CN209705416U - A kind of ears hanger of petrochemical industry horizontal pipe - Google Patents

A kind of ears hanger of petrochemical industry horizontal pipe Download PDF

Info

Publication number
CN209705416U
CN209705416U CN201920396646.4U CN201920396646U CN209705416U CN 209705416 U CN209705416 U CN 209705416U CN 201920396646 U CN201920396646 U CN 201920396646U CN 209705416 U CN209705416 U CN 209705416U
Authority
CN
China
Prior art keywords
nut
shaped frame
horizontal pipe
screw rod
pieces
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920396646.4U
Other languages
Chinese (zh)
Inventor
徐春成
薛为亮
鲁加浪
鲁德亚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yancheng City Ruiheng Electric Power Petrochemical Equipment Co
Original Assignee
Yancheng City Ruiheng Electric Power Petrochemical Equipment Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yancheng City Ruiheng Electric Power Petrochemical Equipment Co filed Critical Yancheng City Ruiheng Electric Power Petrochemical Equipment Co
Priority to CN201920396646.4U priority Critical patent/CN209705416U/en
Application granted granted Critical
Publication of CN209705416U publication Critical patent/CN209705416U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

The utility model discloses a kind of ears hangers of petrochemical industry horizontal pipe, belong to pipe-hanger support field, including including two pieces of beam slabs being oppositely arranged, pass through tenon groove structure and two pieces of beam slabs, two lifting lugs connected vertically, the pin shaft being arranged between two lifting lugs, clamp-close type is connected to the nut pedestal on top at two pieces of beam slab both ends, hangs the U-shaped frame between two nut pedestals, and the U-shaped frame is fastenedly connected on nut pedestal by nut;Smooth chimb plate is fixed at the U-shaped frame both ends, the nut the middle of the base is fixed with the screw rod being vertically arranged, and the chimb plate is equipped with the through-hole passed through for screw rod, and engagement sleeves are equipped with nut on the screw rod, and the chimb plate is located at the top of the nut.The horizontal pipe that the utility model is sling will not be fallen due to nut is damaged or fallen, and be beneficial to prevent horizontal pipe damage, be also beneficial to ensure construction safety.

Description

A kind of ears hanger of petrochemical industry horizontal pipe
Technical field
The utility model relates to pipe-hanger support field, the ears for being specifically related to a kind of petrochemical industry horizontal pipe are hung Frame.
Background technique
Currently, being U for small-bore, intermediate and heavy load pipe-hanger support horizontal tube hanger in pipeline engineering Shape screw rod beam slab assembled hanger, generally comprises twin beams plate, is threaded through the U-shaped screw rod of the tube lining plate of twin beams board ends, twin beams Two lifting lugs with perforation are connected by welding manner among plate, a pin shaft is threaded through in the lifting hole(eyelet) of two lifting lugs.Due to two A lifting lug is all made of welding form connection twin beams plate and therefore brings heavy welding capacity in process of production, while also will appear weldering Connecing deviation, it is not coaxial that welding deviation is likely to result in two lifting lug holes, so that unbalance stress in actual moving process, for welding Form repairing is also more difficult.Horizontal tube hanger for heavy caliber, heavy load pipe-hanger support in large-scale pipeline engineering is U Shape band steel beam slab assembled hanger.U-shaped screw rod is replaced divided by U-shaped band steel in its structure, and outer, Qi Tajie is connect with twin beams board ends Structure and U-shaped screw rod beam slab assembled hanger are unanimous on the whole.Therefore, there is also drawbacks described above for the welding connecting mode of lifting lug.
Currently, the ears for disclosing a kind of horizontal pipe in the patent that Authorization Notice No. is 201535396 U of CN are hung Frame.It includes the U-shaped frame connecting with twin beams board ends, with the double shackle of lifting hole(eyelet), and a pin shaft is threaded through in lifting hole(eyelet);Double shackle point Not Yong tongue-and-groove connect with twin beams plate, can solve two lifting lugs be all made of welding form connection twin beams plate bring defect, using this Connection cooperation may be implemented in structure, reduces welding capacity, so that easy to assembly, suspension and support needed for enriching heavy pipeline engineering Kind.But itself and existing horizontal pipe hanger, which have the following disadvantages: them all, to be used by the screw rod at holding element both ends Nut tightening and the end for being connected to twin beams plate, once nut damage or falling, screw rod will be detached from nut pedestal, to can make The horizontal pipe sling is fallen, and horizontal pipe may be caused to damage, it is also possible to threaten working security.
Utility model content
1. technical problems to be solved
The technical problem to be solved by the present invention is to provide a kind of ears hangers of petrochemical industry horizontal pipe, hang The horizontal pipe risen will not be fallen due to nut is damaged or fallen.
2. technical solution
To solve the above problems, the utility model adopts the following technical scheme:
A kind of ears hanger of petrochemical industry horizontal pipe, the beam slab being oppositely arranged including two pieces, by tenon groove structure with Two pieces of beam slabs, two lifting lugs connected vertically, the pin shaft being arranged between two lifting lugs, clamp-close type are connected to two pieces of beam slab both ends Locate the nut pedestal on top, hang the U-shaped frame between two nut pedestals, the U-shaped frame is fastenedly connected by nut in spiral shell On female pedestal;Smooth chimb plate is fixed at the U-shaped frame both ends, the nut the middle of the base is fixed with the spiral shell being vertically arranged Bar, the chimb plate are equipped with the through-hole passed through for screw rod, and engagement sleeves are equipped with the spiral shell for being supported in chimb board bottom portion on the screw rod It is female.
Further, the both ends of the beam slab offer card slot, and the both ends of the nut pedestal can just be stuck in two pieces On beam slab in the card slot of the same end, and the limit for the beam slab two sides being held below card slot is respectively and fixedly provided at the both ends of nut pedestal Plate, the limit plate and nut pedestal are integrally formed.Being formed between two pieces of limit plates of nut base end more preferably can be for beam slab The card slot being caught in, so that beam slab can also be caught in nut pedestal while being caught in card slot on beam slab for nut pedestal top Lower part may advantageously facilitate being stably connected between nut pedestal and beam slab, and can limit two pieces of beam slabs and two nut pedestals Position, convenient for the installation of lifting lug and U-shaped frame.
Further, the limit being bonded with two pieces of beam slab opposite sides is fixed at the lifting lug two sides and the position of beam slab joggle Position block.It can determine two pieces of relative positions between beam slab and lifting lug, installed convenient for the connection of the two.
Further, two blocks of chimb plates are located at the opposite sides at U-shaped frame both ends, two vertical edges point of the U-shaped frame Not Wei Yu corresponding side nut pedestal outside.Setting can increase the width on the inside of U-shaped frame in this way, so as to be adapted to more specifications Horizontal pipe.
Further, the chimb plate and U-shaped frame are integrally formed, the height between the screw rod fixing end and beam slab bottom The sum of difference and the length of screw rod are not more than the height of U-shaped frame vertical portion.It is not provided with being connected and fixed knot between chimb plate and U-shaped frame Structure can prevent the two from separating, to be more advantageous to the effect for ensureing U-shaped frame anti-dropout.The length of U-shaped frame vertical portion and screw rod It limits, allows U-shaped frame to be moved to chimb plate to screw rod upper end side direction and removed from screw rod upper end, at this point, being just able to achieve U-shaped frame With the separation of the components such as beam slab.In application, U-shaped frame can be removed, level can be fastened in by the side of horizontal pipe any position It (does not need to be inserted in from the end of horizontal pipe) on pipeline, then again install U-shaped frame on screw rod, application is more convenient.
3. beneficial effect
The utility model is fixed with smooth chimb plate at the both ends of U-shaped frame, and nut the middle of the base is fixed with to be set vertically The screw rod set, chimb plate are threaded through on screw rod, and engagement sleeves are equipped with the nut for being supported in chimb board bottom portion on screw rod.In application, if Nut eventually drops to the position of fitting nut pedestal because damaging or falling the supporting role lost to chimb plate, chimb plate, Nut pedestal can prevent chimb plate from continuing to decline, i.e., when nut is damaged or fallen, the U-shaped frame for carrying horizontal pipe can decline A distance, without departing from nut pedestal, the horizontal pipe sling will not be fallen due to nut is damaged or fallen, and be conducive to prevent The flat Pipeline damage of sealing is also beneficial to ensure construction safety.
Detailed description of the invention
Fig. 1 is the schematic perspective view of the utility model;
Fig. 2 is the schematic diagram after each component of the utility model is split.
Appended drawing reference: 1- beam slab, 11- card slot, 2- lifting lug, 21- limited block, 3- pin shaft, 4- nut pedestal, 41- limit plate, 5-U type frame, 51- chimb plate, 6- nut, 7- screw rod, 8- through-hole.
Specific embodiment
The utility model is described in further detail with reference to the accompanying drawings and examples.
Embodiment
A kind of ears hanger of petrochemical industry horizontal pipe as shown in Figures 1 and 2, the beam slab being oppositely arranged including two pieces 1, by 1 connected vertically two lifting lug 2 of tenon groove structure and two pieces of beam slabs, the pin shaft 3 being arranged between two lifting lugs 2, engaging Formula is connected to the nut pedestal 4 on top at two pieces of 1 both ends of beam slab, hangs the U-shaped frame 5 between two nut pedestals 4, the U Type frame 5 is fastenedly connected on nut pedestal 4 by nut 6;Smooth chimb plate 51 is fixed at 5 both ends of U-shaped frame, it is described The screw rod 7 being vertically arranged is fixed in the middle part of nut pedestal 4, the chimb plate 51 is equipped with the through-hole 8 passed through for screw rod 7, described Engagement sleeves are equipped with the nut 6 for being supported in 51 bottom of chimb plate on screw rod 7.
In the present embodiment, the both ends of the beam slab 1 offer card slot 11, and the both ends of the nut pedestal 4 can just It is stuck on two pieces of beam slabs 1 in the card slot 11 of the same end, and is respectively and fixedly provided at the both ends of nut pedestal 4 and is held on 11 lower section of card slot The limit plate 41 of 1 two sides of beam slab, the limit plate 41 are integrally formed with nut pedestal 4.Two pieces of limit plates of 4 end of nut pedestal Being formed between 41 more preferably can be for the card slot 11 that beam slab 1 is caught in, so that being caught in card slot 11 on beam slab 1 for 4 top of nut pedestal Meanwhile beam slab 1 can also be caught in the lower part of nut pedestal 4, may advantageously facilitate being stably connected between nut pedestal 4 and beam slab 1, And the position of two pieces of beam slabs 1 and two nut pedestals 4 can be limited, convenient for the installation of lifting lug 2 and U-shaped frame 5.
In the present embodiment, it is fixed with and two pieces of 1 opposite sides of beam slab at 2 two sides of lifting lug and the position of 1 joggle of beam slab The limited block 21 of fitting.It can determine the relative position between two pieces of beam slabs 1 and lifting lug 2, installed convenient for the connection of the two.
In the present embodiment, two blocks of chimb plates 51 are located at the opposite sides at U-shaped 5 both ends of frame, and the two of the U-shaped frame 5 Vertical edge is located at the outside of corresponding side nut pedestal 4.Setting can increase the width of U-shaped 5 inside of frame in this way, to adapt to In the horizontal pipe of more specifications.
In the present embodiment, the chimb plate 51 is integrally formed with U-shaped frame 5,7 fixing end of screw rod and 1 bottom of beam slab Between difference in height and the sum of the length of screw rod 7 be not more than the height of U-shaped 5 vertical portion of frame.Between chimb plate 51 and U-shaped frame 5 It is not provided with being connected and fixed structure, can prevent the two from separating, to be more advantageous to the effect for ensureing U-shaped 5 anti-dropout of frame.U-shaped frame 5 is perpendicular The length of straight part and screw rod 7 limits, and U-shaped frame 5 is allowed to be moved to chimb plate 51 from screw rod 7 to 7 upper end side direction of screw rod End removes, at this point, being just able to achieve the separation that U-shaped frame 5 waits components with beam slab 1.In application, U-shaped frame 5 can be removed, it can be by level The side of pipeline any position is fastened on horizontal pipe and (does not need to be inserted in from the end of horizontal pipe), then again by U-shaped frame 5 It installs on screw rod 7, application is more convenient.
The concrete application process of the ears hanger of above-mentioned petrochemical industry horizontal pipe are as follows:
Two pieces of beam slabs 1 are first distinguished into joggle in two end sides of lifting lug 2, so that two lifting lugs 2 are parallel to each other and perpendicular to beam Pin shaft 3 is then passed through two lifting lugs 2, then the nut pedestal 4 for being fixed with screw rod 7 is installed on to the end of two pieces of beam slabs 1 by plate 1 Portion, then nut 6 is threaded to the bottom of screw rod 7;
U-shaped frame 5 with chimb plate 51 is fastened in horizontal pipe from any position side of horizontal pipe to be hung Upper (not needing to be inserted in from the end of horizontal pipe) then again simultaneously on two screw rods 7 and adjusts two blocks 51 sets of chimb plate To suitable height, the bottom that nut 6 is threaded to chimb plate 51 is support into chimb plate 51, just can be carried out and horizontal pipe is hung Dress.
Even if nut 6 is damaged or fallen, chimb plate 51 eventually drops to the position of fitting nut pedestal 4, nut pedestal 4 Chimb plate 51 can be prevented to continue to decline, i.e., when nut 6 is damaged or fallen, the U-shaped frame 5 for carrying horizontal pipe can decline one section Distance, without departing from nut pedestal 4, the horizontal pipe sling is not fallen out.
As shown in the above, the horizontal pipe that the utility model is sling will not be fallen due to nut is damaged or fallen, and be had Conducive to preventing horizontal pipe from damaging, it is also beneficial to ensure construction safety.
Those of ordinary skill in the art it should be appreciated that more than embodiment be intended merely to illustrate that this is practical new Type, and be not used as the restriction to the utility model, as long as in the spirit of the utility model, to the above Variation, the modification of embodiment will all be fallen in the scope of the claims of the utility model.

Claims (5)

1. a kind of ears hanger of petrochemical industry horizontal pipe, including two pieces of beam slabs being oppositely arranged (1), by tenon groove structure with Two pieces of beam slabs (1), two lifting lugs (2) connected vertically, the pin shaft (3) being arranged between two lifting lugs (2), clamp-close type is connected to The nut pedestal (4) on top at two pieces of beam slab (1) both ends hangs the U-shaped frame (5) between two nut pedestals (4), the U Type frame (5) is fastenedly connected on nut pedestal (4) by nut (6);It is characterized in that, being fixed at U-shaped frame (5) both ends Smooth chimb plate (51), is fixed with the screw rod (7) being vertically arranged in the middle part of the nut pedestal (4), on the chimb plate (51) Equipped with the through-hole (8) passed through for screw rod (7), engagement sleeves are equipped with the nut for being supported in chimb plate (51) bottom on the screw rod (7) (6)。
2. a kind of ears hanger of petrochemical industry horizontal pipe according to claim 1, which is characterized in that the beam slab (1) both ends offer card slot (11), and the both ends of the nut pedestal (4) can just be stuck in the same end on two pieces of beam slabs (1) Card slot (11) in, and the limit of beam slab (1) two sides being held below card slot (11) is respectively and fixedly provided at the both ends of nut pedestal (4) Position plate (41), the limit plate (41) and nut pedestal (4) are integrally formed.
3. a kind of ears hanger of petrochemical industry horizontal pipe according to claim 1, which is characterized in that the lifting lug (2) limited block (21) being bonded with two pieces of beam slab (1) opposite sides is fixed at two sides and the position of beam slab (1) joggle.
4. a kind of ears hanger of petrochemical industry horizontal pipe according to claim 1, which is characterized in that two pieces described convex Side plate (51) is located at the opposite sides at U-shaped frame (5) both ends, and two vertical edges of the U-shaped frame (5) are located at corresponding side nut bottom The outside of seat (4).
5. a kind of ears hanger of petrochemical industry horizontal pipe according to claim 1 or 3, which is characterized in that described convex Side plate (51) and U-shaped frame (5) are integrally formed, difference in height and screw rod between screw rod (7) fixing end and beam slab (1) bottom (7) the sum of length is not more than the height of U-shaped frame (5) vertical portion.
CN201920396646.4U 2019-03-20 2019-03-20 A kind of ears hanger of petrochemical industry horizontal pipe Active CN209705416U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920396646.4U CN209705416U (en) 2019-03-20 2019-03-20 A kind of ears hanger of petrochemical industry horizontal pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920396646.4U CN209705416U (en) 2019-03-20 2019-03-20 A kind of ears hanger of petrochemical industry horizontal pipe

Publications (1)

Publication Number Publication Date
CN209705416U true CN209705416U (en) 2019-11-29

Family

ID=68645737

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920396646.4U Active CN209705416U (en) 2019-03-20 2019-03-20 A kind of ears hanger of petrochemical industry horizontal pipe

Country Status (1)

Country Link
CN (1) CN209705416U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2022106345A (en) * 2021-01-07 2022-07-20 株式会社山下製作所 Piping support device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2022106345A (en) * 2021-01-07 2022-07-20 株式会社山下製作所 Piping support device
JP7348666B2 (en) 2021-01-07 2023-09-21 株式会社山下製作所 Piping support device

Similar Documents

Publication Publication Date Title
CN209705416U (en) A kind of ears hanger of petrochemical industry horizontal pipe
CN210946813U (en) Bearing platform for installing cast-in-place pile reinforcement cage
CN209145128U (en) A kind of assembled ceiling structure
CN210920331U (en) Concatenation formula pipeline gallows
CN106049692A (en) Light steel house connecting structure
CN112049464A (en) Steel structure support frame for assembly type building
CN109958819A (en) A kind of gas pipeline laying method and its supporting structure
CN208074270U (en) A kind of fixing device of petroleum pipeline
CN209227401U (en) A kind of Hanging Basket bottom basket system hanger
CN204715301U (en) For building the turn-over form of normal concrete
CN209114015U (en) Combined cathode electrophoresis coating hanger
CN209469874U (en) A kind of I-beam pipe installation bracket
CN205681051U (en) A kind of line holder
CN109210275A (en) A kind of I-beam pipe installation bracket
CN102174969B (en) Steel cable hanger and construction method thereof
CN209370591U (en) A kind of rectangle blower antidetonation suspension and support
CN208561418U (en) A kind of heavy equipment special hanger
CN205840001U (en) A kind of light steel house connecting structure
CN209621396U (en) A kind of pit shaft fixing device for pipe
CN110043297A (en) A kind of tunnel inverted arch buried water strip fixture
CN209430875U (en) A kind of antidetonation suspension and support
CN205740006U (en) A kind of high intensity suspension and support
CN211976136U (en) Anti-seismic support and hanger convenient to adjust
CN205034939U (en) Lift by crane special strutting arrangement of water pump
CN204026063U (en) A kind of hoisting structure of LED display

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant