CN107059506A - A method for replacing a track plate of a slab ballastless track - Google Patents

A method for replacing a track plate of a slab ballastless track Download PDF

Info

Publication number
CN107059506A
CN107059506A CN201710343830.8A CN201710343830A CN107059506A CN 107059506 A CN107059506 A CN 107059506A CN 201710343830 A CN201710343830 A CN 201710343830A CN 107059506 A CN107059506 A CN 107059506A
Authority
CN
China
Prior art keywords
track
slab
plate
replaced
rail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710343830.8A
Other languages
Chinese (zh)
Inventor
刘竞
郑新国
谢永江
李书明
曾志
程冠之
董全霄
王月华
杨德军
刘相会
潘永健
冯仲伟
朱长华
翁智财
周骏
刘锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Academy of Railway Sciences Corp Ltd CARS
Railway Engineering Research Institute of CARS
Original Assignee
China Academy of Railway Sciences Corp Ltd CARS
Railway Engineering Research Institute of CARS
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Academy of Railway Sciences Corp Ltd CARS, Railway Engineering Research Institute of CARS filed Critical China Academy of Railway Sciences Corp Ltd CARS
Priority to CN201710343830.8A priority Critical patent/CN107059506A/en
Publication of CN107059506A publication Critical patent/CN107059506A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B29/00Laying, rebuilding, or taking-up tracks; Tools or machines therefor
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B29/00Laying, rebuilding, or taking-up tracks; Tools or machines therefor
    • E01B29/005Making of concrete parts of the track in situ
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2203/00Devices for working the railway-superstructure
    • E01B2203/10Track-lifting or-lining devices or methods
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2204/00Characteristics of the track and its foundations
    • E01B2204/06Height or lateral adjustment means or positioning means for slabs, sleepers or rails
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2204/00Characteristics of the track and its foundations
    • E01B2204/09Ballastless systems
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2204/00Characteristics of the track and its foundations
    • E01B2204/11Embedded tracks, using prefab elements or injecting or pouring a curable material

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Machines For Laying And Maintaining Railways (AREA)

Abstract

The present invention relates to a kind of plate-type ballastless track track plates replacing options, the replacing options include Replacement procedure, equipment frock and injecting paste material, fastener before and after track plates to be replaced is specially unclamped into certain length, rail is risen into certain altitude, track plates to be replaced are subjected to jacking, it is set to depart from bottom filling bed mortar, suspender with multiple suspension centres is installed on track plates, by the switching of gantry crane and suspender suspension centre, to being replaced, track plates progress translation is hung out and the translation of new plate is hung in, after new plate is in place, using fast hard injecting paste material injection filling new-track plate and former unsticking lamellar spacing, recover rail and fastener.

Description

一种板式无砟轨道轨道板更换方法A method for replacing a track plate of a slab ballastless track

技术领域technical field

本发明属于高速铁路板式无砟轨道养护维修技术领域,具体涉及一种板式无砟轨道轨道板更换方法及工装。The invention belongs to the technical field of maintenance and repair of slab-type ballastless track of high-speed railway, and in particular relates to a method and tooling for replacing a track plate of slab-type ballastless track.

背景技术Background technique

板式无砟轨道是当今世界最先进的无砟轨道技术,是我国建造高速铁路所采用的主要轨道结构型式,京津、沪杭、沪宁、武汉城际、京沪、哈大、京石武、杭甬、宁杭、合福、津秦、沪昆、哈齐、宁安、郑徐、沈丹等高速铁路均采用板式无砟轨道型式。目前,我国板式无砟轨道主要CRTSⅠ、Ⅱ、Ⅲ型等三种。其中,CRTS I型板式无砟轨道是在现浇的钢筋混凝土底座上铺装预制轨道板,通过砂浆充填层进行调整,通过凸形挡台进行限位,并适应ZPW-2000轨道电路的单元板式无砟轨道结构型式; CRTS II板式无砟轨道是轨道板通过水泥沥青砂浆充填层,铺设在现场摊铺的混凝土支承层(路基、隧道)或现场浇筑的钢筋混凝土底座(桥梁)上,并适应ZPW-2000轨道电路的纵连板式无砟轨道结构形式;CRTS Ⅲ型板式无砟轨道是在现浇的钢筋混凝土底座或混凝土支承层上铺装预留连接钢筋的预制混凝土轨道板,中间设置自密实混凝土充填层,并适应ZPW-2000轨道电路的无砟轨道结构型式。板式无砟轨道取消了传统有砟轨道的轨枕和道床,采用预制的钢筋混凝土轨道板直接支撑钢轨,并且在轨道板与混凝土底座之间填充水泥乳化沥青砂浆或自密实混凝土充填层,其具有平顺性高、稳定性好、使用寿命长、耐久性好、维修工作量少等技术优势。但是,随着服役时间的延长以及地质情况变化等复杂原因,板式无砟轨道的个别轨道板会出现局部劣化情况,当劣化到一定程度时,需要对个别伤损的轨道板进行更换,以确保无砟轨道的安全性、稳定性和长期耐久性。Slab ballastless track is the most advanced ballastless track technology in the world today. It is the main track structure type used in the construction of high-speed railways in my country. , Hangzhou-Ningbo, Ning-Hang, He-Fu, Jin-Qin, Shanghai-Kunming, Haqi, Ning'an, Zheng-Xu, Shen-Dan and other high-speed railways all adopt slab ballastless track type. At present, there are mainly three types of slab ballastless track in my country: CRTS Ⅰ, Ⅱ, Ⅲ. Among them, the CRTS I-type slab ballastless track is a prefabricated track slab paved on the cast-in-place reinforced concrete base, adjusted through the mortar filling layer, and limited by the convex stopper, and adapted to the unit slab type of ZPW-2000 track circuit Ballastless track structure type; CRTS II slab ballastless track is a track slab filled with cement asphalt mortar, laid on the concrete support layer (roadbed, tunnel) or reinforced concrete base (bridge) poured on site, and adapted to ZPW-2000 track circuit’s vertically connected slab ballastless track structure; CRTS Ⅲ type slab ballastless track is a prefabricated concrete track slab with reserved connecting steel bars laid on the cast-in-place reinforced concrete base or concrete support layer, and an automatic track slab is set in the middle. The dense concrete filling layer is suitable for the ballastless track structure type of ZPW-2000 track circuit. The slab ballastless track cancels the sleeper and ballast bed of the traditional ballast track, and uses the prefabricated reinforced concrete track slab to directly support the rail, and fills the cement emulsified asphalt mortar or self-compacting concrete filling layer between the track slab and the concrete base, which has a smooth High performance, good stability, long service life, good durability, less maintenance workload and other technical advantages. However, with the extension of service time and complex reasons such as changes in geological conditions, individual track slabs of the slab ballastless track will deteriorate locally. When the deterioration reaches a certain level, individual damaged track slabs need to be replaced to ensure Safety, stability and long-term durability of ballastless tracks.

目前,更换轨道板采用的方法是先切断钢轨,再用轨道车的起吊设备将伤损轨道板移出、新轨道板移入,然后重新焊接锁定钢轨。采用该方法须在换板前对钢轨进行切割,且当日天窗须对钢轨进行临时连接恢复,换板后还须对钢轨进行焊接、打磨以及焊缝探伤等,工序较多;另外,增加了钢轨接头,对钢轨损伤较大。At present, the method used to replace the track slab is to cut off the rail first, then use the hoisting equipment of the rail car to move out the damaged track slab, move in the new track slab, and then re-weld and lock the rail. Using this method, the rails must be cut before the plate is changed, and the skylight must be temporarily connected to the rails on the same day. After the plate is changed, the rails must be welded, polished, and weld flaw detection. , greater damage to the rail.

针对切断钢轨更换轨道板的弊端,国内外开展了不切割钢轨情况下,天窗时间内对轨道板更换工艺工装的试验研究,但目前还处于试验开发阶段,其中,专利“一种板式无砟轨道轨道板更换装置及更换方法(201310108682.3)”,提供了一种不切断钢轨情况下,板式无砟轨道轨道板更换装置及更换方法,并未涉及新轨道板与原填充层砂浆的粘结恢复或密贴状态控制技术,且现场安装工装较多,较重,不便于天窗时间施工;而专利“一种地铁换板车及包含该地铁换板车的换板机组(201420251605.3)”所用的设备大型化、复杂化,一旦天窗作业时出现设备故障问题,很难处理,则直接影响线路的正点开通,另外,该专利还不适用于高铁铁路无砟轨道轨道板的更换修复。因此,为根本解决不切断钢轨情况下,天窗时间内板式无砟轨道轨道板的快速更换修复技术难题,系统形成分别适用于CRTSⅠ、Ⅱ、Ⅲ型板式无砟轨道直线段、曲线段板式无砟轨道轨道板更换技术,是本领域亟待解决的问题。In view of the disadvantages of cutting the rails to replace the track slabs, the experimental research on the replacement process tooling of the track slabs within the skylight time has been carried out at home and abroad without cutting the rails, but it is still in the stage of experimental development. Among them, the patent "a slab ballastless track Track slab replacement device and replacement method (201310108682.3)", which provides a track slab replacement device and replacement method for slab-type ballastless track without cutting the rails, and does not involve the bonding restoration of the new track slab and the original filling layer mortar or Close-fitting state control technology, and there are many and heavy on-site installation tools, which are not convenient for construction during skylight time; and the equipment used in the patent "a subway board changing car and a board changing unit including the subway board changing car (201420251605.3)" is large In addition, this patent is not applicable to the replacement and repair of the ballastless track slabs of high-speed railways. Therefore, in order to fundamentally solve the technical problem of rapid replacement and repair of the slab ballastless track slab within the skylight time without cutting the rail, the system formation is applicable to the straight section and curved section of the CRTS Ⅰ, Ⅱ, and Ⅲ slab ballastless track respectively. The track track plate replacement technology is a problem to be solved urgently in this field.

发明内容Contents of the invention

本发明针对切断钢轨情况下对轨道板进行更换的弊端,发明了一种适用于天窗时间内实施的、不切断钢轨情况下对伤损轨道板进行更换的方法及工装。该发明施工快捷、实用可靠、成本经济,为在天窗时间内实现对伤损轨道板的更换修复提供了一种快速、便捷、实用、经济的新方法。Aiming at the disadvantage of replacing the track slab when the rail is cut, the invention invents a method and tooling for replacing the damaged track slab without cutting the rail, which is suitable for implementation within the skylight time. The invention is fast in construction, practical and reliable, and economical in cost, and provides a fast, convenient, practical, and economical new method for replacing and repairing damaged track slabs within the skylight time.

本发明采用以下技术方案实现上述目的:The present invention adopts the following technical solutions to achieve the above object:

本发明涉及一种板式无砟轨道轨道板更换方法,所述更换方法包括更换工艺、设备工装以及注浆材料,具体为将待更换轨道板前后扣件松开一定长度,将钢轨顶高一定高度,将待更换轨道板进行顶升,使其与下部充填层砂浆脱离,在轨道板上安装具有多个吊点的吊具,通过轨道吊车以及吊具吊点的切换对被更换轨道板进行平移吊出以及新板的平移吊入,新板就位后,采用快硬注浆材料注入填充新轨道板与原脱粘层间隙,恢复钢轨和扣件。The invention relates to a method for replacing a track slab of a slab-type ballastless track. The replacement method includes a replacement process, equipment tooling and grouting materials, specifically, loosening the front and rear fasteners of the track slab to be replaced by a certain length, and raising the top of the rail to a certain height , lift the track plate to be replaced to separate it from the mortar of the lower filling layer, install a spreader with multiple lifting points on the track plate, and move the track plate to be replaced through the switching of the track crane and the lifting points of the spreader Hoisting out and lifting in of the new slab, after the new slab is in place, use fast-hardening grouting material to fill the gap between the new track slab and the original debonded layer, and restore the rails and fasteners.

一种板式无砟轨道轨道板更换方法,所述的轨道板更换工艺包含以下步骤:(1)待更换板位置定位标注;(2)扣件系统拆除;(3)轨温测试;(4)垂向抬轨;(5)待更换轨道板顶升;(6)旧板移出及新板移入;(7)轨道板粗铺与精调、钢轨与扣件恢复;(8)板底注胶;(9)线路精调。A method for replacing a track slab of a slab-type ballastless track. The track slab replacement process includes the following steps: (1) positioning and marking the position of the slab to be replaced; (2) removing the fastener system; (3) testing the rail temperature; (4) Vertical rail lifting; (5) Lifting of the track slab to be replaced; (6) Moving out of the old slab and moving in the new slab; (7) Rough laying and fine adjustment of the track slab, restoration of rails and fasteners; (8) Glue injection at the bottom of the slab ; (9) Line fine-tuning.

一种板式无砟轨道轨道板更换方法,所述的吊具通过轨道板吊装孔或板底横跨安装固定于轨道板,其具有多个吊点,吊具的一端可加长或拆卸,以便增减吊点,方便轨道板吊运。A method for replacing a track slab of a slab ballastless track. The sling is fixed on the track slab through the hoisting hole of the track slab or across the bottom of the slab. Reduce the lifting point to facilitate the lifting of the track slab.

一种板式无砟轨道轨道板更换方法,所述的轨道吊车由车头、平板车、吊装设备和液压支腿组成,须满足铁路安全出车条件,其可将新轨道板运送、吊装至换板地点,将旧轨道板吊离、拉运至指定地点。A method for replacing a track slab of a slab-type ballastless track. The track crane is composed of a locomotive, a flatbed truck, hoisting equipment and hydraulic outriggers, and must meet the conditions for safe departure of the railway. It can transport and hoist a new track slab to a replacement site , Lift and transport the old track slab to the designated place.

一种板式无砟轨道轨道板更换方法,所述的轨道吊车具有双组以上的吊装设备,当一组吊装设备出现故障,立即启用另外一组,以确保天窗作业可靠,不影响线路正点开通。A method for replacing a track slab of a slab-type ballastless track. The track crane has more than two sets of hoisting equipment. When one set of hoisting equipment fails, the other set is immediately activated to ensure reliable operation of the skylight without affecting the punctual opening of the line.

一种板式无砟轨道轨道板更换方法,所述的注浆设备压力调节范围为0.1MPa~50MPa、注浆流量调节范围为0L/min~200L/min、对注浆材料加热控温范围为10℃~100℃。A method for replacing a track plate of a slab ballastless track, the pressure adjustment range of the grouting equipment is 0.1MPa~50MPa, the grouting flow rate adjustment range is 0L/min~200L/min, and the temperature control range for the grouting material is 10 ℃~100℃.

一种板式无砟轨道轨道板更换方法,所述的注浆材料为具有膨胀性或无膨胀性的速凝快硬材料,可工作时间为5s~800s,1h抗压强度达设计强度的50%以上;速凝快硬材料为有机类速凝快硬材料聚氨酯、聚脲、环氧树脂、乙烯基树脂或不饱和聚酯等中的一种,或为无机类速凝快硬材料水玻璃—水泥体系、硫铝酸盐体系、铝酸盐和磷酸盐体系中的一种;所述注浆材料具有速凝快硬的特性,从而实现对新更换轨道板的定位,以满足承载与通车的功能要求。A method for replacing the track slab of a slab ballastless track, the grouting material is an expansive or non-expandable quick-setting rapid-hardening material, the working time is 5s~800s, and the 1h compressive strength reaches 50% of the design strength Above; the quick-setting quick-setting material is one of the organic quick-setting quick-setting materials polyurethane, polyurea, epoxy resin, vinyl resin or unsaturated polyester, or the inorganic quick-setting quick-setting material water glass— One of cement system, sulfoaluminate system, aluminate and phosphate system; the grouting material has the characteristics of quick setting and fast hardening, so as to realize the positioning of the newly replaced track slab to meet the load and traffic requirements feature request.

与现有无砟轨道轨道板更换技术相比,本发明具有以下优点:Compared with the existing ballastless track track slab replacement technology, the present invention has the following advantages:

(1)不切割钢轨,对线路扰动小、对钢轨损伤小;(1) No rail cutting, less disturbance to the line and less damage to the rail;

(2)所用工装设备轻便,故障率低,安全性高,确保不影响次日行车;(2) The tooling equipment used is light, with low failure rate and high safety, ensuring that it will not affect the next day's driving;

(3)工艺简单,便于天窗组织施工;(3) The process is simple, which is convenient for the organization and construction of skylights;

(4)所用注浆材料可较多选用无机水泥基材料,耐久性能、环保性能更好,经济性更高,可节省60%以上的修复材料成本;(4) The grouting materials used can be more inorganic cement-based materials, which have better durability, environmental performance, and higher economy, and can save more than 60% of the cost of repair materials;

(5)适用性高,既适用于直线段CRTSⅠ、Ⅱ、Ⅲ型无砟轨道轨道板更换,又适用于曲线段CRTSⅠ、Ⅱ、Ⅲ型无砟轨道轨道板更换。(5) High applicability, not only suitable for the replacement of track slabs of CRTS Ⅰ, Ⅱ, Ⅲ ballastless track in straight section, but also suitable for the track slab replacement of CRTS Ⅰ, Ⅱ, Ⅲ ballastless track in curved section.

综上所述,本发明与现有的轨道板明显不同,在不切断钢轨的条件下,利用天窗时间对伤损轨道板进行更换,并完成新换轨道板与脱粘层间的离缝灌浆修复以及轨道精调、恢复线路等任务,本发明具有施工快捷、成本经济、耐久环保、实用可靠、适用性高等诸多优势,技术经济性显著。To sum up, the present invention is obviously different from the existing track slabs. Under the condition of not cutting the rails, the damaged track slabs are replaced by using the skylight time, and the joint grouting between the newly replaced track slabs and the debonding layer is completed. For tasks such as repairing, track fine-tuning, and line restoration, the present invention has many advantages such as fast construction, low cost, durability and environmental protection, practicality and reliability, and high applicability, and the technical economy is remarkable.

附图说明Description of drawings

图1为本发明所提供的典型轨道板更换施工工艺流程图。Fig. 1 is a typical track slab replacement construction process flow chart provided by the present invention.

图2是典型的轨道板垂向吊起示意图。Figure 2 is a schematic diagram of a typical track slab vertically hoisted.

图3是典型的轨道板平移后落下示意图。Figure 3 is a schematic diagram of a typical track plate falling after translation.

图4是典型的轨道板更换吊装吊点示意图。Figure 4 is a schematic diagram of a typical track slab replacement hoisting point.

图5是典型的轨道板更换吊装吊点后继续向线间平移示意图。Figure 5 is a schematic diagram of a typical track slab that continues to translate between lines after replacing the hoisting point.

图6是典型的拆除吊具可拆卸段、更换吊点使轨道板具有垂向起吊空间示意图。Figure 6 is a typical schematic diagram of removing the detachable section of the spreader and replacing the lifting points so that the track plate has a vertical lifting space.

图7是典型将吊具固定于轨道板板底示意图。Figure 7 is a typical schematic diagram of fixing the spreader to the bottom of the track slab.

附图标记说明:Explanation of reference signs:

1—左线线路中心线;2-1—左线左轨;2-2—左线右轨;3—待更换轨道板;4—混凝土凸台挡台;5—混凝土底座板;6—轨道板吊装孔;7—吊具;7-1—吊点一;7-2—吊点二;7-3—吊点三;7-4—吊点四;7-5—吊点五;7-6—吊具可拆卸部件;8—水泥沥青砂浆充填层;9右线线路中心线;10-1—垫块;10-2—垫块。1—the center line of the left line; 2-1—the left rail of the left line; 2-2—the right rail of the left line; 3—the track plate to be replaced; 4—the concrete boss block; 5—the concrete base plate; 6—the track Plate hoisting hole; 7—sling; 7-1—hanging point one; 7-2—hanging point two; 7-3—hanging point three; 7-4—hanging point four; 7-5—hanging point five; 7 -6—Removable parts of spreader; 8—Cement asphalt mortar filling layer; 9—Center line of right line; 10-1—Cushion block; 10-2—Cushion block.

具体实施方式detailed description

以下通过具体实施例介绍本发明的实现和所具有的有益效果,但本发明并不局限于此,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The implementation and beneficial effects of the present invention will be described below through specific embodiments, but the present invention is not limited thereto, and the described embodiments are only some of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.

实施例1Example 1

本发明实施例1提供了一种用于双线直线段CRTSⅠ型无砟轨道轨道板更换方法,其工艺流程见图1,所述方法具体包括以下内容:Embodiment 1 of the present invention provides a method for replacing the track slab of CRTS I type ballastless track in the double-line straight section. The process flow is shown in Figure 1. The method specifically includes the following contents:

(1)按照电调命令,进行接触网停电、验电、挂地线,并做好相关防护措施;采用弹墨线、靠尺、钢尺、弦线等对原轨道板的平面及高程位置进行测量和标识,并做好数据记录,主要是原轨道板和邻近轨道板之间的相对位置,包括水平位置、板间距离、板间高差、凸台间隙具有定位轨道板状态的参数,标注轨道板移出、入线路并明显标示;(1) According to the ESC order, carry out catenary power outages, power inspections, ground wires, and take relevant protective measures; use ink lines, rulers, steel rulers, strings, etc. to check the plane and elevation positions of the original track slabs Measure and mark, and make data records, mainly the relative position between the original track slab and adjacent track slabs, including horizontal position, distance between plates, height difference between plates, boss clearance, parameters for positioning track slab status, and marking The track plate moves out and enters the line and is clearly marked;

(2)拆除需更换轨道板上所有零配件,拆除需抬起钢轨范围内的螺栓及轨距块,将凸台树脂凿除;(2) Remove all spare parts on the track plate that need to be replaced, remove the bolts and gauge blocks within the range of the rail that need to be lifted, and chisel off the boss resin;

(3)实测钢轨温度28℃,并与实际锁定轨温30℃进行比较,松开更换轨道板前后至少15米的扣件,将其上方钢轨2-1、2-2顶高30cm,如图2所示,同时,将合适高度的垫块置于轨下,以完全避免钢轨直接滑落等意外发生。待抬轨量达到30cm时,在起道点紧邻处以及按一定间距设置尺寸合适的垫块对抬起后的钢轨予以支撑稳固;(3) The measured rail temperature is 28°C, and compared with the actual locked rail temperature of 30°C, loosen the fasteners at least 15 meters before and after the replacement of the track plate, and raise the rails 2-1 and 2-2 above it by 30cm, as shown in the figure As shown in 2, at the same time, place pads of appropriate height under the rails to completely avoid accidents such as rails falling directly. When the amount of rail lifting reaches 30cm, set up pads of appropriate size at the place adjacent to the starting point and at a certain distance to support and stabilize the lifted rail;

(4)通过四个千斤顶将旧轨道板上同步均匀顶升,检查并确认轨道板与充填层砂浆的脱粘情况;(4) Lift the old track plate synchronously and evenly through four jacks, check and confirm the debonding of the track plate and the filling layer mortar;

(5)如图2,通过轨道板吊装孔6将具有多个吊点的吊具7安装固定于轨道板3,停于临线9的轨道吊车组通过该吊具7位于钢轨内外侧的吊点7-3、7-4将轨道板吊起20cm以上30cm以下,即高于混凝土凸台挡台4表面,低于钢轨2-1、2-2的底面,并留有2cm以上的安全距离,然后操作吊车将轨道板3向线间平移,待左侧吊绳接近钢轨2-2内侧时,放置垫块10-1、10-2,然后缓缓将轨道板3放于垫块10-1、10-2,如图3所示,更换吊具吊点至7-1、7-5,如图4所示,继续平移轨道3,直至左侧吊绳接近钢轨2-2内侧,移动垫块10-1、10-2至合适位置,将轨道板放至垫块10-1、10-2,如图5所示,然后将左侧吊点更换至吊点7-2,并将吊具7的可拆卸段7-6拆下,如图6所示,然后将轨道板3垂直吊走至平板车上待运;(5) As shown in Figure 2, install and fix the spreader 7 with multiple lifting points on the track plate 3 through the lifting hole 6 of the track plate, and the rail crane group parked on the line 9 passes through the hanger 7 located on the inner and outer sides of the rail. Points 7-3 and 7-4 lift the track slab by more than 20cm and less than 30cm, that is, higher than the surface of the concrete boss block 4, lower than the bottom surface of the rail 2-1, 2-2, and leave a safety distance of more than 2cm , and then operate the crane to translate the track plate 3 to the line. When the left hanging rope is close to the inner side of the rail 2-2, place the pads 10-1, 10-2, and then slowly put the track plate 3 on the pad 10- 1, 10-2, as shown in Figure 3, replace the hoisting points of the spreader to 7-1, 7-5, as shown in Figure 4, continue to translate the track 3 until the left hanging rope is close to the inside of the rail 2-2, move Put the pads 10-1, 10-2 to the appropriate position, put the track plate on the pads 10-1, 10-2, as shown in Figure 5, then replace the left lifting point with the lifting point 7-2, and place the The detachable section 7-6 of spreader 7 is pulled down, and as shown in Figure 6, track plate 3 is lifted vertically to the flatbed truck and waits to be transported then;

(6)对脱粘层水泥沥青砂浆充填层8表面进行检查,对残留浮渣进行打磨平整、清理干净;(6) Check the surface of the cement asphalt mortar filling layer 8 of the debonded layer, and polish and clean the residual scum;

(7)采用步骤(5)的逆操作将新轨道板移入至钢轨2-1、2-2下方;(7) Use the reverse operation of step (5) to move the new track plate under the rails 2-1 and 2-2;

(8)新轨道板按照测试的原轨道板状态进行粗放,采用精调爪对轨道板进行横、高程方向按原轨道板状态参数数据进行定位,并对轨道板位置进行复核;(8) The new track slab is extensively tested according to the state of the original track slab, and the horizontal and vertical directions of the track slab are positioned according to the state parameter data of the original track slab with fine adjustment claws, and the position of the track slab is rechecked;

(9)将2-1、2-2钢轨落回原位,将换板前后已松开的扣件拧入恢复;钢轨恢复时,同步进行凸台树脂灌注;(9) Drop the 2-1 and 2-2 rails back to their original positions, and screw in the fasteners that have been loosened before and after plate replacement; when the rails are restored, simultaneously carry out boss resin injection;

(10)根据新轨道板的轨道状态以及离缝状态,确定是否进行板底注胶,若新轨道板底与原脱粘表面离缝较大,采用注浆机将快硬注浆材料注入填充至新轨道板与原脱粘层间隙,注浆材料迅速固化,实现对新轨道板定位;(10) According to the state of the track of the new track slab and the state of the gap, determine whether to inject glue at the bottom of the slab. If the gap between the bottom of the new track slab and the original debonded surface is large, use a grouting machine to inject the fast-hardening grouting material into the filling When reaching the gap between the new track slab and the original debonded layer, the grouting material solidifies rapidly, realizing the positioning of the new track slab;

(11)对换板地段前后轨道状态进行全面测量,对线型进行分析,根据分析结果进行轨道微调,确保线路平顺性满足列车开通条件;(11) Conduct a comprehensive measurement of the track status before and after the plate replacement section, analyze the line type, and fine-tune the track according to the analysis results to ensure that the smoothness of the line meets the conditions for the opening of the train;

(12)拆除供电地线,对轨道结构、几何尺寸进行全面检查,清理现场,将工具全部撤出线路,然后开通线路;(12) Remove the power supply ground wire, conduct a comprehensive inspection of the track structure and geometric dimensions, clean up the site, remove all tools from the line, and then open the line;

(13)线路开通后,采用无线传输对换板区段的列车运行稳定性指标、轨道结构部件受力、轨道结构的稳定性指标、轨道刚度指标、轨道结构部件与基础振动加速度进行实时监控。若有异常,及时报告与处理。(13) After the line is opened, use wireless transmission to monitor the train operation stability index, the force of the track structure components, the stability index of the track structure, the track stiffness index, the track structure components and the vibration acceleration of the foundation in the plate replacement section in real time. If there is any abnormality, report and deal with it in time.

实施例2Example 2

本发明实施例2提供了一种用于双线直线段CRTSⅡ型无砟轨道轨道板更换方法,所述方法包括以下内容:Embodiment 2 of the present invention provides a method for replacing a track slab of a CRTS II ballastless track on a double-line straight section, and the method includes the following contents:

CRTSⅡ型无砟轨道轨道板更换方法与CRTSⅠ型无砟轨道轨道板更换方法基本相同,仅是由于CRTSⅡ型无砟轨道轨道板没有吊装孔,需要通过板底将吊具7固定于轨道板上,如图7所示。The replacement method of the CRTS Ⅱ ballastless track track slab is basically the same as that of the CRTS Ⅰ ballastless track slab replacement method, only because the CRTS Ⅱ ballastless track track slab has no hoisting holes, and the spreader 7 needs to be fixed on the track slab through the bottom of the slab. As shown in Figure 7.

Claims (5)

1.一种板式无砟轨道轨道板更换方法,其特征为:所述更换方法包括更换工艺、设备工装以及注浆材料,具体为将待更换轨道板前后扣件松开一定长度,将钢轨顶高一定高度,将待更换轨道板进行顶升,使其与下部充填层砂浆脱离,在轨道板上安装具有多个吊点的吊具,通过轨道吊车以及吊具吊点的切换对被更换轨道板进行平移吊出以及新板的平移吊入,新板就位后,采用快硬注浆材料注入填充新轨道板与原脱粘层间隙,恢复钢轨和扣件。1. A method for replacing track slabs of slab-type ballastless track, characterized in that: the replacement method includes replacing process, equipment tooling and grouting materials, specifically loosening the front and rear fasteners of the track slab to be replaced by a certain length, and the top of the rail To a certain height, lift the track slab to be replaced to separate it from the mortar of the lower filling layer, install a spreader with multiple lifting points on the track slab, and use the track crane and the switching of the lifting points of the spreader to replace the track The slab is lifted out in translation and the new slab is hoisted in. After the new slab is in place, fast-hardening grouting material is used to fill the gap between the new track slab and the original debonding layer, and restore the rails and fasteners. 2.如权利要求1所述的轨道板更换工艺,其特征在于包含以下步骤:(1)待更换板位置定位标注;(2)扣件系统拆除;(3)轨温测试;(4)垂向抬轨;(5)待更换轨道板顶升;(6)旧板移出及新板移入;(7)轨道板粗铺与精调、钢轨与扣件恢复;(8)板底注胶;(9)线路精调。2. The track slab replacement process according to claim 1, characterized in that it comprises the following steps: (1) positioning and marking the position of the slab to be replaced; (2) removing the fastener system; (3) testing the rail temperature; (4) vertically Lifting the rail; (5) Lifting the track plate to be replaced; (6) Moving out the old plate and moving in the new plate; (7) Rough laying and fine adjustment of the track plate, restoration of rails and fasteners; (8) Glue injection at the bottom of the plate; (9) Line fine-tuning. 3.如权利要求1所述的设备工装,其特征在于:所述的吊具通过轨道板吊装孔或板底横跨安装固定于轨道板,其具有多个吊点,吊具的一端可加长或拆卸,以便增减吊点,方便轨道板吊运。3. The equipment tooling according to claim 1, characterized in that: the spreader is installed and fixed on the track plate through the lifting hole of the track plate or the bottom of the plate across the installation, it has a plurality of lifting points, and one end of the spreader can be lengthened Or disassemble, in order to increase or decrease the lifting point, and facilitate the lifting of the track plate. 4.如权利要求1所述的设备工装,其特征在于:所述的注浆设备压力调节范围为0.1MPa~50MPa、注浆流量调节范围为0L/min~200L/min、对注浆材料加热控温范围为10℃~100℃。4. The equipment tooling as claimed in claim 1, characterized in that: the pressure adjustment range of the grouting equipment is 0.1MPa~50MPa, the grouting flow adjustment range is 0L/min~200L/min, and the grouting material is heated The temperature control range is 10°C~100°C. 5.如权利要求1所述的注浆材料,其特征在于:所述的注浆材料为具有膨胀性或无膨胀性的速凝快硬材料,可工作时间为5s~800s,1h抗压强度达设计强度的50%以上;速凝快硬材料为有机类速凝快硬材料聚氨酯、聚脲、环氧树脂、乙烯基树脂或不饱和聚酯等中的一种,或为无机类速凝快硬材料水玻璃—水泥体系、硫铝酸盐体系、铝酸盐和磷酸盐体系中的一种;所述注浆材料具有速凝快硬的特性,从而实现对新更换轨道板的定位,以满足承载与通车的功能要求。5. The grouting material as claimed in claim 1, characterized in that: the grouting material is an expansive or non-expandable quick-setting rapid-hardening material, the working time is 5s~800s, and the compressive strength is 1h reach more than 50% of the design strength; the quick-setting quick-setting material is one of the organic quick-setting quick-setting materials polyurethane, polyurea, epoxy resin, vinyl resin or unsaturated polyester, or the inorganic quick-setting material Rapid hardening material water glass—one of cement system, sulfoaluminate system, aluminate and phosphate system; the grouting material has the characteristics of rapid setting and rapid hardening, thereby realizing the positioning of the newly replaced track plate, In order to meet the functional requirements of carrying and opening to traffic.
CN201710343830.8A 2017-05-16 2017-05-16 A method for replacing a track plate of a slab ballastless track Pending CN107059506A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710343830.8A CN107059506A (en) 2017-05-16 2017-05-16 A method for replacing a track plate of a slab ballastless track

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710343830.8A CN107059506A (en) 2017-05-16 2017-05-16 A method for replacing a track plate of a slab ballastless track

Publications (1)

Publication Number Publication Date
CN107059506A true CN107059506A (en) 2017-08-18

Family

ID=59610266

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710343830.8A Pending CN107059506A (en) 2017-05-16 2017-05-16 A method for replacing a track plate of a slab ballastless track

Country Status (1)

Country Link
CN (1) CN107059506A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107826960A (en) * 2017-10-20 2018-03-23 甘肃酒钢集团宏兴钢铁股份有限公司 A method for replacing crane gantry spreader in a metallurgical workshop
CN108385456A (en) * 2018-03-07 2018-08-10 中国铁道科学研究院铁道建筑研究所 A kind of board-like ballastless track bed board integral replacing method of cast-in-place railway roadbed
CN108385454A (en) * 2018-03-07 2018-08-10 中国铁道科学研究院铁道建筑研究所 A kind of railway plate-type ballastless track working drawing review operational method
CN110106751A (en) * 2019-04-17 2019-08-09 中铁第四勘察设计院集团有限公司 A kind of sedimentation method of adjustment suitable for II plate-type non-fragment orbit of CRTS
CN110331627A (en) * 2019-06-24 2019-10-15 中铁二十一局集团第五工程有限公司 A method of for locked III plate of non-fragment orbit quick-replaceable CRTS of high-speed railway
CN111778786A (en) * 2020-08-21 2020-10-16 台州市天枢机械科技有限公司 A kind of railroad sleeper ballast removal device
CN112195688A (en) * 2020-09-28 2021-01-08 深圳大学 Replaceable track structure at the lesion
CN112921712A (en) * 2021-01-25 2021-06-08 中南大学 High-speed rail track plate structure and repairing method thereof

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5318149A (en) * 1989-03-25 1994-06-07 Alfons Moog Apparatus for inspecting the underside of bridges
US20020148378A1 (en) * 2001-04-11 2002-10-17 Franz Plasser Bahnbaumaschinen-Industriegesellschaft M.B.H. Method of renewing damaged ties of a track
CN201176365Y (en) * 2007-12-27 2009-01-07 中交第二航务工程局有限公司 Light-duty adjustable hanger
CN103147370A (en) * 2013-03-29 2013-06-12 中铁一局集团有限公司 Device and method for replacing track slab of slab ballastless track
CN103437290A (en) * 2013-07-25 2013-12-11 河北工业大学 Folding lower guide beam
CN104213478A (en) * 2014-08-29 2014-12-17 徐州徐工铁路装备有限公司 Maintenance construction method for ballast-less track of high-speed railway
CN104358211A (en) * 2014-10-16 2015-02-18 武汉二航路桥特种工程有限责任公司 Beam bottom overhaul platform capable of spanning bridge piers and obstacle pillars and use method of beam bottom overhaul platform
CN204982677U (en) * 2015-09-08 2016-01-20 贵州省公路工程集团有限公司 Steel longeron cable -stay bridge steel purlin girder segment section overheadhoist

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5318149A (en) * 1989-03-25 1994-06-07 Alfons Moog Apparatus for inspecting the underside of bridges
US20020148378A1 (en) * 2001-04-11 2002-10-17 Franz Plasser Bahnbaumaschinen-Industriegesellschaft M.B.H. Method of renewing damaged ties of a track
CN201176365Y (en) * 2007-12-27 2009-01-07 中交第二航务工程局有限公司 Light-duty adjustable hanger
CN103147370A (en) * 2013-03-29 2013-06-12 中铁一局集团有限公司 Device and method for replacing track slab of slab ballastless track
CN103437290A (en) * 2013-07-25 2013-12-11 河北工业大学 Folding lower guide beam
CN104213478A (en) * 2014-08-29 2014-12-17 徐州徐工铁路装备有限公司 Maintenance construction method for ballast-less track of high-speed railway
CN104358211A (en) * 2014-10-16 2015-02-18 武汉二航路桥特种工程有限责任公司 Beam bottom overhaul platform capable of spanning bridge piers and obstacle pillars and use method of beam bottom overhaul platform
CN204982677U (en) * 2015-09-08 2016-01-20 贵州省公路工程集团有限公司 Steel longeron cable -stay bridge steel purlin girder segment section overheadhoist

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
潘国瑞、杨荣山、刘笑凯、任娟娟: "CRTSⅠ型板式轨道维修的起道分析", 《中国铁路》 *
王涛、邵丕彦、李海燕、刘子科: "不锯轨更换桥上CRTSⅠ型轨道板研究与实践", 《铁道工程学报》 *

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107826960A (en) * 2017-10-20 2018-03-23 甘肃酒钢集团宏兴钢铁股份有限公司 A method for replacing crane gantry spreader in a metallurgical workshop
CN107826960B (en) * 2017-10-20 2019-06-21 甘肃酒钢集团宏兴钢铁股份有限公司 Method for replacing crown block gantry lifting appliance in metallurgical plant
CN108385456A (en) * 2018-03-07 2018-08-10 中国铁道科学研究院铁道建筑研究所 A kind of board-like ballastless track bed board integral replacing method of cast-in-place railway roadbed
CN108385454A (en) * 2018-03-07 2018-08-10 中国铁道科学研究院铁道建筑研究所 A kind of railway plate-type ballastless track working drawing review operational method
CN110106751A (en) * 2019-04-17 2019-08-09 中铁第四勘察设计院集团有限公司 A kind of sedimentation method of adjustment suitable for II plate-type non-fragment orbit of CRTS
CN110106751B (en) * 2019-04-17 2020-10-02 中铁第四勘察设计院集团有限公司 Settlement adjustment method suitable for CRTS II type plate ballastless track
CN110331627A (en) * 2019-06-24 2019-10-15 中铁二十一局集团第五工程有限公司 A method of for locked III plate of non-fragment orbit quick-replaceable CRTS of high-speed railway
CN111778786A (en) * 2020-08-21 2020-10-16 台州市天枢机械科技有限公司 A kind of railroad sleeper ballast removal device
CN111778786B (en) * 2020-08-21 2021-05-14 新昌县水帘峡市政园林有限公司 Railway sleeper ballast removing and dismounting device
CN112195688A (en) * 2020-09-28 2021-01-08 深圳大学 Replaceable track structure at the lesion
CN112921712A (en) * 2021-01-25 2021-06-08 中南大学 High-speed rail track plate structure and repairing method thereof
CN112921712B (en) * 2021-01-25 2022-02-11 中南大学 High-speed rail track plate structure and repairing method thereof

Similar Documents

Publication Publication Date Title
CN107059506A (en) A method for replacing a track plate of a slab ballastless track
CN101503870B (en) Construction method for two-block unballasted track bed board
CN109235292B (en) Railway bridge beam replacing process
CN108385451A (en) Board-like ballastless track boards replacing options under a kind of special operation condition
CN109235291B (en) Railway bridge beam replacing system
CN108374297B (en) Business Line tunnel, bridge section concrete sleeper swap method
CN106192620A (en) A kind of railway ballastless track supporting layer and substructure change method
CN106948228B (en) A kind of rapid replacement method of slab ballastless track track slab
CN109137633A (en) Level crossing mouth railway roadbed and preparation method
CN113152306B (en) Small-radius large-gradient prefabricated T beam frame construction method
CN105908583B (en) System for replacing ballast track bed of tunnel with ballastless track under condition of uninterrupted driving
CN117758549A (en) Construction process of ballastless track of urban railway
CN109338831B (en) Ballastless track deviation rectifying method based on rope saw cutting
CN108385456A (en) A kind of board-like ballastless track bed board integral replacing method of cast-in-place railway roadbed
CN111877060A (en) Ballastless track bed structure part replacement method
CN107059507B (en) A kind of curved section plate-type ballastless track track plates replacing options
CN108385454A (en) A kind of railway plate-type ballastless track working drawing review operational method
CN214459224U (en) A ballastless track structure suitable for long-span bridges
CN117107562A (en) Method for replacing high-speed rail curve super-high section ballastless track plate
CN117107563A (en) A method for replacing ballastless track slabs in the curved super-elevation section of the high-speed railway base section
CN105926381B (en) Method for replacing ballast track bed of tunnel with ballastless track under condition of uninterrupted driving
CN208995842U (en) Level crossing mouth railway roadbed
CN208038934U (en) Existing railway Disease Treatment of Foundation Base fixed track usage plan constructing structure
CN117738032A (en) Ballastless track temporary supporting structure and ballastless track deformation renovation method
CN202298390U (en) Ballastless track rush repair device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: No. 2, Da Liu Shu Road, Haidian District, Beijing

Applicant after: Railway Construction Research Institute of China Railway Research Institute Group Co., Ltd.

Applicant after: China Railway Scientific Research Institute Group Co., Ltd.

Address before: No. 2, Da Liu Shu Road, Haidian District, Beijing

Applicant before: Railway Construction Institute of China Academy of Railway Sciences

Applicant before: China Academy of Railway Sciences

CB02 Change of applicant information
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170818

WD01 Invention patent application deemed withdrawn after publication