CN211014353U - Transformer partial discharge square wave calibration test operating rod - Google Patents

Transformer partial discharge square wave calibration test operating rod Download PDF

Info

Publication number
CN211014353U
CN211014353U CN201821914864.4U CN201821914864U CN211014353U CN 211014353 U CN211014353 U CN 211014353U CN 201821914864 U CN201821914864 U CN 201821914864U CN 211014353 U CN211014353 U CN 211014353U
Authority
CN
China
Prior art keywords
operating rod
square wave
test
wave generator
telescopic operating
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821914864.4U
Other languages
Chinese (zh)
Inventor
张鹏
徐兆丹
覃智贤
陈斌
范宇宁
周闯
熊红德
陈荭
伍任能
孙全才
刘乂溥
林雨果
廖英怀
甘艳飞
潘霞
李犇
韦贤伟
李俊强
伍珈乐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanning Power Supply Bureau of Guangxi Power Grid Co Ltd
Original Assignee
Nanning Power Supply Bureau of Guangxi Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanning Power Supply Bureau of Guangxi Power Grid Co Ltd filed Critical Nanning Power Supply Bureau of Guangxi Power Grid Co Ltd
Priority to CN201821914864.4U priority Critical patent/CN211014353U/en
Application granted granted Critical
Publication of CN211014353U publication Critical patent/CN211014353U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Testing Relating To Insulation (AREA)

Abstract

The utility model discloses a transformer partial discharge square wave calibration test operating rod, which mainly comprises a telescopic operating rod and a square wave generator; the square wave generator is installed at the fixed end of the telescopic operating rod, the square wave generator comprises a test terminal and a grounding terminal, the test terminal is connected with a test wire, and the test wire penetrates through the telescopic operating rod and extends out of the movable end of the telescopic operating rod. The utility model discloses collect the test wire in flexible action bars, can extend as required and shorten, solved the frequent sheathed tube safety risk of climbing of testing personnel, also convenient operation simultaneously. The square wave generator is installed at the fixed end of the telescopic operating rod, and an experimenter can set up a high-frequency pulse transmitting loop through the square wave generator, adjust and simulate different discharge amounts of emission, so that the operation of a ground lapping test line and an instrument can be realized, and the working efficiency is improved.

Description

Transformer partial discharge square wave calibration test operating rod
Technical Field
The utility model belongs to transformer test tool especially relates to a square wave calibration test operation pole is put in transformer office.
Background
When a 220kV main transformer is subjected to a transformer pulse current partial discharge test, in order to eliminate interference, a worker needs to climb onto a main transformer high-voltage sleeve to be calibrated by using a calibration square wave generator. However, the surface of the porcelain skirt is smooth, so that workers are difficult to climb, and need to lean on the sleeve in a hanging manner by hands when operating the instrument, so that the high-altitude falling risk is very high. Meanwhile, the traditional calibration square wave generator is too large in size, difficult to operate on a transformer, long lead wires are needed for grounding, at least two persons are needed for matching, and operation is inconvenient.
Disclosure of Invention
The to-be-solved technical problem of the utility model is to provide a square wave calibration test operating rod is put in transformer office simple structure, convenient and practical
In order to solve the technical problem, the utility model discloses a following technical scheme:
the transformer partial discharge square wave calibration test operating rod mainly comprises a telescopic operating rod and a square wave generator; the square wave generator is installed at the fixed end of the telescopic operating rod, the square wave generator comprises a test terminal and a grounding terminal, the test terminal is connected with a test wire, and the test wire penetrates through the telescopic operating rod and extends out of the movable end of the telescopic operating rod.
The telescopic operating rod is formed by sleeving three sections of sleeves.
The telescopic length of the telescopic operating rod is 1m-5 m.
Aiming at the problems existing in the calibration of the existing square wave generator, the inventor designs and manufactures a transformer partial discharge square wave calibration test operating rod which mainly comprises a telescopic operating rod and a square wave generator; the square wave generator is installed at the fixed end of the telescopic operating rod, the square wave generator comprises a test terminal and a grounding terminal, the test terminal is connected with a test wire, and the test wire penetrates through the telescopic operating rod and extends out of the movable end of the telescopic operating rod. The utility model discloses collect the test wire in flexible action bars, can extend as required and shorten, solved the frequent sheathed tube safety risk of climbing of testing personnel, also convenient operation simultaneously. The square wave generator is installed at the fixed end of the telescopic operating rod, and an experimenter can set up a high-frequency pulse transmitting loop through the square wave generator, adjust and simulate different discharge amounts of emission, so that the operation of a ground lapping test line and an instrument can be realized, and the working efficiency is improved.
Drawings
Fig. 1 is the structure schematic diagram of the square wave calibration test operating rod is put in transformer office of the utility model.
In the figure: 1 test wire, 2 flexible action bars, 3 square wave generators, 4 test terminals, 5 ground terminal.
Detailed Description
As shown in fig. 1, the square wave calibration and test operating rod for transformer partial discharge of the present invention mainly comprises a telescopic operating rod and a square wave generator 3, wherein the telescopic operating rod 2 can be formed by sleeving a plurality of casing pipes (shown as three sections), and the telescopic length is 1m-5 m; the square wave generator is installed at the stiff end of flexible action bars, and square wave generator contains test terminal 4 and ground terminal 5, and test terminal connects the test wire, and test wire 1 runs through flexible action bars and stretches out from the expansion end of flexible action bars.
When the device is used, the fixed end of the operating rod is held by a hand, the movable end of the telescopic operating rod with the test wire is extended, a high-frequency pulse transmitting loop can be built on the ground, different discharge amounts of simulated emission are adjusted, and therefore the ground can be used for overlapping the test wire and an instrument.

Claims (3)

1. A transformer partial discharge square wave calibration test operating rod is characterized by mainly comprising a telescopic operating rod and a square wave generator; the square wave generator is installed at the fixed end of the telescopic operating rod, the square wave generator comprises a test terminal and a grounding terminal, the test terminal is connected with a test wire, and the test wire penetrates through the telescopic operating rod and extends out of the movable end of the telescopic operating rod.
2. The transformer partial discharge square wave calibration test operating rod according to claim 1, characterized in that: the telescopic operating rod is formed by sleeving three sections of sleeves.
3. The transformer partial discharge square wave calibration test operating rod according to claim 1, characterized in that: the telescopic length of the telescopic operating rod is 1m-5 m.
CN201821914864.4U 2018-11-20 2018-11-20 Transformer partial discharge square wave calibration test operating rod Active CN211014353U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821914864.4U CN211014353U (en) 2018-11-20 2018-11-20 Transformer partial discharge square wave calibration test operating rod

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821914864.4U CN211014353U (en) 2018-11-20 2018-11-20 Transformer partial discharge square wave calibration test operating rod

Publications (1)

Publication Number Publication Date
CN211014353U true CN211014353U (en) 2020-07-14

Family

ID=71477500

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821914864.4U Active CN211014353U (en) 2018-11-20 2018-11-20 Transformer partial discharge square wave calibration test operating rod

Country Status (1)

Country Link
CN (1) CN211014353U (en)

Similar Documents

Publication Publication Date Title
CN202903954U (en) Power-frequency arbitrary phase angle superposed lightning impulse testing device for insulator string
CN105510753A (en) 100kA lightning current generator for testing impulse characteristics of grounding device
CN201489038U (en) Flexible Roche coil for measuring impulse current
CN107643478B (en) Lightning stroke test system of lightning stroke tower shrinkage model
CN211014353U (en) Transformer partial discharge square wave calibration test operating rod
CN206275048U (en) A kind of cross-direction shrinkage type occupying device
CN205646216U (en) Insulation is tested denso and is established earth connection auxiliary rod
CN208421149U (en) A kind of power frequency continued flow experimental rig
CN204086456U (en) 750kV insulating tool segmentation alternating-current voltage resistance test device
CN202221437U (en) Special-purpose test tool for electrified lightning arrester
CN210665929U (en) Gap distance adjustable lightning arrester impact action characteristic test system with series gaps
CN205484585U (en) A 100kA thunder current generator for earthing device impact characteristic test
CN205229375U (en) Impulse voltage distributes and measures testing system among transformer winding
CN203705481U (en) Dedicated live-testing wiring rod for lightning arrester of transformer station
CN105319470B (en) System for distribution measurement testing of impulse voltage in transformer winding
CN204705676U (en) A kind of heavy current impact impedance test system
CN103809011A (en) Lightning arrester resistive-current testing tool
CN204101591U (en) A kind of New insulated testing current in resistance property of lightning arrester line erecting tools
CN210038044U (en) Multi-pin type vertical grounding body key parameter testing device
CN209247867U (en) A kind of quick precise measurement conversion equipment of thunder-strike current
CN203722120U (en) Rapid arc extinguisher used for coming out of electric field
CN211554126U (en) Make things convenient for remote electroscope of dismouting
CN206673143U (en) A kind of Multifunction altitude test connection pincers
CN216285465U (en) Multi-voltage adjustable high-voltage electroscope
CN210723970U (en) 66kV transmission live working insulated operating rod

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant