CN210766416U - Bridge cylinder mound construction platform - Google Patents

Bridge cylinder mound construction platform Download PDF

Info

Publication number
CN210766416U
CN210766416U CN201921267569.9U CN201921267569U CN210766416U CN 210766416 U CN210766416 U CN 210766416U CN 201921267569 U CN201921267569 U CN 201921267569U CN 210766416 U CN210766416 U CN 210766416U
Authority
CN
China
Prior art keywords
template
reel
construction platform
support
bridge cylinder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921267569.9U
Other languages
Chinese (zh)
Inventor
杨扬
靳海燕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201921267569.9U priority Critical patent/CN210766416U/en
Application granted granted Critical
Publication of CN210766416U publication Critical patent/CN210766416U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a bridge cylinder mound construction platform, establish the template in the outside of cylinder mound including the cover, the front side, the rear side, the left side and the right side of template all are connected with first slide rail, first slide rail inside slides there is first slider, the first slider outside is connected with the support frame, the support frame left and right sides is connected with the second slider, the left and right sides symmetry of template is provided with the crane, be provided with the second slide rail in the crane inboard vertical direction, second slide rail inside slides the second slider, the upper end of crane is fixed with the horizontal plate, the horizontal plate upside is provided with the reel, the reel outside is twined and is had the haulage rope, the haulage rope runs through the horizontal plate and connects the second slider, be connected with the axis of rotation between two reels, the right side of the reel on the template right side is connected with; the utility model has the advantages of simple structure, safety, practicality, low labor amount, less material consumption and automatic lifting.

Description

Bridge cylinder mound construction platform
Technical Field
The utility model belongs to the technical field of bridge pier stud construction equipment, in particular to bridge cylinder mound construction platform.
Background
In the projects such as bridges such as highway bridges, railway bridges, sidewalks, overpasses, ramp bridges, overpasses and the like, the pier columns are important components for supporting the bridges, the pier columns are relatively independent, the construction working surface is high, in the conventional construction, a scaffold construction platform needs to be erected around each independent pier column, so that a safe construction platform for the personnel to go up and down and the top surface of the pier column is provided, meanwhile, more labor capacity of workers is consumed when the scaffold construction platform is erected, a large amount of materials are wasted, and the construction cost is increased.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a bridge cylinder mound construction platform has simple structure, safe practicality, the low, the consumptive material of the amount of hand labor and can the advantage of automatic rising.
In order to achieve the above object, the utility model provides a following technical scheme: a bridge cylindrical pier construction platform comprises templates sleeved on the outer side of a cylindrical pier, the templates are formed by connecting multiple layers, the front side, the rear side, the left side and the right side of each layer of templates are connected with first slide rails, the first slide rails are mutually connected in the vertical direction, first slide blocks slide in the first slide rails, the outer sides of the first slide blocks are connected with a support frame, the support frame comprises support rods and connecting rods, a plurality of connecting rods are connected between the adjacent support rods, a support plate is arranged on the upper side of the support frame, a protective rod is fixed on the upper side of one end of each support rod, which is far away from the templates, a protective net is wound on the outer side of each protective rod, a second slide block is connected in the middle of the connecting rods on the left side and the right side of the support frame, lifting frames are symmetrically arranged on the left side and the right side of each template, the crane downside is provided with the fixed plate, and the upper end of crane is fixed with the horizontal plate, and the horizontal plate upside is provided with the reel, the outside winding of reel has the haulage rope, connects after the haulage rope runs through the horizontal plate the second slider, reel left and right sides symmetry is provided with the reel support, is connected with the axis of rotation between two reels, the right side of the reel on template right side is connected with the motor band-type brake, and motor band-type brake right side is connected with the motor.
Preferably, the first slide rail and the template are connected through a bolt.
Preferably, the number of the connecting rods connected between the adjacent supporting rods is two, three or four.
Preferably, the supporting rods are horizontally arranged, and one ends of the supporting rods, which are close to the template, are perpendicular to the template.
Preferably, the front side, the rear side and the left side of the lower part of the template left side lifting frame and the front side, the rear side and the right side of the lower part of the template right side lifting frame are respectively provided with an inclined bracket.
Preferably, the hauling cable is a steel wire rope.
Preferably, a rotating rod is connected between the winding drum and the winding drum bracket, and two ends of the rotating rod are connected with a shaft base for supporting the rotation of the rotating rod.
Compared with the prior art, the beneficial effects of the utility model are as follows:
the utility model discloses a design motor, reel, haulage rope pulling support frame's lift can practice thrift the amount of labour that the manual work need build the scaffold like this, can practice thrift raw and other materials again simultaneously, simultaneously through control motor alright realize going up and down, the direct lift of constructor has avoided still needing to build stair to practiced thrift the amount of labour, shortened the construction cycle of cylinder mound, simultaneously the utility model discloses simple structure, safe and reliable, simple to operate.
Drawings
Fig. 1 is a schematic structural diagram of the present invention.
Fig. 2 is a schematic top view of the present invention.
In the figure: 1. the device comprises a template, 2, a first slide rail, 3, a first slide block, 4, a support frame, 41, a support rod, 42, a connecting rod, 5, a support plate, 6, a protective rod, 7, a protective net, 8, a second slide block, 9, a lifting frame, 10, a second slide rail, 11, a fixing plate, 12, an inclined support, 13, a traction rope, 14, a horizontal plate, 15, a winding drum, 16, a winding drum support, 17, a rotating shaft, 18, a motor band-type brake, 19 and a motor.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-2, the embodiment provides a bridge cylindrical pier construction platform, which includes formworks 1 sleeved on the outer sides of cylindrical piers, the formworks 1 are formed by connecting a plurality of layers, a first slide rail 2 is connected to each of the front side, the rear side, the left side and the right side of each layer of formworks 1, the first slide rails 2 are connected to each other in the vertical direction, a first slide block 3 is slid inside the first slide rail 2, a support frame 4 is connected to the outer side of the first slide block 3, the support frame 4 includes support rods 41 and connecting rods 42, a plurality of connecting rods 42 are connected between the adjacent support rods 41, a support plate 5 is arranged on the upper side of the support frame 4, a protection rod 6 is fixed on the upper side of one end of each support rod 41 far from the formworks 1, a protective net 7 is wound on the outer side of each protection rod 6, second slide blocks 8 are connected to the middle parts of the connecting, be provided with second slide rail 10 in the inboard vertical direction of crane 9, the inside slip of second slide rail 10 second slider 8, crane 9 downside are provided with the fixed plate, and crane 9's upper end is fixed with horizontal plate 14, and 14 upsides of horizontal plate are provided with reel 15, the outside winding of reel 15 has haulage rope 13, and haulage rope 13 runs through horizontal plate 14 back and connects second slider 8, 15 left and right sides symmetries of reel are provided with reel support 16, are connected with axis of rotation 17 between two reel 15, the right side of reel 15 on template 1 right side is connected with motor band-type brake 18, and motor band-type brake 18 right side is connected with motor 19.
In order to realize the detachable connection between the first slide rail 2 and the formwork 1, in this embodiment, preferably, the first slide rail 2 and the formwork 1 are connected by bolts.
In order to stabilize the supporting frame 4, in this embodiment, it is preferable that the number of the connecting rods 42 connected between the adjacent supporting rods 41 is two, three or four.
In order to ensure that the supporting frame 4 is in a horizontal state during lifting, in this embodiment, preferably, the supporting rod 41 is horizontally disposed, and one end of the supporting rod 41 close to the formwork 1 is perpendicular to the formwork 1.
In order to stabilize the lifting frame 9 and ensure that the supporting frame 4 can be lifted stably, in the embodiment, preferably, the front side, the rear side and the left side of the lower part of the lifting frame 9 on the left side of the formwork 1 and the front side, the rear side and the right side of the lower part of the lifting frame 9 on the right side of the formwork 1 are all provided with inclined brackets 12.
In order to enable the hauling cable 13 to better haul and lift the support frame 4, in this embodiment, the hauling cable 13 is preferably a steel wire rope.
In order to support the rotation of the winding drum 15, in the present embodiment, it is preferable that a rotation rod is connected between the winding drum 15 and the winding drum support 16, and both ends of the rotation rod are connected with a bearing seat for supporting the rotation thereof.
The utility model discloses a theory of operation: in the process of cylindrical pier construction, the first slide rails 2 are arranged on the front side, the rear side, the left side and the right side of the formwork 1 of each layer, meanwhile, when the cylindrical pier construction is carried out, the first slide rails 2 of each layer are mutually connected in the vertical direction, then the first slide rails 2 of each layer are fixed on the formwork 1 through bolts, after the first slide rails are fixed, the lifting frames 9 are arranged on two sides of the formwork 1, after a power supply of the motor 19 is turned on, the motor 19 drives the winding drums 15 on the left side and the right side above the formwork 1 to synchronously rotate through the rotating shaft 17, the second slide block 8 is pulled by the traction ropes 13 outside the winding drums 15, the second slide block 8 slides inside the second slide rail 10, meanwhile, the second slide block 8 drives the support frame 4 to lift along the direction of the second slide rail 10, the protection rods 6 and the protection net 7 are arranged above the outer side of the support frame 4, constructors inside can be protected, be provided with fixed plate 11 and tilt bracket 12 at the downside of crane 9, can avoid crane 9 to take place the slope to increase crane 9's security performance, motor 19 left side is connected with motor band-type brake 18, can be when motor 19 stops operating, lock motor 19, thereby avoid support frame 4 to descend suddenly under the combined action of dead weight and constructor gravity, increased the utility model discloses a practicality is simultaneously the utility model discloses need not to build the scaffold frame when the construction, also need not to build the stair of crawling, thereby practiced thrift construction material, practiced thrift the amount of labour simultaneously, shortened construction cycle.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (7)

1. The utility model provides a bridge cylinder mound construction platform, establishes the template in the outside of cylinder mound including the cover, its characterized in that: the template is formed by connecting a plurality of layers, the front side, the rear side, the left side and the right side of each layer of template are connected with first slide rails, the first slide rails are mutually connected in the vertical direction, a first slide block slides in the first slide rails, the outer side of the first slide block is connected with a support frame, the support frame comprises support rods and connecting rods, a plurality of connecting rods are connected between the adjacent support rods, a support plate is arranged on the upper side of the support frame, a protective rod is fixed on the upper side of one end of each support rod, which is far away from the template, a protective net is arranged on the outer side of each protective rod, a second slide block is connected in the middle of each connecting rod on the left side and the right side of the support frame, lifting frames are symmetrically arranged on the left side and the right side of each lifting frame, a second slide rail is arranged in the vertical, the horizontal plate upside is provided with the reel, the outside winding of reel has the haulage rope, and the haulage rope runs through the horizontal plate back and connects the second slider, the reel left and right sides symmetry is provided with the reel support, is connected with the axis of rotation between two reels, the right side of the reel on template right side is connected with the motor band-type brake, and the motor band-type brake right side is connected with the motor.
2. The bridge cylinder pier construction platform of claim 1, wherein: the first sliding rail is connected with the template through a bolt.
3. The bridge cylinder pier construction platform of claim 1, wherein: the number of the connecting rods connected between the adjacent supporting rods is two, three or four.
4. The bridge cylinder pier construction platform of claim 1, wherein: the supporting rods are horizontally arranged, and one ends of the supporting rods, which are close to the templates, are perpendicular to the templates.
5. The bridge cylinder pier construction platform of claim 1, wherein: the front side, the rear side and the left side of the lower part of the template left side lifting frame and the front side, the rear side and the right side of the lower part of the template right side lifting frame are all provided with inclined supports.
6. The bridge cylinder pier construction platform of claim 1, wherein: the hauling cable is a steel wire rope.
7. The bridge cylinder pier construction platform of claim 1, wherein: a rotating rod is connected between the winding drum and the winding drum bracket, and two ends of the rotating rod are connected with a shaft base for supporting the rotating rod.
CN201921267569.9U 2019-08-07 2019-08-07 Bridge cylinder mound construction platform Active CN210766416U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921267569.9U CN210766416U (en) 2019-08-07 2019-08-07 Bridge cylinder mound construction platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921267569.9U CN210766416U (en) 2019-08-07 2019-08-07 Bridge cylinder mound construction platform

Publications (1)

Publication Number Publication Date
CN210766416U true CN210766416U (en) 2020-06-16

Family

ID=71057671

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921267569.9U Active CN210766416U (en) 2019-08-07 2019-08-07 Bridge cylinder mound construction platform

Country Status (1)

Country Link
CN (1) CN210766416U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113356078A (en) * 2021-07-07 2021-09-07 甘肃路桥建设集团有限公司 Bridge pier column reinforcement rack

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113356078A (en) * 2021-07-07 2021-09-07 甘肃路桥建设集团有限公司 Bridge pier column reinforcement rack

Similar Documents

Publication Publication Date Title
CN101514586B (en) Hanger rail type electric hanging boat and construction method thereof
CN103306199B (en) Mounting method of bottom width overhaul hanging basket of bridge
CN102146660A (en) Installation methods of cross-arch-rib gantry crane and butterfly arch bridge space structure system
CN107100074A (en) A kind of lower bearing arch bridge concrete bridge deck construction method
CN215756065U (en) Quick hoist device of construction is contained to prefabricated box of bridge
CN108412204A (en) The rack construction of live building 3D printer
CN105839543A (en) High bridge pier self-lifting outer frame over-form construction technology
CN210766416U (en) Bridge cylinder mound construction platform
CN208844424U (en) Multifunctional assembled construction trolley
CN203159089U (en) Telescopic lifting platform for tower crane in cylinder wall construction
CN110820602A (en) Single-segment box girder bridge girder erection machine and operation method thereof
CN202031029U (en) Cross-arch rib gantry crane
CN207512610U (en) A kind of assembled bridge pier construction operation platform
CN103306218A (en) Bottom width overhaul hanging basket of bridge
CN203049587U (en) Multifunctional concrete storehouse surface placing boom
CN1048065C (en) Method and equipment for construction of concrete cylinder
CN203755173U (en) Formwork device used for hydraulic climbing of bridge high pier
CN213417588U (en) Bridge bottom surface construction platform
CN213171212U (en) A hoisting apparatus for building engineering
CN212426741U (en) Movable hanging basket suitable for high-altitude operation
CN201362571Y (en) Equipment of cross beam for hoisting arch-first and girder-late tied bars arch bridge
CN114108446A (en) High-speed railway stay cable bridge structure and construction method
CN203393632U (en) Movable formwork device for negative bending moment tension of precast T-beam flange plate
CN109203218B (en) Prefabricated T roof beam concrete placement protection canopy of railway
CN203452004U (en) Bottom width overhaul hanging basket of bridge

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant