CN211209220U - Pre-buried line box structure - Google Patents

Pre-buried line box structure Download PDF

Info

Publication number
CN211209220U
CN211209220U CN201921408300.8U CN201921408300U CN211209220U CN 211209220 U CN211209220 U CN 211209220U CN 201921408300 U CN201921408300 U CN 201921408300U CN 211209220 U CN211209220 U CN 211209220U
Authority
CN
China
Prior art keywords
shaped
wire box
line box
pouring template
rib
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921408300.8U
Other languages
Chinese (zh)
Inventor
周俊
许蓓
曾军
陈磊
罗文升
蔡民
袁林娜
胡预立
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangxi Construction Engineering Safety And Quality Supervision And Administration Bureau
Jiangxi Second Construction Co ltd
Jiangxi Construction Engineering Group Co ltd
Original Assignee
Jiangxi Construction Engineering Safety And Quality Supervision And Administration Bureau
Jiangxi Second Construction Co ltd
Jiangxi Construction Engineering Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangxi Construction Engineering Safety And Quality Supervision And Administration Bureau, Jiangxi Second Construction Co ltd, Jiangxi Construction Engineering Group Co ltd filed Critical Jiangxi Construction Engineering Safety And Quality Supervision And Administration Bureau
Priority to CN201921408300.8U priority Critical patent/CN211209220U/en
Application granted granted Critical
Publication of CN211209220U publication Critical patent/CN211209220U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a pre-buried wire box structure, which is arranged on a pouring template and comprises a wire box, a metal net and a vertical bar, wherein the wire box is reversely buckled on the pouring template, and the metal net is wrapped on the surface of the shell of the wire box; the frame vertical ribs cover the wire box and are fixedly connected with the pouring template; the utility model discloses a pre-buried line box structure at the enhancement design of pre-buried line box department of floor, compensaties the not enough defect of floor pouring thickness, improves the ability of shearing of line box department floor, prevents to produce the crack around the line box to construction operation is simple and convenient.

