CN210597016U - High-speed railway bridge floor keeps off tiny fragments of stone, coal, etc. wall shear reinforcement installation device - Google Patents

High-speed railway bridge floor keeps off tiny fragments of stone, coal, etc. wall shear reinforcement installation device Download PDF

Info

Publication number
CN210597016U
CN210597016U CN201921376648.3U CN201921376648U CN210597016U CN 210597016 U CN210597016 U CN 210597016U CN 201921376648 U CN201921376648 U CN 201921376648U CN 210597016 U CN210597016 U CN 210597016U
Authority
CN
China
Prior art keywords
shear
splint
wall
reinforcing bar
stone
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921376648.3U
Other languages
Chinese (zh)
Inventor
高伟杰
张少泊
张朋举
母旭彪
智忠磊
张力
杨志伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
No 1 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Original Assignee
No 1 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by No 1 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd filed Critical No 1 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Priority to CN201921376648.3U priority Critical patent/CN210597016U/en
Application granted granted Critical
Publication of CN210597016U publication Critical patent/CN210597016U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model belongs to a high-speed railway bridge floor keeps off tiny fragments of stone, coal, etc. wall shear reinforcement installation device, constitute by the reinforcing bar, middle splint are located between two lateral part splint on syntropy opening limit, two lateral part splint on syntropy opening limit and the middle splint on opening limit are sealed to be laid in opposite directions, the opening that each correspondence of sealed in opposite directions aligns the opening hole that forms the three confession shear connection reinforcing bar that is the interval setting and passes, three shear connection reinforcing bar's middle part is located respectively in each opening hole, three shear connection reinforcing bar's both ends are fixed as an organic whole with the reinforcing bar on the fender tiny fragments of stone, etc. wall reinforcing bar rack of corresponding portion. The utility model discloses can guarantee the breaking joint quality and arrange the fender tiny fragments of stone, coal, etc. wall of breaking joint department both sides with 3 connecting reinforcement that shear's both ends, it is fast to have simple structure, construction speed, and is of high quality, and preparation use cost is low, labour saving and time saving's advantage.

Description

High-speed railway bridge floor keeps off tiny fragments of stone, coal, etc. wall shear reinforcement installation device
Technical Field
The utility model belongs to a high-speed railway bridge floor keeps off tiny fragments of stone, coal, etc. wall shear reinforcement installation device.
Background
In the design of a post-tensioning prestressed concrete simply supported box girder of a ballasted track prefabricated on a high-speed railway at a speed of 240-250 km/h, the design requirement that 3 shear-resistant connecting steel bars are additionally arranged at the discontinuous joints of a ballasted wall of a bridge deck is met. In the prior art, the broken joint of the ballast retaining wall is constructed by taking the edges between the formworks as the width, a broken joint with the width of about 10mm can be formed after formwork removal, the width of the broken joint is difficult to control, the broken joint surface is seriously damaged after the formwork removal, and the quality is difficult to meet the requirement. And shear-resistant connecting reinforcing steel bars are not arranged between the broken joints, so that the ballast retaining wall is seriously staggered, and the overall bearing capacity is reduced. How to guarantee the quality of the broken joint and arrange the two ends of 3 shear-resistant connecting steel bars in the ballast retaining walls on the two sides of the broken joint, is a problem which needs to be solved urgently.
Disclosure of Invention
The utility model aims at providing a high-speed railway bridge floor keeps off tiny fragments of stone, coal, etc. wall shear reinforcement installation device can guarantee the broken joint quality and arrange the both ends of 3 connecting reinforcement that shear in the tiny fragments of stone, coal, etc. wall that keeps off of broken joint department both sides, has simple structure, construction speed fast, and is of high quality, makes low in use cost, labour saving and time saving's advantage.
Therefore, the utility model discloses constitute by the reinforcing bar, wherein:
shearing connecting steel bars: each shear-resistant connecting steel bar is a steel bar with the length of 650mm and the diameter of phi 20, and the steel bar is sleeved into a PVC sleeve with the diameter of 24-25 mm, and two ends of the PVC sleeve are sealed.
Side splints: the rectangular steel plate is 3mm thick, 400mm wide and 1000mm long, 3 gaps 163mm long are arranged on the long edge of one side of the rectangular steel plate at intervals, the gaps extend to the axial lead side of the rectangular steel plate, the inner ends of the gaps are semicircular, and the number of the side clamping plates is two.
A middle clamping plate: the rectangular steel plate is 4mm thick, 210mm wide and 1000mm long, 3 gaps 73mm long are arranged on the long edge of one side of the rectangular steel plate at intervals, the gaps extend to the axial lead side of the rectangular steel plate, the inner ends of the gaps are semicircular, and the middle clamping plate is one.
The middle splint is located between two lateral part splint on syntropy opening limit, two lateral part splint on syntropy opening limit and the middle splint on the opening limit are sealed to be laid in opposite directions, the opening that respectively corresponds of sealed in opposite directions aligns and forms three opening hole that supplies the shearing connecting reinforcement bar that sets up that is the interval distance and passes, the middle part of three shearing connecting reinforcement bars is located each opening hole respectively, the reinforcing bar on the both ends of three shearing connecting reinforcement bars and the fender tiny fragments of stone, etc. wall reinforcing bar rack of corresponding portion is fixed as an organic whole.
Above-mentioned structural design has realized the utility model discloses a purpose.
The utility model discloses can guarantee the breaking joint quality and arrange the fender tiny fragments of stone, coal, etc. wall of breaking joint department both sides with 3 connecting reinforcement that shear's both ends, it is fast to have simple structure, construction speed, and is of high quality, and preparation use cost is low, labour saving and time saving's advantage.
The utility model has the advantages as follows:
1. the utility model discloses can guarantee the breaking joint quality and arrange the broken joint department both sides with 3 shear connection reinforcing bar's both ends in keeping off the tiny fragments of stone, coal, etc. wall, the utility model provides a current difficult problem of construction, the broken joint width is unanimous, and the broken joint face levels after the form removal, and the quality reaches good requirement, and has 3 shear connection reinforcing bars between the broken joint, keeps off tiny fragments of stone, coal, etc. wall and does not have the dislocation, and whole bearing capacity is strong, labour saving and time saving, and construction speed is fast.
2. The utility model has the advantages of simple and reasonable design, preparation and use cost are low, adopt the old and useless steel of building site to prepare the utility model discloses.
3. The utility model discloses construction cost reduces 60 ~ 70%.
Drawings
Fig. 1 is the utility model discloses a connection reinforcing bar structure sketch map shears.
Fig. 2 is a schematic view of the structure of the lateral splint of the present invention.
Fig. 3 is a schematic view of the structure of the middle splint of the present invention.
Fig. 4 is a schematic view of the structure of the lateral part and the middle splint in use.
Fig. 5 is the utility model discloses be interrupted seam department user state structure schematic diagram at fender tiny fragments of stone, coal, etc. wall.
Detailed Description
As shown in fig. 1 to 3, a high-speed railway bridge deck ballast wall shear reinforcement installation device is composed of reinforcements 3, wherein:
shear connection reinforcing bar 1: each shear-resistant connecting steel bar is formed by sleeving a 650mm long steel bar 3 with a diameter of phi 20 into a PVC sleeve 2 with a diameter of 24-25 mm, and two ends of the PVC sleeve are sealed. The shear resistant connecting steel bars are three.
Side splint 4: the rectangular steel plate is 3mm thick, 400mm wide and 1000mm long, 3 gaps 5 which are 163mm long are arranged on the long edge of one side of the rectangular steel plate at intervals, the gaps extend to the axial lead side of the rectangular steel plate, the inner ends of the gaps are semicircular, and the number of the side clamping plates is two.
An intermediate splint 6: the rectangular steel plate is 4mm thick, 210mm wide and 1000mm long, 3 gaps 7 with the length of 73mm are arranged on the long edge of one side of the rectangular steel plate at intervals, the gaps extend to the axial lead side of the rectangular steel plate, the inner end of each gap is semicircular, and the middle clamping plate is one.
The middle splint is positioned between the two lateral splints on the same-direction opening edge, and the two lateral splints on the same-direction opening edge are closely attached to the middle splint on the opposite opening edge. And the corresponding gaps which are closely attached in opposite directions are aligned to form three gap holes 8 which are arranged at intervals and are used for the shearing-resistant connecting steel bars to pass through. The middle parts of the three shear-resistant connecting steel bars are respectively positioned in each opening hole, and the two ends of the three shear-resistant connecting steel bars are fixed (bound by iron wires at the intersection) with the steel bars 9 on the steel bar net rack of the ballast wall at the corresponding part into a whole.
As shown in FIG. 5, when the PVC sleeve pipe is used, firstly, 650mm long phi 20 shear-resistant connecting steel bars are sleeved into PVC sleeve pipes with the diameters of 24-25 mm (so as to ensure that two adjacent ballast walls stretch out and draw back), and two ends of each PVC sleeve pipe are sealed by adhesive tapes (so as to prevent slurry from entering in the concrete pouring process). The middle splint is positioned between the two lateral splints on the same-direction opening edge, and the two lateral splints on the same-direction opening edge are closely attached to the middle splint on the opposite opening edge. And the corresponding gaps which are closely attached in opposite directions are aligned to form three gap holes 8 which are arranged at intervals and are used for the shearing-resistant connecting steel bars to pass through. The middle parts of the three shear-resistant connecting steel bars are respectively positioned in each opening hole, and the two ends of the three shear-resistant connecting steel bars are fixed (bound by iron wires at the intersection) with the steel bars 9 on the steel bar net rack of the ballast wall at the corresponding part into a whole. Namely: 2 side clamping plates and middle clamping plates are installed to enable the shear-resistant connecting steel bars of the ballast retaining wall to penetrate through the clamping plate circular holes and to be fixed at the designed pre-buried positions. Then, placing a ballast retaining wall template 10, pouring concrete in a space enclosed by 2 side clamping plates and the ballast retaining wall template, taking out the middle clamping plate when the strength reaches 50% of the design strength and the template removal condition is met after the ballast retaining wall concrete is poured, and then taking out the side clamping plates, namely forming the ballast retaining wall discontinuous joints with 3 shear-resistant connecting steel bars.
In a word, the utility model discloses can guarantee the crack quality and arrange the fender tiny fragments of stone, coal, etc. wall of crack department both sides with 3 connecting reinforcement that shear's both ends, it is fast to have simple structure, construction speed, and is of high quality, and preparation use cost is low, labour saving and time saving's advantage.

Claims (4)

1. The utility model provides a high-speed railway bridge floor keeps off tiny fragments of stone, coal, etc. wall shear reinforcement installation device, comprises the reinforcing bar, its characterized in that:
shearing connecting steel bars: each shear-resistant connecting steel bar is a steel bar with the length of 650mm and the diameter of phi 20 and is sleeved in a PVC sleeve with the diameter of 24-25 mm, and two ends of the PVC sleeve are sealed;
side splints: the steel plate is a rectangular steel plate with the thickness of 3mm, the width of 400mm and the length of 1000mm, 3 gaps with the length of 163mm are arranged on the long edge of one side of the rectangular steel plate at intervals, the gaps extend to one side of the axial lead of the rectangular steel plate, the inner ends of the gaps are semicircular, and two side clamping plates are arranged;
a middle clamping plate: the rectangular steel plate is 4mm thick, 210mm wide and 1000mm long, 3 gaps 73mm long are arranged on the long edge of one side of the rectangular steel plate at intervals, the gaps extend to one side of the axial lead of the rectangular steel plate, the inner ends of the gaps are semicircular, and the middle clamping plate is one;
the middle splint is located between two lateral part splint on syntropy opening limit, two lateral part splint on syntropy opening limit and the middle splint on the opening limit are sealed to be laid in opposite directions, the opening that respectively corresponds of sealed in opposite directions aligns and forms three opening hole that supplies the shearing connecting reinforcement bar that sets up that is the interval distance and passes, the middle part of three shearing connecting reinforcement bars is located each opening hole respectively, the reinforcing bar on the both ends of three shearing connecting reinforcement bars and the fender tiny fragments of stone, etc. wall reinforcing bar rack of corresponding portion is fixed as an organic whole.
2. The installation device for the shear steel bars of the ballast wall of the bridge deck of the high-speed railway according to claim 1, which is characterized in that: the length and the width of the side clamping plate are larger than the height and the width of the discontinuous seam of the ballast retaining wall.
3. The installation device for the shear steel bars of the ballast wall of the bridge deck of the high-speed railway according to claim 1, which is characterized in that: the length of the middle clamping plate is larger than the height of the discontinuous joint of the ballast retaining wall.
4. The installation device for the shear steel bars of the ballast wall of the bridge deck of the high-speed railway according to claim 1, which is characterized in that: the central axis of each opening is vertical to the central axis of the side splint or the middle splint.
CN201921376648.3U 2019-08-23 2019-08-23 High-speed railway bridge floor keeps off tiny fragments of stone, coal, etc. wall shear reinforcement installation device Expired - Fee Related CN210597016U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921376648.3U CN210597016U (en) 2019-08-23 2019-08-23 High-speed railway bridge floor keeps off tiny fragments of stone, coal, etc. wall shear reinforcement installation device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921376648.3U CN210597016U (en) 2019-08-23 2019-08-23 High-speed railway bridge floor keeps off tiny fragments of stone, coal, etc. wall shear reinforcement installation device

Publications (1)

Publication Number Publication Date
CN210597016U true CN210597016U (en) 2020-05-22

Family

ID=70714139

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921376648.3U Expired - Fee Related CN210597016U (en) 2019-08-23 2019-08-23 High-speed railway bridge floor keeps off tiny fragments of stone, coal, etc. wall shear reinforcement installation device

Country Status (1)

Country Link
CN (1) CN210597016U (en)

Similar Documents

Publication Publication Date Title
CN103924505B (en) Use prefabricated steel-concrete combination T beam and the construction method of Wavelike steel webplate
CN103498425B (en) One completely knocks down multifunctional assembled bearing bracket structure and construction method thereof
CN204435638U (en) A kind of hollow laminated floor slab
CN205205646U (en) Structure of reinforcing prefabricated segment formula concrete bridge intersegmental connection of festival
CN205205654U (en) Seam construction of precast concrete festival segmentation bridge
CN102926504B (en) Construction method of steel and concrete overlapped beam combined part
CN105780964A (en) Connection structure and construction process for lightweight wall block filler wall and frame structure
CN114892552B (en) Box girder type bridge reconstruction construction method
CN103276651A (en) No-cutting-seam cement concrete pavement structure and construction method thereof
CN113653235A (en) Laminated slab, connecting structure of laminated slab and combination beam and construction method
CN104612300A (en) Hollow composite floor slab and construction method thereof
CN110439265A (en) Bilateral column or wall method for synchronously constructing at a kind of narrow expansion joint
CN108678417A (en) A kind of floor of steel structure transformation node
CN113216252A (en) Expansion joint reinforcing device and method for multi-section continuous casting of underground pipe gallery
CN205243063U (en) Masonry structure is consolidated to prefabricated wallboard
CN207846187U (en) A kind of Wavelike steel webplate I-shaped composite beam bridge of maximum assembling
CN103321242A (en) Subsection steel-bar-distribution prestressed concrete continuous wall and construction method thereof
CN106337530B (en) A kind of construction of frame beam seams stifled construction method
CN210597016U (en) High-speed railway bridge floor keeps off tiny fragments of stone, coal, etc. wall shear reinforcement installation device
CN210797241U (en) Prestressed high-strength regenerated hybrid continuous rigid frame bridge system
CN203373774U (en) Subsection steel-bar-distribution pre-stressed concrete continuous wall
CN105804274A (en) Novel light connecting structure of block filling wall and frame structure and construction technique
AU2021102866A4 (en) A method for structure reinforcement of existing tunnel lining
CN109779226A (en) A kind of opposite sex chimney construction security platform structure and its construction method
CN205874960U (en) Profiled sheet wave form steel web truss combination beam

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200522

CF01 Termination of patent right due to non-payment of annual fee