CN210558858U - Balance lifting appliance for hoisting assembly type shear wall - Google Patents

Balance lifting appliance for hoisting assembly type shear wall Download PDF

Info

Publication number
CN210558858U
CN210558858U CN201921159235.XU CN201921159235U CN210558858U CN 210558858 U CN210558858 U CN 210558858U CN 201921159235 U CN201921159235 U CN 201921159235U CN 210558858 U CN210558858 U CN 210558858U
Authority
CN
China
Prior art keywords
hoist
chain block
wire rope
shear wall
steel frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921159235.XU
Other languages
Chinese (zh)
Inventor
孙永亮
姜志浩
朱旭城
陈攀峰
任啸天
安拴平
孙智勇
胡晓辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Third Engineering Bureau Co Ltd
Original Assignee
China Construction Third Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Third Engineering Bureau Co Ltd filed Critical China Construction Third Engineering Bureau Co Ltd
Priority to CN201921159235.XU priority Critical patent/CN210558858U/en
Application granted granted Critical
Publication of CN210558858U publication Critical patent/CN210558858U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a balanced hoist for assembled shear force wall hoist and mount, including shaped steel frame, rings, insurance wire rope, chain block, duckbilled lifting hook and hoist and mount wire rope, shaped steel frame upper end is connected to the tower crane lifting hook through hoist and mount wire rope, and the bottom sets up rings according to the modulus, chain block is installed to the rings below to through duckbilled lifting hook and prefabricated shear force wall in pre-buried hanging nail hasp be connected, still be connected through insurance wire rope between shaped steel frame and the prefabricated shear force wall, form dual protection with chain block. The utility model discloses when using, the tower crane lifting hook is hoisted precast shear wall to mounted position fast, and chain block slowly rises or falls precast shear wall steadily, and the hoisting point position of chain block accessible adjustment on shaped steel frame adapts to the precast shear wall hoist and mount of not unidimensional, different focus positions, makes precast shear wall remain vertical attitude throughout.

Description

Balance lifting appliance for hoisting assembly type shear wall
Technical Field
The utility model belongs to the technical field of the assembly type structure, concretely relates to balanced hoist for hoist and mount of assembled shear force wall.
Background
With the strong push support of national policies, fabricated buildings have been rapidly developed. Precast shear walls are a common form of construction for fabricated buildings. The prefabricated shear wall is prefabricated in a factory and assembled and constructed on site by using hoisting equipment. The prefabricated shear wall belongs to large-scale PC components, and it has characteristics such as monolithic weight is big, the form is various, the size is super large, and prefabricated shear wall installation accuracy requires highly, therefore causes prefabricated shear wall installation effectiveness low, and there is great potential safety hazard in the hoist and mount construction, has seriously influenced assembly type structure's construction quality and progress.
Disclosure of Invention
In order to overcome among the prior art precast shear wall installation effectiveness low, there is the technical problem of great potential safety hazard in the hoist and mount construction, the utility model provides a balanced hoist for assembled shear wall hoist and mount has solved above-mentioned technical problem.
The utility model discloses a following technical scheme realizes above-mentioned purpose, a balanced hoist for assembled shear force wall hoist and mount, including shaped steel frame, rings, safety steel wire rope, chain block, duckbilled lifting hook and hoist and mount wire rope, shaped steel frame upper end is connected to the tower crane lifting hook through hoist and mount wire rope, and the bottom sets up rings according to the modulus, chain block is installed to the rings below to through duckbilled lifting hook and prefabricated shear force wall in pre-buried lifting nail hasp be connected, still be connected through safety steel wire rope between shaped steel frame and the prefabricated shear force wall, form dual protection with chain block.
The balance lifting appliance for lifting the assembled shear wall is suitable for lifting the prefabricated shear walls with different sizes and different gravity center positions by adjusting the lifting point positions of the chain block on the section steel frame, so that the prefabricated shear walls are always kept in a vertical posture.
The above-mentioned a balanced hoist for assembled shear force wall hoist and mount, the tower crane lifting hook hoists precast shear force wall to the mounted position fast, and chain block rises precast shear force wall slowly steadily or falls.
Generally, through the utility model discloses above technical scheme who conceives compares with prior art, can reach following beneficial effect: the utility model relates to a balanced hoist for assembled shear force wall hoist and mount utilizes the balanced effect of shaped steel frame, realizes the maintenance to the perpendicular gesture of precast shear force wall, does benefit to precast shear force wall hoist and mount more and takes one's place, realizes finely tuning the precast shear force wall through hand block, improves the installation effectiveness, and this balanced hoist simple structure, safe and reliable, commonality are strong simultaneously, very big improvement the installation effectiveness of precast shear force wall.
Drawings
The following detailed description of embodiments of the present invention is provided with reference to the accompanying drawings, in which:
fig. 1 is a schematic overall structure diagram of a balance hanger for hoisting an assembled shear wall according to the present invention;
FIG. 2 is a schematic view of the connection relationship between the hoisting steel wire rope and the tower crane hook of the present invention;
FIG. 3 is a schematic view of the connection relationship between the steel frame and the hanging ring;
FIG. 4 is a schematic view of the connection relationship between the hand-drive block and the duckbilled hook according to the present invention;
in the figure: 1-a section steel frame, 2-a lifting ring, 3-a safety steel wire rope, 4-a chain block, 5-a duckbilled lifting hook, 6-a hoisting steel wire rope, 7-a hoisting nail and 8-a tower crane lifting hook.
Detailed Description
As shown in fig. 1, be the utility model relates to a balanced hoist overall structure schematic diagram for assembled shear force wall hoist and mount, including shaped steel frame 1, rings 2, insurance wire rope 3, chain block 4, duckbilled lifting hook 5 and hoist and mount wire rope 6, shaped steel frame 1 upper end is connected to tower crane lifting hook 8 through hoist and mount wire rope 6, and the bottom sets up rings 2 according to the modulus, chain block 4 is installed to rings 2 below to through duckbilled lifting hook 5 and prefabricated shear wall in the pre-buried lifting nail 7 hasp be connected, still be connected through insurance wire rope 3 between shaped steel frame 1 and the prefabricated shear wall, form duplicate protection with chain block 4.
The utility model discloses when specifically using, mainly accomplish transferring and the installation through following use step of precast shear wall:
the method comprises the following steps: the section steel frame 1 is connected with a tower crane hook 8 through a hoisting steel wire rope 6, as shown in fig. 2, the connection relation between the hoisting steel wire rope 6 and the tower crane hook 8 is shown schematically;
step two: a hand hoist 4 and a safety steel wire rope 3 are arranged on a lifting ring 2 below the section steel frame 1, as shown in fig. 3, which is a schematic diagram of the connection relationship between the section steel frame 1 and the lifting ring 2;
step three: fastening and fixing a duckbilled lifting hook 5 on the safety steel wire rope 3 and a hanging nail 7 pre-embedded in the prefabricated shear wall;
step four: fastening and fixing a duckbilled lifting hook 5 on the hand block 4 and a hanging nail 7 pre-embedded in the prefabricated shear wall, as shown in fig. 4, which is a schematic diagram of the connection relationship between the hand block 4 and the duckbilled lifting hook 5 of the present invention, adjusting and pulling a chain block of the hand block 4 until a hoisting steel wire rope 6 is pre-tightened, and the two ends are stressed the same, and making the safety steel wire rope 3 in a slightly loose state;
and fifthly, hoisting the prefabricated shear wall to the installation position quickly by using a tower crane, stopping hoisting by using the tower crane when the distance between the prefabricated shear wall and the installation position is 0.5-1 m, unfastening the safety steel wire rope 3, releasing the hand-operated hoist 4, and slowly dropping the prefabricated shear wall to the position.
It will be understood by those skilled in the art that the foregoing is merely a preferred embodiment of the present invention, and is not intended to limit the invention, and that any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included within the scope of the present invention.

Claims (3)

1. The utility model provides a balanced hoist for assembled shear force wall hoist and mount, includes shaped steel frame (1), rings (2), insurance wire rope (3), chain block (4), duckbilled lifting hook (5) and hoist and mount wire rope (6), its characterized in that: shaped steel frame (1) upper end is connected to tower crane lifting hook (8) through hoist and mount wire rope (6), and bottom sets up rings (2) according to the modulus, chain block (4) are installed to rings (2) below to through duckbilled lifting hook (5) and prefabricated shear wall in pre-buried hanging nail (7) hasp be connected, still be connected through insurance wire rope (3) between shaped steel frame (1) and the prefabricated shear wall, form duplicate protection with chain block (4).
2. The balance sling for hoisting the fabricated shear wall according to claim 1, wherein: the chain block (4) can adapt to the hoisting of the prefabricated shear walls with different sizes and different gravity center positions by adjusting the hoisting point positions on the section steel frame (1), so that the prefabricated shear walls are always kept in vertical postures.
3. The balance sling for hoisting the fabricated shear wall according to claim 1, wherein: the tower crane lifting hook (8) quickly lifts and transports the prefabricated shear wall to the installation position, and the chain block (4) slowly and stably lifts or falls the prefabricated shear wall.
CN201921159235.XU 2019-07-23 2019-07-23 Balance lifting appliance for hoisting assembly type shear wall Active CN210558858U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921159235.XU CN210558858U (en) 2019-07-23 2019-07-23 Balance lifting appliance for hoisting assembly type shear wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921159235.XU CN210558858U (en) 2019-07-23 2019-07-23 Balance lifting appliance for hoisting assembly type shear wall

Publications (1)

Publication Number Publication Date
CN210558858U true CN210558858U (en) 2020-05-19

Family

ID=70634372

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921159235.XU Active CN210558858U (en) 2019-07-23 2019-07-23 Balance lifting appliance for hoisting assembly type shear wall

Country Status (1)

Country Link
CN (1) CN210558858U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112027935A (en) * 2020-09-21 2020-12-04 杭州通达集团有限公司 Hoisting construction method of PC (polycarbonate) wallboard used under window
CN112320559A (en) * 2020-09-27 2021-02-05 中核核电运行管理有限公司 Manhole cover plate hoisting device for voltage stabilizer of nuclear power unit
CN112723151A (en) * 2020-12-30 2021-04-30 湖南鸿云杭萧绿建科技有限公司 Integral roof hoisting and mounting method for assembly type steel structure building
CN113979277A (en) * 2021-10-08 2022-01-28 临泉晶宫绿建节能建筑有限公司 Assembled building lifting device
CN113979277B (en) * 2021-10-08 2024-06-28 临泉晶宫绿建节能建筑有限公司 Assembled building lifting device

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112027935A (en) * 2020-09-21 2020-12-04 杭州通达集团有限公司 Hoisting construction method of PC (polycarbonate) wallboard used under window
CN112027935B (en) * 2020-09-21 2023-02-03 杭州通达集团有限公司 Hoisting construction method of PC (polycarbonate) wallboard used under window
CN112320559A (en) * 2020-09-27 2021-02-05 中核核电运行管理有限公司 Manhole cover plate hoisting device for voltage stabilizer of nuclear power unit
CN112723151A (en) * 2020-12-30 2021-04-30 湖南鸿云杭萧绿建科技有限公司 Integral roof hoisting and mounting method for assembly type steel structure building
CN112723151B (en) * 2020-12-30 2023-06-06 湖南鸿云杭萧绿建科技有限公司 Method for hoisting and installing integral roof of assembled steel structure building
CN113979277A (en) * 2021-10-08 2022-01-28 临泉晶宫绿建节能建筑有限公司 Assembled building lifting device
CN113979277B (en) * 2021-10-08 2024-06-28 临泉晶宫绿建节能建筑有限公司 Assembled building lifting device

Similar Documents

Publication Publication Date Title
CN210558858U (en) Balance lifting appliance for hoisting assembly type shear wall
CN204917648U (en) Turbine rotor lifts by crane instrument
CN201785144U (en) Gin pole crane
CN205419580U (en) A hoist and mount system for dismantling tower crane overlength pull rod
CN209758838U (en) Special lifting appliance device for lifting T beam by bridge girder erection machine
CN101649683A (en) Method for hoisting power transmission iron tower by assembly holding pole technology
CN201264865Y (en) Automatic unhooking hanging hook
CN201334306Y (en) Hoisting machine for upright post member
CN202030434U (en) Large-span whole-section hoisting sling for steel box girder
CN201176365Y (en) Light-duty adjustable hanger
CN101049892B (en) Method for matching balanced system of crane in type of arm support and crane therefor
CN109969929A (en) A kind of omnipotent tail portion suspender of wind-power tower lifting
CN2511654Y (en) Crane hook
CN201825635U (en) Hoisting structure of power station boiler
CN108502700A (en) Engine rooms of wind power generators suspender
CN111153316A (en) Lifting appliance for overlong PC (polycarbonate) component
CN211034952U (en) Maintenance hanging bracket for substation equipment
CN204355947U (en) Large-scale without eye plate lifting beam device
CN208814490U (en) A kind of novel drainage ditch cover plate hanging apparatus
CN201224657Y (en) Special lifting eye for synchronous radiation light source storage ring platform
CN205421883U (en) Suspension type operation platform
CN201864464U (en) Lifting hook capable of unhooking automatically
CN215364462U (en) Balance lifting appliance for prefabricated floor slab components
CN110790121A (en) General hoist based on bridge segment promotes
CN207684728U (en) Towering noble metal tower mast sling system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant