CN210151664U - Slope protective structure for hydraulic and hydroelectric engineering - Google Patents

Slope protective structure for hydraulic and hydroelectric engineering Download PDF

Info

Publication number
CN210151664U
CN210151664U CN201920506743.4U CN201920506743U CN210151664U CN 210151664 U CN210151664 U CN 210151664U CN 201920506743 U CN201920506743 U CN 201920506743U CN 210151664 U CN210151664 U CN 210151664U
Authority
CN
China
Prior art keywords
baffle
plate
fixedly connected
groove
connecting plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201920506743.4U
Other languages
Chinese (zh)
Inventor
陈兵
曾荣福
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Guiyang Engineering Corp Ltd
Original Assignee
PowerChina Guiyang Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Guiyang Engineering Corp Ltd filed Critical PowerChina Guiyang Engineering Corp Ltd
Priority to CN201920506743.4U priority Critical patent/CN210151664U/en
Application granted granted Critical
Publication of CN210151664U publication Critical patent/CN210151664U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Sewage (AREA)

Abstract

The utility model discloses a side slope protective structure that hydraulic and hydroelectric engineering used, including the bank protection body, the water drainage tank has been seted up to one side that the bank protection body is close to the top, the first board that buries of one side fixedly connected with of bank protection body, the first baffle of one side fixedly connected with of burying the board, first draw-in groove has been seted up to one side of first baffle, first baffle is close to one side of first draw-in groove and has been seted up first spout, first baffle is kept away from one side of first draw-in groove and has been seted up the second draw-in groove, first baffle is close to one side of second draw-in groove and has been seted up the second spout. The utility model discloses can solve the slope protective structure that current hydraulic and hydroelectric engineering used, install inconvenient problem.

Description

Slope protective structure for hydraulic and hydroelectric engineering
Technical Field
The utility model relates to a technical field is consolidated to the side slope, a side slope protective structure that hydraulic and hydroelectric engineering used.
Background
The common protective measures for slope engineering include plant protection, engineering protection (sash protection, cover protection, net hanging guniting protection, stone building protection and the like), geotextile protection and the like. In actual engineering application, one of slope treatment measures can be selected or combined according to factors such as the position of a slope place, geological conditions and the like, but the sash protection device is time-consuming and labor-consuming to install, so that improvement is needed.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a side slope protective structure that hydraulic and hydroelectric engineering used to solve the side slope protective structure that current hydraulic and hydroelectric engineering used, install inconvenient problem.
In order to achieve the above object, the utility model provides a following technical scheme:
the utility model provides a side slope protective structure that hydraulic and hydroelectric engineering used, includes the bank protection body, the water drainage tank has been seted up to one side that the bank protection body is close to the top, the first board that buries of one side fixedly connected with of bank protection body, the first baffle of one side fixedly connected with of first board that buries, first draw-in groove has been seted up to one side of first baffle, first baffle is close to one side of first draw-in groove and has been seted up first spout, first baffle is kept away from one side of first draw-in groove and has been seted up the second draw-in groove, first baffle is close to one side of second draw-in groove and has been seted up.
Optionally, the inner portion of the first baffle is movably connected with a first connecting plate and a second connecting plate, one side of the first connecting plate and one side of the second connecting plate are respectively fixedly connected with a first clamping block and a second clamping block, and the first clamping block is clamped in the first clamping groove.
Optionally, the second clamping block is clamped inside the second clamping groove, and one side of the first connecting plate is fixedly connected with the first cross plate and the second cross plate respectively.
Optionally, one end of each of the first cross plate and the second cross plate, which is far away from the first connecting plate, is fixedly connected with the second connecting plate, and a precast plate stop block is fixedly connected to the centers of the first cross plate and the second cross plate.
Optionally, one side fixedly connected with prefabricated column of prefabricated plate dog, the slope protection body is close to one side fixedly connected with second of bottom and buries the board, the top fixedly connected with second baffle of board is buried to the second.
Optionally, the first buried plate, the first baffle, the first connecting plate, the second connecting plate, the first fixture block, the second fixture block, the first cross plate, the second cross plate, the prefabricated plate stop block, the prefabricated column, the second buried plate and the second baffle are all made of reinforced concrete, a connection angle between the first buried plate and the first baffle is an obtuse angle, the first baffle is perpendicular to the slope, and an angle at which the second buried plate is connected with the second baffle is ninety degrees.
The utility model discloses following technological effect has:
(1) this side slope protective structure that hydraulic and hydroelectric engineering used, through setting up first baffle, two draw-in grooves and two spouts have been seted up to the inside of the first baffle of one side fixedly connected with of first buried plate, bury the inside of bank protection body with first buried plate during use and fix, first baffle is perpendicular with domatic, then put the inside of first spout and second spout with first connecting plate and second connecting plate, the inside of first draw-in groove and second draw-in groove is gone into to first fixture block and second fixture block card respectively, the mode of joint is more convenient, labour saving and time saving's purpose has been reached, through setting up prefabricated post, connecting plate and the cross slab that the joint entered are fixed through the fixed connection of prefabricated post and bank protection body during the use, reach the mesh that reduces the rainwash.
(2) This side slope protective structure that hydraulic and hydroelectric engineering used, through setting up water drainage tank and second baffle, the water drainage tank has been seted up to one side that the bank protection body is close to the top, and the rainwater on slope top can discharge through water drainage tank, reaches the purpose that reduces the erodeing, and the top fixedly connected with second baffle of board is buried to the second, buries the board with the second during the use and buries the bottom of bank protection body, and the second baffle can stop the rainwater down-flow on the bank protection, reduces soil erosion and water loss.
Drawings
Fig. 1 is a schematic perspective view of the present invention;
FIG. 2 is a schematic side view of the present invention;
FIG. 3 is a schematic structural view of a first baffle of the present invention;
fig. 4 is a schematic structural diagram of the first connecting plate of the present invention.
Description of reference numerals: the slope protection structure comprises the following components, by weight, 1-a slope protection body, 2-a drainage channel, 3-a first embedded plate, 4-a first baffle, 5-a first sliding groove, 6-a second clamping groove, 7-a second sliding groove, 8-a first connecting plate, 9-a second connecting plate, 10-a first clamping block, 11-a second clamping block, 12-a first cross plate, 13-a second cross plate, 14-a prefabricated plate stop block, 15-a prefabricated column, 16-a second embedded plate, 17-a second baffle and 18-a first clamping groove.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "mounted", "provided", "sleeved/connected", "connected", and the like are to be understood in a broad sense, such as "connected", which may be fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
Example 1:
a side slope protection structure for water conservancy and hydropower engineering comprises a slope protection body 1, wherein one side of the slope protection body 1 close to the top is provided with a drainage channel 2, rainwater on the slope top can be drained through the drainage channel 2 to achieve the purpose of reducing scouring, one side of the slope protection body 1 is fixedly connected with a first embedded plate 3, when in use, the first embedded plate 3 is embedded into the slope protection body 1 to be fixed, one side of the first embedded plate 3 is fixedly connected with a first baffle plate 4, the first baffle plate 4 is vertical to a slope surface, one side of the first baffle plate 4 is provided with a first clamping groove 18, one side of the first baffle plate 4 close to the first clamping groove 18 is provided with a first chute 5, one side of the first baffle plate 4 far away from the first clamping groove 18 is provided with a second clamping groove 6, one side of the first baffle plate 4 close to the second clamping groove 6 is provided with a second chute 7, a first connecting plate 8 and a second connecting plate 9 are placed into the first chute 5 and the, the first latch 10 and the second latch 11 are respectively latched inside the first latch groove 18 and the second latch groove 6.
As an optional technical solution of the utility model:
the inside swing joint of first baffle 4 has first connecting plate 8 and second connecting plate 9, and one side of first connecting plate 8 and second connecting plate 9 is the first fixture block 10 of fixedly connected with and second fixture block 11 respectively, and first fixture block 10 joint is in the inside of first draw-in groove 18.
As an optional technical solution of the utility model:
the second clamping block 11 is clamped inside the second clamping groove 6, and one side of the first connecting plate 8 is fixedly connected with a first cross plate 12 and a second cross plate 13 respectively.
As an optional technical solution of the utility model:
one ends of the first cross plate 12 and the second cross plate 13 far away from the first connecting plate 8 are fixedly connected with the second connecting plate 9, and a precast slab stop 14 is fixedly connected at the centers of the first cross plate 12 and the second cross plate 13.
As an optional technical solution of the utility model:
prefabricated post 15 of one side fixedly connected with of prefabricated plate dog 14, the connecting plate and the cross slab that the joint was gone into are fixed through prefabricated post 15 and the fixed connection of bank protection body 1 during the use, bank protection body 1 buries board 16 near the one side fixedly connected with second of bottom, the top fixedly connected with second baffle 17 of board 16 is buried to the second, bury board 16 the bottom of bank protection body 1 with the second during the use, second baffle 17 can stop the rainwater of down-flow on the bank protection, reduce soil erosion and water loss.
As an optional technical solution of the utility model:
the first buried plate 3, the first baffle plate 4, the first connecting plate 8, the second connecting plate 9, the first clamping block 10, the second clamping block 11, the first cross plate 12, the second cross plate 13, the precast slab baffle plate 14, the precast column 15, the second buried plate 16 and the second baffle plate 17 are all made of reinforced concrete, the connecting angle of the first buried plate 3 and the first baffle plate 4 is an obtuse angle, the first baffle plate 4 is perpendicular to the slope surface, and the angle of the second buried plate 16 connected with the second baffle plate 17 is ninety degrees.
When using, bury the inside of board 3 and bury slope protection body 1 and fix, first baffle 4 is perpendicular with domatic, then put first spout 5 and second spout 7's inside with first connecting plate 8 and second connecting plate 9, first fixture block 10 and second fixture block 11 are gone into first draw-in groove 18 and second draw-in groove 6's inside respectively, connecting plate and the cross board that the joint was entered through prefabricated post 15 and slope protection body 1's fixed connection during the use are fixed, the rainwater on the top of the slope can discharge through water drainage tank 2, bury the bottom that board 16 buries slope protection body 1 with the second during the use, second baffle 17 can stop the rainwater of down-flow on the slope protection.
To sum up, the slope protection structure for the water conservancy and hydropower engineering is used, when in use, the first baffle 4 is arranged, the first baffle 4 is fixedly connected to one side of the first embedded plate 3, two clamping grooves and two sliding grooves are formed in the first baffle 4, the first embedded plate 3 is embedded into the slope protection body 1 to be fixed when in use, the first baffle 4 is perpendicular to the slope surface, then the first connecting plate 8 and the second connecting plate 9 are placed in the first sliding groove 5 and the second sliding groove 7, the first clamping block 10 and the second clamping block 11 are respectively clamped into the first clamping groove 18 and the second clamping groove 6, the clamping mode is more convenient, the purposes of saving time and labor are achieved, the prefabricated column 15 is arranged, the connecting plate clamped into the prefabricated column 15 and the cross plate are fixed through the fixed connection of the prefabricated column 15 and the slope protection body 1 when in use, the purpose of reducing rainwater erosion is achieved, and the drainage groove 2 and the second baffle 17 are arranged, water drainage tank 2 has been seted up to slope protection body 1 one side near the top, and the rainwater on slope top can discharge through water drainage tank 2, reaches the purpose that reduces and erode, and the top fixedly connected with second baffle 17 of board 16 is buried to the second, buries board 16 with the second during the use and buries the bottom of slope protection body 1, and second baffle 17 can stop the rainwater of down-flow on the slope protection, reduces soil erosion and water loss.
Although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments or portions thereof without departing from the spirit and scope of the invention.

Claims (6)

1. The utility model provides a side slope protective structure that hydraulic and hydroelectric engineering used, includes slope protection body (1), its characterized in that: drainage channel (2) have been seted up to one side that bank protection body (1) is close to the top, first board (3) of burying of one side fixedly connected with of bank protection body (1), first baffle (4) of one side fixedly connected with of board (3) are buried to the first side, first draw-in groove (18) have been seted up to one side of first baffle (4), first spout (5) have been seted up to one side that first baffle (4) are close to first draw-in groove (18), second draw-in groove (6) have been seted up to one side that first baffle (4) were kept away from first draw-in groove (18), second spout (7) have been seted up to one side that first baffle (4) are close to second draw-in groove (6).
2. The slope protective structure that hydraulic and hydroelectric engineering used of claim 1, characterized in that: the inside swing joint of first baffle (4) has first connecting plate (8) and second connecting plate (9), one side of first connecting plate (8) and second connecting plate (9) is first fixture block (10) of fixedly connected with and second fixture block (11) respectively, first fixture block (10) joint is in the inside of first draw-in groove (18).
3. The slope protective structure that hydraulic and hydroelectric engineering used according to claim 2, characterized in that: the second clamping block (11) is clamped inside the second clamping groove (6), and one side of the first connecting plate (8) is fixedly connected with a first cross plate (12) and a second cross plate (13) respectively.
4. The slope protective structure that hydraulic and hydroelectric engineering used according to claim 3, characterized in that: one ends, far away from the first connecting plate (8), of the first cross plate (12) and the second cross plate (13) are fixedly connected with the second connecting plate (9), and precast plate stoppers (14) are fixedly connected to the centers of the first cross plate (12) and the second cross plate (13).
5. The slope protective structure that hydraulic and hydroelectric engineering used according to claim 4, characterized in that: one side fixedly connected with prefabricated post (15) of prefabricated plate dog (14), slope protection body (1) is close to one side fixedly connected with second of bottom and buries board (16), the top fixedly connected with second baffle (17) of board (16) are buried to the second.
6. The slope protective structure that hydraulic and hydroelectric engineering used of claim 1, characterized in that: the first buried plate (3), the first baffle (4), the first connecting plate (8), the second connecting plate (9), the first clamping block (10), the second clamping block (11), the first cross plate (12), the second cross plate (13), the prefabricated plate stop block (14), the prefabricated column (15), the second buried plate (16) and the second baffle (17) are all made of reinforced concrete, the connecting angle of the first buried plate (3) and the first baffle (4) is an obtuse angle, the first baffle (4) is perpendicular to the slope surface, and the angle of the second buried plate (16) connected with the second baffle (17) is ninety degrees.
CN201920506743.4U 2019-04-15 2019-04-15 Slope protective structure for hydraulic and hydroelectric engineering Withdrawn - After Issue CN210151664U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920506743.4U CN210151664U (en) 2019-04-15 2019-04-15 Slope protective structure for hydraulic and hydroelectric engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920506743.4U CN210151664U (en) 2019-04-15 2019-04-15 Slope protective structure for hydraulic and hydroelectric engineering

Publications (1)

Publication Number Publication Date
CN210151664U true CN210151664U (en) 2020-03-17

Family

ID=69756951

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920506743.4U Withdrawn - After Issue CN210151664U (en) 2019-04-15 2019-04-15 Slope protective structure for hydraulic and hydroelectric engineering

Country Status (1)

Country Link
CN (1) CN210151664U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109958100A (en) * 2019-04-15 2019-07-02 中国电建集团贵阳勘测设计研究院有限公司 A kind of slope protection structure and means of defence of hydraulic and hydroelectric engineering

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109958100A (en) * 2019-04-15 2019-07-02 中国电建集团贵阳勘测设计研究院有限公司 A kind of slope protection structure and means of defence of hydraulic and hydroelectric engineering
CN109958100B (en) * 2019-04-15 2024-03-01 中国电建集团贵阳勘测设计研究院有限公司 Side slope protection structure and protection method for hydraulic and hydroelectric engineering

Similar Documents

Publication Publication Date Title
CN208563522U (en) A kind of side slope riding track Rainwater collection system
CN210151664U (en) Slope protective structure for hydraulic and hydroelectric engineering
CN109958100B (en) Side slope protection structure and protection method for hydraulic and hydroelectric engineering
CN211621620U (en) Slope stabilizing and supporting structure
CN201162228Y (en) Shore-protection structure
CN109371947A (en) A kind of ocean engineering platform anticorrosion shell structure and construction method
CN201598645U (en) Advanced water stop post-pouring belt for base soleplate
CN211498867U (en) A envelope for underground works excavation foundation ditch engineering on a large scale
CN212223776U (en) Novel hydraulic engineering side slope construction protection system
CN211849708U (en) Water film waterscape
CN107401205A (en) A kind of karst depression rainfall utilizes system
CN205171533U (en) Drainage structures of courtyard sinks
CN216075174U (en) Foundation pit slope supporting structure
CN216130131U (en) Foundation ditch prevention of seepage supporting construction
CN214883839U (en) Concrete retaining wall with bearing structure and be convenient for assembly
CN204059378U (en) The priming device of deep-foundation side wall
CN211143096U (en) Deep foundation pit drainage structure
CN211172068U (en) Soil ecological remediation structure
CN211922503U (en) Hydraulic engineering bank protection
CN209179064U (en) A kind of outdoor switch case well head basis
CN212129240U (en) Drainage well lid for building engineering
CN220977882U (en) Ecological level ditch slope protection structure
CN214401285U (en) Urban road seepage prevention design structure
CN217104934U (en) Slope body bearing structure for hydraulic engineering
CN214994054U (en) Stepped high-ecological retaining wall

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20200317

Effective date of abandoning: 20240301

AV01 Patent right actively abandoned

Granted publication date: 20200317

Effective date of abandoning: 20240301