Description

Pre-buried line box structure
Technical Field
The utility model relates to a building engineering technical field, more specifically the utility model relates to a pre-buried line box structure that says so.
Background
The thickness of the floor slab of the house building is generally 100mm and 120mm, the thickness of the floor slab at the pre-buried wire box is reduced, cracks are easy to generate, and the weak part of the floor slab has certain influence on the quality of the floor. At the position of the floor line box, the thickness of the floor is reduced, and the local shear resistance is weakened; cracks are easily generated around the wire box, and the quality of the concrete floor is affected.
Therefore, how to provide a pre-buried junction box structure which can improve the shearing resistance of a floor slab at the junction box and prevent cracks from generating around the junction box is a problem which needs to be solved by the technical personnel in the field.
SUMMERY OF THE UTILITY MODEL
In view of this, the utility model provides a pre-buried line box structure aims at solving one of above-mentioned technical problem at least, in floor line box department, compensaties the not enough problem of floor thickness, makes not produce the crack around the line box to the construction is simple and convenient.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
a pre-embedded wire box structure is arranged on a pouring template and comprises a wire box, a metal net and a vertical bar, wherein the wire box is reversely buckled on the pouring template, and the metal net is wrapped on the surface of a shell of the wire box; the frame vertical ribs cover the wire box and are fixedly connected with the pouring template;
the frame vertical rib consists of a U-shaped rib part, a transverse rib part and a right-angle rib part; the U-shaped rib part is perpendicular to the pouring template and is connected with the pouring template; the number of the transverse rib parts is two, the two transverse rib parts are arranged in a vertical crossing manner, one ends of the two transverse rib parts are respectively connected with two ends of the U-shaped rib part, and the other ends of the two transverse rib parts are respectively connected with the right-angle rib part; and the two right-angle rib parts are respectively attached to two adjacent side surfaces of the wire box.
Preferably, in the above-mentioned pre-buried line box structure, the set of upright bars is formed by bending a steel bar.
Preferably, in the above embedded junction box structure, the U-shaped rib portion of the erection rib is nailed to the casting formwork through a nail.
Preferably, in the above-mentioned pre-buried line box structure, the nail is the staple, the U-shaped muscle portion card is in the U-shaped inslot of staple.
Preferably, in the above pre-buried line box structure, the metal mesh is a steel wire mesh.
Preferably, in the above-mentioned pre-buried line box structure, two right angle muscle portion with U-shaped muscle portion is to two diagonal angles of line box carry on spacingly, fix the line box.
According to the technical scheme, compared with the prior art, the utility model discloses a pre-buried wire box structure, which solves the problems that the wire box of the existing cast floor slab is reduced in thickness of the floor slab, the local shearing resistance is weakened, cracks are easy to generate around the wire box, and the quality of the concrete floor is influenced; the wire box wraps the steel wire mesh, and shrinkage stress generated by concrete is effectively resisted.
The utility model discloses at the enhancement design of the pre-buried line box department of floor, compensate the not enough defect of floor pouring thickness, improve the ability of shearing of line box department floor, prevent to produce the crack around the line box to construction operation is simple and convenient.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required to be used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to the provided drawings without creative efforts.
Fig. 1 is a schematic structural view of the present invention when installed on a pouring form;
fig. 2 is a schematic structural diagram of the frame stud.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
The embodiment of the utility model discloses pre-buried line box structure, at the enhancement design of pre-buried line box department of floor, compensate the not enough defect of floor pouring thickness, improve the ability of shearing of line box department floor, prevent to produce the crack around the line box to construction operation is simple and convenient.
The utility model discloses a pre-buried wire box 2 structure, the pre-buried wire box 2 structure is installed on a pouring template 1, comprising a wire box 2, a metal net 3 and a vertical bar 4, wherein, the wire box 2 is reversely buckled on the pouring template 1, and the metal net 3 is wrapped on the surface of the shell of the wire box 2; the frame vertical ribs 4 cover the wire box 2 and are fixedly connected with the pouring template 1;
the vertical frame rib 4 is composed of a U-shaped rib part 41, a transverse rib part 42 and a right-angle rib part 43; the U-shaped rib part 41 is perpendicular to the pouring template 1 and is connected with the pouring template; two transverse rib parts 42 are arranged, the two transverse rib parts 42 are vertically crossed, one ends of the two transverse rib parts 42 are respectively connected with two ends of the U-shaped rib part 41, and the other ends of the two transverse rib parts 42 are respectively connected with a right-angle rib part 43; the two right-angle rib portions 43 are respectively attached to two adjacent side surfaces of the thread cassette 2.
In order to further optimize the technical scheme, the vertical ribs 4 are formed by bending a steel bar.
In order to further optimize the above technical solution, the U-shaped rib portions 41 of the erection bars 4 are nailed to the casting form 1 by nails 5.
In order to further optimize the above technical solution, the nail 5 is a U-shaped nail, and the U-shaped rib 41 is clamped in a U-shaped groove of the U-shaped nail.
In order to further optimize the technical scheme, the metal mesh 3 is a steel wire mesh.
In order to further optimize the above technical solution, the two right-angle rib parts 43 and the U-shaped rib part 41 limit two opposite angles of the wire box 2, and fix the wire box 2.
The utility model provides a pair of 2 structure construction steps of pre-buried line box do:
1. bending and processing the plain round steel bars into the same shape of the erected steel bars in advance;
2. drawing a position line of a pre-buried wire box 2 on a pouring template 1 of a floor slab according to design requirements;
3. placing the wire box 2 at the position required by the design of the wire box 2, then reversely buckling the wire box 2 on the pouring template 1, wrapping a layer of steel wire mesh and fixing;
4. the erection bars 4 are covered on the wire box 2 wrapped by the steel wire mesh, and the erection bars 4 are fixed on the pouring template 1 by nails 5.
The embodiments in the present description are described in a progressive manner, each embodiment focuses on differences from other embodiments, and the same and similar parts among the embodiments are referred to each other. The device disclosed by the embodiment corresponds to the method disclosed by the embodiment, so that the description is simple, and the relevant points can be referred to the method part for description.
The previous description of the disclosed embodiments is provided to enable any person skilled in the art to make or use the present invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the generic principles defined herein may be applied to other embodiments without departing from the spirit or scope of the invention. Thus, the present invention is not intended to be limited to the embodiments shown herein but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.

