CN209669806U - A kind of hydraulic engineering ecological protection slope - Google Patents

A kind of hydraulic engineering ecological protection slope Download PDF

Info

Publication number
CN209669806U
CN209669806U CN201920147148.6U CN201920147148U CN209669806U CN 209669806 U CN209669806 U CN 209669806U CN 201920147148 U CN201920147148 U CN 201920147148U CN 209669806 U CN209669806 U CN 209669806U
Authority
CN
China
Prior art keywords
fixedly connected
protection
slope
discharge pipe
diversion pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201920147148.6U
Other languages
Chinese (zh)
Inventor
陆旻瑶
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuxi Institute of Arts and Technology
Original Assignee
Wuxi Institute of Arts and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuxi Institute of Arts and Technology filed Critical Wuxi Institute of Arts and Technology
Priority to CN201920147148.6U priority Critical patent/CN209669806U/en
Application granted granted Critical
Publication of CN209669806U publication Critical patent/CN209669806U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

The utility model discloses a kind of hydraulic engineering ecological protection slopes, including slopes, the bottom side of the slopes is provided with bank body, the top surface of the bank body is fixedly connected with the first slope protection, the surface of first slope protection is fixedly connected with the first planting frame, the inner wall of first slope protection is fixedly connected with the surface of protection pedestal, the top of the protection pedestal is fixedly connected with the bottom end of ballistic support column, the side of the ballistic support column is fixedly connected with the surface of protective net, the top of the ballistic support column is fixedly connected by bearing with the top of reinforcing rod, the bottom end of the reinforcing rod is fixedly connected with the top surface of classification platform, the inner wall of the slopes is fixedly connected with the surface of the first discharge pipe.The hydraulic engineering ecological protection slope has achieved the effect that shunt in time in flood by setting slopes, the first slope protection, protective net, reinforcing rod, the first discharge pipe, the first diversion pipe, the second slope protection, the second discharge pipe and the second diversion pipe.

Description

A kind of hydraulic engineering ecological protection slope
Technical field
The utility model relates to hydraulic engineering technical field, specially a kind of hydraulic engineering ecological protection slope.
Background technique
Slope protection refers to the various general designations paved and transplanted to prevent side slope from being washed away, done in slope surface.Bridge site institute In section, the concave bank on riverbank is met year by year by current scour, riverbank can be made constantly to collapse.For protection bridge and embankment safety, palpus Protective structure is built in concave bank.In addition, cause river water flow direction variation because setting bridge, concave bank and when jeopardizing farmland and villages and small towns, Also protective structure must be built on riverbank.The form of shore protection has directly protection and protection indirectly, and ecological slope protection is integration engineering The basic knowledge of the subjects such as mechanics, agrology, ecology and botany carries out supporting to slope or side slope, is formed by plant or work The bulkhead tech of the synthesis slope protection system of journey and plant composition.
Existing most of ecological slope protections plant certain vegetation or are laid with certain grass after building merely by concrete Skin is to have the function that protection, but common ecological slope protection does not have the effect of prevention waterlogging completely, must when in face of flood By artificial means flood discharge, and flood discharge effect is very poor.
Utility model content
The purpose of this utility model is to provide a kind of hydraulic engineering ecological protection slopes, to solve to propose in above-mentioned background technique The problem of.
To achieve the above object, the utility model provides the following technical solutions: a kind of hydraulic engineering ecological protection slope, including slope Body, the bottom side of the slopes are provided with bank body, and the top surface of the bank body is fixedly connected with the first slope protection, first slope protection Surface be fixedly connected with the first planting frame, the inner wall of first slope protection is fixedly connected with the surface of protection pedestal, described anti- The top of shield pedestal is fixedly connected with the bottom end of ballistic support column, and the side of the ballistic support column and the surface of protective net are fixed Connection, the top of the ballistic support column is fixedly connected by bearing with the top of reinforcing rod, the bottom end of the reinforcing rod with divide The top surface of grade platform is fixedly connected, and the inner wall of the slopes is fixedly connected with the surface of the first discharge pipe, first discharge pipe Surface be fixedly connected with one end of the first diversion pipe, the top surface of the classification platform is fixedly connected with the second slope protection, described the The surface of two slope protections is fixedly connected with the second planting frame, and the inner wall of the slopes is fixedly connected with the surface of the second discharge pipe, institute The surface for stating the second discharge pipe is fixedly connected with one end of the second diversion pipe, and the top surface of the slopes is fixedly connected with top horizontal Platform.
Preferably, the first discharge pipe is run through in one end of first diversion pipe, and extends to the inside of the first discharge pipe, and The other end of first diversion pipe runs through the inner wall of the first slope protection, and extends to the outside of the first slope protection.
Preferably, the second discharge pipe is run through in one end of second diversion pipe, and extends to the inside of the second discharge pipe, and The other end of second diversion pipe runs through the inner wall of the second slope protection, and extends to the outside of the second slope protection.
Preferably, the protection pedestal runs through the inner wall of the first slope protection, and extends to the outside of the first slope protection.
Preferably, area of the area of first planting frame less than the second planting frame.
Preferably, outlet height of the level height of the protective net lower than the first diversion pipe after the first slope protection.
Preferably, hydroelectric generator is provided with inside first discharge pipe and the second discharge pipe.
Beneficial effect
The utility model provides a kind of hydraulic engineering ecological protection slope, has the advantages that
1. the hydraulic engineering ecological protection slope, by setting slopes, the first slope protection, the first planting frame, protective net, reinforcing rod, First discharge pipe, the first diversion pipe, the second slope protection, the second discharge pipe and the second diversion pipe, when water level is in the first diversion pipe pipe When under mouthful, water level normal discharge in a safe condition, when water level reach the first diversion pipe nozzle and the second diversion pipe nozzle it Between when, be in hidden danger water level, the first diversion pipe and the first discharge pipe start to shunt at this time, when water level reach the second diversion pipe nozzle On when, be in flood stage, the second diversion pipe and the second discharge pipe also assist in shunting and make water level without departing from top platform, reach To the effect shunted in time in flood.
2. the hydraulic engineering ecological protection slope works as water by setting protection pedestal, protective net, reinforcing rod and ballistic support column When position needs the first discharge pipe to shunt more than the first diversion pipe nozzle, protective net can be by the fixed rubbish of the bulk in river or leaf Stop, prevents rubbish or leaf from entering the first diversion pipe and the second diversion pipe, having reached prevents the first discharge pipe and the second flood discharge The effect of blockage.
3. the hydraulic engineering ecological protection slope, by the first slope protection of setting, the first diversion pipe, the first discharge pipe, the second slope protection, Second diversion pipe, the second discharge pipe and hydroelectric generator, when water level is excessively high, the potential energy of river water is also larger, when river water passes through the Enter the first discharge pipe and the second discharge pipe after one diversion pipe and the second diversion pipe and potential energy is converted into electricity by hydroelectric generator Can, the energy is provided for other flood discharge means, has achieved the effect that energy-saving and emission-reduction.
Detailed description of the invention
Fig. 1 is that structural schematic diagram is cutd open in the utility model side;
Fig. 2 is the utility model positive structure diagram;
Fig. 3 is structural schematic diagram at the utility model protective net.
In figure: 1 slopes, 2 bank bodies, 3 first slope protections, 4 first planting frames, 5 protection pedestals, 6 ballistic support columns, 7 protective nets, 8 reinforcing rods, 9 first discharge pipes, 10 first diversion pipes, 11 classification platforms, 12 second slope protections, 13 second planting frames, 14 second are let out Hong Guan, 15 second diversion pipes, 16 top platforms, 17 hydroelectric generators.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
Fig. 1-3 is please referred to, the utility model provides a kind of technical solution: a kind of hydraulic engineering ecological protection slope, including slopes 1, the bottom side of slopes 1 is provided with bank body 2, and the top surface of bank body 2 is fixedly connected with the first slope protection 3, and the surface of the first slope protection 3 is solid Surely it is connected with the first planting frame 4, the inner wall of the first slope protection 3 is fixedly connected with the surface of protection pedestal 5, and protection pedestal 5 is through the The inner wall of one slope protection 3, and the outside of the first slope protection 3 is extended to, the bottom end on the top and ballistic support column 6 of protecting pedestal 5 is fixed Connection, the side of ballistic support column 6 are fixedly connected with the surface of protective net 7, and the top of ballistic support column 6 by bearing and is reinforced The top of bar 8 is fixedly connected, and the bottom end of reinforcing rod 8 is fixedly connected with the top surface of classification platform 11, and the inner wall of slopes 1 is let out with first The surface of big vast pipe 9 is fixedly connected, and the surface of the first discharge pipe 9 is fixedly connected with one end of the first diversion pipe 10, the first diversion pipe The first discharge pipe 9 is run through in 10 one end, and extends to the inside of the first discharge pipe 9, and the other end of the first diversion pipe 10 runs through The inner wall of first slope protection 3, and the outside of the first slope protection 3 is extended to, the level height of protective net 7 runs through lower than the first diversion pipe 10 Outlet height after first slope protection 3, the top surface of classification platform 11 are fixedly connected with the second slope protection 12, and the surface of the second slope protection 12 is solid Surely the second planting frame 13, area of the area less than the second planting frame 13 of the first planting frame 4, the inner wall of slopes 1 and are connected with The surface of two discharge pipes 14 is fixedly connected, and is provided with hydroelectric generator 17 inside the first discharge pipe 9 and the second discharge pipe 14, the The surface of two discharge pipes 14 is fixedly connected with one end of the second diversion pipe 15, and the second discharge pipe is run through in one end of the second diversion pipe 15 14, and the inside of the second discharge pipe 14 is extended to, and the other end of the second diversion pipe 15 runs through the inner wall of the second slope protection 12, and prolongs Extend to the outside of the second slope protection 12, the top surface of slopes 1 is fixedly connected with top platform 16, by setting slopes 1, the first slope protection 3, First planting frame 4, protective net 7, reinforcing rod 8, the first discharge pipe 9, the first diversion pipe 10, the second slope protection 12, the second discharge pipe 14 With the second diversion pipe 15, when water level is under 10 nozzle of the first diversion pipe, water level normal discharge in a safe condition works as water When position is reached between 10 nozzle of the first diversion pipe and 15 nozzle of the second diversion pipe, it is in hidden danger water level, at this time the first diversion pipe 10 Start to shunt with the first discharge pipe 9, when water level reaches on 15 nozzle of the second diversion pipe, is in flood stage, the second water conservancy diversion Pipe 15 and the second discharge pipe 14 also assist in shunting makes water level without departing from top platform 16, has reached and has shunted in time in flood Effect, by setting protection pedestal 5, protective net 7, reinforcing rod 8 and ballistic support column 6, when water level is more than the first diversion pipe 10 pipe When mouthful the first discharge pipe 9 being needed to shunt, protective net 7 can stop the fixed rubbish of the bulk in river or leaf, prevent rubbish or Leaf enters the first diversion pipe 10 and the second diversion pipe 15, and having reached prevents the first discharge pipe 9 and the second discharge pipe 14 from blocking Effect, by the way that the first slope protection 3, the first diversion pipe 10, the first discharge pipe 9, the second slope protection 12, the second diversion pipe 15, second is arranged Discharge pipe 14 and hydroelectric generator 17, when water level is excessively high, the potential energy of river water is also larger, when river water passes through 10 He of the first diversion pipe Enter the first discharge pipe 9 and the second discharge pipe 14 after second diversion pipe 15 and potential energy be converted into electric energy by hydroelectric generator 17, The energy is provided for other flood discharge means, has achieved the effect that energy-saving and emission-reduction.
Working principle: when water level is under 10 nozzle of the first diversion pipe, water level normal discharge in a safe condition, when When water level is reached between 10 nozzle of the first diversion pipe and 15 nozzle of the second diversion pipe, it is in hidden danger water level, at this time the first diversion pipe 10 and first discharge pipe 9 start to shunt, potential energy is passed through hydroelectric generation into the first discharge pipe 9 by the first diversion pipe 10 by river water Machine 17 is converted to electric energy, and protective net 7 can stop the fixed rubbish of the bulk in river or leaf, prevents rubbish or leaf from entering the One diversion pipe 10 is in flood stage when water level reaches on 15 nozzle of the second diversion pipe, and the second diversion pipe 15 and second is let out Big vast pipe 14, which also assists in shunting, makes water level without departing from top platform 16, and river water enters the second discharge pipe 14 by the second diversion pipe 15 Potential energy is converted into electric energy by hydroelectric generator 17, provides the energy for other flood discharge means, has been reached in flood and the time-division Stream and the effect of energy energy-saving and emission-reduction.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art, It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.

Claims (7)

1. a kind of hydraulic engineering ecological protection slope, including slopes (1), it is characterised in that: the bottom side of the slopes (1) is provided with The top surface of bank body (2), the bank body (2) is fixedly connected with the first slope protection (3), and the surface of first slope protection (3) is fixedly connected Have the first planting frame (4), the inner wall of first slope protection (3) is fixedly connected with the surface of protection pedestal (5), the protection pedestal (5) top is fixedly connected with the bottom end of ballistic support column (6), the side of the ballistic support column (6) and the table of protective net (7) Face is fixedly connected, and the top of the ballistic support column (6) is fixedly connected by bearing with the top of reinforcing rod (8), the reinforcement The bottom end of bar (8) is fixedly connected with the top surface of classification platform (11), the inner wall of the slopes (1) and the table of the first discharge pipe (9) Face is fixedly connected, and the surface of first discharge pipe (9) is fixedly connected with one end of the first diversion pipe (10), the classification platform (11) top surface is fixedly connected with the second slope protection (12), and the surface of second slope protection (12) is fixedly connected with the second planting frame (13), the inner wall of the slopes (1) is fixedly connected with the surface of the second discharge pipe (14), the surface of second discharge pipe (14) It is fixedly connected with one end of the second diversion pipe (15), the top surface of the slopes (1) is fixedly connected with top platform (16).
2. a kind of hydraulic engineering ecological protection slope according to claim 1, it is characterised in that: first diversion pipe (10) The first discharge pipe (9) are run through in one end, and extend to the inside of the first discharge pipe (9), and the other end of the first diversion pipe (10) passes through The inner wall of the first slope protection (3) is worn, and extends to the outside of the first slope protection (3).
3. a kind of hydraulic engineering ecological protection slope according to claim 1, it is characterised in that: second diversion pipe (15) The second discharge pipe (14) are run through in one end, and extend to the inside of the second discharge pipe (14), and the other end of the second diversion pipe (15) Inner wall through the second slope protection (12), and extend to the outside of the second slope protection (12).
4. a kind of hydraulic engineering ecological protection slope according to claim 1, it is characterised in that: the protection pedestal (5) is run through The inner wall of first slope protection (3), and extend to the outside of the first slope protection (3).
5. a kind of hydraulic engineering ecological protection slope according to claim 1, it is characterised in that: first planting frame (4) Area of the area less than the second planting frame (13).
6. a kind of hydraulic engineering ecological protection slope according to claim 1, it is characterised in that: the level of the protective net (7) Outlet height of the height lower than the first diversion pipe (10) after the first slope protection (3).
7. a kind of hydraulic engineering ecological protection slope according to claim 1, it is characterised in that: first discharge pipe (9) and Hydroelectric generator (17) are provided with inside second discharge pipe (14).
CN201920147148.6U 2019-01-20 2019-01-20 A kind of hydraulic engineering ecological protection slope Expired - Fee Related CN209669806U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920147148.6U CN209669806U (en) 2019-01-20 2019-01-20 A kind of hydraulic engineering ecological protection slope

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920147148.6U CN209669806U (en) 2019-01-20 2019-01-20 A kind of hydraulic engineering ecological protection slope

Publications (1)

Publication Number Publication Date
CN209669806U true CN209669806U (en) 2019-11-22

Family

ID=68567467

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920147148.6U Expired - Fee Related CN209669806U (en) 2019-01-20 2019-01-20 A kind of hydraulic engineering ecological protection slope

Country Status (1)

Country Link
CN (1) CN209669806U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111406547A (en) * 2020-04-08 2020-07-14 深圳九方生态建设有限公司 Greening device for preventing water and soil loss
CN113853983A (en) * 2021-10-11 2021-12-31 深圳市雨博士雨水利用设备有限公司 Energy-concerving and environment-protective ecological bank protection of being convenient for to consolidate with retaining performance

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111406547A (en) * 2020-04-08 2020-07-14 深圳九方生态建设有限公司 Greening device for preventing water and soil loss
CN113853983A (en) * 2021-10-11 2021-12-31 深圳市雨博士雨水利用设备有限公司 Energy-concerving and environment-protective ecological bank protection of being convenient for to consolidate with retaining performance

Similar Documents

Publication Publication Date Title
Greer Water Management in the Yellow River Basin of China
CN209669806U (en) A kind of hydraulic engineering ecological protection slope
CN108978585A (en) A kind of flood control dam of protection against erosion
EP2606221B2 (en) Hydroelectric power plant comprising a screen arrangement
CN108166511B (en) A kind of geological hazard control system
CN102926362B (en) Pollution control and emission reduction method for farmland drainage
CN101892649A (en) Project and method for preventing and controlling flood and drought
CN206693187U (en) A kind of spillway structure
CN201386269Y (en) River channel bypass trash blocking device
CN208009531U (en) A kind of forebay of electricity generation with static water
CN209555882U (en) A kind of hydraulic engineering ecological protection slope
CN209482259U (en) It is a kind of to cross water landscape earth dam structure
CN101538838A (en) Application of rubber dam in cofferdam water retaining
CN208183678U (en) A kind of hydraulic engineering column simple submerged water Fen Shui
CN206902664U (en) A kind of hydraulic engineering ecological protection slope based on multilayer proofing structure
CN104099908B (en) Gravity type sand obstructing and guiding structure
CN109356224A (en) A kind of skyscraper rainwater-collecting self-loopa utilizes system
CN206034381U (en) Multi -functional overflow dam in small -size river course
CN209523169U (en) A kind of protection slope device
CN205421162U (en) Hydraulic engineering ecological protection slope
CN212388485U (en) Device for large variation of reservoir water level, intercepting sewage, guaranteeing flood discharge and generating safety
CN210827325U (en) Multi-functional protection slope with high strength structure
CN211872838U (en) River course slope protection frame with scales for water utilization
CN203866795U (en) Standby water source of water turbine main shaft seal
CN108086264B (en) Intensive flooded channel

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20191122

Termination date: 20210120