectively with the two ends spiral shell of inner thread sleeve 31
Two external thread rods 32 that stricture of vagina coordinates, are installed with a connection at two external thread rods 32 respectively away from one end of described inner thread sleeve 31
Journal stirrup 33, offers the first connecting hole 34 on described connection journal stirrup 33;Oblique corresponding to being positioned at two in the lower end of described two perpendicular supports 1
The position of the first connecting hole 34 of the lower splay end of support 3 offers the second connecting hole respectively, is positioned at the first of 3 times splay ends of diagonal brace and connects
Connect hole 34 and described second connecting hole and connect cooperation by connector;Described two stulls 2 corresponding to be positioned at two diagonal braces 3 upper tiltedly
The position of the first connecting hole 34 of end offers the 3rd connecting hole respectively, be positioned at the first connecting hole 34 of splay end on diagonal brace 3 with
Described 3rd connecting hole is connected by a connection piece and coordinates.
In the present embodiment, described second connecting hole can be opened in external groove sidevall (the most above-mentioned first groove of described perpendicular support 1
Wall) lower end position at, on the other side, described 3rd connecting hole can be opened in the external groove sidevall of described stull 2 away from outward
The position, one end of wall.Described second connecting hole can also be opened on the internal groove side wall of described perpendicular support 1 (the most above-mentioned second groove
Wall) lower end position at, on the other side, described 3rd connecting hole can also be opened in the internal groove side wall of described stull 2 away from
The position, one end of exterior wall.
Staff grips this diagonal brace 3, outside the inner thread sleeve 31 of described diagonal brace 3 at rotation diagonal brace 3 for convenience
Side face is provided with gripping handle 35.
Air-conditioning formwork support structure at the present embodiment is A-frame system, and its good stability, fastness are preferable.Tiltedly
Support 3 can rotate relative to the fixing point in perpendicular support 1, facilitates staff to install;Diagonal brace 3 uses sleeve two to terminate screw rod, permissible
Adapt to the stull 2 of different length, adapt to the support of different embodiment hollow adjustment mould plate length.
When installing the air-conditioning formwork support structure of the present embodiment, can first be connected fixing with perpendicular support 1 for stull 2, then
Again diagonal brace 3 is connected between perpendicular support 1 and stull 2, forms triangular support structure, then make the stull 2 of two triangular structures
It is positioned at same level, two triangular support structure are fixed on exterior wall;Can also be first by two perpendicular support 1 same level height
Be installed on exterior wall, the most again stull 2 is arranged on correspondence perpendicular support 1 upper end, then by the splay end up and down of diagonal brace 3 respectively with
Corresponding stull 2 and perpendicular support 1 connection.
After air-conditioning formwork support structure is installed on exterior wall, starts formwork, will be placed in two stulls 2 by end template,
Then being respectively provided with the side template of three sides, template is coordinated in groove-like by Zhi Haohou and metope;Last pour in groove for
Support the air-conditioning concrete slab of outdoor machine of air-conditioner.
In the present embodiment, in order to increase the versatility of air-conditioning template so that it is be applicable to the pouring of air-conditioning plate of different length,
Also have additional and be across in two stulls 2 and arbitrarily can slide and any section can be fixed on along described stull 2 length direction
The template length governor motion 5 of position.
What what this template length governor motion 5 included being placed in each stull 2 can slide on this stull 2 length direction
Slide construction 51, one baffle plate 52 and slide construction 51 can be fixed in described stull 2 fixed knot at any fragment position
Structure, the length direction of described baffle plate 52 is perpendicular with the length direction of described stull 2, and the length of described baffle plate 52 is more than two
Spacing between slide construction 51, the two ends of the bottom of described baffle plate 52 are individually fixed on two slide constructions 51.So, when same
During slide construction 51 in Shi Yidong two stull 2, two slide constructions 51 drive described baffle plate 52 along the length direction of described stull 2
Mobile, when slide construction 51 moves to destination locations, use fixed structure to fix this slide construction 51.In this way,
The effect of the length of adjusting template can be played, finally play the extension that can regulate cast-in-place air-conditioning concrete slab, be suitable for
Demand in different embodiments.
In the present embodiment, described slide construction 51 in described stull 2 channel-section steel match can movement on translot
Mount structure, the lower diapire at described mount structure offers a screwed hole, and described fixed structure is to fix bolt 53, described fixing
Bolt 53 from the bottom to top through the one of the lower diapire can being butted in described stull 2 after described screwed hole towards described mount structure
Face.When the mobile described mount structure of needs, looser a bolt and i.e. may move described mount structure, after being displaced into destination locations, then twist
Tight described mount structure is i.e. securable to this position.