Claims (6)

1. A pre-embedded wire box structure is arranged on a pouring template and is characterized by comprising a wire box, a metal net and a vertical bar, wherein the wire box is reversely buckled on the pouring template, and the metal net is wrapped on the surface of a shell of the wire box; the frame vertical ribs cover the wire box and are fixedly connected with the pouring template;
the frame vertical rib consists of a U-shaped rib part, a transverse rib part and a right-angle rib part; the U-shaped rib part is perpendicular to the pouring template and is connected with the pouring template; the number of the transverse rib parts is two, the two transverse rib parts are arranged in a vertical crossing manner, one ends of the two transverse rib parts are respectively connected with two ends of the U-shaped rib part, and the other ends of the two transverse rib parts are respectively connected with the right-angle rib part; and the two right-angle rib parts are respectively attached to two adjacent side surfaces of the wire box.
2. The pre-buried line box structure of claim 1, wherein the erection bars are formed by bending a steel bar.
3. The pre-buried line box structure of claim 1, wherein the U-shaped rib portions of the erection ribs are nailed to the pouring template through nails.
4. The embedded wire box structure according to claim 3, wherein the nails are U-shaped nails, and the U-shaped ribs are clamped in U-shaped grooves of the U-shaped nails.
5. The pre-buried line box structure of claim 1, wherein the metal mesh is a steel wire mesh.
6. The pre-buried line box structure of claim 1, wherein the two right-angle rib portions and the U-shaped rib portions limit two opposite angles of the line box to fix the line box.
CN201921408300.8U 2019-08-28 2019-08-28 Pre-buried line box structure Active CN211209220U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921408300.8U CN211209220U (en) 2019-08-28 2019-08-28 Pre-buried line box structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921408300.8U CN211209220U (en) 2019-08-28 2019-08-28 Pre-buried line box structure

Publications (1)

Publication Number Publication Date
CN211209220U true CN211209220U (en) 2020-08-07

Family

ID=71882770

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921408300.8U Active CN211209220U (en) 2019-08-28 2019-08-28 Pre-buried line box structure

Country Status (1)

Country Link
CN (1) CN211209220U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113356890A (en) * 2021-07-19 2021-09-07 中铁一局集团有限公司 Tunnel lining reserved hole construction method
CN114293776A (en) * 2022-01-04 2022-04-08 佛山市新一建筑集团有限公司 Component for storage box of floor slab or wall slab and method for using component

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113356890A (en) * 2021-07-19 2021-09-07 中铁一局集团有限公司 Tunnel lining reserved hole construction method
CN114293776A (en) * 2022-01-04 2022-04-08 佛山市新一建筑集团有限公司 Component for storage box of floor slab or wall slab and method for using component

Similar Documents

Publication Publication Date Title
CN106498844B (en) A kind of high speed railway box beam bridge floor pre-fabricated electric cables slot
CN211209220U (en) Pre-buried line box structure
KR102004419B1 (en) Structure for reinforcing column using V-shaped ties
CN103195172B (en) A kind of prefabrication and assembly construction concrete frame beam-column connection structure
CN105133830A (en) Formwork reinforcing system replacing wood with steel and construction technology thereof in external wall construction
JP6108595B2 (en) Ribbed precast concrete plate and method of placing concrete floor slab and beam using it
CN209670127U (en) A kind of fabricated construction of prefabricated steel reinforced concrete shear walls
CN207812307U (en) The construction system of Cable stayed Bridge Main Tower and steel anchor beam
CN203200925U (en) Prefabricated concrete framework beam column connected node structure
KR101358878B1 (en) Reinforcement member and girder using the same
CN108316150A (en) The construction system and construction method of Cable stayed Bridge Main Tower and steel anchor beam
TW201420848A (en) Steel structure for reinforced concrete wall panel and method thereof
CN108824191B (en) Construction process of group nail connecting device with corrugated sleeve
KR101994089B1 (en) Precast Concrete Slab With Pullout-Shear Resistance Elements Of Mesh Rib And Manufacturing Method Thereof
CN204940845U (en) A kind of with the formwork reinforcement system of steel generation wood
CN212405654U (en) Ribbed prestressed laminated slab
CN210421625U (en) Cast-in-place combination beam structure of assembled
JP2009144500A (en) Shearing reinforcement structure for column-beam joint part of uppermost story
KR101311706B1 (en) Corner bar and method for constructing concrete forms using the same
CN108951618B (en) Pile anchor supporting device
CN217998630U (en) Soil nail reinforcing bar protective layer thickness control ship type locator card making devices
CN218205692U (en) Device for intercepting post-cast strip of shear wall
CN217680585U (en) Encapsulating construction supporting structure
CN214940425U (en) Building bottom positioning steel bar mounting structure
CN209874073U (en) Masonry wall embedded part structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant