CN209652904U - A kind of vertical pre-reinforcement processing structure for massif tunnel excavation - Google Patents

A kind of vertical pre-reinforcement processing structure for massif tunnel excavation Download PDF

Info

Publication number
CN209652904U
CN209652904U CN201920204507.7U CN201920204507U CN209652904U CN 209652904 U CN209652904 U CN 209652904U CN 201920204507 U CN201920204507 U CN 201920204507U CN 209652904 U CN209652904 U CN 209652904U
Authority
CN
China
Prior art keywords
reinforcing
reinforcing pile
pile
tunnel
tunnel excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201920204507.7U
Other languages
Chinese (zh)
Inventor
曾开华
李学军
陈芳亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanchang College Of Engineering
Nanchang Institute of Technology
Original Assignee
Nanchang College Of Engineering
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanchang College Of Engineering filed Critical Nanchang College Of Engineering
Priority to CN201920204507.7U priority Critical patent/CN209652904U/en
Application granted granted Critical
Publication of CN209652904U publication Critical patent/CN209652904U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The utility model discloses a kind of vertical pre-reinforcement processing structures for massif tunnel excavation, belong to tunnelling technical field of construction, including reinforcing cave, the reinforcing cave is provided at tunnel center, it is connected at the top of the reinforcing cave with the vertical passageway, basis is equipped in the reinforcing cave, the ground beneath is fixedly connected with the reinforcing pile I for underpinning, the basis top is fixedly connected with reinforced column, the reinforced column extends at the top of the vertical passageway along the vertical passageway, it is fixed at the top of the vertical passageway at the top of the reinforced column by the reinforcing pile II;II top of reinforcing pile is equipped with a plurality of reinforcing pile III along tunnel top;Vertical pre-reinforcement processing structure provided by the utility model, construction is simple are carried out reinforcement measure before tunnel excavation, are also reinforced during excavation to the region newly dug out, and the stability of tunnel surrounding and the safety of tunnel excavation construction are improved.

Description

A kind of vertical pre-reinforcement processing structure for massif tunnel excavation
Technical field
The utility model belongs to tunnelling technical field of construction, and in particular to a kind of for the vertical of massif tunnel excavation Pre-reinforcement processing structure.
Background technique
Tunnel easily causes rock stratum around during excavation and changes, and causes to deform, bad stability, to tunnel Safe construction causes serious security threat.Therefore, it needs to carry out consolidation process to tunnel when constructing tunnel, at present using more Reinforcement measure have slip casting, ductule, front bolt anchorage measure, but there is drawback, for example, grouting operation execution conditions It is higher, it is easy to since construction wrong causes to crack, in turn result in spillage problem.Therefore it is simple and add to provide a kind of construction method Gu the good pre-reinforcement processing structure of effect is necessary.
Utility model content
The purpose of the utility model is to provide a kind of vertical pre-reinforcement processing structures for massif tunnel excavation, solve The problem of the complexity of tunnel pre-reinforcement construction at present and consolidation effect difference.
The utility model is the technical scheme adopted is that a kind of vertical pre-reinforcement for massif tunnel excavation handles knot Structure, including reinforce cave, vertical passageway, basis, reinforced column, reinforcing pile I, reinforcing pile II and reinforcing pile III, the reinforcing cave and open up At tunnel center, be connected at the top of the reinforcing cave with the vertical passageway, equipped with basic in the reinforcings cave, it is described it is basic under Side is fixedly connected with the reinforcing pile I for underpinning, and the basis top is fixedly connected with reinforced column, and the reinforced column is along institute It states vertical passageway to extend at the top of the vertical passageway, the reinforced column top is fixed on described vertical by the reinforcing pile II Channel roof;A plurality of reinforcing pile III is equipped with above the reinforcing pile II, a plurality of reinforcing pile III is both secured to tunnel top.
The utility model is also characterized by the reinforcing pile I is root pile.
The utility model is also characterized by the reinforcing pile II is root pile.
The utility model is also characterized by the reinforcing pile III is root pile.
The utility model is also characterized by the reinforcing pile III is in dispersed along the soil body above tunnel excavation contour line It is distributed in rock-soil layer.
The utility model is also characterized by the reinforcing pile III is above tunnel excavation contour line along the fan-shaped shape of the soil body It is distributed in rock-soil layer.
The utility model is also characterized by the reinforcing pile III is the steel pipe filled with air-free concrete.
The beneficial effects of the utility model are: going out to reinforce cave in tunnel central excavation first, reinforcing in tunnel excavation Vertical passageway is excavated out on cave top, is reinforcing installation foundation below cave, and the bottom installation root pile on basis is reinforced, and is improved The bearing capacity on basis;Reinforced column is installed to be mounted at the top of reinforced column on the basis of the bottom of reinforced column is mounted in vertical passageway The top of vertical passageway;The construction and excavation at left and right sides of the top of Vertical Channel, with the process of excavation, at the top of tunnel arch Drill hole of drilling machine, then descending reinforcing cage can be used on the rock stratum on top, reinject the form setting reinforcing pile of concrete, it can be effectively The intensity of tunnel contour line top geotechnical structure during raising tunnel excavation;Then rest part in tunnel is dug again It removes, and is laid with waterproof layer in tunnel;Reinforcing pile, basis are removed, complete tunnel domes are formed;It is provided by the utility model Vertical pre-reinforcement processing structure, construction is simple carry out reinforcement measure before tunnel excavation, to the area newly dug out during excavation Domain is also reinforced, and the stability of tunnel surrounding and the safety of tunnel excavation construction are improved.
Detailed description of the invention
Fig. 1 is the reinforcing cave of the vertical pre-reinforcement processing structure provided by the utility model for massif tunnel excavation and erects To channel design figure;
Fig. 2 is basis and I connection relationship diagram of reinforcing pile;
Fig. 3 is tunnel domes schematic diagram;
Fig. 4 is III schematic diagram of reinforcing pile.
Description of symbols:
1, reinforcing cave, 2, vertical passageway, 3, basis, 4, reinforcing pile I, 5, reinforced column, 6, reinforcing pile II, 7, reinforcing pile III, 8, domes, 9, tunnel surrounding.
Specific embodiment
With reference to the accompanying drawing, a specific embodiment of the utility model is described in detail, it is to be understood that this The protection scope of utility model is not limited by the specific implementation.
A kind of vertical pre-reinforcement processing structure for massif tunnel excavation as shown in Figs 1-4, including reinforces cave 1, vertical Channel 2, basis 3, reinforced column 5, reinforcing pile I 4, reinforcing pile II 6 and reinforcing pile III 7, the reinforcing cave 1 are provided with tunnel center Place, 1 top of reinforcing cave are connected to the vertical passageway 2, and basis 3 is equipped in the reinforcing cave 1, and basic 3 lower section is solid Surely it is connected with the reinforcing pile I 4 for underpinning 3, the reinforcing pile I 4 is root pile, and basic 3 top is fixedly connected with Reinforced column 5, the reinforced column 5 extend to 2 top of vertical passageway along the vertical passageway 2, pass through at the top of the reinforced column 5 The reinforcing pile II 6 is fixed on 2 top of vertical passageway;The reinforcing pile II 6 is root pile, II 6 top of reinforcing pile It is equipped with a plurality of reinforcing pile III 7 along tunnel top, the reinforcing pile III 7 is root pile, and the reinforcing pile III 7 is along tunnel excavation profile It is distributed in rock-soil layer along the soil body in dispersed above line.
Further, in order to improve the stability of tunnel top country rock, the reinforcing pile III 7 is along tunnel excavation contour line Side is distributed in rock-soil layer along the fan-shaped shape of the soil body, and the reinforcing pile III 7 is the steel pipe filled with air-free concrete.
The application method of the utility model: in tunnel excavation, the central excavation first in tunnel goes out to reinforce cave 1, is adding Gu vertical passageway 2 is excavated out on 1 top of cave, installation foundation 3 below cave 1 is being reinforced, the bottom installation reinforcing pile I 4 on basis 3 carries out It reinforces, reinforcing pile I 4 is root pile, improves the bearing capacity on basis 3;Reinforced column 5, the bottom of reinforced column 5 are installed in vertical passageway 2 It is mounted on basis 3, the bottom of reinforced column 5 is that movable end is mounted on basis 3, and the top of reinforced column 5 is pacified by reinforcing pile II 6 Mounted in the top of vertical passageway 2;At left and right sides of the top of Vertical Channel 2 construction and excavation goes out domes 8, with excavation into Drill hole of drilling machine, then descending reinforcing cage can be used on the tunnel surrounding 9 on 8 top top of domes, reinject concrete for journey Reinforcing pile III 7 is arranged in form, can effectively improve the strong of the 8 top geotechnical structure of domes in tunnel during tunnel excavation Degree;Then excavate by rest part in tunnel, and be laid with waterproof layer;Reinforcing pile 5, basis 3 are removed, complete tunnel is formed The domes 8 in road;Vertical pre-reinforcement processing structure provided by the utility model, construction is simple carry out reinforcing before tunnel excavation Measure also reinforces the region newly dug out during excavation, improves the stability and tunnel excavation of tunnel surrounding The safety of construction.
Disclosed above is only specific embodiment of the utility model, and still, the utility model embodiment is not limited to This, the changes that any person skilled in the art can think of should all fall into the protection scope of the utility model.

Claims (7)

1. a kind of vertical pre-reinforcement processing structure for massif tunnel excavation, which is characterized in that including reinforcing cave (1), vertically Channel (2), basic (3), reinforced column (5), reinforcing pile I (4), reinforcing pile II (6) and reinforcing pile III (7), the reinforcing cave (1) are opened It is located at tunnel center, is connected at the top of the reinforcing cave (1) with the vertical passageway (2), basis is equipped in the reinforcing cave (1) (3), it is fixedly connected with the reinforcing pile I (4) for underpinning (3) below described basic (3), is fixed at the top of the basis (3) It is connected with reinforced column (5), the reinforced column (5) extends at the top of the vertical passageway (2) along the vertical passageway (2), described It is fixed at the top of the vertical passageway (2) at the top of reinforced column (5) by the reinforcing pile II (6);Above the reinforcing pile II (6) Equipped with a plurality of reinforcing pile III (7), a plurality of reinforcing pile III (7) is both secured to tunnel top.
2. the vertical pre-reinforcement processing structure according to claim 1 for massif tunnel excavation, which is characterized in that described Reinforcing pile I (4) is root pile.
3. the vertical pre-reinforcement processing structure according to claim 1 for massif tunnel excavation, which is characterized in that described Reinforcing pile II (6) is root pile.
4. the vertical pre-reinforcement processing structure according to claim 1 for massif tunnel excavation, which is characterized in that described Reinforcing pile III (7) is root pile.
5. the vertical pre-reinforcement processing structure according to claim 4 for massif tunnel excavation, which is characterized in that described Reinforcing pile III (7) is distributed in rock-soil layer along the soil body in dispersed above tunnel excavation contour line.
6. the vertical pre-reinforcement processing structure according to claim 4 for massif tunnel excavation, which is characterized in that described Reinforcing pile III (7) is distributed in rock-soil layer above tunnel excavation contour line along the fan-shaped shape of the soil body.
7. the vertical pre-reinforcement processing structure according to claim 4 for massif tunnel excavation, which is characterized in that described Reinforcing pile III (7) is the steel pipe filled with air-free concrete.
CN201920204507.7U 2019-02-18 2019-02-18 A kind of vertical pre-reinforcement processing structure for massif tunnel excavation Expired - Fee Related CN209652904U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920204507.7U CN209652904U (en) 2019-02-18 2019-02-18 A kind of vertical pre-reinforcement processing structure for massif tunnel excavation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920204507.7U CN209652904U (en) 2019-02-18 2019-02-18 A kind of vertical pre-reinforcement processing structure for massif tunnel excavation

Publications (1)

Publication Number Publication Date
CN209652904U true CN209652904U (en) 2019-11-19

Family

ID=68524416

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920204507.7U Expired - Fee Related CN209652904U (en) 2019-02-18 2019-02-18 A kind of vertical pre-reinforcement processing structure for massif tunnel excavation

Country Status (1)

Country Link
CN (1) CN209652904U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114233336A (en) * 2021-11-03 2022-03-25 中交一公局集团有限公司 Tree-shaped steel pipe pile for supporting arch springing of soft foundation arch in tunnel and construction process thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114233336A (en) * 2021-11-03 2022-03-25 中交一公局集团有限公司 Tree-shaped steel pipe pile for supporting arch springing of soft foundation arch in tunnel and construction process thereof
CN114233336B (en) * 2021-11-03 2024-01-30 中交一公局集团有限公司 Tree-shaped steel pipe pile for supporting arch springing of soft foundation arch frame in tunnel and construction process of tree-shaped steel pipe pile

Similar Documents

Publication Publication Date Title
CN104264688B (en) Manually digging hole non-uniform pile support construction process
CN202969392U (en) Complex geology deep excavation pit combined support
CN106761778B (en) A kind of underground digging in subway station construction technology suitable for upper-soft lower-hard ground
CN108005664A (en) A kind of hole pile construction method of platform structure
CN103882881B (en) Go deep into rock construction method under water
CN105672348A (en) Construction method for cropping bridge pile foundation at sandy gravel stratum of abyssal region
CN105257301A (en) Method for reinforcing collapse of weak surrounding rock of shallow embedded and mining tunnel
CN107218046A (en) Mechanical assistance sealing Station structure and construction method in a kind of pilot tunnel
CN103321244B (en) Sand foundation existing building sets up the construction method of basement
CN108204240A (en) Newly built tunnels closely on across existing tunnel anti-floating reinforcement system and its reinforcement means
CN108487911A (en) The compound crossing method construction method of longspan tunnel bilateral wall under complex geological condition
CN103572765B (en) Treatment and construction method of bridge site river bank expansive soil landslide positions
CN106437726A (en) Ground fracture crushed zone passing construction method for shallow-buried tunnel excavation
CN110017144A (en) A kind of three step construction method of loess tunnel considering bottom stab ilization processing
CN105239598A (en) Integral sinking construction method for well-type full-automatic stereo garage
CN205013013U (en) Secretly dig station supporting construction suitable for last soft hard formation down
CN207063982U (en) Mechanical assistance sealing Station structure in a kind of pilot tunnel
CN207934910U (en) A kind of newly built tunnels closely on across existing tunnel anti-floating reinforcement system
CN110043264A (en) A kind of construction method of jacking prefabricated rectangle shaft structure pattern
CN108797620A (en) A kind of OPT construction method of interlocking pile
CN107503754A (en) A kind of construction method of VI grade of country rock rich water Shallow tunnel with large cross-section
CN106049195A (en) Method for strengthening subgrade basement of existing high speed railway line
CN108150190A (en) Unevenly-pressured shallow tunnel rock crusher section excavates safeguard structure and construction method
CN109441456A (en) A kind of the tunnel structure and its construction method of weakness Facility-sliding strata
CN106640096A (en) Construction method for penetrating through tunnel of backfilling soil section and transition section

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20191119

Termination date: 20210218