In the present embodiment, this baffle plate 52 uses as a side plate away from exterior wall in air-conditioning template, therefore when formwork,
Only need a bed die can form concreting groove with two relative side forms;Template length governor motion can not only regulate
Template length, the versatility making air-conditioning formwork support structure is more preferable, it is possible to the air-conditioning plate adapting to different length requirement pours, and also saves
Cost-saving, it is not necessary to make the side template away from exterior wall again, reduces the formwork time.By this template length adjustment structure, at dynamic model
Loosen the bolt of fender plate 52 before, tight a bolt after being adjusted to adapt to length fixing, thus carry out pouring plate face length degree
Adjust.After the intensity of concrete reaches 100%, back-out fender plate 52 bolt, reverse controllable register 52, then reversely rotate support bar
Screw shell shortens support bar length, sheds support force, finally removes M20 bolt, takes off gusseted system.
This utility model utilizes adjustable triangle support support shuttering to carry out pouring of air-conditioning plate at different level, simplifies tradition
Steel tube fastener formula support system, thus reach accelerating construction progress, improve the effect of construction quality.This utility model uses shaped steel
Setting up, intensity is high, fully meets pouring of thin plate, and reusable, improves the utilization rate of material, saves construction cost, carries
High construction quality.Between each support bar of the present utility model with bolts, lay down support can by level to channel-section steel draw in,
Storage is convenient, takes up room little.Owing to this gusseted system uses adjustable support, one can be entered by regulation support bar length
Step meets the thin plate of different angles and supports, and adds the range of this utility model.
These are only embodiment of the present utility model, not thereby limit the scope of the claims of the present utility model, every profit
The equivalent structure made by this utility model description and accompanying drawing content or equivalence flow process conversion, or directly or indirectly it is used in it
The technical field that he is correlated with, is the most in like manner included in scope of patent protection of the present utility model.
Claims (8)
1. an air-conditioning formwork support structure, it is characterised in that: include being detachably secured on wall face, being positioned at same level
Height and the two perpendicular supports being parallel to each other, upper ends being removably fixed in two perpendicular supports respectively and to the direction water away from described wall face
Flat two stulls extended and two diagonal braces, the lower splay end of described two diagonal braces is detachably secured to the lower end of two perpendicular supports, institute respectively
State the upper splay end of two diagonal braces and be detachably secured in two stulls the one end away from wall face respectively.
2. air-conditioning formwork support structure as claimed in claim 1, it is characterised in that: two erect support is notch to away from wall face
The channel-section steel in direction, the upper end symmetry at the cell wall of two perpendicular supports offers two first installing holes;Two stulls be notch downwards and notch
Width is less than the channel-section steel of the width of rebate of perpendicular support, and the inner end symmetry at the cell wall of two stulls offers two second installing holes;Described
The inner end of two stulls is the most laterally inserted in the upper end of two perpendicular supports, and clamping screw sequentially passes through first on first cell wall of perpendicular support
Installing hole, corresponding stull be in close proximity to the second installing hole on a cell wall of first cell wall of perpendicular support, described corresponding stull another
Coordinate with nut check after the first installing hole on second installing hole of one cell wall and second cell wall of described perpendicular support.
3. air-conditioning formwork support structure as claimed in claim 2, it is characterised in that: described two erect support is the light-duty groove of 6.5#
Steel.
4. air-conditioning formwork support structure as claimed in claim 3, it is characterised in that: described two stulls are 5# thin-wall channel.
5. air-conditioning formwork support structure as claimed in claim 2, it is characterised in that: the lower splay end of described two diagonal braces is the most removable
On first cell wall being fixed on described two perpendicular supports unloaded, the upper splay end of described two diagonal braces is detachably secured to two stulls respectively
Adjacent on a cell wall of this first cell wall.
6. air-conditioning formwork support structure as claimed in claim 2, it is characterised in that: the lower splay end of described two diagonal braces is the most removable
On second cell wall being fixed on described two perpendicular supports unloaded, the upper splay end of described two diagonal braces is detachably secured to two stulls respectively
Adjacent on a cell wall of this second cell wall.
7. air-conditioning formwork support structure as claimed in claim 1, it is characterised in that: each diagonal brace all includes an inner screw sheath
Cylinder, respectively with two external thread rods of the two ends threaded engagement of inner thread sleeve, at two external thread rods away from described inner thread sleeve
One end be installed with a connection journal stirrup respectively, described connection journal stirrup offers the first connecting hole;Under described two perpendicular supports
Hold the position corresponding to the first connecting hole of the lower splay end being positioned at two diagonal braces to offer the second connecting hole respectively, be positioned under diagonal brace
First connecting hole of splay end and described second connecting hole are connected by a connection piece and coordinate;In described two stulls corresponding to being positioned at two
The position of the first connecting hole of the upper splay end of diagonal brace offers the 3rd connecting hole respectively, is positioned at the first connection of splay end on diagonal brace
Hole is connected cooperation with described 3rd connecting hole by a connection piece.
8. air-conditioning formwork support structure as claimed in claim 7, it is characterised in that: the outer peripheral face at described inner thread sleeve sets
It is equipped with gripping handle.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201620804234.6U CN205857710U (en) | 2016-07-28 | 2016-07-28 | Air-conditioning formwork support structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201620804234.6U CN205857710U (en) | 2016-07-28 | 2016-07-28 | Air-conditioning formwork support structure |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN205857710U true CN205857710U (en) | 2017-01-04 |
Family
ID=57649503
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201620804234.6U Active CN205857710U (en) | 2016-07-28 | 2016-07-28 | Air-conditioning formwork support structure |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN205857710U (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN113216613A (en) * | 2021-05-29 | 2021-08-06 | 中铁建设集团华北工程有限公司 | L-beam construction device and construction method for house structure reinforcement |
| CN114906480A (en) * | 2022-06-10 | 2022-08-16 | 中冶建工集团有限公司 | Portable adjustable horizontal bracket and use method |
-
2016
- 2016-07-28 CN CN201620804234.6U patent/CN205857710U/en active Active
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN113216613A (en) * | 2021-05-29 | 2021-08-06 | 中铁建设集团华北工程有限公司 | L-beam construction device and construction method for house structure reinforcement |
| CN114906480A (en) * | 2022-06-10 | 2022-08-16 | 中冶建工集团有限公司 | Portable adjustable horizontal bracket and use method |
| CN114906480B (en) * | 2022-06-10 | 2024-09-13 | 中冶建工集团有限公司 | Portable adjustable horizontal bracket and use method thereof |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN106088587A (en) | A kind of Combined formwork support system | |
| CN102031868A (en) | Building construction erecting formwork | |
| CN102493642A (en) | Method of adopting tool type clamp to support ground beam template side molds | |
| CN208251619U (en) | A kind of assembling truss floor support plate support | |
| CN205857710U (en) | Air-conditioning formwork support structure | |
| CN205857709U (en) | Air-conditioning template length governor motion and air-conditioning formwork support structure | |
| CN206128634U (en) | Air conditioner shelf and window one -piece casting template support structure that wafts | |
| CN210754890U (en) | An adjustable tire frame for making steel cages | |
| CN110017141A (en) | A kind of ultra-deep shaft concrete ring grid beam quick template supporting system and its construction method | |
| CN104018655B (en) | A kind of assembly type monomer bracing frame | |
| CN107299759A (en) | A kind of method that template is adjusted in skyscraper | |
| CN209129367U (en) | A kind of adjustable side form structure dropping plate construction for kitchen and bath | |
| CN206737428U (en) | A kind of wall form verticality adjusting device | |
| CN218881662U (en) | Fixing device of wall under prefabricated station platen of subway station | |
| CN217812477U (en) | High and large space composite sound insulation wallboard mounting device | |
| CN206902768U (en) | A kind of post-cast strip adjustable supporting | |
| CN217151174U (en) | Construction is with convenient to detach's supplementary installation device of scaffold frame | |
| CN211850824U (en) | Supporting unit and supporting device | |
| CN206971725U (en) | Hang the erecting device of mould | |
| CN205421971U (en) | Assembly type structure outer wall bearing structure | |
| CN212535081U (en) | Opposite-pulling plate fixing device for building beam side template | |
| CN212027094U (en) | Integral aluminum formwork based on narrow expansion joints | |
| CN202324614U (en) | Lead screw connected bidirectional variable tool type ground beam clamp | |
| CN209924989U (en) | Rapid formwork system for concrete ring frame beam of ultra-deep shaft | |
| CN208280644U (en) | Open caisson and reverse-working internal mold supporting device |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant |