CN107842199B - A kind of preforming combination tool of mattess partitioning slot and its built-in process - Google Patents

A kind of preforming combination tool of mattess partitioning slot and its built-in process Download PDF

Info

Publication number
CN107842199B
CN107842199B CN201711297711.XA CN201711297711A CN107842199B CN 107842199 B CN107842199 B CN 107842199B CN 201711297711 A CN201711297711 A CN 201711297711A CN 107842199 B CN107842199 B CN 107842199B
Authority
CN
China
Prior art keywords
steel plate
segmentation
bolt
slide channel
segmentation steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201711297711.XA
Other languages
Chinese (zh)
Other versions
CN107842199A (en
Inventor
盛景
吴晓明
马一方
董兆鹏
张昊
田长平
金磊
白珂
程瑶
樊星
贾业鑫
崔超群
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Engineering Division Corp Ltd
Sixth Construction Co Ltd of China Construction Fourth Engineering Division Co Ltd
Original Assignee
China Construction Fourth Engineering Division Corp Ltd
Sixth Construction Co Ltd of China Construction Fourth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fourth Engineering Division Corp Ltd, Sixth Construction Co Ltd of China Construction Fourth Engineering Division Co Ltd filed Critical China Construction Fourth Engineering Division Corp Ltd
Priority to CN201711297711.XA priority Critical patent/CN107842199B/en
Publication of CN107842199A publication Critical patent/CN107842199A/en
Application granted granted Critical
Publication of CN107842199B publication Critical patent/CN107842199B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The present invention discloses a kind of preforming combination tool of mattess partitioning slot and its built-in process, the tool by shoring steel plate, segmentation steel plate, lifting hole, bolt slide channel, bolt, rope form;Wherein, segmentation steel plate one end top is cut into a bolt slide channel along its length;The other end shored steel plate and be welded on segmentation steel plate;In the one lifting hole of cutting on the segmentation steel plate at bolt slide channel;The bolt slide channel of two blocks of segmentation steel plates is bonded to each other, and two bolts are installed in slideway;Rope is put between the lifting hole of two blocks of segmentation steel plates.Construction method of the present invention is simple, easy to operate, has visibility and controllability, works well;The present invention can effectively reduce the problem of Cracking on ground at door opening, and this approach reduces the difficulty of construction of worker, the perception degree on increased ground has biggish development prospect.

Description

A kind of preforming combination tool of mattess partitioning slot and its built-in process
Technical field
The invention belongs to the realm of building construction, are related to one kind and are embedded in door opening bottom, energy before mattess pours Mattess irregular cracks will be split and reduces by enough playing inside and outside the ground of door opening bottom, guarantee ground impression quality Construction tool, the preforming combination tool of specifically a kind of mattess partitioning slot and its built-in process.
Background technique
Nowadays construction is substantially to construct together at traditional flooring hole, is not divided using ground, in ground coagulation Soil gradually in upper intensity process, causes concrete surface easily to shrink, especially door opening position, it may appear that many cracks, In Later period takes the other materials such as brushing interfacial agents for crack, but the time is slightly long, and ground there is also crack, repair in this way It mends, will cause the later period a large amount of manpower and material resources of investment to repair, generate the maintenance cost of great number.
Current a large amount of residential buildings, office occupancy and basement use mattess, convenient, construction that mattess is drawn materials Technical maturity, but the concrete cracking problem at indoor mattess doorway is difficult to solve always, from ground construction quality and Many troubles are also resulted in later period maintenance in terms of perception.
Summary of the invention
In order to improve the perception degree of existing building flooring, the crack of mattess is reduced, the present invention provides one Kind design is unique, novel in design, structure is simple, it is cheap, can be used in turn, assemble and disassemble easy, concrete ground easy to operate Partitioning slot preforming combination tool in face is particularly suitable for the building concrete ground construction scene currently widely used in China and pushes away It is wide to use.
Another object of the present invention is to provide a kind of mattess partitioning slot combination tool built-in process, by using The built-in process can make ground at door opening be not likely to produce crack, reduce the closure of later period ground fractures, make the perception on ground Effect is more preferable.
The purpose of the present invention can be achieved through the following technical solutions:
A kind of preforming combination tool of mattess partitioning slot, the tool by shore steel plate, segmentation steel plate, lifting hole, Bolt slide channel, bolt, rope composition;Wherein, segmentation steel plate one end top is cut into a bolt slide channel along its length; The other end shored steel plate and be welded on segmentation steel plate;In one lifting of cutting on the segmentation steel plate at bolt slide channel Hole;The bolt slide channel of two blocks of segmentation steel plates is bonded to each other, and two bolts are installed in slideway;Two pieces divide mentioning for steel plate Rope is put between pulling eye.
The segmentation steel plate specification is 200mm high, 3mm thick;The long 300mm of bolt slide channel, high 15mm;The top Support steel plate specification is 60*60*3;The lifting bore dia is 15mm.
A kind of built-in process of the preforming combination tool of mattess partitioning slot, this method includes following construction procedure: Special segmentation steel plate is placed in the middle part of door opening first, then unclamps two bolts in slideway in the middle part of steel plate, will be divided It cuts the steel plate of shoring that steel plate two sides are laterally arranged to hold out against on the side wall of door opening two sides, then fixing bolt, finally carries out ground Construction;After carrying out intensity on ground, by segmentation steel plate extraction.
Special segmentation steel plate includes two independent segmentation steel plates and two bolts;Each segmentation steel plate one end cutting Equipped with bolt slide channel, the bolt slide channel of two segmentation steel plates is merged, and is tightened finally by two bolts.
The top of each segmentation steel plate is cut into a hole formation lifting hole, uses steel wire bundle between two lifting holes Connection forms rope.
Divide steel plate and uses 3mm thick steel plate;Steel plate is shored using 100*100mm steel plate;In segmentation steel plate bottom winding one Enclose plastic adhesive tape.
The entire length of segmentation steel plate is first determined according to door opening size, then carries out the cutting of bolt slide channel, divides steel plate It presses closer and shores steel plate in door opening, while guaranteeing that dividing steel plate is above the ground level 20mm.
Beneficial effects of the present invention: 1, segmentation steel plate in ground all uses 3mm thick steel plate to make, the stress in construction, no As for deformation;2, make it flexible modulation size with double bolts on ground segmentation steel plate, equally can tightly fix door opening side wall On, moreover it is possible to continuous turnover;3, steel plate is shored in setting on the outside of ground segmentation steel plate, is increased stress section, is made its hard in abutment.
For the present invention when progress ground pours, worker need to only guarantee that photoreceiver device does not touch segmentation steel plate, just when receiving light It can guarantee its crack and segmentation steel plate with wide;Construction method of the present invention is simple, easy to operate, has visibility and controllability, effect Fruit is good;The present invention can effectively reduce the problem of Cracking on ground at door opening, this approach reduces the difficulty of construction of worker, The perception degree on increased ground has biggish development prospect.
Detailed description of the invention
In order to facilitate the understanding of those skilled in the art, the present invention will be further described below with reference to the drawings.
Fig. 1 is a kind of preforming combination tool main view of mattess partitioning slot of the present invention;
Fig. 2 is a kind of preforming combination tool top view of mattess partitioning slot of the present invention;
Fig. 3 is a kind of preforming combination tool structure partial figure of mattess partitioning slot of the present invention.
Specific embodiment
Technical solution of the present invention is clearly and completely described below in conjunction with embodiment, it is clear that described reality Applying example is only a part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, this field is general Logical technical staff all other embodiment obtained without creative efforts belongs to what the present invention protected Range.
A kind of preforming combination tool of mattess partitioning slot, referring to Fig. 1-3, the tool is by shoring steel plate 1, segmentation steel Plate 2, lifting hole 3, bolt slide channel 4, bolt 5, rope 6 form;
Using the segmentation steel plate 2 of two pieces of identical (be less than door opening) size 200mm high, 3mm thickness, portion (edge on one end Length direction) it is cut into a long 300mm, the bolt slide channel 4 of high 15mm, then be welded on the steel plate 1 of shoring of 60*60*3 specification The other end for dividing steel plate 2, forms overall skeleton;A diameter is being cut on the segmentation steel plate at bolt slide channel 4 For the lifting hole 3 of 15mm;
The bolt slide channel 4 of two blocks of segmentation steel plates 2 is bonded to each other, and two bolts 5 are installed in slideway;Two blocks of segmentation steel plates Rope 6 is put between 2 lifting hole 3, on ground when casting concrete, after segmentation steel plate is fixed according to door opening size, Stepped up with double bolts 5.
Segmentation steel plate just separates ground inside and outside door, avoids generating a large amount of cracks at door opening.Divide steel plate, lifting Rope, bolt nut, which design, selects steel, makes it to bear very big stress, is unlikely to deform, is less likely to be damaged steel tool, can The steel plate of dismounting, bolt by ground segmentation steel plate can it is easy to disassemble, can repeatedly be used in turn.Two panels segmentation steel plate can arbitrarily be torn open It unloads, by the design that size assembles, various sizes of doorway can be met.Steel plate is shored in setting on the outside of segmentation steel plate, is increased stress and is cut Face makes its hard in abutment.
Embodiment:
It chooses two blocks of steel plates and is made into segmentation steel plate, mattess is first embedded in door opening bottom before pouring, pours on ground When building concrete, after segmentation steel plate is fixed according to door opening size, stepped up with double bolts.It can be with after mattess pours It is pulled out, is used in turn with rope.
A kind of built-in process of the preforming combination tool of mattess partitioning slot, including following construction procedure: first will Special segmentation steel plate is placed in the middle part of door opening, is then unclamped two bolts in slideway in the middle part of steel plate, will be divided steel plate What two sides were laterally arranged, which shore steel plate, holds out against on the side wall of door opening two sides, then fixing bolt, finally carries out the construction on ground; After carrying out intensity on ground, by segmentation steel plate extraction.
Referring to Fig. 1-3, special segmentation steel plate includes two independent segmentation steel plates 2 and two bolts 5;Each segmentation steel The cutting of 2 one end of plate is equipped with bolt slide channel 4, and the bolt slide channel 4 of two segmentation steel plates 2 merges, finally by two spiral shells Bolt 5 is tightened, and makes it when pouring ground, should not be loosened;
The top of each segmentation steel plate 2 is cut into a hole formation lifting hole 3, uses steel wire between two lifting holes 3 Binding connection forms rope 6, guarantees that the later period is easy to take out;
Divide steel plate 2 and uses 3mm thick steel plate;It shores steel plate 1 and uses 100*100mm steel plate;It is wound in segmentation 2 bottom of steel plate One circle plastic adhesive tape.
The entire length of segmentation steel plate is first determined according to door opening size, then carries out the cutting of bolt slide channel, makes to divide steel Plate presses closer in door opening, while guaranteeing that dividing steel plate is above the ground level 20mm.
It is scalable to divide steel plate, various sizes of door opening can be directed to, it is solid using double bolts after door opening size determines It is fixed, it can construct.
Segmentation steel plate is relatively thin, and partition seam is also relatively thin, and construction in later period finishes, and can not have to be blocked, water is used if blocking Mud is filled.
Segmentation steel plate is more suitable for the ground there are height difference, and segmentation steel plate, will not be to periphery concrete when taking out in the later period Generate destruction.
Partition seam dividing method in ground of the present invention greatly reduces the cracking situation on ground at door opening, makes ground perception Effect is more preferable, reduces later period artificial large surface mending ground fractures, and easy to operate.Simultaneously gap it is smaller, the later period only It needs to be blocked with interfacial agents.
Present invention disclosed above preferred embodiment is only intended to help to illustrate the present invention.There is no detailed for preferred embodiment All details are described, are not limited the invention to the specific embodiments described.Obviously, according to the content of this specification, It can make many modifications and variations.These embodiments are chosen and specifically described to this specification, is in order to better explain the present invention Principle and practical application, so that skilled artisan be enable to better understand and utilize the present invention.The present invention is only It is limited by claims and its full scope and equivalent.

Claims (3)

1. a kind of built-in process of the preforming combination tool of mattess partitioning slot, the mattess partitioning slot are preforming Combination tool is by shoring steel plate (1), segmentation steel plate (2), lifting hole (3), bolt slide channel (4), bolt (5), rope (6) group At;Wherein, segmentation steel plate (2) one end top is cut into a bolt slide channel (4) along its length;It is described to shore steel plate (1) It is welded on the other end of segmentation steel plate (2);In one lifting hole (3) of cutting on the segmentation steel plate at bolt slide channel (4);Point It cuts steel plate (2) and amounts to two pieces, the bolt slide channels (4) of two pieces of segmentations steel plate (2) are bonded to each other, and install two in slideway Bolt (5);Rope (6) are cased between the lifting hole (3) of two pieces of segmentations steel plate (2);Segmentation steel plate (2) specification is 200mm high, 3mm are thick;Bolt slide channel (4) the long 300mm, high 15mm;The lifting hole (3) diameter is 15mm;Its feature exists In this method includes following construction procedure: segmentation steel plate being placed in the middle part of door opening first, then by two in steel plate slideway A bolt unclamps, and will divide the steel plate of shoring that steel plate two sides are laterally arranged and holds out against on the side wall of door opening two sides, then fixed spiral shell Bolt finally carries out the construction on ground;After carrying out intensity on ground, by segmentation steel plate extraction.
2. built-in process according to claim 1, which is characterized in that segmentation steel plate uses 3mm thick steel plate;Steel plate is shored to adopt With 100 × 100mm steel plate;In one circle plastic adhesive tape of segmentation steel plate bottom winding.
3. built-in process according to claim 1, which is characterized in that first determine the whole of segmentation steel plate according to door opening size Body length, then the cutting of bolt slide channel is carried out, segmentation steel plate, which presses closer, shores steel plate in door opening, while guaranteeing to divide steel plate height In ground 20mm.
CN201711297711.XA 2017-12-08 2017-12-08 A kind of preforming combination tool of mattess partitioning slot and its built-in process Expired - Fee Related CN107842199B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711297711.XA CN107842199B (en) 2017-12-08 2017-12-08 A kind of preforming combination tool of mattess partitioning slot and its built-in process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711297711.XA CN107842199B (en) 2017-12-08 2017-12-08 A kind of preforming combination tool of mattess partitioning slot and its built-in process

Publications (2)

Publication Number Publication Date
CN107842199A CN107842199A (en) 2018-03-27
CN107842199B true CN107842199B (en) 2019-11-22

Family

ID=61663694

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711297711.XA Expired - Fee Related CN107842199B (en) 2017-12-08 2017-12-08 A kind of preforming combination tool of mattess partitioning slot and its built-in process

Country Status (1)

Country Link
CN (1) CN107842199B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110295733B (en) * 2019-08-01 2024-01-23 北京城建六建设集团有限公司 Partition seam die, partition seam structure and construction method of partition seam die

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100396859C (en) * 2007-07-19 2008-06-25 河北建设集团有限公司 Pouring concrete separating crack structure and construction method thereof
CN201180366Y (en) * 2008-03-14 2009-01-14 中建三局建设工程股份有限公司 Ultra-large area concrete construction surface construction and partition seam remaining construction apparatus
CN103114728B (en) * 2013-03-04 2014-01-29 温州建设集团有限公司 Grid construction method of large area cement wear-resisting floor
CN106193545A (en) * 2016-09-20 2016-12-07 中铁建设集团有限公司 Floating screed partitioning slot molding external member and floor leveling layer construction method
CN207813039U (en) * 2017-12-08 2018-09-04 中建四局第六建筑工程有限公司 A kind of preforming combination tool of mattess partitioning slot

Also Published As

Publication number Publication date
CN107842199A (en) 2018-03-27

Similar Documents

Publication Publication Date Title
CN104088254B (en) Pressure-bearing reinforced concrete structure leakage repair device and construction method thereof
CN206815838U (en) A kind of easy-to-mount mortar leakage prevention sizing mould bases
CN103498486B (en) A kind of sleeve pipe that adopts implements the method for shutoff to ater-casting precipitation pipe well
CN104947719A (en) Basement roof post-cast strip hanging support formwork structure and post-cast strip construction method thereof
CN103485537A (en) Construction method and structure of embedded reinforcement of super high-rise horizontal secondary structure
CN102561402A (en) Treatment method for construction joint between top plate and wall of individual underground civil air defense project constructed by covered top-down excavation method
CN203947772U (en) A kind of kitchen and toilet draining main riser service sleeve
CN208792737U (en) For hanging the detachable connecting part of external platform hanging girder steel
CN107842199B (en) A kind of preforming combination tool of mattess partitioning slot and its built-in process
CN207376637U (en) A kind of open caisson seepage-proof structure
CN114482135A (en) Advanced water stop structure of basement exterior wall post-cast strip and construction method
CN210659701U (en) Pre-buried antiseep of building window frame attaches frame structure
CN207813039U (en) A kind of preforming combination tool of mattess partitioning slot
CN203977368U (en) Pressure-bearing reinforced concrete structure leakage repair device
CN208777690U (en) A kind of reserved floor sealing hole template component of drainage pipeline
CN109372541A (en) A kind of portal temporary plugging structure and its construction method suitable for shield tunnel
CN203701112U (en) Composite foundation grouting steel tube type reinforced slope
CN107100197A (en) A kind of detachable water-stop opposite-pulling screw rod erecting device of large steel moulding plate
CN103981909A (en) Rapid repair method and structure for broken foundation bolt
CN217001019U (en) Integrated device for grouting and reinforcing concrete slab and reinforced and formed floor slab
CN203514332U (en) Casing for blocking dewatering tube well of post-cast strip
CN209670134U (en) Assembled wall right angle connecting structure
CN203429798U (en) Embedded bar structure for horizontal secondary structure of super high-rise
CN110005197A (en) A kind of construction method of wall column cleanout
CN211173065U (en) Basement outer wall construction joint anti-seepage template structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: 230000 building 3, 262 Heping Road, Yaohai District, Hefei City, Anhui Province

Patentee after: No 6 Construction Co.,Ltd. of China Construction Fourth Engineering Bureau

Patentee after: CHINA CONSTRUCTION FOURTH ENGINEERING DIVISION CORP.,LTD.

Address before: No. 262, Heping Road, Yaohai District, Hefei City, Anhui Province, 230011

Patentee before: CHINA CONSTRUCTION 4TH ENGINEERING BUREAU, 6TH Co.,Ltd.

Patentee before: CHINA CONSTRUCTION FOURTH ENGINEERING DIVISION CORP.,LTD.

CP03 Change of name, title or address
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20191122

CF01 Termination of patent right due to non-payment of annual fee