CN210340091U - Column main reinforcement hoisting tool of concrete cast-in-place steel rib column - Google Patents

Column main reinforcement hoisting tool of concrete cast-in-place steel rib column Download PDF

Info

Publication number
CN210340091U
CN210340091U CN201920719030.6U CN201920719030U CN210340091U CN 210340091 U CN210340091 U CN 210340091U CN 201920719030 U CN201920719030 U CN 201920719030U CN 210340091 U CN210340091 U CN 210340091U
Authority
CN
China
Prior art keywords
post
owner muscle
sleeve
steel
platform sling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920719030.6U
Other languages
Chinese (zh)
Inventor
张雪峰
昝俊锋
贠子斌
屈磊
陈磊
吴东
李晓刚
付超斌
吴鹏
燕成飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SCEGC No 5 Construction Engineering Group Co Ltd
Original Assignee
SCEGC No 5 Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SCEGC No 5 Construction Engineering Group Co Ltd filed Critical SCEGC No 5 Construction Engineering Group Co Ltd
Priority to CN201920719030.6U priority Critical patent/CN210340091U/en
Application granted granted Critical
Publication of CN210340091U publication Critical patent/CN210340091U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a post owner muscle lifting device of cast-in-place reinforcing bar post of concrete, including the platform sling with install on the platform sling and with hoist complex lug, set up a plurality of through-holes that are used for spliced pole owner muscle on the platform sling, the one end of post owner muscle is passed through-hole and sleeve cooperation, post owner muscle is provided with the external screw thread with sleeve complex one end, post owner muscle is provided with the one end and the sleeve screw-thread fit of external screw thread, telescopic external diameter is greater than the internal diameter of through-hole. The utility model relates to a novelty utilizes the cooperation of post owner muscle, sleeve and platform sling, adopts the artifical mode of hoist cooperation, can install many post owner muscle handling, reduces the post reinforcing bar installation labour's of reinforcing bar post input and drop into labour's intensity of labour.

Description

Column main reinforcement hoisting tool of concrete cast-in-place steel rib column
Technical Field
The utility model belongs to the technical field of post owner muscle lifting device, concretely relates to post owner muscle lifting device of cast-in-place reinforcing bar post of concrete.
Background
In large-scale electronic factory building or logistics storage, its major structure is mostly the steel structure, cast in situ concrete mixed structure, and the main part construction in earlier stage mainly uses the steel structure construction as the main, accomplishes the steel structure installation back, carries out the cast in situ concrete construction again. In the overall structure of a factory building, a steel rib column is a main stress component, column main reinforcements of the steel rib column are designed in a plurality of modes, the steel reinforcement types are large, and the column main reinforcements of the traditional steel rib column are installed by adopting manual carrying or hoisting one by one and other methods.
SUMMERY OF THE UTILITY MODEL
The utility model aims to solve the technical problem that not enough among the above-mentioned prior art is directed against, provide a post owner muscle lifting device of cast-in-place reinforcing bar post of concrete, its novel in design is reasonable, utilizes the cooperation of post owner muscle, sleeve and platform sling, adopts the artifical mode of hoist cooperation, can install many post owner muscle handling, reduces the post reinforcing bar installation labour's of reinforcing bar post input and the intensity of labour that drops into, convenient to popularize and use.
In order to solve the technical problem, the utility model discloses a technical scheme is: the utility model provides a post owner muscle lifting device of cast-in-place reinforcing bar post of concrete which characterized in that: including the platform sling and install on the platform sling and with hoist complex lug, set up a plurality of through-holes that are used for spliced pole owner muscle on the platform sling, the through-hole is passed to the one end of post owner muscle and sleeve cooperation, and post owner muscle is provided with the external screw thread with sleeve complex one end, and post owner muscle is provided with the one end and the sleeve screw-thread fit of external screw thread, and telescopic external diameter is greater than the internal diameter of through-hole.
Foretell post owner muscle lifting device of cast-in-place reinforcing bar post of concrete, its characterized in that: the number of the sleeves is multiple, and the number of the sleeves is equal to that of the through holes and corresponds to that of the through holes one by one.
Foretell post owner muscle lifting device of cast-in-place reinforcing bar post of concrete, its characterized in that: the hanging scaffold is a steel hanging scaffold, and the lifting lugs are steel lifting lugs.
Foretell post owner muscle lifting device of cast-in-place reinforcing bar post of concrete, its characterized in that: the steel lifting lug is welded on the steel lifting platform and is positioned at the center of the steel lifting platform.
Foretell post owner muscle lifting device of cast-in-place reinforcing bar post of concrete, its characterized in that: the sleeve is arranged on the end face of the hanging scaffold welded with the lifting lugs.
Foretell post owner muscle lifting device of cast-in-place reinforcing bar post of concrete, its characterized in that: the inner diameter of the through hole is larger than the outer diameter of the column main rib.
Compared with the prior art, the utility model has the following advantage:
1. the utility model discloses a set up a plurality of through-holes on the platform sling, every through-hole supplies a post owner muscle to pass, and the sleeve is installed to the one end that post owner muscle passed through-hole on the platform sling, sleeve and platform sling joint, make the cooperation of post owner muscle, sleeve and platform sling become an organic whole, the whole handling installation of being convenient for, convenient to popularize and use.
2. The utility model discloses a set up the lug on the platform sling, utilize the cooperation of lug and hoist, realize mechanized operation, reduce the post reinforcing bar installation labour's of reinforcing bar post input and drop into labour's intensity of labour, reliable stable, excellent in use effect.
3. The utility model relates to a novelty is reasonable, and post owner muscle lifting device simple manufacture, and repeatedly usable, easy operation in the work progress can solve the direct handling installation of post owner muscle, practices thrift construction cost, convenient to popularize and use.
To sum up, the utility model relates to a novelty is reasonable, utilizes the cooperation of post owner muscle, sleeve and platform sling, adopts the artifical mode of hoist cooperation, can install many post owner muscle handling, reduces the post reinforcing bar installation labour's of reinforcing bar post input and drop into labour's intensity of labour, convenient to popularize and use.
The technical solution of the present invention is further described in detail by the accompanying drawings and examples.
Drawings
Fig. 1 is a usage state diagram of the present invention.
Fig. 2 is a schematic structural diagram of the present invention.
Description of reference numerals:
1-hanging scaffold; 2, lifting lugs; 3-column main reinforcement;
4, sleeving a sleeve; 5-through hole.
Detailed Description
As shown in fig. 1 and 2, the utility model discloses a platform sling 1 with install on platform sling 1 and with hoist complex lug 2, set up a plurality of through-holes 5 that are used for spliced pole owner muscle 3 on the platform sling 1, the one end of post owner muscle 3 is passed through-hole 5 and is cooperated with sleeve 4, post owner muscle 3 is provided with the external screw thread with sleeve 4 complex one end, post owner muscle 3 is provided with the one end and the sleeve 4 screw-thread fit of external screw thread, sleeve 4's external diameter is greater than the internal diameter of through-hole 5.
It should be noted that a plurality of through holes 5 are formed in the hanging scaffold 1, each through hole 5 is used for a column main rib 3 to pass through, a sleeve 4 is installed at one end of each column main rib 3, which passes through the through hole 5 in the hanging scaffold 1, and the sleeves 4 are clamped with the hanging scaffold 1, so that the column main ribs 3, the sleeves 4 and the hanging scaffold 1 are matched into a whole, and the integral hanging and installation are facilitated; the lifting lugs 2 are arranged on the hanging scaffold 1, and the mechanical operation is realized by utilizing the matching of the lifting lugs 2 and the lifting appliance, so that the investment of installation labor force of the column steel bars 3 of the steel rib column and the labor intensity of labor force investment are reduced, and the operation is reliable and stable; the column main rib hoisting tool is simple to manufacture and can be repeatedly used, the operation is simple in the construction process, the direct hoisting and installation of the column main ribs can be realized, the construction cost is saved, the purpose that the outer diameter of the sleeve 4 is larger than the inner diameter of the through hole 5 is to avoid the situation that the sleeve 4 cannot abut against the hanging scaffold 1, and the installation failure of the column main ribs 3 is caused.
In this embodiment, the number of the sleeves 4 is plural, and the number of the sleeves 4 is equal to the number of the through holes 5 and corresponds to one another.
In this embodiment, the hanging scaffold 1 is a steel hanging scaffold, and the lifting lug 2 is a steel lifting lug.
It should be noted that the hanging scaffold 1 is made of steel and the hanging lugs 2 are made of steel so as to meet the requirement of construction strength and avoid the damage to the hanging scaffold 1 due to the self weight of the column steel bars 3.
In this embodiment, the steel lifting lug is welded on the steel platform sling and is located at the center of the steel platform sling.
It should be noted that the purpose of welding the steel lifting lugs on the steel platform sling and locating at the center of the steel platform sling is to keep the stress balance of the steel platform sling, facilitate the lifting of the lifting appliance, realize the vertical lifting of the column steel bars 3, and avoid unnecessary damage to surrounding buildings and constructors caused by the inclination of the column steel bars 3.
In this embodiment, the sleeve 4 is arranged on the end surface of the hanging scaffold 1 to which the lifting lug 2 is welded.
It should be noted that the sleeve 4 is arranged on the end face of the hanging scaffold 1 welded with the lifting lugs 2, so that the unloading direction of the column steel bars 3 is kept on the same side, and the simultaneous installation of a plurality of column steel bars 3 of the same steel column is realized.
In this embodiment, the inner diameter of the through hole 5 is larger than the outer diameter of the column main rib 3.
It should be noted that, the purpose that the internal diameter of through-hole 5 is greater than the external diameter of post owner muscle 3 is to satisfy the use of the post owner muscle 3 of multiple model, through the cooperation of the sleeve 4 of the post owner muscle 3 of different models and corresponding size, reduces the preparation quantity of platform sling 1, and the commonality is strong.
The utility model discloses during the use, be provided with many post owner muscle 3 one end of external screw thread and stretch into in the through-hole 5 that platform sling 1 corresponds, be connected post owner muscle 3 and platform sling 1 through sleeve 4 on the another side of platform sling 1, utilize the cooperation of hoist and lug 2, lift by crane many post owner muscle 3 simultaneously and install to the reinforcing bar post that corresponds in, reduce the post reinforcing bar installation labour's of reinforcing bar and drop into labour's intensity of labour, it is efficient.
The above, only be the utility model discloses a preferred embodiment, it is not right the utility model discloses do any restriction, all according to the utility model discloses the technical entity all still belongs to any simple modification, change and the equivalent structure change of doing above embodiment the utility model discloses technical scheme's within the scope of protection.

Claims (6)

1. The utility model provides a post owner muscle lifting device of cast-in-place reinforcing bar post of concrete which characterized in that: including platform sling (1) and install on platform sling (1) and with hoist complex lug (2), set up a plurality of through-holes (5) that are used for spliced pole owner muscle (3) on platform sling (1), the one end of post owner muscle (3) is passed through-hole (5) and is cooperated with sleeve (4), post owner muscle (3) is provided with the external screw thread with sleeve (4) complex one end, post owner muscle (3) are provided with the one end and the sleeve (4) screw-thread fit of external screw thread, the external diameter of sleeve (4) is greater than the internal diameter of through-hole (5).
2. The column main reinforcement hoisting tool of the concrete cast-in-place steel reinforced column according to claim 1, characterized in that: the number of the sleeves (4) is multiple, and the number of the sleeves (4) is equal to that of the through holes (5) and corresponds to that of the through holes one to one.
3. The column main reinforcement hoisting tool of the concrete cast-in-place steel reinforced column according to claim 1, characterized in that: the hanging scaffold (1) is a steel hanging scaffold, and the lifting lugs (2) are steel lifting lugs.
4. The column main reinforcement hoisting tool of the concrete cast-in-place steel reinforced column according to claim 3, characterized in that: the steel lifting lug is welded on the steel lifting platform and is positioned at the center of the steel lifting platform.
5. The column main reinforcement hoisting tool of the concrete cast-in-place steel reinforced column according to claim 1, characterized in that: the sleeve (4) is arranged on the end face of the hanging scaffold (1) welded with the lifting lugs (2).
6. The column main reinforcement hoisting tool of the concrete cast-in-place steel reinforced column according to claim 1, characterized in that: the inner diameter of the through hole (5) is larger than the outer diameter of the column main rib (3).
CN201920719030.6U 2019-05-18 2019-05-18 Column main reinforcement hoisting tool of concrete cast-in-place steel rib column Active CN210340091U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920719030.6U CN210340091U (en) 2019-05-18 2019-05-18 Column main reinforcement hoisting tool of concrete cast-in-place steel rib column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920719030.6U CN210340091U (en) 2019-05-18 2019-05-18 Column main reinforcement hoisting tool of concrete cast-in-place steel rib column

Publications (1)

Publication Number Publication Date
CN210340091U true CN210340091U (en) 2020-04-17

Family

ID=70183585

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920719030.6U Active CN210340091U (en) 2019-05-18 2019-05-18 Column main reinforcement hoisting tool of concrete cast-in-place steel rib column

Country Status (1)

Country Link
CN (1) CN210340091U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111591876A (en) * 2020-07-24 2020-08-28 胜利油田新大管业科技发展有限责任公司 Backing plate lifting appliance, backing plate paving equipment and paving method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111591876A (en) * 2020-07-24 2020-08-28 胜利油田新大管业科技发展有限责任公司 Backing plate lifting appliance, backing plate paving equipment and paving method
CN111591876B (en) * 2020-07-24 2020-10-23 胜利油田新大管业科技发展有限责任公司 Backing plate lifting appliance, backing plate paving equipment and paving method

Similar Documents

Publication Publication Date Title
CN106988299B (en) The pay-off method of assembled steel reinforced cage descending frame and steel reinforcement cage
CN104480930B (en) A kind of filling pile cage of reinforcement hangs fixing construction method
CN102261067A (en) Method for installing reinforcement cage of large-diameter ultra-long pile
CN210439705U (en) Precast concrete superimposed sheet hoist device
CN206428964U (en) A kind of Combined aluminum plate device for building
CN210340091U (en) Column main reinforcement hoisting tool of concrete cast-in-place steel rib column
CN100429375C (en) Formworkfor elevator well of high rising building and construction method thereof
CN107043072B (en) Falling-beam-free integrated inner climbing tower crane supporting device and implementation method
CN210619969U (en) Prefabricated staircase hoist and mount subassembly
CN211141282U (en) Steel reinforcement cage installation hoist device
CN218619794U (en) Prefabricated stand special lifting device based on UHPC connects
CN102777036A (en) Air reverse mechanical joint construction method of super-long vertical reinforcement cage
CN104528519A (en) Clamping tool for assisting in hoisting cement electric poles
CN212712478U (en) Dismounting device for cargo boom and balance arm of tower crane
CN210620081U (en) Cantilever crane device suitable for dismantling external scaffold of assembled high-rise residence
CN102704691A (en) Whole-bundle disanchoring device and disanchoring method adopting same
CN111794120A (en) Device for mounting thin-wall box-shaped structural steel bars of bridge tower
CN202689531U (en) Flexible and retractable climbing shuttering system for single-cylinder-body structure
CN204199271U (en) A kind of filling pile cage of reinforcement hangs fastening devices
CN216638684U (en) Lifting and hanging device
CN201362860Y (en) Building concrete pile detection device
CN218881561U (en) Combined building template
CN221545624U (en) Self-adaptive quick-dismantling steel bar structure hoisting interface
CN213173755U (en) Beam column type support steel-pipe pile pothook
CN220336401U (en) Open caisson operation platform structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant