CN210562201U - Be applied to framework of steel reinforcement cement scraper blade in construction of making level of waterproof base face - Google Patents
Be applied to framework of steel reinforcement cement scraper blade in construction of making level of waterproof base face Download PDFInfo
- Publication number
- CN210562201U CN210562201U CN201920839561.9U CN201920839561U CN210562201U CN 210562201 U CN210562201 U CN 210562201U CN 201920839561 U CN201920839561 U CN 201920839561U CN 210562201 U CN210562201 U CN 210562201U
- Authority
- CN
- China
- Prior art keywords
- muscle
- envelope
- scraper blade
- waterproof base
- cement
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Finishing Walls (AREA)
Abstract
The utility model relates to a be applied to framework of steel reinforcement cement scraper blade in waterproof base face construction of making level belongs to waterproof base face screed-coat technical field, and it includes envelope, envelope is last fixedly connected with perpendicular to envelope's fulcrum muscle, and envelope's one end is kept away from to the fulcrum muscle is located same vertical face, and envelope's tip fixedly connected with skeleton muscle is kept away from to the fulcrum muscle, a plurality of vertical cement-coated panels of fixedly connected with on the skeleton muscle, the utility model discloses the effect of being convenient for the construction has.
Description
Technical Field
The utility model belongs to the technical field of the technique of waterproof base face screed-coat and specifically relates to a be applied to framework of steel reinforcement cement scraper blade in waterproof base face construction of making level.
Background
The cement hanging board is a novel interior and exterior wall decoration material at present, and is mainly used for the decoration and the transformation of the exterior facade of villas, factory buildings and houses; decorating a building roof; indoor wall decoration, suspended ceilings, partition walls and retaining walls; indoor and outdoor ground decoration; a grid fence and various garden building shapes and accessories.
The conventional auxiliary enclosure structure for the station selects the section steel cement mixing wall, the construction of the net sprayed concrete and the waterproof mortar leveling layer is usually adopted for leveling the side wall waterproof base surface of the enclosure structure, the construction of the net sprayed concrete and the waterproof mortar leveling layer needs to thoroughly clean loose rock blocks and strongly weathered soil on the original wall surface of the enclosure structure, otherwise, the concrete and the waterproof mortar are difficult to be well combined with the sprayed surface, and the construction quality is influenced.
The above prior art solutions have the following drawbacks: after loose rock blocks and strongly weathered soil on the original wall surface of the enclosure structure are thoroughly cleaned, garbage generated by shoveling the original wall surface of the enclosure structure needs to be cleared, so that the construction is complicated.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a be applied to framework of steel reinforcement cement scraper blade in waterproof base face construction of making level convenient to construction.
The above utility model discloses an above-mentioned utility model purpose can realize through following technical scheme:
the utility model provides a be applied to framework of steel reinforcement cement scraper blade in waterproof base face construction of making level, includes envelope, envelope is last fixedly connected with perpendicular to envelope's fulcrum muscle, and envelope's one end is located same vertical face is kept away from to the fulcrum muscle, and envelope's tip fixedly connected with skeleton muscle is kept away from to the fulcrum muscle, fixedly connected with a plurality of vertical cement link plates on the skeleton muscle.
By adopting the technical scheme, the pivot ribs can be directly driven into the original wall surface of the enclosure structure, then the framework ribs are welded at the end parts of the pivot ribs, the framework ribs are also vertically arranged, finally, the cement hanging plates are fixedly connected onto the framework ribs in sequence, the cement hanging plates are installed completely, direct construction is realized under the condition that the original wall surface of the enclosure structure is not removed, the steps of removing the original wall surface of the enclosure structure and clearing and transporting garbage generated by removing the original wall surface of the enclosure structure are reduced, construction is convenient, construction progress is greatly accelerated, garbage clearing and labor consumption are reduced, meanwhile, the purchasing cost of the cement hanging plates is lower, engineering cost is effectively reduced, and pollution of the original wall surface of the enclosure structure to the environment is avoided.
The utility model discloses further set up to: the binding belt is bound on the cement hanging plate, connecting holes are formed in the cement hanging plate, every two connecting holes are in a group, and the binding belt penetrates through the group of connecting holes to be connected with the framework ribs.
Through adopting above-mentioned technical scheme, place the position of cement hanging plate and finish the back, pass two connecting holes of a set of connecting hole respectively with the both ends of ligature area, then stride the skeleton muscle and tighten the both ends of ligature area, the cement hanging plate is fixed to the skeleton muscle promptly, makes the cement hanging plate be connected with the skeleton muscle through the ligature area to the connection that makes the cement hanging plate is comparatively convenient and quick.
The utility model discloses further set up to: each group of connecting holes are respectively positioned at two sides of the framework rib close to the connecting holes.
Through adopting above-mentioned technical scheme, the back is passed in two connecting holes of a set of connecting hole are followed respectively at the both ends of ligature area, directly passes from the both sides of skeleton muscle, later with the direct ligature in the both ends of ligature area, makes the ligature area stride the skeleton muscle more convenient, is favorable to accelerating ligature speed.
The utility model discloses further set up to: the edge of cement link plate evenly ligatures a plurality of ligatures area.
Through adopting above-mentioned technical scheme, make the cement link plate by fixed comparatively stable, avoided the cement link plate to produce on the skeleton muscle to remove and rock.
The utility model discloses further set up to: the number of the binding bands is at least six.
Through adopting above-mentioned technical scheme, guaranteed that the ligature has certain quantity to can provide sufficient holding power to the cement link plate, avoid the cement link plate to drop from the skeleton muscle because of the dead weight.
The utility model discloses further set up to: the skeleton muscle includes horizontal muscle and vertical muscle of indulging, and the cross section of horizontal muscle and indulging the muscle all with fulcrum muscle fixed connection.
Through adopting above-mentioned technical scheme, make being connected between skeleton muscle and the fulcrum muscle comparatively even and firm, guaranteed the supporting role that the fulcrum muscle is stable to the skeleton muscle can produce stable supporting role to the cement hanging board, has guaranteed the stability of the position of cement hanging board.
The utility model discloses further set up to: and a filling layer is filled between the cement hanging plate and the building envelope.
By adopting the technical scheme, the filling layer provides certain thrust far away from the enclosure structure for the cement hanging plate, so that the cement hanging plate is not easy to shake, the stability of the position of the cement hanging plate can be further kept, the vertical state of the cement hanging plate can be well kept, and the quick leveling of the base surface of the cement hanging plate is facilitated.
The utility model discloses further set up to: the filling layer is a filling layer of perlite particles.
By adopting the technical scheme, the granular perlite can be well dispersed between the cement hanging plate and the enclosure structure, so that the filling effect is good; the filling layer can generate certain thrust to the cement hanging plate, the perlite particles are light in texture, the generated thrust cannot be too large, and the cement hanging plate with the framework ribs and the fulcrum ribs is prevented from being separated from the enclosure structure due to the fact that the thrust is too large, so that the stability of connection between the cement hanging plate base surface and the enclosure structure is guaranteed; meanwhile, the perlite has certain functions of heat preservation, heat insulation and sound absorption, so that the cement hanging plate base surface formed at last has certain functions of heat preservation, heat insulation and sound absorption, noise reduction is facilitated, and heat insulation is realized, and energy waste is reduced.
To sum up, the utility model discloses a beneficial technological effect does:
1. by arranging the supporting point ribs, the framework ribs and the cement hanging plates, direct construction is realized under the condition that the original wall surface of the building enclosure is not removed, the steps of removing the original wall surface of the building enclosure and cleaning garbage generated by removing the original wall surface of the building enclosure are reduced, construction is more convenient, and construction progress is greatly accelerated;
2. the cross parts of the transverse ribs and the longitudinal ribs are fixedly connected with the supporting point ribs, so that the stable supporting effect of the supporting point ribs on the framework ribs is ensured, and the position of the cement hanging plate is relatively stable;
3. through setting up the filling layer, the certain thrust of keeping away from envelope of cement link plate in filling layer makes the cement link plate be difficult for looking for and produces and rock, and can further keep the stability of self position.
Drawings
Fig. 1 is a schematic structural diagram of the present invention;
FIG. 2 is an enlarged partial schematic view of portion A of FIG. 1;
fig. 3 is a horizontal sectional view of the pegboard.
In the figure, 1, a building envelope; 11. a fulcrum rib; 2. framework ribs; 21. transverse ribs; 22. longitudinal ribs; 3. cement hanging plates; 31. connecting holes; 32. binding tapes; 4. and (5) filling the layer.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings.
Refer to fig. 1, for the utility model discloses a be applied to steel reinforcement framework cement scraper blade in waterproof base face construction of making level, including envelope 1, envelope 1 goes up fixedly connected with perpendicular to envelope 1's fulcrum muscle 11, and envelope 1's one end is located same vertical face is kept away from to fulcrum muscle 11, and envelope 1's tip fixedly connected with skeleton muscle 2 is kept away from to fulcrum muscle 11, and a plurality of vertical cement hanging plates 3 of fixedly connected with are gone up to skeleton muscle 2, and the requirement such as 3 base flatness of cement hanging plates is lower, has reduced the former wall of shoveling envelope 1 and has carried out the step of clearing away to the rubbish that the former wall of shoveling envelope 1 produced, makes the construction comparatively convenient.
Referring to fig. 1 and 2, connecting hole 31 has been seted up on cement hanging plate 3, every two of connecting hole 31 are a set of, two connecting holes 31 of every group connecting hole 31 are located the both sides of its skeleton muscle 2 that is close to respectively, the edge of cement board is comparatively even sets up six at least groups of connecting holes 31, a plurality of ligature areas 32 of the even ligature of edge of cement hanging plate 3, two connecting holes 31 are passed simultaneously respectively at the both ends of ligature area 32, two connecting holes 31 are a set of connecting hole 31, afterwards, the both sides of skeleton muscle 2 are passed from the both ends of ligature area 32, directly the ligature in the both ends of ligature area 32 gets up, ligature area 32 is connected cement hanging plate 3 and skeleton.
Referring to fig. 1, skeleton muscle 2 includes horizontal muscle 21 and vertical muscle 22 of indulging, and horizontal muscle 21 all with the 11 fixed connection of fulcrum muscle with the cross section of indulging muscle 22, makes skeleton muscle 2 more with the junction of fulcrum muscle 11, and distributes comparatively evenly to fulcrum muscle 11 can play comparatively stable supporting role to skeleton muscle 2, thereby skeleton muscle 2 can produce stable supporting role to cement hanging board 3, has guaranteed the stability of cement hanging board 3's position.
Referring to fig. 3, a filling layer 4 is filled between the cement hanging plate 3 and the envelope structure 1, the filling layer 4 is a filling layer 4 of perlite particles, after the cement hanging plate 3 is bound with the framework ribs 2 by the binding tapes 32, the perlite particles are filled between the cement hanging plate 3 and the envelope structure 1 to form the filling layer 4, and the filling layer 4 generates certain thrust to the cement hanging plate 3, so that the cement hanging plate 3 is not easy to move, the stability of the position of the cement hanging plate is further improved, and the stability of the base surface of the cement hanging plate 3 is facilitated.
The implementation principle of the embodiment is as follows: the method comprises the steps of driving a fulcrum bar 11 into a building envelope 1, enabling the end part of the fulcrum bar 11 to be located on the same vertical plane, welding a framework bar 2 at the end part of the fulcrum bar 11, enabling the outer side surface of the framework bar 2 to be flush with the end part of the fulcrum bar 11, enabling the framework bar 2 to be located on the same vertical plane, enabling two ends of a binding band 32 to penetrate through two connecting holes 31 of a group of connecting holes 31 respectively, enabling the two ends of the binding band 32 to penetrate through two sides of the framework bar 2 directly, binding the two ends of the binding band 32 directly, binding a plurality of binding bands 32 on the edge of a cement hanging plate 3 in sequence, fixing the cement hanging plate 3 on the framework bar 2, finishing installation of the cement hanging plate 3, enabling the cement hanging plate 3 to be located on the same vertical plane, ensuring that the cement hanging plate 3 is located on the same horizontal plane, then filling granular perlite between the cement hanging plate 3, the filling layer 4 supplies thrust far away from the enclosure structure 1 to the side face, close to the enclosure structure 1, of the cement hanging plate 3, so that the cement hanging plate 3 is not prone to shaking, the stability of the position of the cement hanging plate can be further kept, direct construction is realized under the condition that the original wall face of the enclosure structure 1 is not removed, the steps of removing the original wall face of the enclosure structure 1 and clearing garbage generated by removing the original wall face of the enclosure structure 1 are reduced, construction is convenient, construction progress is greatly accelerated, garbage clearing and labor consumption are reduced, meanwhile, the purchasing cost of the cement hanging plate 3 is low, engineering cost is effectively reduced, and meanwhile, pollution of the original wall face of the enclosure structure 1 to the environment is avoided.
The embodiment of this specific implementation mode is the preferred embodiment of the present invention, not limit according to this the utility model discloses a protection scope, so: all equivalent changes made according to the structure, shape and principle of the utility model are covered within the protection scope of the utility model.
Claims (8)
1. The utility model provides a be applied to skeleton of steel reinforcement cement scraper blade in waterproof base face construction of making level, includes envelope (1), its characterized in that: fixedly connected with pivot muscle (11) perpendicular to envelope (1) on envelope (1), the one end that envelope (1) was kept away from in pivot muscle (11) is located same vertical face, and envelope (1) was kept away from in pivot muscle (11) tip fixedly connected with skeleton muscle (2), fixedly connected with a plurality of vertical cement hanging plate (3) on skeleton muscle (2).
2. The reinforced concrete scraper blade applied to leveling construction of a waterproof base surface according to claim 1, which is characterized in that: the binding band (32) is bound on the cement hanging plate (3), the connecting holes (31) are formed in the cement hanging plate (3), every two connecting holes (31) form a group, and the binding band (32) penetrates through the connecting holes (31) to be connected with the framework ribs (2).
3. The reinforced concrete scraper blade applied to leveling construction of a waterproof base surface according to claim 2, wherein: each group of connecting holes (31) are respectively positioned at two sides of the framework rib (2) close to the connecting holes.
4. The reinforced concrete scraper blade applied to leveling construction of a waterproof base surface according to claim 2, wherein: a plurality of ligature bands (32) are evenly banded at the edge of the cement hanging plate (3).
5. The reinforced concrete scraper blade applied to leveling construction of waterproof base surfaces according to claim 4, wherein: the number of the binding bands (32) is at least six.
6. The reinforced concrete scraper blade applied to leveling construction of a waterproof base surface according to claim 1, which is characterized in that: the framework rib (2) comprises a horizontal transverse rib (21) and a vertical longitudinal rib (22), and the intersection of the horizontal rib (21) and the longitudinal rib (22) is fixedly connected with the fulcrum rib (11).
7. The reinforced concrete scraper blade applied to leveling construction of a waterproof base surface according to claim 1, which is characterized in that: and a filling layer (4) is filled between the cement hanging plate (3) and the envelope structure (1).
8. The reinforced concrete scraper blade applied to leveling construction of a waterproof base surface according to claim 7, wherein: the filling layer (4) is a filling layer (4) of perlite particles.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920839561.9U CN210562201U (en) | 2019-06-04 | 2019-06-04 | Be applied to framework of steel reinforcement cement scraper blade in construction of making level of waterproof base face |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920839561.9U CN210562201U (en) | 2019-06-04 | 2019-06-04 | Be applied to framework of steel reinforcement cement scraper blade in construction of making level of waterproof base face |
Publications (1)
Publication Number | Publication Date |
---|---|
CN210562201U true CN210562201U (en) | 2020-05-19 |
Family
ID=70633922
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201920839561.9U Active CN210562201U (en) | 2019-06-04 | 2019-06-04 | Be applied to framework of steel reinforcement cement scraper blade in construction of making level of waterproof base face |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN210562201U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112281859A (en) * | 2020-09-27 | 2021-01-29 | 中铁一局集团有限公司 | Cement hanging plate type underground fender pile waterproof base surface |
-
2019
- 2019-06-04 CN CN201920839561.9U patent/CN210562201U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112281859A (en) * | 2020-09-27 | 2021-01-29 | 中铁一局集团有限公司 | Cement hanging plate type underground fender pile waterproof base surface |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US6718722B2 (en) | Construction composition, structure, and method | |
CN103615110B (en) | Random oblique netted nine-squares beam Hyperbolic Roof construction method | |
CN101845857B (en) | Metal mesh built-in insulating outer wall and construction method thereof | |
CN108412093B (en) | Modern landscape decorative rammed earth wall and construction method thereof | |
CN110607853B (en) | Fireproof composite wall body for protecting building | |
US6370835B1 (en) | Method and apparatus for low cost housing construction | |
CN105780976A (en) | Compound concrete shear wall structure and concrete pouring method thereof | |
CN113374295A (en) | Old steel-wood structure roof truss dismantling and rebuilding construction method | |
CN210562201U (en) | Be applied to framework of steel reinforcement cement scraper blade in construction of making level of waterproof base face | |
CN110469138B (en) | Traditional rammed earth building repairing method and structure | |
CN108118807A (en) | A kind of steel framework concrete partition and its construction method | |
CN105239701A (en) | Construction process of rammed earth wall | |
CN108130992A (en) | Rubble plate, styrofoam and porous brick compound thermal-insulating decorative external wall construction engineering method | |
TWM616467U (en) | Partition wall structure without dismantling grouting formwork | |
CN104763158B (en) | Tenon joint type light-weight aggregate chained block construction method | |
CN207553357U (en) | Rubble plate, styrofoam and porous brick compound thermal-insulating decorative exterior wall | |
CN113914530B (en) | Inclined roof fish scale type concrete structure and construction method | |
CN110158612B (en) | Construction method of steel bar framework cement hanging plate applied to leveling construction of waterproof base plane | |
CN113463861A (en) | Design method of carbon fixation type replaceable hanging plate type building skin | |
CN106193462A (en) | Roofing Splitting Tile construction method modelled after an antique | |
CN207392518U (en) | A kind of lightweight steel construction assembles the metope modular system of decoration integrated external wall | |
CN202202475U (en) | Wood-plastic perlite composite wallboard | |
CN2467626Y (en) | Civil construction wall body structure | |
CN211597236U (en) | Building ardealite infilled wall structure | |
CN108978943A (en) | The wall of the fixed ceramic tile casting foamed cement of pillar |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |