CN110043297A - A kind of tunnel inverted arch buried water strip fixture - Google Patents

A kind of tunnel inverted arch buried water strip fixture Download PDF

Info

Publication number
CN110043297A
CN110043297A CN201910468207.4A CN201910468207A CN110043297A CN 110043297 A CN110043297 A CN 110043297A CN 201910468207 A CN201910468207 A CN 201910468207A CN 110043297 A CN110043297 A CN 110043297A
Authority
CN
China
Prior art keywords
channel steel
hole
bolt
inverted arch
buried water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910468207.4A
Other languages
Chinese (zh)
Inventor
姜枫
刁春杰
唐太恩
马建锋
王斯聪
刘振华
姚嫉
杨佑强
王辉
李翔
吴家鹏
王炜
李宏宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Construction Engineering Group Co Ltd
Original Assignee
China Railway Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Construction Engineering Group Co Ltd filed Critical China Railway Construction Engineering Group Co Ltd
Priority to CN201910468207.4A priority Critical patent/CN110043297A/en
Publication of CN110043297A publication Critical patent/CN110043297A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • E21D11/381Setting apparatus or devices

Abstract

The present invention relates to constructing tunnel equipment technical fields, more particularly to a kind of tunnel inverted arch buried water strip fixture, including clamping piece and several connectors, clamping piece includes the first channel steel and the second channel steel, the upper leg of first channel steel is equipped with several first through hole, the upper leg of second channel steel is equipped with the second through-hole corresponding with first through hole, locating rack is respectively arranged below in the first channel steel and the second channel steel, the connector includes U-bolt, one end of U-bolt is equipped with positioning mechanism, the second nut is welded with across one end of the U-bolt of the second through-hole, the second screw rod is threaded on second nut.The problem of the present invention program solves prior art buried water strip fixture peace and tears inconvenience open, and fixture cannot be used in turn.

Description

A kind of tunnel inverted arch buried water strip fixture
Technical field
The present invention relates to tunnel inverted arch waterstop construction fields, and in particular to a kind of tunnel inverted arch buried water strip fixture.
Background technique
In constructing tunnel quality, tunnel water handling is the key points and difficulties of construction quality, and tunnel inverted arch waterstop is pacified Dress is the important link in tunnel waterproof and water drainage system.Currently, inverted arch short abutment wall buried water strip fixture in tunnel is by reinforcing bar mostly Equal profiles are welded to form, and the buried water strip fixture peace of this welding tears inconvenience open, not reproducible to be used in turn.
Summary of the invention
The purpose of the present invention is to provide a kind of tunnel inverted arch buried water strip fixtures, in the short abutment wall of tunnel inverted arch Buried water strip is installed, cannot be used in turn with solving the problem of that buried water strip fixture peace tears inconvenience fixture open in the prior art. To achieve the goals above, scheme provided by the invention is as follows:
A kind of tunnel inverted arch buried water strip fixture, including clamping piece and several connectors, the clamping piece include first The waist of channel steel and the second channel steel, first channel steel and the second channel steel is close to each other, and the upper leg of the first channel steel is equipped with several edges The upper leg of the uniformly distributed first through hole of first channel steel length direction, the second channel steel is equipped with several corresponding with the first through hole second Through-hole is respectively arranged below locating rack, the locating rack lower part and two side plane of tunnel inverted arch in the first channel steel and the second channel steel It is fixedly connected, the connector includes U-bolt, and the both ends of U-bolt are each passed through first through hole and the second through-hole, passes through the One end of the U-bolt of one through-hole is removably connected with positioning mechanism, is welded with across one end of the U-bolt of the second through-hole Two nuts are threaded with the second screw rod on second nut, wirerope are connected on U-bolt.
The principle of base case of the present invention is:
The second screw rod on second nut is unscrewed off the second nut, after one end of U-bolt is passed through first through hole Positioning mechanism is put on, the second screw rod is screwed in into the second nut after the second through-hole by the other end of U-bolt, sealing is buried by Band is put into the crack between the first channel steel and the second channel steel waist close to each other, adjusts the overhang of buried water strip After height, the second screw rod of turn moves the second screw rod to the first channel steel direction, and the second screw rod is by the second channel steel to the first channel steel Direction promotes in the crack to which buried water strip to be clamped between the first channel steel and the second channel steel waist close to each other, root After connecting multiple U-bolts with clamping piece according to the length of inverted arch, the wirerope on U-bolt is hung over to the suspension hook of boom hoisting On, clamping piece is lain in a horizontal plane on locating rack by boom hoisting, buried water strip lower end is made to keep vertical state.
The beneficial effect that this programme generates is:
One, this programme presss from both sides clamping piece to waterstop by turn screw rod in U-bolt one end welded nut Tightly, facilitate the height dimension of adjustment waterstop overhang, while screw rod plays the role of lifting clamping piece.
Two, being detachably connected for U-bolt and channel steel keeps fixture reusable.
Three, locating rack is set below clamping piece, improves the levelness that clamping piece is placed, ensure that hanging down for waterstop installation Straight degree.
Further, the optimization as basic scheme, first channel steel are identical as the specification of second channel steel.
The channel steel pairing use of two same sizes clamps buried water strip from two sides, buries only during when lifting is entire The two sides weight of water band is identical, is not susceptible to deflect, and is conducive to buried water strip and keeps vertical state.
Further, the positioning mechanism is the first nut cooperated with U-bolt.Connect in the other end screw thread of U-bolt Connected nut can adjust the effect of waterstop two sides channel steel height when lifting by crane clamping piece.
Further, the rounded hole of first through hole, the diameter of first through hole are greater than the diameter 2-5mm of U-bolt.Facilitate U-shaped Bolt guarantees that the first nut will not be such that nut plays and undertake the first channel steel weight by first through hole by first through hole Effect.
Further, the axis of thread of second nut is vertical with the second channel steel waist side.
Further, third screw rod is welded on U-bolt, two adjacent U-bolts are connected by connecting plate, the company Fishplate bar both ends are respectively equipped with the third through-hole of the cooperation of the third screw rod with two on adjacent U-bolt.When will be adjacent with connecting plate When two U-bolts are fixedly connected, the U-bolt when lifting to fixture is made not effectively prevent U to lifting center position deflection The bending deformation of type bolt.
Further, the third through-hole is in long hole, and the length direction of the long hole is consistent with the second channel steel length direction.
Detailed description of the invention
Fig. 1 is a kind of left view of tunnel inverted arch buried water strip fixture of the present invention.
Fig. 2 is a kind of front view of tunnel inverted arch buried water strip fixture of the present invention.
Specific embodiment
It is further described below by specific embodiment:
Appended drawing reference in Figure of description includes: the first channel steel 10, the second channel steel 11, first through hole 12, the second through-hole 13, locating rack 14, U-bolt 15, the first nut 16, the second nut 17, the second screw rod 18, wirerope 19, buried water strip 21, Connecting plate 31, third screw rod 32, inverted arch 5, short abutment wall 6.
A kind of tunnel inverted arch buried water strip fixture, as depicted in figs. 1 and 2, including clamping piece and several connectors, clamping Part includes identical first channel steel 10 of specification and the second channel steel 11, and the first channel steel 10 and the second channel steel 11 are No. 10 channel steels, the The waist of one channel steel 10 and the second channel steel 11 is close to each other, and the upper leg of the first channel steel 10 is equipped with 3 along 10 length side of the first channel steel To uniformly distributed first through hole 12, the rounded hole of first through hole 12, the upper leg of the second channel steel 11 is equipped with corresponding with first through hole 12 Second through-hole 13 is respectively arranged below the locating rack 14 by reinforcement welding, locating rack 14 in the first channel steel 10 and the second channel steel 11 Lower part is fixedly connected with two side planes of tunnel inverted arch 5, and the upper end level of locating rack 14 and the casting level of short abutment wall 6 are contour, Connector includes U-bolt 15, and the both ends of U-bolt 15 are each passed through first through hole 12 and the second through-hole 13, and it is logical to pass through first The threaded one end of the U-bolt 15 in hole 12 connects the first nut 16, and one end across the U-bolt 15 of the second through-hole 13 is welded with The axis of thread of second nut 17, the second nut 17 is vertical with 11 waist side of the second channel steel, is threadedly coupled on the second nut 17 There is the second screw rod 18, U-bolt 15 can make the curved of U-bolt to lifting center position deflection when lifting to fixture in order to prevent Song deformation, is welded with third screw rod 32, the third screw rod 32 on two adjacent U-bolts 15 passes through connection on U-bolt 15 Plate 31 connects, and connecting plate 31 is made of 5mm steel plate, and 31 both ends of connecting plate are respectively equipped with two on adjacent U-bolt 15 The third through-hole that third screw rod 32 cooperates, third through-hole are in long hole, the length direction of long hole and 11 length direction phase of the second channel steel Unanimously, wirerope 19 is connected on U-bolt 15.First through hole is passed through in order to facilitate U-bolt 15, while making the first nut Play the role of the lifting of playing to the first channel steel, the diameter of setting first through hole 12 is greater than 2~5mm of diameter of U-bolt 15.
A kind of working process and principle of tunnel inverted arch buried water strip fixture of the present invention are:
The second screw rod 18 on second nut 17 is unscrewed off the second nut 17, one end of U-bolt 15 is passed through the The first nut 16 is taken after one through-hole 12, and the other end of U-bolt 15 is screwed in the second screw rod 18 after the second through-hole 13 Buried water strip 21 is put into the crack between the first channel steel 10 and the second channel steel 11 waist close to each other by the second nut 17, After the height for adjusting the overhang of buried water strip 21, the second screw rod of turn 18 makes the second screw rod 18 to 10 side of the first channel steel To movement, the second screw rod 18 promotes the second channel steel 11 to 10 direction of the first channel steel buried water strip 21 is clamped in first In crack between channel steel 10 and the second channel steel 11 waist close to each other, the third through-hole at 31 both ends of connecting plate is respectively aligned to Two adjacent third screw rods 32 are inserted in, and are fixedly connected with connecting plate 31 with U-bolt 15 by nut and third screw rod 32, After being connect multiple U-bolts 15 with clamping piece according to the length of buried water strip 21, the wirerope 19 on U-bolt 15 is hung On the suspension hook of the boom hoisting of peripheral hardware, being lain in a horizontal plane in clamping piece on locating rack 14 and by hawkbill by boom hoisting makes Clamping piece is fixedly connected with locating rack 14, and fixture is made to keep horizontality, so that the lower end of buried water strip 21 keeps catenary State can open hawkbill and the first nut of turn 16 after the overhang to buried water strip carries out casting concrete With the second screw rod 18, separate fixture so that subsequent installation continues to use with buried water strip 21 and locating rack 14.
The above are merely the embodiment of the present invention, the common sense such as well known specific structure and characteristic are not made excessively herein in scheme Description.It should be pointed out that for those skilled in the art, without departing from the structure of the invention, can also make Several modifications and improvements, these also should be considered as protection scope of the present invention, these all will not influence the effect that the present invention is implemented And patent practicability.The scope of protection required by this application should be based on the content of the claims, specific in specification The records such as embodiment can be used for explaining the content of claim.

