CN210032685U - Construction thickness adjusting device of regularization screeding - Google Patents

Construction thickness adjusting device of regularization screeding Download PDF

Info

Publication number
CN210032685U
CN210032685U CN201920533359.3U CN201920533359U CN210032685U CN 210032685 U CN210032685 U CN 210032685U CN 201920533359 U CN201920533359 U CN 201920533359U CN 210032685 U CN210032685 U CN 210032685U
Authority
CN
China
Prior art keywords
rib
thickness adjusting
punching
shaped
leveling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920533359.3U
Other languages
Chinese (zh)
Inventor
柴慧豪
吴坚
伍维强
陈伟
刘斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Northwest Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201920533359.3U priority Critical patent/CN210032685U/en
Application granted granted Critical
Publication of CN210032685U publication Critical patent/CN210032685U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a construction thickness adjusting device of a shaped punching bar, which comprises a punching bar long rod (1), a punching bar short rod (2), a leveling component, a thickness adjusting ruler (4) and a spatula (5); the two long stamping rib rods and the two short stamping rib rods are connected to form a stamping rib frame mold, and a strip-shaped stamping rib hollow part is formed in the stamping rib frame mold; the leveling assemblies are respectively arranged on the reinforcement punching frame type die, and the end parts of the leveling assemblies are contacted and attached with the building wall surface, so that the reinforcement punching frame type die is arranged in parallel to the building wall surface through the leveling assemblies; one end of each of the two thickness adjusting rules is connected to the side wall of the rib-punching frame-shaped mould, mortar is filled between the rib-punching frame-shaped mould and the building wall along the strip-shaped rib-punching hollow, and the mortar is trowelled and leveled by the trowels. The utility model discloses cooperation laser marking appearance uses during the construction, can effectual assurance screed thickness, has ensured the shaping quality of the engineering of plastering, and very big intensity of labour who has alleviateed operating personnel is showing and is accelerating the construction progress, practices thrift the time limit for a project.

Description

Construction thickness adjusting device of regularization screeding
Technical Field
The utility model relates to a decoration and finishing instrument of construction especially relates to a construction thickness adjusting device of regularization screeding.
Background
Wall plastering is used as a basic layer of wall decoration and finishing, is the basis for ensuring the molding quality of later wall decoration and finishing, when building decoration is carried out, if the wall plastering area is large, small mortar cakes (also called dotting) are generally made on the wall by mortar according to a certain interval before plastering, then one or more mortar ribs (generally the interval is not more than 1.5m) are made by mortar continuously along the vertical and horizontal directions of the small mortar cakes so as to control the plastering thickness and the flatness, and the process is called screeding.
The traditional indoor screeding and plastering construction method is old, the squareness of a room is poor, the plastering thickness cannot be guaranteed, the construction precision is low, the technical requirement on workers is high, the dimensional consistency of the room cannot be controlled, and the problems of construction precision, efficiency and the like exist.
Disclosure of Invention
An object of the utility model is to provide a construction thickness adjusting device of regularization dowel, cooperation laser marking instrument uses during the construction, can effectual assurance dowel thickness, has ensured the shaping quality of the engineering of plastering, and very big intensity of labour who has alleviateed operating personnel is showing and is accelerating the construction progress, practices thrift the time limit for a project.
The utility model discloses a realize like this:
a construction thickness adjusting device for a shaped punching bar comprises a long punching bar rod, a short punching bar rod, a leveling component, a thickness adjusting ruler and a spatula; the two long stamping rib rods and the two short stamping rib rods are connected to form a stamping rib frame mold, and a strip-shaped stamping rib hollow part is formed in the stamping rib frame mold; the leveling assemblies are respectively arranged on the reinforcement punching frame type die, and the end parts of the leveling assemblies are contacted and attached with the building wall surface, so that the reinforcement punching frame type die is arranged in parallel to the building wall surface through the leveling assemblies; one end of each of the two thickness adjusting rulers is connected to the side wall of the stamping rib frame-shaped mould, and the two thickness adjusting rulers are respectively positioned at the two ends of the stamping rib long rod; and filling mortar between the rib punching frame mold and the building wall along the strip-shaped punched rib in a hollow manner, and trowelling the mortar.
The leveling component comprises a leveling nut and a leveling bolt, the nut is fixed at the corner of the punching rib frame type die, and the leveling bolt is screwed with the leveling nut through thread matching and is in contact with the wall surface of the building.
The knife face of the spatula is provided with an additional spatula, the width of the additional spatula is equivalent to that of the strip-shaped punched rib hollow part, so that the additional spatula can be embedded into the strip-shaped punched rib hollow part.
The thickness of the additional trowel is smaller than that of the punching rib frame type die, so that a gap is reserved between the additional trowel and the building wall surface.
The end part of the additional spatula is of a wedge-shaped structure.
The 0-scale line end of the two thickness adjusting rulers is connected with the punching rib frame-shaped die, and the two thickness adjusting rulers are both vertically arranged with the punching rib long rod, so that the two thickness adjusting rulers are vertical to the laser surface of the laser graticule instrument.
The utility model discloses cooperation laser marking appearance construction can effectual assurance screed thickness, has ensured the shaping quality of the engineering of plastering, and very big intensity of labour who has alleviateed operating personnel is showing and is accelerating the construction progress, practices thrift the time limit for a project, low in manufacturing cost, easy operation is convenient, maneuverability is strong.
Drawings
FIG. 1 is a front view of a frame-shaped die for forming a reinforcement in the device for adjusting the thickness of a reinforcement in construction of a shaped reinforcement of the present invention;
FIG. 2 is an enlarged view of a portion of FIG. 1;
FIG. 3 is a side view of a frame-shaped die for forming a reinforcement in the device for adjusting the thickness of a reinforcement in construction of a shaped reinforcement of the present invention;
FIG. 4 is an enlarged view of a portion of FIG. 3;
FIG. 5 is a front view of a spatula in the construction thickness adjusting device of the shaped screed of the present invention;
FIG. 6 is a side view of the spatula in the construction thickness adjusting device of the shaped screed of the present invention;
FIG. 7 is a schematic construction view of the construction thickness adjusting device of the shaped screed according to the present invention;
FIG. 8 is an enlarged partial view of FIG. 7;
fig. 9 is a front view of fig. 8.
In the figure, a long punched rib rod 1, a short punched rib rod 2, a leveling nut 31, a leveling bolt 32, a thickness adjusting ruler 4, a spatula 5, an additional spatula 51, a wedge-shaped structure 511, a laser striping machine 6, a laser surface 61 and a building wall surface 7.
Detailed Description
The invention will be further explained with reference to the drawings and the specific embodiments.
Referring to fig. 1 to 4, a construction thickness adjusting device for a shaped screed comprises a screed long rod 1, a screed short rod 2, a leveling component, a thickness adjusting ruler 4 and a spatula 5; the two long punched rib rods 1 and the two short punched rib rods 2 are connected to form a punched rib frame mold, and a strip-shaped punched rib hollow part is formed in the punched rib frame mold; the leveling assemblies are respectively arranged on the punching rib frame type die, and the end parts of the leveling assemblies are contacted and attached with the building wall surface 7, so that the punching rib frame type die is arranged in parallel to the building wall surface 7 through the leveling assemblies; one end of each of the two thickness adjusting rulers 4 is respectively connected to the side wall of the stamping rib frame-shaped mould, and the two thickness adjusting rulers 4 are respectively positioned at the two ends of the stamping rib long rod 1; referring to the attached figure 7, mortar is filled between the punching rib frame-shaped mould and the building wall surface 7 along the strip-shaped punching rib in a hollow mode, and the mortar is trowelled through a trowel 5.
Referring to fig. 2 and 4, the leveling component includes a leveling nut 31 and a leveling bolt 32, the nut 31 is fixed at the corner of the screed frame-shaped mold, the leveling bolt 32 and the leveling nut 31 are screwed in a matching manner through threads and are in contact with the building wall 7, preferably, 4 leveling nuts 31 and 4 leveling bolts 32 are adopted for matching connection, and the distance between the screed frame-shaped mold and the building wall 7 is adjusted through screwing in or screwing out of the 4 leveling bolts 32, so that the purpose of leveling the screed frame-shaped mold and the building wall 7 is achieved.
Referring to fig. 5, an additional spatula 51 is arranged on a surface of the spatula 5, and the width of the additional spatula 51 is equal to the width of the strip-shaped punched rib hollow, so that the additional spatula 51 can be just embedded into the strip-shaped punched rib hollow, thereby compacting the mortar filled in the strip-shaped punched rib hollow and keeping the thickness of the punched rib uniform.
Referring to fig. 8, the thickness of the additional trowel 51 is smaller than that of the screed frame mold, so that a gap is left between the additional trowel 51 and the building wall surface 7, and the thickness of the mortar filled and compacted in the gap is the thickness of the screed.
Referring to fig. 6, preferably, the end of the additional trowel 51 may be designed into a wedge-shaped structure 511 to facilitate the leveling of the mortar. The additional spatula 51 can be made of a steel plate with the thickness of 2mm through stamping, the thickness of the additional spatula 51 is 15mm, the length of the additional spatula 51 is 120mm, and the length of the wedge-shaped structure 511 is 50 mm.
Referring to fig. 7, the 0-scale line end of the two thickness adjusting rulers 4 is connected with the punching rib frame-shaped mold, the two thickness adjusting rulers 4 are both arranged perpendicular to the long punching rib rod 1, so that the two thickness adjusting rulers 4 are perpendicular to the laser surface 61 of the laser striping machine 6, and the purpose of controlling the parallel arrangement of the punching rib frame-shaped mold and the building wall surface 7 is achieved by the scales on the laser surface 61 and the two thickness adjusting rulers 4.
Referring to fig. 1 to 6, during manufacturing, an aluminum alloy square tube with a length of 2000mm, a cross section of 20 × 15mm and a thickness of 2mm is used as a long stamping bar 1, an aluminum alloy square tube with a length of 30mm, a cross section of 20 × 15mm and a thickness of 2mm is used as a short stamping bar 2, the two long stamping bar 1 and the two short stamping bar 2 are welded to form a stamping bar frame-shaped die with a rectangular frame-shaped structure, the length of the stamping bar frame-shaped die is 2000mm, the width of the stamping bar frame-shaped die is 60mm, and the width of the strip-shaped stamping bar is 30 mm. The method is characterized in that 4M 6 nuts are used as leveling nuts 31, one straight edge of each leveling nut is welded on the outer sides of two ends of two long stamping bar 1 and is positioned at four corners of a stamping frame type die, 4M 6 bolts matched with the M6 nuts are used as leveling bolts 32 and are correspondingly connected with 4M 6 nuts, and the horizontal position of the leveling bolts 32 is adjusted through rotation of threads, so that the distance between the stamping frame type die and a building wall surface 7 is adjusted, and the thickness of a stamping bar is controlled. A0-600 mm straight steel ruler is adopted as the thickness adjusting ruler 4, the 0 scale directions of the two thickness adjusting rulers 4 are welded with the outer sides of two ends of one punching rib long rod 1, and the distance between the punching rib frame-shaped die and the building wall surface 7 can be further accurately controlled by matching with a laser marking instrument 6.
Referring to fig. 7 to 9, the using method of the present invention is as follows:
1. controlling the line: when the building line is bounced on the floor, plastering control lines are synchronously popped at two sides of the building line (the outer wall is the inner side and the single side), the control lines are parallel to the building line, and the offset distance is preferably uniformly controlled to be 300-500 mm.
2. Placing and leveling a laser striping machine 6: a prior art laser striping machine 6 is placed at the intersection of two perpendicular control lines and leveled.
3. Placing and leveling a rib punching frame type die: the punching rib frame-shaped die is arranged at a designated position, and the leveling bolt 32 is adjusted by the degree of the laser surface 61 and the upper and lower thickness adjusting ruler 4, so as to control the thickness of the punching rib.
4. Filling and leveling mortar: filling the prepared mortar into the hollow space of the strip-shaped punching rib of the punching rib frame type mould, wherein the mortar is preferably filled in an excess amount manner so as to ensure that the punching rib is compact and full; and then, embedding the additional trowel 51 of the trowel 5 into the strip-shaped punched rib hollow and troweling the mortar from top to bottom along the strip-shaped punched rib hollow.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and should not be taken as limiting the scope of the present invention, therefore, any modifications, equivalents, improvements and the like made within the spirit and principles of the present invention should be included in the scope of the present invention.

Claims (6)

1. The utility model provides a construction thickness adjusting device of regularization dowel, characterized by: comprises a long punched rib rod (1), a short punched rib rod (2), a leveling component, a thickness adjusting ruler (4) and a spatula (5); the two long stamping rib rods (1) and the two short stamping rib rods (2) are connected to form a stamping rib frame type die, and a strip-shaped stamping rib hollow is formed in the stamping rib frame type die; the leveling assemblies are respectively arranged on the punching rib frame type die, and the end parts of the leveling assemblies are contacted and attached with the building wall surface (7), so that the punching rib frame type die is arranged parallel to the building wall surface (7) through the leveling assemblies; one end of each of the two thickness adjusting rulers (4) is respectively connected to the side wall of the stamping rib frame-shaped mould, and the two thickness adjusting rulers (4) are respectively positioned at the two ends of the stamping rib long rod (1); mortar is filled between the punching rib frame type mould and the building wall surface (7) along the strip-shaped punching rib in a hollow way, and the mortar is trowelled by a trowel (5).
2. The construction thickness adjusting device of the finalized screed according to claim 1, wherein: the leveling component comprises a leveling nut (31) and a leveling bolt (32), the nut (31) is fixed at the corner of the punching rib frame type die, and the leveling bolt (32) is matched with the leveling nut (31) through threads, screwed and contacted with the building wall surface (7).
3. The construction thickness adjusting device of the finalized screed according to claim 1, wherein: the auxiliary trowel (51) is arranged on the surface of the trowel (5), the width of the auxiliary trowel (51) is equivalent to that of the strip-shaped punched rib hollow, and the auxiliary trowel (51) can be embedded into the strip-shaped punched rib hollow.
4. The setting screed construction thickness adjusting apparatus as claimed in claim 3, wherein: the thickness of the additional spatula (51) is smaller than that of the punching rib frame type mould, so that a gap is reserved between the additional spatula (51) and the building wall surface (7).
5. The setting screed construction thickness adjusting apparatus as claimed in claim 3, wherein: the end of the additional spatula (51) is of a wedge-shaped structure (511).
6. The construction thickness adjusting device of the finalized screed according to claim 1, wherein: the 0-scale line end of the two thickness adjusting rulers (4) is connected with the punching rib frame-shaped die, and the two thickness adjusting rulers (4) are both arranged perpendicular to the punching rib long rod (1), so that the two thickness adjusting rulers (4) are perpendicular to the laser surface (61) of the laser striping machine (6).
CN201920533359.3U 2019-04-18 2019-04-18 Construction thickness adjusting device of regularization screeding Active CN210032685U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920533359.3U CN210032685U (en) 2019-04-18 2019-04-18 Construction thickness adjusting device of regularization screeding

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920533359.3U CN210032685U (en) 2019-04-18 2019-04-18 Construction thickness adjusting device of regularization screeding

Publications (1)

Publication Number Publication Date
CN210032685U true CN210032685U (en) 2020-02-07

Family

ID=69360368

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920533359.3U Active CN210032685U (en) 2019-04-18 2019-04-18 Construction thickness adjusting device of regularization screeding

Country Status (1)

Country Link
CN (1) CN210032685U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111672659A (en) * 2020-05-29 2020-09-18 上海二十冶建设有限公司 Installation method for accurately controlling spraying radius of hot blast stove pipeline

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111672659A (en) * 2020-05-29 2020-09-18 上海二十冶建设有限公司 Installation method for accurately controlling spraying radius of hot blast stove pipeline

Similar Documents

Publication Publication Date Title
EP3635176B1 (en) Method for producing a paving area
CN106836718A (en) Precast floor system and its assembly method
CN210032685U (en) Construction thickness adjusting device of regularization screeding
CN109252659B (en) Template descending and supporting mold and method for shaped toilet
CN206512966U (en) Precast floor system
JP6510377B2 (en) Method of manufacturing precast concrete plate having three-dimensional curved surface and formwork
CN109112903A (en) Solid concrete roabed trackless construction technology is cheated in a kind of phase library inner column formula inspection
CN218493149U (en) Mortar laying device for construction
CN207295770U (en) A kind of finished product concrete fetal membrane and molding die
CN204850478U (en) Controlling means is pour to concrete floor thickness
CN206941968U (en) Reinforcing bar limiting card with the upper oblique bayonet socket being parallel to each other
CN107214819B (en) Building constructional column shaping moulding box
CN105484476B (en) Building decoration gets patch cake device and ash cake forming method ready
CN109385977B (en) Anti-cracking concrete panel and construction method thereof
CN210134654U (en) Adjustable floor control device
CN107237436A (en) A kind of method of temporarily fixing during cavity floor construction
CN207290432U (en) A kind of simplicity detachable wedge concrete precast block die device
CN209114685U (en) A kind of lightweight assembled house floor
CN207934463U (en) cast-in-place concrete board thickness control device
CN207499463U (en) A kind of cast-in-place concrete floor elevation control device
CN110424532A (en) Large-span prestressed structure floor and high-precision construction floor one-pass molding construction method
CN211622654U (en) Adjustable thick and receipts face roughness controlling means of concrete placement in-process
CN218508779U (en) Brick body structure beneficial to quality control of wall mortar joint filling
CN215291439U (en) A template for infilled wall high accuracy bank platform
CN214329773U (en) Large-area facing brick pasting mortar paving device

Legal Events

Date Code Title Description
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20201231

Address after: No. 14701, 47 / F, unit 1, green space center, block a, northeast corner of cross between Jinye road and zhangbaer Road, Zhangba Street office, high tech Zone, Xi'an City, Shaanxi Province, 710076

Patentee after: Northwest Construction Co.,Ltd. of China Construction Eighth Engineering Bureau

Address before: 200122 Pudong New Area, Shanghai, China (Shanghai) free trade trial area 1568 Century Avenue 27

Patentee before: CHINA CONSTRUCTION EIGHTH ENGINEERING DIVISION Co.,Ltd.