CN209723027U - A kind of green ecological modular reinforced earth bulkhead - Google Patents
A kind of green ecological modular reinforced earth bulkhead Download PDFInfo
- Publication number
- CN209723027U CN209723027U CN201920284793.2U CN201920284793U CN209723027U CN 209723027 U CN209723027 U CN 209723027U CN 201920284793 U CN201920284793 U CN 201920284793U CN 209723027 U CN209723027 U CN 209723027U
- Authority
- CN
- China
- Prior art keywords
- module
- reinforced earth
- water guide
- storehouse
- green ecological
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Revetment (AREA)
Abstract
The utility model discloses a kind of green ecological modular reinforced earth bulkheads, including A module, B module, A, B module guarantees that the flatness and globality of installation, the raw storehouse of the reserved plant of the A module and rubble water guide storehouse, the B module reserve rubble water guide storehouse using curved surface occlusion.A module, B module, it is vertical to stack, in picturesque disorder growing space is formed, vertical rubble water guide up and down is constituted and contains aquaporin, with reinforced earth bulkhead drainage system connection, create reinforced earth bulkhead green ecological system.This structure is suitable for highway and civilian infrastructure field reinforced earth bulkhead, reinforced earth abutment, reinforced earth culvert opening, reinforced earth tunnel portal.Using the Reinforced Material with Clay Engineering of the utility model, quickly, low cost is in picturesque disorder for construction, and ecology is harmonious.
Description
Technical field:
The utility model relates to a kind of green ecological modular reinforced earth bulkhead, it is suitable for highway and civilian infrastructure is led
Domain reinforced earth bulkhead, reinforced earth abutment, reinforced earth culvert opening, reinforced earth tunnel portal.
Background technique:
Reinforced earth bulkhead panel uses the form of module, can manually carry construction, is not necessarily to additional lifting machine and supporter
System, construction is quick, low cost, but reinforced earth modular barricade can not usually afforest.
Utility model content:
The utility model provides a kind of green ecological modular reinforced earth bulkhead, and this novel green ecological module formula adds
Muscle soil barricade guarantees the flatness and globality of installation using A, B module of curved surface occlusion, plants raw storehouse using A module is reserved
And rubble water guide storehouse, B module reserve rubble water guide storehouse, create reinforced earth bulkhead green ecological system.This structure is suitable for highway
And civilian infrastructure field reinforced earth bulkhead, reinforced earth abutment, reinforced earth culvert opening, reinforced earth tunnel portal.
The utility model is achieved through the following technical solutions:
A kind of green ecological modular reinforced earth bulkhead includes
Concrete continuous footing;
Wall, the wall include the A module vertically stacked on concrete continuous footing, B module, and A module, B module
The alignment of one side end face forms wall back, and another side end face is interspersed, before forming spatially concave-convex wall, A module and B module group
At the wall of the barricade;
Coping block, the coping block are pressed in the top of wall part;
Wherein, the raw storehouse of the reserved plant of the A module and rubble water guide storehouse, the B module reserve rubble water guide storehouse, A module
The rubble water guide storehouse of rubble water guide storehouse and B module spatially up and down, forms rubble water guide and contains aquaporin.
It is equipped with reinforcing bar in the A module and B module, passes through the fixed embedded ribs material of reinforcing bar.
The A module, B module, there are wedge mouths up and down, play positioning action, and the wedge mouth is built into overhanging dentation connection
Part, the overhanging serrated attachment are connected with TGXG hole.
The A inside modules are equipped with cavity, and rubble water guide storehouse and the raw storehouse of plant are placed in the cavity, wherein planting raw storehouse part bottom
Portion, which is equipped with, plants raw bottom plate.
The B inside modules are equipped with cavity, and rubble water guide storehouse is placed in the cavity.
The rubble water guide carries on the back weeper drain connection by bright gutter before drainpipe and wall or wall containing aquaporin.
Using utility model has the advantages that
Vertically stacked using A, B module, constitute vertical rubble water guide up and down and contain aquaporin, A module plant raw storehouse with
Rubble water guide storehouse is built together, and is provided and is retained the aqueous raw environment of green ecological plant;
The reinforced earth bulkhead constituted using such green ecological modular reinforced earth bulkhead, in picturesque disorder, ecology is harmonious;
Reinforced earth bulkhead green ecological system is created, it is prefabricated simple, it is easy for construction, and construction investment is effectively reduced,
Reinforced earth bulkhead green ecological is improved, there is extraordinary application prospect.
Detailed description of the invention:
It, below will be to required in embodiment description in order to illustrate more clearly of the technical scheme in the embodiment of the utility model
Attached drawing to be used is briefly described, it should be apparent that, the accompanying drawings in the following description is only some realities of the utility model
Example is applied, it for those of ordinary skill in the art, without creative efforts, can also be according to these attached drawings
Obtain other attached drawings;
Fig. 1 is green ecological modular reinforced earth bulkhead diagrammatic cross-section, and wherein Figure 1A is to cut open at bottom A module centers line
Face schematic diagram, Figure 1B are diagrammatic cross-section at bottom B module centers line;
Fig. 2 is A module diagram;Wherein Fig. 2A is A module three-dimensional figure, and Fig. 2 B is A module front view, and Fig. 2 C is A module
Rearview, Fig. 2 D are A module side view, and Fig. 2 E is A module top view, and Fig. 2 F is A module bottom view;
Fig. 3 is B module diagram;Wherein Fig. 3 A is B module three-dimensional figure, and Fig. 3 B is B module front view, and Fig. 3 C is B module
Rearview, Fig. 3 D are B module side view, and Fig. 3 E is B module top view, and Fig. 3 F is B module bottom view;
Fig. 4 is to plant raw floor diagram;Wherein Fig. 4 A is to plant raw bottom plate three-dimensional figure, and Fig. 4 B is to plant raw bottom plate front view, figure
4C is to plant raw bottom plate side view, and Fig. 4 D is to plant raw bottom plate top view, and Fig. 4 E is to plant raw bottom view of the floor;
Fig. 5 is A module and the raw bottom plate assembling schematic diagram of plant;Wherein Fig. 2A is that A module and the raw bottom plate of plant assemble three-dimensional figure, figure
2B is A module and plants raw bottom plate assembly front view, and Fig. 2 C is A module and plants raw bottom plate assembled rear view, and Fig. 2 D is A module
With plant life bottom plate assembling side elevation, Fig. 2 E is A module and plants raw bottom plate assembling plan view, and Fig. 2 F is A module and the raw bottom of plant
Plate assembles bottom view;
Fig. 6 is a kind of combination schematic diagram using A, B module;Wherein Fig. 6 A is the combination three-dimensional figure, Fig. 6 B
For the combination front view, Fig. 6 C is the combination side view, and Fig. 6 D is the combination top view, and Fig. 6 E is the combination
Mode bottom view;
Fig. 7 is another combination schematic diagram using A, B module;Wherein Fig. 7 A is the combination three-dimensional figure, figure
7B is the combination front view, and Fig. 7 C is the combination side view, and Fig. 7 D is the combination top view, and Fig. 7 E is the group
Conjunction mode bottom view;
Fig. 8 is module embedded ribs material schematic diagram;
Fig. 9 stays wedge mouth cooperation special connecting piece and muscle material connection schematic diagram by module;
Figure 10 is rubble water guide containing aquaporin and reinforced earth bulkhead drainage system connection schematic diagram;
In figure: 1-A module, 2-B modules, 3-rubble water guide storehouses, the raw storehouse of 4-plants, the raw bottom plates of 5-plants, 6-wedge mouths,
7-rubble water guides contain aquaporin, and 8-plant biological bags, 9-muscle materials, 10- concrete continuous footing, 11- coping block, 12- wedge shape are cast-in-place
Levelling section, 13- reinforcing bar, 14- special connecting piece, 15- drainpipe, the bright gutter 16-, 17- wall back draining blind pipe.
Specific embodiment:
It is practical new below in conjunction with this to keep the objectives, technical solutions, and advantages of the embodiments of the present invention clearer
Type embodiment, the technical scheme in the utility model embodiment is clearly and completely described, it is clear that described implementation
Example is the utility model a part of the embodiment, instead of all the embodiments.Based on the embodiments of the present invention, this field
Those of ordinary skill's every other embodiment obtained without creative efforts, belongs to the utility model
The range of protection.
It is as shown in Figure 1 green ecological modular reinforced earth bulkhead diagrammatic cross-section, mainly includes concrete bar shaped base
Plinth 10, the A module 1 vertically stacked, B module 2 and the coping block 11 at top carry on the back lacing wire material 9 in A module 1,2 wall of B module.Muscle
Material 9 can be embedded in advance by form shown in Fig. 7 in module or muscle material 9 can by way of Fig. 8 using special connecting piece 14 with
Reinforced earth bulkhead connection.A module 1 with 2 stacked on top of B module, the rubble water guide storehouse 3 of A module 1 and the rubble of B module 2 by leading
Sump 3 spatially up and down, forms rubble water guide and contains aquaporin.A module 1 by with 2 stacked on top of B module, formed space
On bumps, give birth to storehouse 4 for overhanging plants of A module 1 and provide plant upward growing space.
It is illustrated in figure 2 A module diagram, is precast concrete or dry-pressing building block.A inside modules are equipped with sky
Chamber, space needed for which has reserved rubble water guide storehouse 3 and planted raw storehouse 4 need to cooperate the raw bottom plate 5 of plant to make wherein planting raw 4 part of storehouse
With.
It is illustrated in figure 3 B module diagram, is precast concrete or dry-pressing building block.B inside modules are equipped with sky
Chamber, the cavity is as rubble water guide storehouse 3.
It is illustrated in figure 4 the raw floor diagram of plant, is precast concrete or dry-pressing building block.It plants raw bottom plate 4 and cooperates A
Module 1 uses.
It is illustrated in figure 5 module and plants raw bottom plate assembling schematic diagram.After the raw storehouse 4 of A module plant is built into the raw bottom plate 5 of plant, put
Enter plant biological bag or planting soil etc..
It is illustrated in figure 6 a kind of combination schematic diagram using A, B module.It is used in 2 horizontal direction of A module 1 and B module
Curved surface occlusion is erected upwardly through the positioning of wedge mouth, to guarantee the flatness and globality of installation.A module 1 by with B module 2
The rubble water guide storehouse 3 of stacked on top, the rubble water guide storehouse 3 of A module 1 and B module 2 spatially up and down, forms rubble water guide
Containing aquaporin.A module 1 by with 2 stacked on top of B module, form bumps spatially, mentioned for the raw storehouse 4 of the overhanging plant of A module 1
For the upward growing space of plant.
It is illustrated in figure 7 another combination schematic diagram using A, B module.It is adopted in 2 horizontal direction of A module 1 and B module
With curved surface occlusion, erect upwardly through the positioning of wedge mouth, to guarantee the flatness and globality of installation.A module 1 by with B mould
The rubble water guide storehouse 3 of 2 stacked on top of block, the rubble water guide storehouse 3 of A module 1 and B module 2 spatially up and down, forms rubble and leads
Water contains aquaporin.A module 1 by with 2 stacked on top of B module, form bumps spatially, be the raw storehouse 4 of the overhanging plant of A module 1
There is provided plant upward growing space.
It is illustrated in figure 8 module embedded ribs material schematic diagram, short muscle material is embedded in module when module is prefabricated.
It is illustrated in figure 9 the stayed wedge mouth cooperation special connecting piece of module and muscle material connection schematic diagram, A module 1 and B module 2
Upper wedge mouth 6 is other than positioning action, it may also be used for using the connection of special connecting piece 14 and muscle material;Special connecting piece 14 is overhanging
Serrated attachment, the A module, B module, there are wedge mouths up and down, play positioning action, the wedge mouth is built into and TGXG
The overhanging serrated attachment of hole occlusion is connect with TGXG.
It is as shown in Figure 10 rubble water guide containing aquaporin and reinforced earth bulkhead drainage system connection schematic diagram.Rubble water guide contains
Aquaporin carries on the back 17 connection of weeper drain by bright gutter 16 before drainpipe 15 and wall or wall.
Its sequence of construction is to purchase muscle material, and Prefabricated block A1, module B2 prepare backfill material.Construction concrete bar shaped first
Basis 10, construction in layer modules A 1, module B2, muscle material 4 and backfill material 5, coping block 11 of finally constructing.
From the present embodiment as can be seen that the green ecological modular reinforced earth bulkhead of the utility model, is dexterously configured with
Raw storehouse, creation reinforced earth are planted containing aquaporin and evagination by rubble water guide vertically up and down in rubble water guide storehouse and the raw storehouse of plant
Barricade green ecological system.Its is prefabricated simple, easy for construction, and effectively reduces construction investment, and it is green to improve reinforced earth bulkhead
Color ecology, has very high practical value and extraordinary application prospect.
It should be noted that, in this document, relational terms such as first and second and the like are used merely to a reality
Body or operation are distinguished with another entity or operation, are deposited without necessarily requiring or implying between these entities or operation
In any actual relationship or order or sequence.Moreover, the terms "include", "comprise" or its any other variant are intended to
Non-exclusive inclusion, so that the process, method, article or equipment including a series of elements is not only wanted including those
Element, but also including other elements that are not explicitly listed, or further include for this process, method, article or equipment
Intrinsic element.In the absence of more restrictions, the element limited by sentence "including a ...", it is not excluded that
There is also other identical elements in process, method, article or equipment including the element.
Above embodiments are only to illustrate the technical solution of the utility model, rather than its limitations;Although referring to aforementioned reality
Example is applied the utility model is described in detail, those skilled in the art should understand that: it still can be to preceding
Technical solution documented by each embodiment is stated to modify or equivalent replacement of some of the technical features;And these
It modifies or replaces, the spirit and model of various embodiments of the utility model technical solution that it does not separate the essence of the corresponding technical solution
It encloses.
Claims (6)
1. a kind of green ecological modular reinforced earth bulkhead, it is characterised in that: include
Concrete continuous footing;
Wall, the wall include the A module vertically stacked on concrete continuous footing, B module, and A module, B module side
End face alignment forms wall back, and another side end face is interspersed, and before forming spatially concave-convex wall, A module and B module composition should
The wall of barricade;
Coping block, the coping block are pressed in the top of wall part;
Wherein, the raw storehouse of the reserved plant of the A module and rubble water guide storehouse, the B module reserve rubble water guide storehouse, the rubble of A module
The rubble water guide storehouse of water guide storehouse and B module spatially up and down, forms rubble water guide and contains aquaporin.
2. a kind of green ecological modular reinforced earth bulkhead according to claim 1, it is characterised in that: in the A module
Portion is equipped with cavity, and rubble water guide storehouse and the raw storehouse of plant are placed in the cavity, wherein planting raw storehouse section bottom is equipped with the raw bottom plate of plant.
3. a kind of green ecological modular reinforced earth bulkhead according to claim 1, it is characterised in that: in the B module
Portion is equipped with cavity, and rubble water guide storehouse is placed in the cavity.
4. a kind of green ecological modular reinforced earth bulkhead according to claim 1, it is characterised in that: the rubble water guide
Weeper drain connection is carried on the back by bright gutter before drainpipe and wall or wall containing aquaporin.
5. a kind of green ecological modular reinforced earth bulkhead according to claim 1, it is characterised in that: the A module and B
It is equipped with reinforcing bar in module, passes through the fixed embedded ribs material of reinforcing bar.
6. a kind of green ecological modular reinforced earth bulkhead according to claim 1, it is characterised in that: the A module, B
Module, up and down there are wedge mouth, the wedge mouth is built into overhanging serrated attachment, the overhanging serrated attachment and TGXG hole
Gap is connected.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920284793.2U CN209723027U (en) | 2019-03-06 | 2019-03-06 | A kind of green ecological modular reinforced earth bulkhead |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920284793.2U CN209723027U (en) | 2019-03-06 | 2019-03-06 | A kind of green ecological modular reinforced earth bulkhead |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209723027U true CN209723027U (en) | 2019-12-03 |
Family
ID=68685290
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201920284793.2U Active CN209723027U (en) | 2019-03-06 | 2019-03-06 | A kind of green ecological modular reinforced earth bulkhead |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209723027U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112647486A (en) * | 2020-03-04 | 2021-04-13 | 广州市设计院 | Retaining wall water drainage method and retaining wall water drainage system |
CN115288186A (en) * | 2022-07-23 | 2022-11-04 | 云南省设计院集团有限公司 | Novel combination formula reinforced earth barricade module panel of green planting wall |
-
2019
- 2019-03-06 CN CN201920284793.2U patent/CN209723027U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112647486A (en) * | 2020-03-04 | 2021-04-13 | 广州市设计院 | Retaining wall water drainage method and retaining wall water drainage system |
CN115288186A (en) * | 2022-07-23 | 2022-11-04 | 云南省设计院集团有限公司 | Novel combination formula reinforced earth barricade module panel of green planting wall |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206655248U (en) | A kind of assembly concrete empty van soil-baffling structure | |
CN109555153B (en) | Assembled ecological gravity type retaining wall | |
CN209723027U (en) | A kind of green ecological modular reinforced earth bulkhead | |
CN110241779A (en) | A kind of ecological block barricade and its construction method | |
CN110306589B (en) | Method for forming assembled reinforced earth retaining wall | |
CN106088318A (en) | The overlapping assembled integral basement that flat slab system is combined with post and lintel system | |
CN106121035A (en) | A kind of overlapping assembled integral basement of flat slab system | |
CN209555948U (en) | A kind of pin-connected panel ecology retaining plate between piles construction | |
CN209066479U (en) | Assembled green ecological reinforced earth retaining wall | |
CN105780756B (en) | Protecting wall and H-type prestressed-concrete pile for the protecting wall | |
CN210658432U (en) | Assembled concrete box retaining wall | |
CN108867668B (en) | Ecological retaining plate structure | |
CN208219673U (en) | Greening Retaining Wall construction between stake | |
CN210263127U (en) | A panel modular unit and reinforced earth retaining wall for reinforced earth retaining wall | |
CN205894279U (en) | Integral basement of coincide assembly of hollow superstructure system of no roof beam | |
CN205894278U (en) | Solid superstructure beam -columns system's integral basement of coincide assembly | |
CN213038303U (en) | Ecological concrete vegetation slope protection structure | |
CN215330002U (en) | Ecological building block reaches ecological building block wainscot structure who contains it | |
CN209837087U (en) | Assembled ecological anchoring plate retaining wall | |
CN210439275U (en) | Consolidation structure for treating soft soil foundation | |
CN209693554U (en) | A kind of pin-connected panel ecology gravity retaining wall | |
CN210857151U (en) | Ecological coping structure with drainage function | |
CN208844608U (en) | A kind of assembled ecological anchor rod retaining wall structure | |
CN114086505A (en) | River course slope protection structure for hydraulic engineering and laying construction method | |
CN111663543A (en) | Ear wall formula open cut tunnel structure of stake board formula |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |