Prior art keywords
sedimentation tank
place
placing
building site
basket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201920764120.7U
Other languages
Chinese (zh)
Inventor
吴张芳
贺源全
雷雪娟
谢桦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Xiangmin Construction Development Co Ltd
Original Assignee
Fujian Xiangmin Construction Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian Xiangmin Construction Development Co Ltd filed Critical Fujian Xiangmin Construction Development Co Ltd
Priority to CN201920764120.7U priority Critical patent/CN210030224U/en
Application granted granted Critical
Publication of CN210030224U publication Critical patent/CN210030224U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Sewage (AREA)

Abstract

The utility model discloses a building site waste water, rainwater cyclic utilization system, it is including the escape canal that is used for collecting the ground rainwater that connects in order, the sedimentation tank, filter equipment, water-collecting device, spray set, be connected through the pipe between escape canal and the sedimentation tank, the sedimentation tank bottom is connected with the mud pipe, sedimentation tank lateral wall department is provided with the interception subassembly, the interception subassembly includes two dead levers of fixed connection lateral wall in the sedimentation tank, place two between two dead levers and place the pole, fixed connection is at two horizontal poles of placing the pole top, one side that the sedimentation tank was kept away from to fixed connection at both sides dead lever is used for the gag lever post of gag lever post horizontal migration, fixed connection places a plurality of baskets between the pole in two, it is located the bottom of round bar to place the basket, place and be connected through the locking subassembly between pole and the dead lever. The utility model discloses have the escape canal and flow into the inside stone of sedimentation tank or hard thing and intercept, do not influence the effect of the normal use of sedimentation tank.

Description

Building site waste water, rainwater cyclic utilization system
Technical Field
The utility model belongs to the technical field of the building site water treatment technique and specifically relates to a building site waste water, rainwater cyclic utilization system is related to.
Background
Currently, construction site water includes: construction process water, construction machinery water, construction site domestic water, domestic water and fire water. At present, construction water generally all derives from the running water, and is lower to the utilization ratio of construction waste water, domestic wastewater and rainwater on the building site, causes the waste of water resource, and the precipitation and the untimely discharge of rainwater in construction field still can cause place ponding, road mire, influence construction simultaneously.
The traditional Chinese patent with publication number CN105064448A discloses a water recycling system for a construction site, which comprises a high-altitude water tank system, a spraying system and a water pipe for a water circulating system, wherein the high-altitude water tank system is connected with water pipes for water inlet and water outlet; the lower end of the water pipe for feeding water is sequentially connected with a garden landscape pool, a third-level sedimentation tank and a drainage ditch; water pumps are arranged on the water pipes between the high-altitude water tank system and the garden landscape pool as well as between the garden landscape pool and the third-level sedimentation tank; the lower end of the water outlet pipe is sequentially connected with a gate valve and each spraying system arranged on a construction site; and water sprayed by the spraying system flows into the drainage ditch to finally form an integral water circulation system.
The above prior art solutions have the following drawbacks: spray system spun rivers flow into the escape canal in, the escape canal is collected and is sprayed rivers, collects the rainwater simultaneously, and the water that the escape canal was collected flows into and deposits in the tertiary sedimentation tank and filter the back, gets into the system through water pump and water pipe. In-process of practical use, because the use place can get into a lot of stones or hard thing in the escape canal at the building site, sedimentation tank one side can be provided with the mud pipe moreover, and the stone or hard thing are piled up and are influenced the normal use of mud pipe to influence sedimentation tank's normal use.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a building site waste water, rainwater cyclic utilization system, the catch basin flows in the inside stone of sedimentation tank or hard thing and intercepts, does not influence the normal use of sedimentation tank.
The above technical purpose of the present invention can be achieved by the following technical solutions: the utility model provides a building site waste water, rainwater cyclic utilization system, is including the escape canal, sedimentation tank, filter equipment, water-collecting device, the spray set that are used for collecting the ground rainwater that connect in order, be connected through the pipe between escape canal and the sedimentation tank, the sedimentation tank bottom is connected with the mud pipe, sedimentation tank lateral wall department is provided with the interception subassembly, the interception subassembly includes two dead levers of fixed connection lateral wall in the sedimentation tank, places two between two dead levers and places pole, fixed connection is used for two gag lever posts, the fixed connection that the sedimentation tank was kept away from to two horizontal poles, the fixed connection of placing the pole top place two a plurality of baskets of placing between the pole, place the bottom that the basket is located the round bar, place and be connected through the locking subassembly between pole and the dead lever.
By adopting the technical scheme, when the basket is used, the placing basket with the highest horizontal position is placed at the bottom of the circular tube, waste water in the drainage ditch flows into the sedimentation tank, water in the drainage ditch flows into the sedimentation tank to carry stone blocks, the stone blocks fall into the placing basket, after sundries in the placing basket are collected, a user pulls the placing rod upwards by hand, and at the moment, the placing rod is connected with the fixed rod through the locking assembly; the drainage ditch is intercepted by the stone or hard objects flowing into the sedimentation tank, so that the normal use of the sedimentation tank is not influenced.
The utility model discloses further set up to, two it has the dwang to place to peg graft between the pole, the dwang passes place the basket, place the relative dwang of basket and can rotate.
Through adopting above-mentioned technical scheme, make and place the relative dwang of basket and can rotate, make things convenient for the staff to rotate placing the basket, just place the inside debris of basket with the clearance.
The utility model discloses further set up to, two it has spacing to peg graft between the dead lever, spacing and place one side butt that the frame is close to the escape canal.
Through adopting above-mentioned technical scheme, owing to place basket inside and placed various debris, place the basket and probably rotate along the dwang, but set up spacing, place the relative dwang of basket and can not take place to rotate, place the basket comparatively firm.
The utility model discloses further set up to, the locking subassembly is including seting up at the square groove of placing pole upper portion, seting up at the square mouth that dead lever upper portion and square groove cooperation were used, place at the inside spring of square mouth, place at the square inslot portion and the set-square of being connected with spring one end, two inclined planes of set-square set up along the horizontal centerline symmetry of square groove, square mouth department lid is equipped with the apron.
Through adopting above-mentioned technical scheme, during the use, the staff will place the pole and upwards stimulate, and the set-square receives the compression of standing groove lateral wall, and the set-square this moment is located places mouthful inside, and the spring receives the compression, and when placing the square mouth of next square groove on the pole and corresponding, the spring was ejecting with the set-square, and it is fixed form to place pole dead lever this moment.
The utility model discloses further set up to, the spring is close to the one end department of apron and is connected with the curb plate.
Through adopting above-mentioned technical scheme, in order to be connected comparatively stably between messenger's spring and the apron, reduce the crooked condition of spring appearance, so be connected with the curb plate in the spring one end department of being close to the apron.
The utility model discloses further set up to, be connected with the telescopic link between curb plate and the set-square.
Through adopting above-mentioned technical scheme, because in the use, after the live time is longer, the spring can become loose, sets up the telescopic link to make the pop-up distance of spring be fixed distance, it is convenient relatively, avoid the spring to stretch out and place the mouth outward.
The utility model discloses further set up as, the lateral wall department of placing the basket is connected with the handle.
Through adopting above-mentioned technical scheme, set up the handle, make things convenient for the staff to place the basket and overturn, it is comparatively convenient.
The utility model discloses further set up to, the sedimentation tank is close to the lateral wall fixedly connected with of dead lever and places the board, place board upper portion and placed the waste material fill, waste material fill bottom fixedly connected with dovetail, it corresponds dovetail department and has seted up the dovetail to place the board.
Through adopting above-mentioned technical scheme, during the use, insert the waste material fill along the length direction who places the board, the forked tail piece is inserted in the dovetail, and the waste material fill is located and places board upper portion this moment, and the material of placing basket inside falls down in the waste material fill can.
To sum up, the utility model discloses following beneficial effect has:
1. the stones and hard objects in the drainage ditch can be conveniently dropped into the collection basket, the whole process is convenient, and the use of the sedimentation tank is not influenced;
2. the rotating rods are arranged between the placing baskets, and the placing baskets can rotate relative to the placing rods, so that the effect is good;
3. set up spacing, avoid placing the basket and take place to rotate, make and place the basket comparatively stable when placing.
Drawings
FIG. 1 is a schematic view of the overall structure of the embodiment;
FIG. 2 is a schematic diagram illustrating the connection between the interception component and the sedimentation tank according to the embodiment;
FIG. 3 is a schematic diagram of an embodiment showing a structure of an interception component;
FIG. 4 is a schematic diagram of a locking assembly according to an embodiment.
Reference numerals: 1. a drainage ditch; 11. a circular tube; 2. a sedimentation tank; 21. placing the plate; 211. a dovetail groove; 22. a waste hopper; 221. a dovetail block; 23. a sludge discharge pipe; 3. a filtration device; 31. a first water pump; 32. a filter; 33. an ultrafilter; 4. a water collection device; 41. a high pressure water pump; 42. a water pipe; 43. a water collecting tank; 5. a spraying device; 51. a second water pump; 52. a shower pipe; 53. a spray head; 6. an interception component; 61. fixing the rod; 62. placing a rod; 621. a limiting strip; 63. a cross bar; 64. a limiting rod; 65. placing a basket; 651. rotating the rod; 652. a handle; 7. a locking assembly; 71. a square groove; 72. a square opening; 73. a spring; 731. a telescopic rod; 732. a side plate; 74. a set square; 741. and (7) a cover plate.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings.
Referring to fig. 1, for the utility model discloses a building site waste water, rainwater cyclic utilization system, including the escape canal 1, sedimentation tank 2, filter equipment 3, water-collecting device 4, the spray set 5 that are used for collecting the ground rainwater that connect in order.
Referring to fig. 1, the filtering apparatus 3 includes a first water pump 31 connected to the settling tank 2, a filter 32 connected to the first water pump 31, and an ultrafilter 33 connected to an outlet of the filter 32.
Referring to fig. 1, the water collecting device 4 includes a high pressure water pump 41 communicating with an outlet of the ultrafilter 33, a water pipe 42 communicating with the high pressure water pump 41, and a water collecting tank 43 communicating with an end of the water pipe 42 remote from the ultrafilter 33.
Referring to fig. 1, the spray device 5 includes a second water pump 51 connected to the sump 43, a spray pipe 52 connected to the second water pump 51, and a spray head 53 connected to the spray pipe 52.
Referring to fig. 2-3, a drainage ditch 1 (shown in fig. 1) is connected with a sedimentation tank 2 through a circular pipe 11, the bottom of the sedimentation tank 2 is connected with a sludge discharge pipe 23, and the upper part of the sludge discharge pipe 23 is provided with a valve; the lateral wall of pipe 11 flushes with the inside wall of sedimentation tank 2, and sedimentation tank 2 lateral wall department is provided with interception subassembly 6, and interception subassembly 6 includes dead lever 61, places pole 62, horizontal pole 63, gag lever post 64, places basket 65. The two fixing rods 61 are vertically and fixedly connected to the inner side wall of the sedimentation tank 2 and symmetrically arranged along the circular pipe 11; the two placing rods 62 are arranged and placed between the two fixing rods 61; the cross bar 63 is fixedly connected with the ends of the two placing rods 62; the limiting rods 64 are fixedly connected to the fixing rods 61 at two sides, and are far away from one side of the drainage ditch 1, and the limiting rods 64 are arranged, so that the placing rod 62 can only vertically move, and the situation that the placing rod 62 is inclined is avoided; three placing baskets 65 are vertically arranged between the two placing rods 62, the top of each placing basket 65 is in an opening shape, and stones and hard objects gushing from the inside of the water pipe 42 fall into the placing baskets 65; two levels of placing between the pole 62 are pegged graft and are had three dwang 651, and the dwang 651 all passes adjacent basket 65 of placing, so make and place the relative dwang 651 of basket 65 and can rotate, make things convenient for the people hand to rotate placing basket 65, just place the inside debris of basket 65 with the clearance.
Referring to fig. 2-3, a handle 652 is connected to an outer side wall of the basket 65 for facilitating rotation of the basket 65 by a human hand. During the use, place the basket 65 that places that horizontal position is the highest in the 11 bottoms of pipe, after the collection is accomplished, will place pole 62 through the staff and upwards pull up, be provided with locking Assembly 7 on dead lever 61, will place pole 62 fixed relative dead lever 61, the basket 65 of placing that is located the middle part this moment is located 11 bottoms of pipe, after the collection is accomplished, the staff will place pole 62 and upwards pull up, the basket 65 of placing that is located the bottom this moment is located 11 bottoms of pipe, the basket 65 of placing that is located the top is located sedimentation tank 2 outsidely.
Referring to fig. 3, since various sundries are placed inside the basket 65, the basket 65 may rotate along the rotating rod 651, three limiting strips 621 are inserted horizontally between the two placing rods 62, the limiting strips 621 correspond to the three placing baskets 65 respectively, and the side walls of the limiting strips 621 abut against one side of the placing basket 65 close to the drainage ditch 1 (shown in fig. 1).
Referring to fig. 4, the locking assembly 7 includes a square groove 71, a square opening 72, a spring 73, a triangle 74, and a cover plate 741. The three square grooves 71 are vertically arranged on the side wall of the placing rod 62; the square opening 72 is formed in the side wall of the fixing rod 61, and the square opening 72 is communicated with the square groove 71; the spring 73 is placed inside the square mouth 72; the triangular plate 74 is placed in the square groove 71 and is fixedly connected with one end of the spring 73; a cover plate 741 covers the top of the square opening 72.
Referring to fig. 4, in order to stabilize the connection between the spring 73 and the cover 741 and reduce the distortion of the spring 73, a side plate 732 is connected to one end of the spring 73 close to the cover 741.
Referring to fig. 4, in order to further increase the connection between the side plate 732 and the triangular plate 74 and to reduce the elastic reduction of the spring 73 and the occurrence of the spring 73 protruding out of the opening, an expansion link 731 is connected between the side plate 732 and the triangular plate 74.
Referring to fig. 2, in order to facilitate cleaning of impurities collected inside the placing basket 65, a placing plate 21 is fixedly connected to the outer side wall of the sedimentation tank 2 close to the fixing rod 61, a waste hopper 22 is placed on the upper portion of the placing rod 62, a dovetail block 221 extending in the length direction of the waste hopper 22 is fixedly connected to the bottom of the waste hopper 22, and a dovetail groove 211 is formed in the placing plate 21 corresponding to the dovetail block 221.
This embodiment is when using, during the use, place the basket 65 that places that horizontal position is the highest in the 11 bottoms of pipe, the inside waste water of escape canal 1 flows out in sedimentation tank 2, the stone that carries when the inside rivers of escape canal 1 flow into sedimentation tank 2, the stone falls places in the basket 65, after placing the inside debris collection of basket 65 and accomplishing, the staff will place pole 62 and upwards pull up, set-square 74 receives the compression of square groove 71 lateral wall, set-square 74 is located inside square mouth 72 this moment, spring 73 receives the compression, when placing next square groove 71 on pole 62 and corresponding square mouth 72, spring 73 is ejecting with set-square 74, it is fixed for the relative dead lever 61 of pole 62 this moment to place, will place basket 65 and rotate, will place the inside debris of basket 65 and fall in the waste bin 22.
The embodiment of this specific implementation mode is the preferred embodiment of the present invention, not limit according to this the utility model discloses a protection scope, so: all equivalent changes made according to the structure, shape and principle of the utility model are covered within the protection scope of the utility model.

Claims (8)

1. The utility model provides a building site waste water, rainwater cyclic utilization system, is used for collecting escape canal (1), sedimentation tank (2), filter equipment (3), water-collecting device (4), spray set (5) of ground rainwater including connecting in order, its characterized in that: the drainage ditch (1) is connected with the sedimentation tank (2) through a circular pipe (11), the bottom of the sedimentation tank (2) is connected with a sludge discharge pipe (23), the side wall of the sedimentation tank (2) is provided with an interception component (6), the intercepting component (6) comprises two fixed rods (61) fixedly connected with the inner side wall of the sedimentation tank (2), two placing rods (62) placed between the two fixed rods (61), a cross rod (63) fixedly connected with the tops of the two placing rods (62), a limiting rod (64) fixedly connected with one side of the fixed rods (61) at the two sides far away from the sedimentation tank (2) and used for limiting the horizontal movement of the rods, and a plurality of placing baskets (65) fixedly connected between the two placing rods (62), the placing basket (65) is positioned at the bottom of the round rod, and the placing rod (62) is connected with the fixing rod (61) through a locking assembly (7).
2. The building site wastewater and rainwater recycling system according to claim 1, characterized in that: two place and peg graft between pole (62) and have dwang (651), dwang (651) pass place basket (65), place basket (65) relatively dwang (651) can rotate.
3. The building site wastewater and rainwater recycling system according to claim 2, characterized in that: two it has spacing (621) to peg graft between dead lever (61), spacing (621) with place the frame and be close to one side butt in escape canal (1).
4. The building site wastewater and rainwater recycling system according to claim 1, characterized in that: locking Assembly (7) including seting up square groove (71) on placing pole (62) upper portion, seting up square mouth (72) that use with square groove (71) cooperation in dead lever (61) upper portion, place spring (73) inside square mouth (72), place triangle (74) inside square groove (71) and be connected with spring (73) one end, two inclined planes of triangle (74) set up along the horizontal central line symmetry of square groove (71), square mouth (72) department lid is equipped with apron (741).
5. The building site wastewater and rainwater recycling system according to claim 4, characterized in that: one end of the spring (73) close to the cover plate (741) is connected with a side plate (732).
6. The building site wastewater and rainwater recycling system according to claim 5, characterized in that: an expansion link (731) is connected between the side plate (732) and the triangular plate (74).
7. The building site wastewater and rainwater recycling system according to claim 1, characterized in that: the side wall of the placing basket (65) is connected with a handle (652).
8. The building site wastewater and rainwater recycling system according to claim 1, characterized in that: the sedimentation tank (2) are close to lateral wall fixedly connected with of dead lever (61) and place board (21), place board (21) upper portion and placed waste material fill (22), waste material fill (22) bottom fixedly connected with dovetail block (221), place board (21) and correspond dovetail block (221) department and seted up dovetail (211).
CN201920764120.7U 2019-05-24 2019-05-24 Building site waste water, rainwater cyclic utilization system Expired - Fee Related CN210030224U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920764120.7U CN210030224U (en) 2019-05-24 2019-05-24 Building site waste water, rainwater cyclic utilization system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920764120.7U CN210030224U (en) 2019-05-24 2019-05-24 Building site waste water, rainwater cyclic utilization system

Publications (1)

Publication Number Publication Date
CN210030224U true CN210030224U (en) 2020-02-07

Family

ID=69344246

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920764120.7U Expired - Fee Related CN210030224U (en) 2019-05-24 2019-05-24 Building site waste water, rainwater cyclic utilization system

Country Status (1)

Country Link
CN (1) CN210030224U (en)

Similar Documents

Publication Publication Date Title
CN210827511U (en) Three-dimensional ecological bank protection in gardens with rainwater filters and gu native function
CN100400439C (en) Artificial wetland in use for processing polluted water
CN205875349U (en) Gardens rainwater in sponge city utilizes system
CN105683447A (en) Filtering system for artificial recharge and cleaning method for filtering system for artificial recharge
CN210030224U (en) Building site waste water, rainwater cyclic utilization system
CN2920987Y (en) Artificial wet land for treating sewage
CN211312481U (en) Hydraulic engineering retaining wall drainage structures
CN210202763U (en) Sponge urban green belt
CN208876341U (en) A kind of novel integrated Showering bottom basin
CN205875351U (en) Rainwater in sponge city filters collecting system
CN215888510U (en) Take slope resin concrete escape canal
CN213836257U (en) Landing stage platform drainage structures
CN106638899B (en) Gardens rain water collecting system
CN109024765A (en) A kind of plug-in rainwater recycle reuse means of wall
CN2918404Y (en) Artificial wetland for processing sewage
CN207376763U (en) A kind of collection urban rainwater anti-clogging pipeline
CN206121283U (en) Filter equipment is collected to agricultural irrigation water
CN207974215U (en) A kind of gardens rainwater utilization system in sponge city
CN206103449U (en) Rainwater processing system who has a self -cleaning function in sponge city
CN218479272U (en) Water conservancy construction waterproof drainage device
CN213114173U (en) Highway drainage structures
CN220433696U (en) Slope nursing structure
KR102310849B1 (en) Apparatus for filtration and exclusion initial rainwater
CN212956878U (en) Unobstructed device of road filtration drainage based on municipal garden
CN208465289U (en) Rainwater-collecting hanging basket device

Legal Events

Date Code Title Description
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200207