Claims (7)

1. a kind of tunnel inverted arch buried water strip fixture, including clamping piece and several connectors, it is characterised in that: the clamping piece Including the first channel steel and the second channel steel, the waist of first channel steel and the second channel steel is close to each other, and the upper leg of the first channel steel is set There are several first through hole uniformly distributed along the first channel steel length direction, the upper leg of the second channel steel is equipped with several and first through hole pair The second through-hole answered is respectively arranged below locating rack, the locating rack lower part and tunnel inverted arch in the first channel steel and the second channel steel Two side planes be fixedly connected, the connector includes U-bolt, and the both ends of U-bolt are each passed through first through hole and second Through-hole, one end across the U-bolt of first through hole be removably connected with positioning mechanism, across the U-bolt of the second through-hole One end is welded with the second nut, is threaded with the second screw rod on second nut, wirerope is connected on U-bolt.
2. a kind of tunnel inverted arch buried water strip fixture according to claim 1, it is characterised in that: first channel steel with The specification of second channel steel is identical.
3. a kind of tunnel inverted arch buried water strip fixture according to claim 1, it is characterised in that: the positioning mechanism is With the first nut of U-bolt cooperation.
4. a kind of tunnel inverted arch buried water strip fixture according to claim 3, it is characterised in that: first through hole is rounded The diameter in hole, first through hole is greater than 2~5mm of U-bolt diameter.
5. a kind of tunnel inverted arch buried water strip fixture according to claim 1, it is characterised in that: second nut The axis of thread is vertical with the second channel steel waist side.
6. a kind of tunnel inverted arch buried water strip fixture according to claim 1, it is characterised in that: welded on U-bolt It is connected to third screw rod, two adjacent U-bolts are connected by connecting plate, and the connection board ends are respectively equipped with the adjacent U with two The third through-hole of third screw rod cooperation on type bolt.
7. a kind of tunnel inverted arch buried water strip fixture according to claim 6, it is characterised in that: the third through-hole is in Long hole, the length direction of the long hole are consistent with the second channel steel length direction.
CN201910468207.4A 2019-05-31 2019-05-31 A kind of tunnel inverted arch buried water strip fixture Pending CN110043297A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910468207.4A CN110043297A (en) 2019-05-31 2019-05-31 A kind of tunnel inverted arch buried water strip fixture

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910468207.4A CN110043297A (en) 2019-05-31 2019-05-31 A kind of tunnel inverted arch buried water strip fixture

Publications (1)

Publication Number Publication Date
CN110043297A true CN110043297A (en) 2019-07-23

Family

ID=67284249

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910468207.4A Pending CN110043297A (en) 2019-05-31 2019-05-31 A kind of tunnel inverted arch buried water strip fixture

Country Status (1)

Country Link
CN (1) CN110043297A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112610245A (en) * 2020-12-02 2021-04-06 中国十九冶集团有限公司 Tunnel inverted arch rubber waterstop fixing device and construction method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05133199A (en) * 1991-11-06 1993-05-28 Fujita Corp Installing method of waterstop
CN202391435U (en) * 2011-12-14 2012-08-22 中铁十二局集团第二工程有限公司 Vertical buried type water stop clamp of inverted arch
CN205577133U (en) * 2016-03-18 2016-09-14 北京建工集团有限责任公司 A U type bolt fastening presss from both sides and fixation clamp structure for fixing outer wall rubber waterstop
CN105971631A (en) * 2016-05-03 2016-09-28 中铁隧道集团二处有限公司 Fixture type end formwork containing steel bar arch wall in tunnel and installation method
CN106930238A (en) * 2017-05-13 2017-07-07 师海林 A kind of hydraulic engineering waterstop fixing device and application method
CN107130984A (en) * 2017-06-19 2017-09-05 中铁隧道集团二处有限公司 A kind of tunnel inverted arch waterstop positioning fixture
CN206752528U (en) * 2017-03-28 2017-12-15 中交第一航务工程局有限公司 A kind of device for the installation of high-speed railway waterstop
CN209959263U (en) * 2019-05-31 2020-01-17 中铁建工集团有限公司 Bury waterstop anchor clamps in tunnel invert

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05133199A (en) * 1991-11-06 1993-05-28 Fujita Corp Installing method of waterstop
CN202391435U (en) * 2011-12-14 2012-08-22 中铁十二局集团第二工程有限公司 Vertical buried type water stop clamp of inverted arch
CN205577133U (en) * 2016-03-18 2016-09-14 北京建工集团有限责任公司 A U type bolt fastening presss from both sides and fixation clamp structure for fixing outer wall rubber waterstop
CN105971631A (en) * 2016-05-03 2016-09-28 中铁隧道集团二处有限公司 Fixture type end formwork containing steel bar arch wall in tunnel and installation method
CN206752528U (en) * 2017-03-28 2017-12-15 中交第一航务工程局有限公司 A kind of device for the installation of high-speed railway waterstop
CN106930238A (en) * 2017-05-13 2017-07-07 师海林 A kind of hydraulic engineering waterstop fixing device and application method
CN107130984A (en) * 2017-06-19 2017-09-05 中铁隧道集团二处有限公司 A kind of tunnel inverted arch waterstop positioning fixture
CN209959263U (en) * 2019-05-31 2020-01-17 中铁建工集团有限公司 Bury waterstop anchor clamps in tunnel invert

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112610245A (en) * 2020-12-02 2021-04-06 中国十九冶集团有限公司 Tunnel inverted arch rubber waterstop fixing device and construction method
CN112610245B (en) * 2020-12-02 2022-11-11 中国十九冶集团有限公司 Tunnel inverted arch rubber waterstop fixing device and construction method

Similar Documents

Publication Publication Date Title
CN204781607U (en) Prestressing force carbon fiber plate stretch -draw anchored integrated device
CN110043297A (en) A kind of tunnel inverted arch buried water strip fixture
CN209130471U (en) A kind of antidetonation suspension and support
CN204454226U (en) A kind of welded suspension centre adjustable and balancing beam of I-shaped steel
CN202416881U (en) Steel girder mounting auxiliary appliance
CN103089010A (en) Cradle construction device replacing reinforced concrete beam bottom protection layer and cradle construction method
CN109736352B (en) Beret beam fixing device and method for suspension pipeline
CN205829049U (en) A kind of secondary stringing adjustable connecting hardware fitting
CN209959263U (en) Bury waterstop anchor clamps in tunnel invert
CN207829276U (en) A kind of furred ceiling is from gripping
CN113529571B (en) Positioning device for rhombic wire-separating pipe cable saddle of short-tower cable-stayed bridge
CN212078774U (en) Load-bearing tripod
CN208100687U (en) Clamping screw and concrete formation mold with clamping screw
CN208100688U (en) Precast concrete wall panel production mould system
CN205294595U (en) Cardboard T is hung
CN215626209U (en) Hoisting clamp for H-shaped steel
CN206467872U (en) Adjustable derrick rig in large span space grid structure furred ceiling
CN205314367U (en) Prestress wire anchor
CN212297950U (en) Novel hoisting piece and hanging bracket
CN111412330B (en) Hoisting piece and hanging bracket at pipeline connecting position
CN203462743U (en) Adjustable cantilever frame I-beam anchoring embedded part
CN219491890U (en) Steel pipe tower cross arm device convenient to install fast
CN204920242U (en) Transmission line tala line installation specialized tool that acts as go -between
CN211622526U (en) Attached cantilever beam
CN216740616U (en) A suspension type operation platform for girder steel construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination