CN210659701U - Pre-buried antiseep of building window frame attaches frame structure - Google Patents

Pre-buried antiseep of building window frame attaches frame structure Download PDF

Info

Publication number
CN210659701U
CN210659701U CN201921367779.5U CN201921367779U CN210659701U CN 210659701 U CN210659701 U CN 210659701U CN 201921367779 U CN201921367779 U CN 201921367779U CN 210659701 U CN210659701 U CN 210659701U
Authority
CN
China
Prior art keywords
window frame
buried
antiseep
mounting
frame structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921367779.5U
Other languages
Chinese (zh)
Inventor
李骏毅
唐颖
徐林
张智
高峰
李琼霞
李修富
张泽华
李倩
龚立
王梓丞
季超
李畅
郑耀华
李诗韬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Jiangong No11 Building Engineering Co ltd
Chongqing Construction Engineering Group Co Ltd
Original Assignee
Chongqing Jiangong No11 Building Engineering Co ltd
Chongqing Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Jiangong No11 Building Engineering Co ltd, Chongqing Construction Engineering Group Co Ltd filed Critical Chongqing Jiangong No11 Building Engineering Co ltd
Priority to CN201921367779.5U priority Critical patent/CN210659701U/en
Application granted granted Critical
Publication of CN210659701U publication Critical patent/CN210659701U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Door And Window Frames Mounted To Openings (AREA)

Abstract

The utility model provides a pre-buried antiseep attaches frame structure of building window frame, including the mounting, it is pre-buried in the concrete wall, one side of the mounting exposes with the concrete wall is used for being connected with the window frame outward; and the connecting piece is connected with one surface of the fixing piece, which is far away from the window frame. The window frame is direct to be connected with pre-buried mounting, and the distance of being connected between window frame and the mounting can be less than 5mm, consequently can directly beat and glue the processing, need not the cement mortar crack to can improve window frame seepage problem effectively.

Description

Pre-buried antiseep of building window frame attaches frame structure
Technical Field
The utility model relates to a construction field, concretely relates to pre-buried antiseep of building window frame attaches frame structure.
Background
In the field of buildings, the problem of leakage of a window frame caused by difficult seam plugging or improper seam plugging is always a common quality problem which is difficult to solve, and is also one of the quality problems which are much complained by owners. The traditional window frame mounting mode is that the window frame begins to be installed after the building entrance to a cave is handled and finishes, and the window frame can leave the gap about 3cm because of the irregularity of window entrance to a cave construction dimension at the in-process of installation, and this gap needs to carry out the secondary caulking joint with cement mortar and handles, and the processing procedure is troublesome, and the caulking joint department also can cause the seepage because of handling the mistake. Although the method can control the installation quality of the window to a certain extent, the method still has the defect of large leakage. The quality of its caulking has very big artificial nature, and the caulking degree of difficulty is big, can cause the construction difficulty to influence the construction progress, and the seepage problem that leads to the fact also can increase the maintenance cost in later stage. The above problems are problems that the art needs to solve.
SUMMERY OF THE UTILITY MODEL
The to-be-solved technical problem of the utility model is to provide a pre-buried antiseep of building window frame attaches frame structure that can effectively improve the seepage problem.
In order to solve the technical problem, the utility model provides a scheme is: a pre-embedded anti-seepage attached frame structure of a building window frame comprises a fixing piece, wherein the fixing piece is pre-embedded in a concrete wall body, and one surface of the fixing piece is exposed out of the concrete wall body and is used for being connected with the window frame; and
and the connecting piece is connected with one surface of the fixing piece, which is far away from the window frame.
Further, the method comprises the following steps: the template is detachably connected with the top of the fixing piece.
Further, the method comprises the following steps: the template is made of aluminum.
Further, the method comprises the following steps: the connecting piece comprises a connecting portion, the connecting portion is connected with the bottom of the fixing piece, and embedding portions gradually far away from the fixing piece are arranged on two sides of the connecting portion.
Further, the method comprises the following steps: the fixing piece comprises a piece body, a groove is formed in the center of the top of the piece body, a thread groove is formed in the groove, and thread grooves corresponding to the fixing piece are formed in the template and the window frame.
Further, the method comprises the following steps: the fixing piece is made of a PVC steel common body material.
The utility model has the advantages that: the window frame is direct to be connected with pre-buried mounting, and the distance of being connected between window frame and the mounting can be less than 5mm, consequently can directly beat and glue the processing, need not the cement mortar crack to can improve window frame seepage problem effectively.
Drawings
FIG. 1 is a general schematic of the present application;
FIG. 2 is a schematic view of a template being supported;
FIG. 3 is a schematic view of the present application in connection with a window frame;
FIG. 4 is a schematic view of the present application during glue application;
the reference numbers are as follows: the concrete window comprises a fixing piece 1, a connecting piece 2, a concrete wall 3, a template 4, a window frame 5, foaming glue 6 and sealant 7.
Detailed Description
The present invention is further described with reference to the following drawings and specific embodiments so that those skilled in the art can better understand the present invention and can implement the present invention, but the embodiments are not to be construed as limiting the present invention.
As shown in fig. 1 to 4, an auxiliary frame structure for preventing leakage of a building window frame 5 is pre-embedded, which includes a fixing member 1, which is pre-embedded in a concrete wall 3, one surface of the fixing member 1 is exposed outside the concrete wall 3, specifically, a hole is opened in the concrete wall 3 for installing the window frame 5, wherein one surface of the fixing member 1 faces the inside of the hole for connecting with the window frame 5. The bottom of the fixing member 1 is also connected to a connecting member 2.
This application is through 5 marginal concrete placement in-process pre-buried mountings 1 in advance of cast-in-place structure window frame, and during 5 installations of later stage window frame, directly be connected window frame 5 with pre-buried attaches frame mounting 1 in advance, and this kind of structure can effectual reduction window frame 5 and the clearance between the building entrance to a cave, can cover clearance control usually within 5mm to can directly adopt between window frame 5 and mounting 1 and beat to glue the processing, play effectual antiseep and fixed action. Wherein, the fixing piece 1 is made of a PVC steel common body material.
As shown in fig. 2, in order to facilitate pre-embedding processing of the fixing member 1, the fixing member further includes a template 4, wherein the template 4 is detachably connected to the top of the fixing member 1.
In order to facilitate understanding of the present application, the working process and the construction method of the present application are described below, as shown in fig. 2 to 4, first, the connecting member 2 is sequentially formed by reserving the position of the fixing member 1 when the wall is poured, and connecting one side of the fixing member 1 with the formwork 4, preferably, the formwork 4 is made of a high-rigidity material to form the arching deformation of the formwork 4, for example, the formwork 4 is made of an aluminum material, after the fixing member 1 and the formwork 4 are fixed, the fixing member 1 is fixedly placed in the reserved position in the wall by erecting the formwork 4, wherein, in order to make the fixing member 1 fixed firmly after the processing, the connecting member 2 is provided, the connecting member 2 is opened in a splayed shape, specifically, the connecting member 2 includes a connecting portion connected with the bottom of the fixing member 1, and two sides of the connecting portion are provided with an embedding portion gradually distant from the fixing, in order to guarantee its can with the better integration of concrete to fix mounting 1 better after pre-buried, then can pour the entrance to a cave of mounting 1 after establishing template 4, pour and accomplish pre-buried mounting 1 in concrete wall 3, remove the mould this moment, be connected window frame 5 and mounting 1, this moment to window frame 5 and mounting 1's gap intussuseption foaming adhesive 6 can, then outside the notch fill in the sealed glue 7 of caulking, accomplish processing.
This application compares with 5 crack processing method of traditional window frame, and fixed pre-buried in concrete wall 3 in this application pours simultaneously with major structure, need not cement mortar crack when making 5 installations of window frame, has reduced because of the produced seepage hidden danger of crack problem.
The window frame 5 is directly connected with the pre-buried mounting 1, and the connection distance between the window frame 5 and the mounting 1 can be less than 5mm, so that the gluing treatment can be directly carried out, and the operation is more convenient and fast.
In addition, because the window frame 5 does not need to be directly glued by cement mortar for caulking, the indoor wet operation caused by caulking during the construction of the window frame 5 is reduced, and the on-site environment is ensured.
In this application, mounting 1 is provided with the recess including the body, body top central authorities, is provided with the thread groove in the recess, is provided with the thread groove that corresponds with mounting 1 on template 4 and the window frame 5, and template 4 passes through threaded connection with setting element top recess, and template 4 and window frame 5 all pass through threaded connection with mounting 1, and wherein, set up the thread groove in the recess and can further reduce the clearance between window frame 5 and the mounting 1 when connecting window frame 5.
Finally, although the present invention has been described in detail with reference to the preferred embodiments, it should be understood by those skilled in the art that the present invention can be modified or replaced by other means without departing from the spirit and scope of the present invention, which should be construed as limited only by the appended claims.

Claims (6)

1. The pre-embedded anti-seepage auxiliary frame structure of the building window frame is characterized by comprising a fixing piece, wherein the fixing piece is pre-embedded in a concrete wall body, and one surface of the fixing piece is exposed outside the concrete wall body and is used for being connected with the window frame; and
and the connecting piece is connected with one surface of the fixing piece, which is far away from the window frame.
2. The pre-buried antiseep attached frame structure of building window frame of claim 1, further comprising a template, wherein said template is detachably connected with the top of said fixing member.
3. The pre-buried antiseep attached frame structure of building window frame of claim 2, wherein said template is made of aluminum.
4. The pre-buried antiseep attached frame structure of building window frame of claim 1, wherein, said connecting piece includes a connecting portion, said connecting portion is connected with the bottom of the fixing piece, and two sides of said connecting portion are provided with an embedding portion gradually far away from said fixing piece.
5. A pre-buried antiseep attached frame structure of building window frame as claimed in claim 1, wherein said fixing member comprises a body, a groove is provided at the center of the top of said body, a thread groove is provided in said groove, and thread grooves corresponding to said fixing member are provided on said form and said window frame.
6. The pre-buried antiseep attached frame structure of building window frame of claim 1, wherein said fixing member is made of PVC steel.
CN201921367779.5U 2019-08-22 2019-08-22 Pre-buried antiseep of building window frame attaches frame structure Expired - Fee Related CN210659701U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921367779.5U CN210659701U (en) 2019-08-22 2019-08-22 Pre-buried antiseep of building window frame attaches frame structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921367779.5U CN210659701U (en) 2019-08-22 2019-08-22 Pre-buried antiseep of building window frame attaches frame structure

Publications (1)

Publication Number Publication Date
CN210659701U true CN210659701U (en) 2020-06-02

Family

ID=70837093

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921367779.5U Expired - Fee Related CN210659701U (en) 2019-08-22 2019-08-22 Pre-buried antiseep of building window frame attaches frame structure

Country Status (1)

Country Link
CN (1) CN210659701U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114033276A (en) * 2021-11-22 2022-02-11 上海开捷门窗幕墙工程有限公司 Door and window frame mounting system and door and window system
CN114033275A (en) * 2021-11-22 2022-02-11 上海开捷门窗幕墙工程有限公司 Door and window frame mounting system and door and window system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114033276A (en) * 2021-11-22 2022-02-11 上海开捷门窗幕墙工程有限公司 Door and window frame mounting system and door and window system
CN114033275A (en) * 2021-11-22 2022-02-11 上海开捷门窗幕墙工程有限公司 Door and window frame mounting system and door and window system

Similar Documents

Publication Publication Date Title
CN210659701U (en) Pre-buried antiseep of building window frame attaches frame structure
CN205841994U (en) A kind of new indoor drainage system combined water proof pipe collar
AU2018229509B2 (en) Shower hob apparatus
CN109322505A (en) A kind of roofing reserved opening concrete plugging device and preparation method thereof
CN107196257B (en) House wiring structure and wiring method
CN112942600A (en) Construction device and construction method for improving construction quality of post-cast joint concrete of prefabricated laminated slab
CN104975614B (en) Shaped steel combination formula single side formwork strengthening construction engineering method
CN107269001A (en) Concealed distribution box is with the whole construction method poured of concrete wall structure
CN214784228U (en) Prefabricated plate advanced closing structure of outer wall post-cast strip
CN110004974A (en) A kind of prefabricated waterproof Retaining wall plate structure and its construction method
CN206973068U (en) A kind of through-flooring is pre-buried to use the pre-buried adapter of flexible interface adjusting center
CN110552378A (en) Underground space roof subsides post-cast strip and seals structure in advance
CN112709431A (en) Material conveying port device with embedded steel bars and method for presetting material conveying port
CN204551694U (en) A kind of pre-buried type balcony floor drain
CN103883108B (en) Easy house kitchen toilet exhaust passage construction method of installation
CN109518769A (en) A kind of method and structure using PVC waterstop joint installation sewer pipe
CN107989205A (en) The plugging system of toilet bath room floor sewer pipe preformed hole
CN201428342Y (en) Aluminum alloy window
CN209891256U (en) Basement outer wall post-cast strip structure
CN107842199B (en) A kind of preforming combination tool of mattess partitioning slot and its built-in process
CN207813039U (en) A kind of preforming combination tool of mattess partitioning slot
CN110593560A (en) Concrete wall column inner wire box installation method
KR101834770B1 (en) Precast concrete type housing water block wall and construction method thereof
CN105649331B (en) A kind of interior standpipe water-leakage construction method
CN115182580B (en) Water pipe well floor slab hanging die and water pipe well post-pouring construction method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200602