CN210779813U - Special tool for adjusting sag of 220kV vertically-arranged double-bundle conductor in electrified manner - Google Patents

Special tool for adjusting sag of 220kV vertically-arranged double-bundle conductor in electrified manner Download PDF

Info

Publication number
CN210779813U
CN210779813U CN201921965499.4U CN201921965499U CN210779813U CN 210779813 U CN210779813 U CN 210779813U CN 201921965499 U CN201921965499 U CN 201921965499U CN 210779813 U CN210779813 U CN 210779813U
Authority
CN
China
Prior art keywords
bundle conductor
special tool
adjusting
shackles
sag
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921965499.4U
Other languages
Chinese (zh)
Inventor
张孝祖
张梁
李海顺
王加海
訾军
吕金
孙鱇
梅耕宁
王磊
其他发明人请求不公开姓名
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kunming Power Supply Bureau of Yunnan Power Grid Co Ltd
Original Assignee
Kunming Power Supply Bureau of Yunnan Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kunming Power Supply Bureau of Yunnan Power Grid Co Ltd filed Critical Kunming Power Supply Bureau of Yunnan Power Grid Co Ltd
Priority to CN201921965499.4U priority Critical patent/CN210779813U/en
Application granted granted Critical
Publication of CN210779813U publication Critical patent/CN210779813U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Electric Cable Installation (AREA)

Abstract

本实用新型公开了一种带电调整220kV垂直排列双分裂导线弧垂专用工具,旨在提供一种可提高作业效率的带电调整220kV垂直排列双分裂导线弧垂专用工具。该专用工具包括配套使用的调节装置和保护装置;所述调节装置包括螺套,两旋拧于螺套两端的丝杆,两分别连接于两丝杆端部的第一卸扣,以及固定设置于螺套中部、与螺套构成T形的柄杆。本实用新型调节方便快速,可降低等电位员工作业强度,减少作业时间。

Figure 201921965499

The utility model discloses a special tool for adjusting the sag of 220kV vertically arranged double-split conductors under live voltage, which aims to provide a special tool for adjusting the sag of 220kV vertically arranged double-split conductors under live voltage which can improve the working efficiency. The special tool includes a matching adjusting device and a protecting device; the adjusting device includes a screw sleeve, two screw rods screwed on both ends of the screw sleeve, two first shackles respectively connected to the ends of the two screw rods, and a fixed setting A T-shaped shank is formed with the screw sleeve in the middle of the screw sleeve. The utility model is convenient and quick to adjust, and can reduce the work intensity of equipotential employees and reduce the work time.

Figure 201921965499

Description

一种带电调整220kV垂直排列双分裂导线弧垂专用工具A special tool for sag adjustment of 220kV vertically arranged double-split conductors

技术领域technical field

本实用新型涉及电网施工器具技术领域,尤其是涉及一种带电调整220kV垂直排列双分裂导线弧垂专用工具。The utility model relates to the technical field of power grid construction appliances, in particular to a special tool for adjusting the sag of 220kV vertically arranged double-split conductors with electricity.

背景技术Background technique

目前,在调整220kV输电线路垂直排列双分裂导线弧垂时,采用的是停电作业。作业人员攀登杆塔至安装位置后,通过地面电工吊送链条葫芦、后备钢绳,由作业人员进行安装,该种传统施工方法的缺陷是:作业人员多,链条葫芦质量大,在安装、拆除过程中对作业人员要求较高,且采用钢丝绳套连接链条葫芦工具时,由于现有可行工具链条葫芦和作为后备保护的钢绳套较长且都是金属工器具,控制不好时极易发生相间短路,因而不能采用带电作业的方式来进行,带来极大安全隐患;且链条葫芦重量较大,作业人员携带及操作的劳动强度很高,作业风险高,所需工器具较多,作业流程较为复杂,增加了线路停电时间,减少供电量。At present, when adjusting the sag of the 220kV transmission line vertically arranged double-split conductors, the blackout operation is adopted. After the operator climbs the tower to the installation position, the chain hoist and the backup steel rope are hoisted by the ground electrician and installed by the operator. The defects of this traditional construction method are: there are many operators and the quality of the chain hoist is large. The requirements for operators are relatively high, and when the wire rope sleeve is used to connect the chain hoist tool, because the existing feasible tool chain hoist and the steel rope sleeve used as backup protection are long and both are metal tools, it is easy to occur when the control is not good. Short circuit, so it cannot be carried out by live operation, which brings great safety hazards; and the chain hoist is heavy, the labor intensity of the operator to carry and operate is high, the operation risk is high, the required tools are many, and the operation process It is more complicated, which increases the power outage time of the line and reduces the power supply.

实用新型内容Utility model content

本实用新型的目的旨在克服现有技术存在的不足,提供了一种质量轻,携带方便且可提高作业效率的带电调整220kV垂直排列双分裂导线弧垂专用工具。The purpose of the utility model is to overcome the deficiencies of the prior art, and to provide a special tool for adjusting the sag of 220kV vertically arranged double-split conductors in live charging, which is light in weight, easy to carry and can improve work efficiency.

为了解决上述技术问题,本实用新型是通过以下技术方案实现的:In order to solve the above-mentioned technical problems, the utility model is realized through the following technical solutions:

一种带电调整220kV垂直排列双分裂导线弧垂专用工具,包括配套使用的调节装置和保护装置;所述调节装置包括螺套,两旋拧于螺套两端的丝杆,两分别连接于两丝杆端部的第一卸扣,以及固定设置于螺套中部、与螺套构成T形的柄杆。A special tool for adjusting the sag of 220kV vertically arranged double-split conductors with electricity, including a matching adjustment device and a protection device; the adjustment device includes a screw sleeve, two screw rods screwed on both ends of the screw sleeve, and two screws are respectively connected to the two wires. The first shackle at the end of the rod, and the handle rod which is fixedly arranged in the middle of the screw sleeve and forms a T-shape with the screw sleeve.

优选的是,所述保护装置包括第一迪尼玛绳扣,以及两分别连接于第一迪尼玛绳扣两端的第二卸扣。Preferably, the protection device includes a first Dyneema cord buckle, and two second shackles respectively connected to both ends of the first Dyneema cord buckle.

优选的是,其中一所述第一卸扣通过第二迪尼玛绳扣与相应的丝杆连接。Preferably, one of the first shackles is connected with a corresponding screw rod through a second Dyneema rope buckle.

优选的是,其还包括可拆卸连接于柄杆端部的加长杆。Preferably, it also includes an extension rod detachably connected to the end of the handle.

优选的是,所述丝杆用于连接第一卸扣的端部设置有U形的通槽,该通槽的口部设置供卸扣连接的螺栓。Preferably, the end of the screw rod for connecting the first shackle is provided with a U-shaped through groove, and the mouth of the through groove is provided with a bolt for connecting the shackle.

与现有技术相比,本实用新型具有如下优点:Compared with the prior art, the utility model has the following advantages:

本实用新型可在带电情况下,安全、快速对220kV垂直排列双分裂导线弧垂进行调整;弧垂调整工作和导线保护采用迪尼玛绳扣,消除了金属工具在带电作业中可能引发短路的风险;本实用新型结构轻便,调节方便快速,可大大降低工器具重量,降低等电位员工作业强度,减少作业时间。The utility model can safely and quickly adjust the sag of 220kV vertically arranged double-split conductors under live conditions; the Dyneema rope buckle is used for sag adjustment and conductor protection, which eliminates the possibility of short-circuits caused by metal tools during live work. Risk; the utility model has the advantages of light structure, convenient and fast adjustment, and can greatly reduce the weight of tools, reduce the work intensity of equipotential employees, and reduce the work time.

附图说明Description of drawings

为了更清楚地说明本实用新型实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本实用新型的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其它的附图。In order to more clearly illustrate the embodiments of the present utility model or the technical solutions in the prior art, the following briefly introduces the accompanying drawings that need to be used in the description of the embodiments or the prior art. Obviously, the accompanying drawings in the following description These are just some embodiments of the present invention, and for those of ordinary skill in the art, other drawings can also be obtained from these drawings without creative effort.

图1为本实用新型的结构示意图,其中示出了第一卸扣与导线连接的相关结构。FIG. 1 is a schematic structural diagram of the present invention, which shows the related structure of the connection between the first shackle and the wire.

图中:螺套1、丝杆2、第一卸扣3、柄杆4、第二卸扣5、第一迪尼玛绳扣6、通槽7、螺栓8,卡线器9,导线10。In the figure: screw sleeve 1, lead screw 2, first shackle 3, handle rod 4, second shackle 5, first Dyneema rope buckle 6, through slot 7, bolt 8, wire clamp 9, wire 10 .

具体实施方式Detailed ways

下面将结合本实用新型实施例中的附图,对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本实用新型一部分实施例,而不是全部的实施例。基于本实用新型中的实施例,本领域普通技术人员在没有付出创造性劳动前提下所获得的所有其他实施例,都属于本实用新型保护的范围。在以下描述中,为了清楚展示本实用新型的结构及工作方式,将以附图为基准,借助诸多方向性词语进行描述,但是应当将“前”、“后”、“左”、“右”、“上”、“下”等词语理解为方便用语,而不应当理解为限定性词语。The technical solutions in the embodiments of the present utility model will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present utility model. Obviously, the described embodiments are only a part of the embodiments of the present utility model, rather than all the implementations. example. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention. In the following description, in order to clearly show the structure and working mode of the present invention, the drawings will be used as a reference to describe with the help of many directional words, but "front", "rear", "left" and "right" should be used for description. , "上", "下" and other words are understood as convenient terms, and should not be understood as limiting words.

图1所示的带电调整220kV垂直排列双分裂导线弧垂专用工具,包括配套使用的调节装置和保护装置;所述调节装置包括螺套1,两旋拧于螺套1两端的丝杆2,两分别连接于两丝杆2端部的第一卸扣3,以及固定设置于螺套1中部、与螺套1构成T形的柄杆4。The special tool for live adjustment of 220kV vertically arranged double-split conductor sag shown in Fig. 1 includes a matching adjustment device and a protection device; the adjustment device includes a screw sleeve 1, and two screw rods 2 screwed on both ends of the screw sleeve 1, Two first shackles 3 respectively connected to the ends of the two screw rods 2, and a shank 4 fixedly arranged in the middle of the screw sleeve 1 and forming a T-shape with the screw sleeve 1.

作为优选的技术方案,所述保护装置包括第一迪尼玛绳扣6,以及两分别连接于第一迪尼玛绳扣6两端的第二卸扣5,该种保护装置重量轻便,且具有相间绝缘功能。显然保护装置也可采用目前常见的保护装置。As a preferred technical solution, the protection device includes a first Dyneema cord buckle 6 and two second shackles 5 respectively connected to both ends of the first Dyneema cord buckle 6. The protection device is lightweight and has Phase-to-phase insulation. Obviously, the protection device can also adopt the common protection device at present.

作为进一步的改进,其中一所述第一卸扣3通过第二迪尼玛绳扣(图中未示出)与相应的丝杆2连接,第二迪尼玛绳扣的两端均通过快拆连接件(如挂扣等)与相应的第一卸扣3及丝杆2连接,以满足当螺套1加两丝杆2最大长度不够时使用,提高适用性。As a further improvement, one of the first shackles 3 is connected to the corresponding lead screw 2 through a second Dyneema rope buckle (not shown in the figure), and both ends of the second Dyneema rope buckle are The dismantling connector (such as hanging buckle, etc.) is connected with the corresponding first shackle 3 and the lead screw 2, so as to meet the requirements when the maximum length of the screw sleeve 1 and the two lead screws 2 is not enough, and improve the applicability.

作为进一步的改进,其还包括可拆卸连接于柄杆4端部的加长杆(图中未示出),加长杆可通过螺纹结构或卡接结构与柄杆4连接,拆卸后方便携带,使用时组装后可省力。As a further improvement, it also includes an extension rod (not shown in the figure) that is detachably connected to the end of the handle rod 4. The extension rod can be connected to the handle rod 4 through a threaded structure or a snap connection structure. After disassembly, it is convenient to carry and use. It can save labor after assembly.

本实施例中,所述丝杆2用于连接第一卸扣3的端部设置有U形的通槽7,该通槽7的口部设置供卸扣连接的螺栓8。显然也可在丝杆2端板固定设置吊环等便于第一卸扣3连接的结构或构件。In this embodiment, the end of the screw rod 2 for connecting the first shackle 3 is provided with a U-shaped through groove 7 , and the opening of the through groove 7 is provided with a bolt 8 for connecting the shackle. Obviously, structures or components such as lifting rings that facilitate the connection of the first shackle 3 can also be fixedly arranged on the end plate of the screw rod 2 .

当需要进行,220kV垂直排列双分裂导线弧垂调整时,作业人员携带该专用工具通过攀爬软梯到达等电位安装位置,若需携带工具较多,该专用工具也可通过地面电工吊送;接着将保护装置一端的第二卸扣与三角联板的一施工孔连接,另一端的第二卸扣通过卡线器(直接与导线接触并锁紧,是工具与导线的受力点,根据不同导线的线径选取不同规格的卡线器。)与导线连接,此时保护装置安装完成。接着将调节装置一端的第一卸扣3与三角联板连接,另一端的第一卸扣3通过卡线器与导线连接,连接完成后,即可转动柄杆4使调节装置缩短,致使三角联板与导线的连接端受力解除,此时即可松开三角联板与导线连接处的连接件,对三角联板与导线的连接位置进行调整后并紧固连接件,继而实现导线弧垂的调整,调整完成后,即可依次拆除调节装置及保护装置。When it is necessary to adjust the sag of the 220kV vertically arranged double-split conductors, the operator carries the special tool to reach the equipotential installation position by climbing the soft ladder. If more tools need to be carried, the special tool can also be hoisted by the ground electrician; then Connect the second shackle at one end of the protection device to a construction hole in the triangle joint plate, and the second shackle at the other end through the wire clamp (directly contacting and locking the wire, which is the stress point between the tool and the wire. The wire diameter of the wire is selected from the wire clips of different specifications.) Connect with the wire, and the installation of the protection device is completed at this time. Next, connect the first shackle 3 at one end of the adjusting device to the triangle connecting plate, and connect the first shackle 3 at the other end with the wire through the wire clamp. The connection end between the connecting plate and the wire is released from the force. At this time, the connecting piece at the connection between the triangle connecting plate and the wire can be loosened. After adjusting the connection position of the triangle connecting plate and the wire, the connecting piece is tightened, and then the wire arc is realized. After the adjustment is completed, the adjustment device and the protection device can be removed in turn.

以上所述仅为本实用新型的较佳实施例而已,并不用以限制本实用新型的保护范围。对于本领域的技术人员而言,凡在本实用新型的精神和原则之内,其对上述具体实施例所记载的技术方案或部分技术特征进行的任何修改、等同替换及改进等,均应包含在本实用新型的保护范围之内。The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the protection scope of the present invention. For those skilled in the art, any modifications, equivalent replacements and improvements made to the technical solutions or part of the technical features described in the above-mentioned specific embodiments within the spirit and principles of the present invention shall include within the scope of protection of the present invention.

Claims (5)

1. A special tool for adjusting 220kV vertically-arranged double-bundle conductor sag in an electrified way comprises a regulating device and a protecting device which are matched with each other; the method is characterized in that: the adjusting device comprises a threaded sleeve, two screw rods which are screwed at two ends of the threaded sleeve, two first shackles which are respectively connected with the end parts of the two screw rods, and a handle rod which is fixedly arranged in the middle of the threaded sleeve and forms a T shape with the threaded sleeve.
2. The tool special for electrified adjustment of 220kV vertical arrangement double-bundle conductor sag according to claim 1, characterized in that: the protection device comprises a first Dynima rope fastener and two second shackles which are respectively connected with two ends of the first Dynima rope fastener.
3. The tool special for electrified adjustment of 220kV vertical arrangement double-bundle conductor sag according to claim 1 or 2, wherein: one of the first shackles is connected with the corresponding screw rod through a second Dyneema rope buckle.
4. The tool special for electrified adjustment of 220kV vertical arrangement double-bundle conductor sag according to claim 1 or 2, wherein: it also includes an extension bar detachably connected to the end of the handle bar.
5. The tool special for electrified adjustment of 220kV vertical arrangement double-bundle conductor sag according to claim 1 or 2, wherein: the end part of the screw rod, which is used for connecting the first shackle, is provided with a U-shaped through groove, and the opening part of the through groove is provided with a bolt for connecting the shackles.
CN201921965499.4U 2019-11-14 2019-11-14 Special tool for adjusting sag of 220kV vertically-arranged double-bundle conductor in electrified manner Active CN210779813U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921965499.4U CN210779813U (en) 2019-11-14 2019-11-14 Special tool for adjusting sag of 220kV vertically-arranged double-bundle conductor in electrified manner

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921965499.4U CN210779813U (en) 2019-11-14 2019-11-14 Special tool for adjusting sag of 220kV vertically-arranged double-bundle conductor in electrified manner

Publications (1)

Publication Number Publication Date
CN210779813U true CN210779813U (en) 2020-06-16

Family

ID=71034570

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921965499.4U Active CN210779813U (en) 2019-11-14 2019-11-14 Special tool for adjusting sag of 220kV vertically-arranged double-bundle conductor in electrified manner

Country Status (1)

Country Link
CN (1) CN210779813U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110707599A (en) * 2019-11-14 2020-01-17 云南电网有限责任公司昆明供电局 A special tool for sag adjustment of 220kv vertically arranged double-split conductors

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110707599A (en) * 2019-11-14 2020-01-17 云南电网有限责任公司昆明供电局 A special tool for sag adjustment of 220kv vertically arranged double-split conductors
CN110707599B (en) * 2019-11-14 2024-11-15 云南电网有限责任公司昆明供电局 A special tool for live adjustment of 220kv vertically arranged double-split conductor sag

Similar Documents

Publication Publication Date Title
CN101820144B (en) Special tool of live line work for replacing rectilinear insulator string of large-section double multiple wire
CN204144479U (en) A kind of earth connection
CN105914646A (en) Working method for replacing 35kV tension insulator strings with power on
CN204481391U (en) A kind of replacing double bundle conductor conductor spacer specific purpose tool
CN210779813U (en) Special tool for adjusting sag of 220kV vertically-arranged double-bundle conductor in electrified manner
CN110707599B (en) A special tool for live adjustment of 220kv vertically arranged double-split conductor sag
CN103779809B (en) The two oidiospore wire pitch operational method of charged adjustment
CN208337014U (en) A kind of charged for replacement Voltage for Insulators on HV Lines lifting block hanging point heightening device
CN203289006U (en) Insulation adjustable yoke plate
CN102227062B (en) Operating tool for hot-line replacement of ring-type mount-point suspended insulator and operating method thereof
CN205753176U (en) A kind of all-directional rotation telescopic insulating ladder
CN204809744U (en) Wire end broadsword type load support fixture and insulator chain change device
CN210201444U (en) Circuit breaking structure
CN220976379U (en) A kind of auxiliary replacement device of column insulator
CN110653741A (en) Tool for electrically fastening clamp bolt in overhead electrified remote control of power transmission line
CN206302092U (en) Overhead transmission line cable drafting tool
CN205882560U (en) Special circulation cord rack device of distribution live working earth potential
CN113852003B (en) Wire hanging pulley combination tool for equipotential operation of power transmission line and hanging method thereof
CN210704540U (en) A tool for high-altitude live remote control electric tightening of wire clamp bolts for transmission lines
CN204941333U (en) Electric power pylon high-altitude cat ladder suspension arrangement
CN205385267U (en) Parallel groove clamp for power transmission and transformation
CN204651789U (en) The special hanger of hot-line insulator string replacement
CN210957558U (en) Lifting assistor tool for insulated operating rod
CN210468603U (en) Join in marriage net live working and prevent that pine wire presss from both sides dress pole
CN210956301U (en) Insulator string suspension device for salt density test

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant