CN201176365Y - Light-duty adjustable hanger - Google Patents

Light-duty adjustable hanger Download PDF

Info

Publication number
CN201176365Y
CN201176365Y CNU2007203004635U CN200720300463U CN201176365Y CN 201176365 Y CN201176365 Y CN 201176365Y CN U2007203004635 U CNU2007203004635 U CN U2007203004635U CN 200720300463 U CN200720300463 U CN 200720300463U CN 201176365 Y CN201176365 Y CN 201176365Y
Authority
CN
China
Prior art keywords
lifting
lifting support
holes
light
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU2007203004635U
Other languages
Chinese (zh)
Inventor
张鸿
刘先鹏
罗承斌
陈鸣
黄朝晖
周汉发
何官健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Second Harbor Engineering Co
CCCC Road and Bridge Special Engineering Co Ltd
Original Assignee
CCCC Second Harbor Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Second Harbor Engineering Co filed Critical CCCC Second Harbor Engineering Co
Priority to CNU2007203004635U priority Critical patent/CN201176365Y/en
Application granted granted Critical
Publication of CN201176365Y publication Critical patent/CN201176365Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a portable and adjustable lifting support, which comprises a lifting support of a frame structure, wherein lifting eyes are connected on the upper and the lower portions of the lifting support, and lifting holes are arranged on the lifting eyes at intervals, the lifting eyes are symmetrically arranged on the upper and the lower edges of the lifting support, and the lifting holes which are arranged on the lifting eyes are symmetrically arranged. The lifting support of the frame structure is made through welding section steel and steel plates and adapts to the variation of the space between lifting points due to the variation of the external dimension of a steel anchor box through arranging the lifting holes with various intervals on a lower and an upper eye plates of the lifting support. The holes which are arranged on the lower and the upper eye plates of the lifting support are in an one-to-one corresponding mode, thereby the partial stress is optimized, the structure is simple and the weight is light, hanging points of a main hanging rope and an auxiliary hanging rope of the lifting support are positioned on the same section, thereby the structural stress is reasonable, the structure of the lifting support is designed light, and lifting holes which are arranged on the upper and the lower eye plates of the lifting support have different intervals, thereby the requirements of the variation of the length of the steel anchor box can be satisfied only through installing the main and the auxiliary lifting ropes on the lifting holes, and the use of the lifting support is very convenient.

Description

Light-duty adjustable suspension bracket
Technical field
The utility model belongs to lifting device, is specifically related to a kind of light-duty adjustable suspension bracket that is used for the steel anchor box lifting.
Background technology
Steel anchor box is to be used for the anchoring of bridge Sarasota upper king-post strut suspension cable.When constructing, the steel anchor box hoisting height is big, and (the steel anchor box setting height(from bottom) is 230m~300m), be subjected to wind effect remarkable, lifting often, and the suspension centre spacing of each length direction is all different, for safety, finish steel anchor box lifting efficiently, economically, need that structure is slim and graceful, area exposed to the wind is less, especially can adapt to the suspension centre spacing change, once overlapping the suspension bracket that can finish all steel anchor box segment lifting tasks of single tower.And now still do not have corresponding suspension bracket to be applicable to the lifting of above-mentioned steel anchor box.
Summary of the invention
The purpose of this utility model is to provide a kind of light-duty adjustable suspension bracket that is suitable for the steel anchor box lifting, to address the above problem.
The technical solution of the utility model is: light-duty adjustable suspension bracket, and it comprises the suspension bracket of framed structure, suspension bracket is connected with hanger up and down, offers lifting hole(eyelet) on the hanger at interval.
Described hanger is symmetricly set on suspension bracket both sides up and down.Lifting hole(eyelet) symmetry on hanger is offered.
This suspension bracket framed structure is by shaped steel and welded steel plate, by lower ear plate on suspension bracket the hole for hoist of different spacing is set, and changes the variation of the suspension centre spacing of bringing with the overall dimensions that adapt to steel anchor box.The lower ear plate perforate is corresponding one by one on the suspension bracket, to optimize local pressure; Simple in structure, in light weight.Suspension bracket master hoist cable and time hoist cable hanging point are on the same section, and structure stress is reasonable, and the hanger structure design is by light and handy; The upper and lower otic placode of suspension bracket is provided with the hole for hoist of different spacing, as long as the primary and secondary hoist cable is installed on the hole for hoist, just can satisfy the requirement of steel anchor box length variations, and is extremely easy to use.
Description of drawings
The light-duty adjustable hanger structure scheme drawing of Fig. 1.
The light-duty adjustable hanger structure schematic top plan view of Fig. 2.
The light-duty adjustable suspension bracket lifting scheme drawing of Fig. 3.
The specific embodiment
As shown in Figure 2, connecting stirrup 3 in the framework that connected into by crossbeam 1, longeron 2 of light-duty adjustable suspension bracket and the framework is connected to form;
As shown in Figure 1, crossbeam 1 is symmetrically connected with hanger 4 and following hanger 5 up and down, last hanger 4 and following hanger 5 symmetries offer lifting hole(eyelet) 6 and following lifting hole(eyelet) 7.Last lifting hole(eyelet) 6 and following lifting hole(eyelet) 7 are provided with at interval.
As shown in Figure 3, suspension bracket top otic placode links to each other with suspension hook by main hoist cable during use, and suspension bracket bottom otic placode links to each other with steel anchor box (hanging object) by time hoist cable, and main hoist cable and time hoist cable change hole for hoist by moving synchronously, and be equipped with and increase, subtract the adjusting shackle, can lift the steel anchor box of different length.

Claims (3)

1, a kind of light-duty adjustable suspension bracket, it comprises the suspension bracket of framed structure, it is characterized in that suspension bracket is connected with hanger up and down, offers lifting hole(eyelet) on the hanger at interval.
2, light-duty according to claim 1 adjustable suspension bracket is characterized in that hanger is symmetricly set on suspension bracket both sides up and down.
3, light-duty as claimed in claim 1 or 2 adjustable suspension bracket is characterized in that the lifting hole(eyelet) symmetry on the hanger is offered.
CNU2007203004635U 2007-12-27 2007-12-27 Light-duty adjustable hanger Expired - Fee Related CN201176365Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2007203004635U CN201176365Y (en) 2007-12-27 2007-12-27 Light-duty adjustable hanger

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2007203004635U CN201176365Y (en) 2007-12-27 2007-12-27 Light-duty adjustable hanger

Publications (1)

Publication Number Publication Date
CN201176365Y true CN201176365Y (en) 2009-01-07

Family

ID=40216380

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2007203004635U Expired - Fee Related CN201176365Y (en) 2007-12-27 2007-12-27 Light-duty adjustable hanger

Country Status (1)

Country Link
CN (1) CN201176365Y (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102092625A (en) * 2010-12-24 2011-06-15 南通振华重型装备制造有限公司 Universal hoisting hanging beam
CN104044992B (en) * 2014-05-27 2017-06-16 北京航天发射技术研究所 The big vertical hoisting sling of rigidity frame structure of oblique pull suspension cable type and assembling suspender
CN107059506A (en) * 2017-05-16 2017-08-18 中国铁道科学研究院铁道建筑研究所 A kind of plate-type ballastless track track plates replacing options
CN111502278A (en) * 2020-04-23 2020-08-07 湖南教建集团有限公司 Tower crane full-mold building construction method
CN112709140A (en) * 2020-12-23 2021-04-27 中铁广州工程局集团有限公司 Construction method for concrete box girder of three-hole hanging bracket and half-through basket steel tube concrete arch bridge

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102092625A (en) * 2010-12-24 2011-06-15 南通振华重型装备制造有限公司 Universal hoisting hanging beam
CN104044992B (en) * 2014-05-27 2017-06-16 北京航天发射技术研究所 The big vertical hoisting sling of rigidity frame structure of oblique pull suspension cable type and assembling suspender
CN107059506A (en) * 2017-05-16 2017-08-18 中国铁道科学研究院铁道建筑研究所 A kind of plate-type ballastless track track plates replacing options
CN111502278A (en) * 2020-04-23 2020-08-07 湖南教建集团有限公司 Tower crane full-mold building construction method
CN112709140A (en) * 2020-12-23 2021-04-27 中铁广州工程局集团有限公司 Construction method for concrete box girder of three-hole hanging bracket and half-through basket steel tube concrete arch bridge

Similar Documents

Publication Publication Date Title
CN201176365Y (en) Light-duty adjustable hanger
CN204847764U (en) Prefabricated component production is with hoist and mount frame
CN102733615A (en) Unsymmetrical integral lifting construction method
CN102795532A (en) Hoisting tool for large heavy object with enter of gravity deviated from geometric center and hoisting method thereof
CN202848940U (en) Chamber roof truss overall declining removal device of large gas chamber
CN204917648U (en) Turbine rotor lifts by crane instrument
CN202214131U (en) Three-point lifting beam
CN205576744U (en) Special jack -up hoist is erect to cable -stay bridge cordless district large -tonnage steel case girder segment section
CN203255914U (en) Unit-typed curtain wall lifting device
CN202754690U (en) Large weight hoisting tools with center of gravity deviating from geometric center to one side
CN206720558U (en) A kind of adjustable steel-reinforcement cage hanger
CN204454235U (en) A kind of novel many suspension centres equalizing bar device
CN203959697U (en) The equalizing bar of hoisting platform truss
CN104030176B (en) The equalizer bar of hoisting platform truss and hanging method thereof
CN201406269Y (en) Three-unit crane lifting T-shaped sling
CN101768925B (en) Mounting equipment of beam falling prevention stopping block and construction method thereof
CN204752012U (en) Wall -hanging miniature hoist
CN103979442B (en) The method of 6400 tons of Hydraulic double-type crane lifting cost tropsch reactors
CN201825635U (en) Hoisting structure of power station boiler
CN202924577U (en) Special hanger frame for small lid of electric furnace
CN203095390U (en) Mounting structure of FPSO (floating production storage and offloading) module lifting eye
CN206090314U (en) Steel anchor beam lifting sling
CN202358822U (en) Hoisting structure for oil field skid block
CN204897147U (en) Horizontal panel hoist
CN207312920U (en) The suspender of steel containment vessel in nuclear power station

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Assignee: CCCC SHEC Fourth Engineering Co., Ltd.

Assignor: China Communications 2nd Navigational Bureau

Contract record no.: 2010420000184

Denomination of utility model: Light-duty adjustable hanger

Granted publication date: 20090107

License type: Exclusive License

Record date: 20101115

ASS Succession or assignment of patent right

Owner name: WUHAN CCCC ROAD + BRIDGE SPECIAL ENGINEERING CO.,

Effective date: 20120608

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 430014 WUHAN, HUBEI PROVINCE TO: 430032 WUHAN, HUBEI PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20120608

Address after: 430032. 11 Golden Lake Road, Dongxihu lake, Wuhan, Hubei

Co-patentee after: CCCC Road & Bridge Special Engineering Co., Ltd.

Patentee after: China Communications 2nd Navigational Bureau

Address before: 430014 No. 16, Nanjing Road, Jianghan District, Hubei, Wuhan

Patentee before: China Communications 2nd Navigational Bureau

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20090107

Termination date: 20161227