CN209637782U - Tunnel waterproof and drainage structure - Google Patents
Tunnel waterproof and drainage structure Download PDFInfo
- Publication number
- CN209637782U CN209637782U CN201920216810.9U CN201920216810U CN209637782U CN 209637782 U CN209637782 U CN 209637782U CN 201920216810 U CN201920216810 U CN 201920216810U CN 209637782 U CN209637782 U CN 209637782U
- Authority
- CN
- China
- Prior art keywords
- tunnel
- pipe
- drainage
- layer
- waterproof
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
Description
技术领域technical field
本实用新型涉及隧道施工技术领域,具体涉及一种隧道防水排水结构。The utility model relates to the technical field of tunnel construction, in particular to a tunnel waterproof and drainage structure.
背景技术Background technique
隧道工程中,需要在构筑的隧道壁内埋设环向排水通道和纵向排水通道,一般环向排水通道连通到纵向排水通道,环向排水通道和纵向排水通道均为透水结构,使隧道衬砌背后的积水由纵向排水通道的出口排出到隧道两侧的测沟内,减少衬砌结构背后水压力。In tunnel engineering, it is necessary to bury the circumferential drainage channel and the longitudinal drainage channel in the constructed tunnel wall. Generally, the circumferential drainage channel is connected to the longitudinal drainage channel. Both the circumferential drainage channel and the longitudinal drainage channel are permeable structures, so that the tunnel lining behind the The accumulated water is discharged from the outlet of the longitudinal drainage channel into the measuring trenches on both sides of the tunnel to reduce the water pressure behind the lining structure.
隧道衬砌回填注浆施工时,由于注入台车模板内的混凝土有一定压力,注浆时浆液可能会进入纵向排水通道和环向排水通道并流出,为防止浆液流出,需将纵向排水通道的出口堵塞,因此排水管道内会累积一定量的水泥浆液导致纵向排水通道的排水口发生堵塞,隧道衬砌结构背后水不能顺利排出,衬砌结构背后水压力增大会严重影响隧道结构的稳定性,衬砌渗水的几率大大提高。During the grouting construction of tunnel lining backfill, due to the certain pressure of the concrete injected into the formwork of the trolley, the grout may enter the longitudinal drainage channel and the circumferential drainage channel and flow out during grouting. To prevent the grout from flowing out, the outlet of the longitudinal drainage channel Therefore, a certain amount of cement slurry will accumulate in the drainage pipe and cause the outlet of the longitudinal drainage channel to be blocked. The water behind the tunnel lining structure cannot be discharged smoothly. The increase of water pressure behind the lining structure will seriously affect the stability of the tunnel structure. The odds are greatly improved.
公开号为CN104879164A的中国专利文献公开了一种隧道环向排水结构,该隧道环向排水结构采用易腐蚀的麻绳埋设在初期支护层与二次衬砌层之间,在工程建成初期,只能依靠麻绳的吸水性小量排水,需等到麻绳腐蚀完成后,才能形成自然的排水通道,在工程建成初期到麻绳腐蚀间隔时间太长,这期间隧道壁背面水压力较高,隧道壁有较大的损坏漏水的风险。The Chinese patent document whose publication number is CN104879164A discloses a tunnel circumferential drainage structure. The tunnel circumferential drainage structure is embedded between the primary support layer and the secondary lining layer with corrosive hemp rope. In the initial stage of project completion, only A small amount of water can be discharged by relying on the water absorption of the hemp rope. It is necessary to wait until the hemp rope is corroded to form a natural drainage channel. The interval between the initial construction of the project and the corrosion of the hemp rope is too long. During this period, the water pressure on the back of the tunnel wall is high, and the tunnel There is a greater risk of damage to the walls from water leaks.
公开号为CN207297089U的中国专利文献记载了一种适用于无砟道床隧道仰拱的新型防排水系统,其包括具有隧道侧沟、隧道中心水沟的隧道排水系统,隧底结构包括仰拱和仰拱初期支护,该隧道防水系统设置的纵向盲管容易发生堵塞,后期需要维修,由于排水口数量较多,维修费用较高。The Chinese patent document with the publication number CN207297089U records a new type of waterproof and drainage system suitable for the invert of a ballastless ballast bed tunnel, which includes a tunnel drainage system with a tunnel side ditch and a tunnel center ditch. The tunnel bottom structure includes an invert and an invert Arch initial support, the vertical blind pipe set by the tunnel waterproof system is prone to blockage, and maintenance will be required in the later stage. Due to the large number of drainage outlets, the maintenance cost is high.
基于上述原因,有必要提供一种可降低后期维修成本、能够有效将隧道背面水排出以降低隧道背面水压的防水排水结构。Based on the above reasons, it is necessary to provide a waterproof and drainage structure that can reduce maintenance costs in the later period and can effectively drain the water at the back of the tunnel to reduce the water pressure at the back of the tunnel.
实用新型内容Utility model content
本实用新型旨在提供一种隧道防水排水结构,解决现有技术中隧道的排水孔容易发生堵塞,使得隧道衬砌结构背面水压力增大,进而导致隧道衬砌结构有损伤风险的技术问题。The utility model aims to provide a waterproof and drainage structure for a tunnel, which solves the technical problem in the prior art that the drainage holes of the tunnel are prone to blockage, which increases the water pressure on the back of the tunnel lining structure, thereby causing the risk of damage to the tunnel lining structure.
为解决上述技术问题,本发明采用的技术方案是:In order to solve the problems of the technologies described above, the technical solution adopted in the present invention is:
设计一种隧道防水排水结构,包括在开挖隧道的壁面依次设置的初期支护层、防水卷材层、二次模筑衬砌层组成的隧道拱墙,在开挖隧道底面衬砌结构的两侧分别设有纵向延伸的侧沟,在隧道拱墙底部埋设有纵向盲管,所述纵向盲管的两端向内弯曲并连通到所述侧沟,所述初期支护层和防水卷材层之间间隔设有环向排水盲管或/和在施工缝两侧设有环向排水板,所述环向排水板或/和环向排水盲管的两端连通到对应的所述纵向盲管;在隧道拱墙的底部还设有横向的备用泄水管,所述备用泄水管的外端连通到对应的所述侧沟,里端位于所述初期支护层。Design a tunnel waterproof and drainage structure, including the tunnel arch wall composed of the initial support layer, waterproof membrane layer, and secondary molded lining layer arranged sequentially on the wall of the excavated tunnel, and on both sides of the lining structure at the bottom of the excavated tunnel There are longitudinally extending side ditches respectively, and a longitudinal blind pipe is buried at the bottom of the tunnel arch wall, and the two ends of the longitudinal dead pipe are bent inward and connected to the side ditch, and the primary support layer and the waterproof membrane layer are There are annular drainage blind pipes at intervals or/and annular drainage plates on both sides of the construction joints, and the two ends of the annular drainage plates or/and the annular drainage blind pipes are connected to the corresponding longitudinal blind pipes. The bottom of the arch wall of the tunnel is also equipped with a horizontal backup drain pipe, the outer end of the backup drain pipe is connected to the corresponding side ditch, and the inner end is located in the initial support layer.
优选的,所述备用泄水管的里端口用透明胶带封口,外端口绑扎土工布,在所述备用泄水管底部设置支撑钢筋,所述支撑钢筋的里端插入隧道壁面。Preferably, the inner port of the spare drain pipe is sealed with scotch tape, the outer port is tied with geotextile, and a supporting steel bar is arranged at the bottom of the spare drain pipe, and the inner end of the supporting steel bar is inserted into the tunnel wall.
优选的,在隧道环向施工缝的两侧各设置一根所述备用泄水管,隧道环向施工缝两侧的相邻两根所述备用泄水管间距50-80cm。Preferably, one backup drain pipe is provided on both sides of the construction joint around the tunnel, and the distance between two adjacent backup drain pipes on both sides of the construction joint around the tunnel is 50-80cm.
优选的,所述纵向盲管为打孔波纹管,所述纵向盲管位于所述初期支护层和防水卷材层之间,所述纵向盲管周围浇筑C15无砂砼排水体;所述备用泄水管和纵向盲管外均包裹一层土工布,所述初期支护层和防水卷材层之间铺设有一层土工布。Preferably, the longitudinal blind pipe is a perforated corrugated pipe, and the longitudinal blind pipe is located between the initial support layer and the waterproof membrane layer, and a C15 sand-free concrete drainage body is poured around the longitudinal blind pipe; A layer of geotextile is wrapped outside the spare drain pipe and the longitudinal blind pipe, and a layer of geotextile is laid between the primary support layer and the waterproof membrane layer.
优选的,在开挖隧道底面衬砌结构以下两侧分别设有纵向延伸的底部排水盲管,所述底部排水盲管之间设有横向排水盲管。Preferably, vertically extending bottom drainage blind pipes are respectively provided on both sides below the lining structure of the excavated tunnel bottom, and horizontal drainage blind pipes are arranged between the bottom drainage blind pipes.
优选的,在隧道拱墙的环向施工缝和变形施工缝的中部设有中埋式橡胶止水带,顶部位于所述防水卷材层下方设有背贴式橡胶止水带。Preferably, a mid-buried rubber waterstop is provided in the middle of the circumferential construction joints and deformed construction joints of the tunnel arch wall, and a back-adhesive rubber waterstop is provided at the top below the waterproof membrane layer.
优选的,在隧道仰拱的环向施工缝和变形施工缝的底部设有背贴式橡胶止水带,中部设有中埋式橡胶止水带;在隧道仰拱的变形施工缝处还间隔埋设有纵向的无缝钢管,所述无缝钢管内填充黄油。Preferably, a back-adhesive rubber waterstop is provided at the bottom of the circumferential construction joints and deformation construction joints of the tunnel invert, and a mid-buried rubber waterstop is provided in the middle; A longitudinal seamless steel pipe is buried, and the seamless steel pipe is filled with butter.
优选的,在隧道拱墙的顶部防水卷材层下方沿纵向设有预贴软式透水管,所述预贴软式透水管的一端设有竖向的镀锌钢管,所述镀锌钢管的一端连通到所述预贴软式透水管,另一端连通到隧道拱墙的下表面。Preferably, a pre-attached soft permeable pipe is arranged longitudinally under the top waterproof coil layer of the tunnel arch wall, and one end of the pre-attached soft permeable pipe is provided with a vertical galvanized steel pipe, and the galvanized steel pipe One end is connected to the pre-attached soft permeable pipe, and the other end is connected to the lower surface of the tunnel arch wall.
本实用新型的有益技术效果在于:The beneficial technical effects of the utility model are:
1.本实用新型提供的隧道防水排水结构设有备用泄水管备用泄水管,在纵向盲管的两端口被凝固的混凝土堵塞后,可启用备用泄水管,备用泄水管为直管,其外端采用透明胶带密封,隧道拱墙浇筑后,采用刀具环切透明胶带即可通水,降低隧道拱墙背面的水压力,防止由于水压过高导致隧道结构受损。1. The tunnel waterproof and drainage structure provided by the utility model is provided with a spare drain pipe. After the two ports of the vertical blind pipe are blocked by solidified concrete, the spare drain pipe can be used. The spare drain pipe is a straight pipe, and its outer end It is sealed with scotch tape. After the tunnel arch wall is poured, use a knife to cut the scotch tape to pass water, reduce the water pressure on the back of the tunnel arch wall, and prevent the tunnel structure from being damaged due to excessive water pressure.
2.纵向盲管的两端口被凝固的混凝土堵塞后,不需要对其进行维修打通,降低维修费用,并降低维修带来的隧道结构损伤的风险。2. After the two ports of the longitudinal blind pipe are blocked by solidified concrete, there is no need to repair and open them, which reduces maintenance costs and reduces the risk of damage to the tunnel structure caused by maintenance.
3.在隧道仰拱的变形施工缝地段设有无缝钢管,既可适应结构纵向伸缩的变形要求,又可协调变形施工缝两侧的沉降,有利于减少不均匀沉降,减少止水带拉伸量,延长止水带使用寿命,增强防水效果。3. There are seamless steel pipes in the deformed construction joint section of the inverted arch of the tunnel, which can not only meet the deformation requirements of the longitudinal expansion and contraction of the structure, but also coordinate the settlement on both sides of the deformed construction joint, which is conducive to reducing uneven settlement and waterstop pull Elongation, prolong the service life of the waterstop, and enhance the waterproof effect.
4.该隧道防水排水结构在各环向施工缝和变形缝地段设有背贴式止水带和中埋式止水带,使得较薄弱的隧道环向施工缝和变形缝地段具有较好的防水性能。4. The waterproof and drainage structure of the tunnel is equipped with back-adhesive waterstops and mid-buried waterstops in the circumferential construction joints and deformation joints, so that the weaker tunnel circumferential construction joints and deformation joints have better protection. Water resistance.
5.在隧道的底部设有底部纵向盲管,可通过底部纵向盲管将隧道衬砌结构底部外的水排出,防止隧道衬砌结构底部水压力过大。5. There is a bottom longitudinal blind pipe at the bottom of the tunnel, through which the water outside the bottom of the tunnel lining structure can be discharged to prevent excessive water pressure at the bottom of the tunnel lining structure.
附图说明Description of drawings
图1为本实用新型实施例1隧道防水排水结构的横截面结构示意图;Fig. 1 is a schematic cross-sectional structure diagram of a tunnel waterproof and drainage structure in Embodiment 1 of the present utility model;
图2为图1中的A部放大图;Fig. 2 is an enlarged view of part A in Fig. 1;
图3为本实用新型实施例1隧道防水排水结构中防水卷材层的平铺示意图;Figure 3 is a schematic diagram of laying the waterproof coiled material layer in the tunnel waterproof and drainage structure of Example 1 of the present utility model;
图4为本实用新型实施例1隧道防水排水结构中防水卷材层的安装固定示意图;Fig. 4 is a schematic diagram of the installation and fixation of the waterproof coiled material layer in the tunnel waterproof and drainage structure of the utility model embodiment 1;
图5为本实用新型实施例1隧道防水排水结构中环向排水板的安装示意图;Fig. 5 is a schematic diagram of the installation of the circumferential drainage plate in the waterproof and drainage structure of the tunnel in Example 1 of the utility model;
图6为本实用新型实施例1隧道防水排水结构中备用泄水孔的安装平面图;Fig. 6 is the installation plan view of the spare weep hole in the waterproof drainage structure of the tunnel in the first embodiment of the utility model;
图7为本实用新型实施例1隧道防水排水结构中备用泄水孔的安装横截面图;Fig. 7 is an installation cross-sectional view of a spare weep hole in the waterproof and drainage structure of the tunnel in Example 1 of the utility model;
图8为本实用新型实施例1隧道防水排水结构中环向施工缝地段和变形施工缝地段的横截面结构示意图;Fig. 8 is a cross-sectional schematic diagram of the circular construction joint section and the deformed construction joint section in the waterproof and drainage structure of the tunnel in Example 1 of the utility model;
图9为本实用新型实施例1隧道防水排水结构中环向施工缝地段的纵向截面结构示意图;Fig. 9 is a schematic diagram of the longitudinal section structure of the circular construction joint section in the waterproof and drainage structure of the tunnel in Example 1 of the utility model;
图10为本实用新型实施例1隧道防水排水结构中变形施工缝地段的纵向截面结构示意图Fig. 10 is a schematic diagram of the longitudinal section structure of the deformed construction joint section in the waterproof and drainage structure of the tunnel in Example 1 of the utility model
图11为本实用新型实施例1隧道防水排水结构中拱顶背后回填注浆示意图;Figure 11 is a schematic diagram of backfilling and grouting behind the vault in the waterproof and drainage structure of the tunnel in Example 1 of the utility model;
图12为本实用新型实施例1隧道防水排水结构中拱顶背后回填注浆的纵向剖面图;Fig. 12 is a longitudinal section view of the backfill grouting behind the vault in the waterproof and drainage structure of the tunnel in Example 1 of the utility model;
图13为本实用新型实施例2隧道防水排水结构的横截面结构示意图;Fig. 13 is a cross-sectional schematic diagram of the waterproof and drainage structure of the tunnel in Embodiment 2 of the utility model;
图14为本实用新型实施例2隧道防水排水结构中隧道仰拱的环向施工缝地段的纵向截面结构示意图;Fig. 14 is a schematic diagram of the longitudinal section structure of the circular construction joint section of the inverted arch of the tunnel in the waterproof and drainage structure of the tunnel in Example 2 of the utility model;
图15为本实用新型实施例2隧道防水排水结构中隧道仰拱的变形施工缝地段的纵向截面结构示意图。Fig. 15 is a schematic diagram of the longitudinal section structure of the deformed construction joint section of the inverted arch of the tunnel in the waterproof and drainage structure of the tunnel in Example 2 of the utility model.
图中,各标号示意为:初期支护层11、围岩111、防水卷材层12、土工布121、铆接组件122、热熔衬垫1221、射钉1222、金属垫圈1223、边墙部123、顶拱部124、二次模筑衬砌层13、二次模筑衬砌层根部131、纵向施工缝132、中埋式橡胶止水带133、环向施工缝134、台车模板135、模板开孔1351、中埋式橡胶止水带136、背贴式橡胶止水带137、变形施工缝138、脱空部139、底板141、背贴式橡胶止水带1411、排水渠道142、侧沟1421、侧边排水沟1422、填充层143、道床1431、中埋式橡胶止水带1432、纵向盲管151、弯曲部1511、C15无砂砼排水体1512、环向排水板16、备用泄水管17、透明胶带171、支撑钢筋172、预贴软式透水管181、镀锌钢管182、隧道中线191、内轨顶面192、初期支护层21、防水卷材层22、二次模筑衬砌层23、变形施工缝232、无缝钢管233、底部初期支护层241、背贴式橡胶止水带2411、底部二次模筑衬砌层242、中埋式橡胶止水带2421、填充层243。In the figure, each label is shown as: initial support layer 11, surrounding rock 111, waterproof membrane layer 12, geotextile 121, riveting assembly 122, hot-melt liner 1221, nail 1222, metal washer 1223, side wall 123 , top arch part 124, secondary molding lining layer 13, secondary molding lining layer root 131, longitudinal construction joint 132, mid-buried rubber waterstop 133, circumferential construction joint 134, trolley template 135, template opening Hole 1351, mid-buried rubber waterstop 136, back-adhesive rubber waterstop 137, deformation construction joint 138, void 139, bottom plate 141, back-attached rubber waterstop 1411, drainage channel 142, side ditch 1421 , side drainage ditch 1422, filling layer 143, ballast bed 1431, buried rubber waterstop 1432, longitudinal blind pipe 151, curved part 1511, C15 sand-free concrete drainage body 1512, circumferential drainage board 16, spare drainage pipe 17 , scotch tape 171, supporting steel bar 172, pre-attached soft permeable pipe 181, galvanized steel pipe 182, tunnel center line 191, inner rail top surface 192, initial support layer 21, waterproof coil layer 22, secondary molded lining layer 23. Deformed construction joints 232, seamless steel pipes 233, bottom primary support layer 241, back-adhesive rubber waterstop 2411, bottom secondary molding lining layer 242, mid-buried rubber waterstop 2421, filling layer 243.
具体实施方式Detailed ways
下面结合附图和实施例来说明本实用新型的具体实施方式,但以下实施例只是用来详细说明本实用新型,并不以任何方式限制本实用新型的范围。The specific implementation of the present utility model will be described below in conjunction with the accompanying drawings and examples, but the following examples are only used to describe the utility model in detail, and do not limit the scope of the utility model in any way.
整条隧道施工过程中,根据围岩等级确定隧道衬砌结构的施工方式,Ⅰ、Ⅱ级围岩的层间结合良好,一般不会出现不稳定块体,而Ⅲ、Ⅳ、Ⅴ级围岩洞段的结构面的咬合力弱,具有较多的不稳定块体,因此,在Ⅰ、Ⅱ级围岩洞段,隧道衬砌结构的底部为底板施工方式,在Ⅲ、Ⅳ、Ⅴ级围岩洞段,隧道衬砌结构的底部需要进行仰拱施工。During the construction of the entire tunnel, the construction method of the tunnel lining structure is determined according to the grade of the surrounding rock. The interlayer bonding of the surrounding rocks of grades I and II is good, and generally no unstable blocks will appear, while the tunnels of grades III, IV and V The occlusal force of the structural surface of the section is weak, and there are many unstable blocks. Therefore, in the I and II surrounding rock cave sections, the bottom of the tunnel lining structure is constructed by the bottom plate, and in the III, IV, and V surrounding rock cave sections Inverted arch construction is required at the bottom of the tunnel lining structure.
实施例1:Example 1:
一种隧道防水排水结构,请一并参阅图1至图10。A waterproof and drainage structure for a tunnel, please refer to Fig. 1 to Fig. 10 together.
如图1和图2所示,本实施例提供的隧道防水排水结构用于Ⅰ、Ⅱ级围岩洞段,该隧道防水排水结构包括在开挖隧道的壁面依次设置的初期支护层11、防水卷材层12、二次模筑衬砌层13,初期支护层11为喷射在开挖隧道壁面上的混凝土泥浆或先在开挖隧道壁面上打入锚杆再喷射混凝土泥浆,初期支护层11和防水卷材层12之间铺设有一层土工布121,土工布121具有良好透水性能,且能够保护防止防水卷材层12,防止其被刺破,二次模筑衬砌层13是通过在土工布121下方支护台车模板后浇筑混凝土形成。由初期支护层11、防水卷材层12、二次模筑衬砌层13组成隧道拱墙。As shown in Figure 1 and Figure 2, the tunnel waterproof and drainage structure provided by this embodiment is used in the first and second grade surrounding rock cave sections, and the tunnel waterproof and drainage structure includes initial support layers 11, Waterproof membrane layer 12, secondary molded lining layer 13, primary support layer 11 is concrete slurry sprayed on the wall of the excavated tunnel or the anchor rod is first driven into the wall of the excavated tunnel and then concrete slurry is sprayed. A layer of geotextile 121 is laid between the layer 11 and the waterproof membrane layer 12. The geotextile 121 has good water permeability and can protect and prevent the waterproof membrane layer 12 from being punctured. The secondary molded lining layer 13 is passed Pour concrete to form after supporting the formwork of the trolley under the geotextile 121. The arch wall of the tunnel is composed of the primary supporting layer 11, the waterproof membrane layer 12 and the secondary molding lining layer 13.
如图3-1和图3-2所示,防水卷材层12通过铆接组件122固定在围岩111上浇筑的初期支护层11上,防水卷材层12的上下两侧为边墙部123,中间部分为顶拱部124,边墙部123对应于铺设在隧道拱墙的边墙上,顶拱部124对应于铺设在隧道拱墙的拱顶上,边墙部123上的铆接组件122较为稀疏,顶拱部124上的铆接组件122较为稠密。As shown in Figure 3-1 and Figure 3-2, the waterproof coiled material layer 12 is fixed on the primary support layer 11 poured on the surrounding rock 111 through riveting components 122, and the upper and lower sides of the waterproof coiled material layer 12 are side walls 123, the middle part is the top arch portion 124, the side wall portion 123 corresponds to the side wall laid on the tunnel arch wall, and the top arch portion 124 corresponds to the riveted assembly laid on the tunnel arch wall vault, the side wall portion 123 122 is relatively sparse, and the riveted components 122 on the top arch 124 are relatively dense.
铆接组件122包括热熔衬垫1221、射钉1222、金属垫圈1223,固定土工布121采用射钉枪,将金属垫圈1223压在射钉1222下,将热熔衬垫1221压在金属垫圈1223之下,热熔垫圈1221与防水卷材层12间焊接采用压焊器,防水卷材层12上相邻防水卷材的焊接采用双缝热熔焊机。The riveting assembly 122 includes a hot-melt liner 1221, a nail 1222, and a metal washer 1223. A nail gun is used to fix the geotextile 121, and the metal washer 1223 is pressed under the nail 1222, and the hot-melt liner 1221 is pressed on the metal washer 1223. Next, the welding between the hot-melt gasket 1221 and the waterproof coiled material layer 12 adopts a pressure welder, and the welding of adjacent waterproof coiled materials on the waterproof coiled material layer 12 adopts a double-slit hot-melt welder.
开挖隧道底面衬砌结构包括底板141和排水渠道142,排水渠道142内侧设有纵向延伸的侧沟1421,外侧设有侧边排水沟1422,底板141为混凝土浇筑层,其顶部为填充层143,填充层143采用C20砼浇筑,底板141的强度要高于填充层143,填充层143顶部为道床1431,道床1431顶部为内轨顶面192,道床1431上铺设碎石,碎石上铺设轨道,整个隧道在隧道中线191两侧相对称。The lining structure at the bottom of the excavated tunnel includes a bottom plate 141 and a drainage channel 142. The inner side of the drainage channel 142 is provided with a longitudinally extending side ditch 1421, and the outer side is provided with a side drainage ditch 1422. The bottom plate 141 is a concrete pouring layer, and its top is a filling layer 143. The filling layer 143 is poured with C20 concrete, the strength of the base plate 141 is higher than that of the filling layer 143, the top of the filling layer 143 is the ballast bed 1431, the top of the ballast bed 1431 is the inner rail top surface 192, and gravel is laid on the ballast bed 1431, and the track is laid on the gravel. The entire tunnel is symmetrical on both sides of the tunnel center line 191 .
侧边排水沟1422和道床1431的顶面通过横向泄水管1423连通到侧沟1421,横向泄水管1423为内径50mm管道,其在侧沟1421旁沿纵向3-5m间隔布设。排水时,内轨顶面的水排入侧边排水沟1422,侧边排水沟1422和道床1431中的水均排入侧沟1421,最终通过侧沟1421排到隧道外。The side drainage ditch 1422 and the top surface of the ballast bed 1431 are connected to the side ditch 1421 through the horizontal drain pipe 1423, and the horizontal drain pipe 1423 is a pipe with an inner diameter of 50mm, which is arranged at intervals of 3-5m along the longitudinal direction beside the side ditch 1421. When draining water, the water on the top surface of the inner rail is discharged into the side drainage ditch 1422, and the water in the side drainage ditch 1422 and the ballast bed 1431 is discharged into the side ditch 1421, and finally is discharged outside the tunnel through the side ditch 1421.
在隧道拱墙底部埋设有纵向盲管151,纵向盲管外包裹一层土工布,纵向盲管151的两端为弯曲部1511,弯曲部1511向内弯曲并连通到侧沟1421,二次模筑衬砌层13的底部为二次模筑衬砌层根部131,二次模筑衬砌层根部131与二次模筑衬砌层13上部的主体之间设有纵向施工缝132,纵向施工缝132中间设有中埋式橡胶止水带133,纵向盲管151埋设在初期支护层11和防水卷材层12之间,在纵向盲管151外包裹一层土工布,纵向盲管151为内径107mm的打孔波纹管,纵向盲管151的周围浇筑C15无砂砼排水体1512,C15无砂砼排水体1512内部为粗孔结构,具有透水性能,围岩中的水通过初期支护层11上的裂缝进入C15无砂砼排水体1512,并最终进入纵向盲管151排入到侧沟1421内。A longitudinal blind pipe 151 is buried at the bottom of the tunnel arch wall, and the longitudinal dead pipe is wrapped with a layer of geotextile. The two ends of the longitudinal dead pipe 151 are curved parts 1511. The curved parts 1511 are bent inward and connected to the side ditch 1421. The bottom of the lining layer 13 is the root portion 131 of the secondary molded lining layer, and a longitudinal construction joint 132 is arranged between the root portion 131 of the secondary molded lining layer and the main body of the upper part of the secondary molded lining layer 13. There is a mid-buried rubber waterstop 133, and the longitudinal blind pipe 151 is buried between the initial support layer 11 and the waterproof coiled material layer 12, and a layer of geotextile is wrapped outside the longitudinal dead pipe 151, and the longitudinal blind pipe 151 has an inner diameter of 107 mm. Perforated corrugated pipe, C15 sand-free concrete drainage body 1512 is poured around the longitudinal blind pipe 151. The interior of the C15 sand-free concrete drainage body 1512 is a coarse-hole structure with water permeability. The water in the surrounding rock passes through the primary support layer 11 The cracks enter the C15 sand-free concrete drainage body 1512, and finally enter the vertical blind pipe 151 and discharge into the side ditch 1421.
如图4所示,初期支护层11和防水卷材层12之间在施工缝两侧各设有一个环向排水板16,每一个环向排水板16的宽度L1为50cm,As shown in Figure 4, between the initial support layer 11 and the waterproof coiled material layer 12, a circumferential drainage board 16 is respectively provided on both sides of the construction joint, and the width L1 of each circumferential drainage board 16 is 50 cm.
每一环隧道拱墙的两侧分别埋设一根纵向盲管151,这两个环向排水板16同一侧的端头连通到对应的纵向盲管151,围岩中的水通过初期支护层11上的裂缝进入环向排水板16,再由环向排水板16排入纵向盲管151,最终排入到侧沟1421内,以减小隧道拱墙背面的水压力。A longitudinal blind pipe 151 is respectively buried on both sides of each tunnel arch wall, and the ends of the two circumferential drainage plates 16 on the same side are connected to the corresponding longitudinal blind pipe 151, and the water in the surrounding rock passes through the primary support layer. The crack on 11 enters the circumferential drainage plate 16, and then is discharged into the vertical blind pipe 151 by the circumferential drainage plate 16, and finally discharged into the side ditch 1421, so as to reduce the water pressure on the back side of the tunnel arch wall.
进一步的,在富水地段,按照纵向间距2m还布置有φ50mm的环向排水盲管,该环向排水盲管的两端也连通到对应的纵向盲管。Further, in the water-rich section, circular drainage blind pipes of φ50mm are also arranged at a longitudinal interval of 2m, and the two ends of the circular drainage dead pipes are also connected to the corresponding longitudinal blind pipes.
进一步的,如图5-1和图5-2所示,在隧道拱墙的底部还设有横向的备用泄水管17,具体的,一环隧道拱墙长度约10米,纵向盲管151的两端口之间间距约9米,一环隧道拱墙在纵向盲管151的两侧各设有一根备用泄水管17,备用泄水管17与纵向盲管151位于同一高程。备用泄水管17的外端连通到对应的侧沟1421且绑扎土工布,里端位于初期支护层11且用透明胶带171封口。Further, as shown in Figure 5-1 and Figure 5-2, there is also a horizontal spare drain pipe 17 at the bottom of the tunnel arch wall. Specifically, the length of a tunnel arch wall is about 10 meters, and the vertical blind pipe 151 The distance between the two ports is about 9 meters. A ring tunnel arch wall is provided with a spare drain pipe 17 on both sides of the longitudinal blind pipe 151. The spare drain pipe 17 and the longitudinal dead pipe 151 are located at the same elevation. The outer end of the spare drain pipe 17 is connected to the corresponding side ditch 1421 and bound with geotextiles, and the inner end is located at the primary support layer 11 and sealed with a scotch tape 171 .
台车模板135对应于纵向盲管151的弯曲部1511端头和备用泄水管17的外端均设有模板开孔1351,在预埋备用泄水管17时,备用泄水管17外包裹一层土工布,备用泄水管17的外端穿过台车模板135的模板开孔1351,在备用泄水管17底部设置支撑钢筋172,支撑钢筋172的里端插入隧道壁面的初期支护层11和围岩内,支撑钢筋172直径16mm,以保证支撑稳固。The trolley formwork 135 corresponds to the end of the bending part 1511 of the longitudinal blind pipe 151 and the outer end of the spare drain pipe 17 are provided with template openings 1351. When the spare drain pipe 17 is pre-embedded, the spare drain pipe 17 is wrapped with a layer of geotechnical material. cloth, the outer end of the spare drain pipe 17 passes through the formwork opening 1351 of the trolley formwork 135, and the supporting steel bar 172 is arranged at the bottom of the spare drain pipe 17, and the inner end of the supporting steel bar 172 is inserted into the primary support layer 11 and the surrounding rock of the tunnel wall. Inside, the supporting steel bars 172 have a diameter of 16 mm to ensure stable support.
相邻两环隧道拱墙之间为环向施工缝134,在隧道环向施工缝134的两侧各设置一根备用泄水管17,隧道环向施工缝134两侧的相邻两根备用泄水管17之间间距60cm。There is a circumferential construction joint 134 between the arch walls of adjacent two-ring tunnels, and a spare drain pipe 17 is provided on both sides of the tunnel circumferential construction joint 134, and two adjacent spare drain pipes 17 are arranged on both sides of the tunnel circumferential construction joint 134. The distance between the water pipes 17 is 60cm.
当纵向盲管151的弯曲部1511端头堵塞后,水在纵向盲管151中累积导致纵向盲管151附近水压增大,而备用泄水管17与初期支护层11之间接触点水压小,水会从高压处流到低压处并沿备用泄水管17排除,防止隧道拱墙背面水压过大导致衬砌结构不稳定或发生损坏。When the end of the bending part 1511 of the longitudinal blind pipe 151 is blocked, the accumulation of water in the longitudinal dead pipe 151 causes the water pressure near the longitudinal dead pipe 151 to increase, while the water pressure at the contact point between the backup drain pipe 17 and the primary support layer 11 Small, the water will flow from the high pressure to the low pressure and get rid of along the backup drain pipe 17, preventing the lining structure from being unstable or damaged due to excessive water pressure on the back of the tunnel arch wall.
在两环隧道拱墙的施工缝和变形施工缝处,对防水能力要求更高,因此,如图7所示,在环向施工缝134或变形施工缝138处,在底板141顶部设有背贴式橡胶止水带1411,在填充层143中部埋设有中埋式橡胶止水带1432。如图8-1和图8-2所示,在二次模筑衬砌层13内设有中埋式橡胶止水带136,在二次模筑衬砌层13的顶部位于防水卷材层12下方设有背贴式橡胶止水带137,中埋式橡胶止水带136、中埋式橡胶止水带1432宽L2均为40cm。At the construction joints and deformation construction joints of the two-ring tunnel arch wall, the waterproof ability is required to be higher. Therefore, as shown in FIG. The pasted rubber waterstop 1411 is embedded with a mid-buried rubber waterstop 1432 in the middle of the filling layer 143 . As shown in Figure 8-1 and Figure 8-2, a buried rubber waterstop 136 is provided in the secondary molded lining layer 13, and the top of the secondary molded lining layer 13 is located under the waterproof membrane layer 12 There are back-mounted rubber waterstops 137, mid-buried rubber waterstops 136, and mid-buried rubber waterstops 1432. The width L2 is 40cm.
进一步的,在底板141下方两侧分别设有纵向延伸的底部排水盲管,底部排水盲管之间设有横向排水盲管,通过横向排水盲管将底板141下方的水排入底部排水盲管,在通过底部排水盲管将水排到隧道外,防止底板141下方水压过大。Further, vertically extending bottom drain blind pipes are respectively arranged on both sides below the bottom plate 141, and horizontal drainage blind pipes are arranged between the bottom drain blind pipes, through which the water below the bottom plate 141 is discharged into the bottom drain blind pipes. , the water is drained out of the tunnel through the bottom drainage blind pipe to prevent excessive water pressure under the bottom plate 141 .
如图9和图10所示,在浇筑二次模筑衬砌层13时,二次模筑衬砌层13的顶部会存在脱空部139,导致隧道拱墙顶部不密实,不利于防水排水,因此,在隧道拱墙的顶部防水卷材层12下方沿纵向设有预贴软式透水管181,预贴软式透水管181靠近台车模板端面1352的一端设有竖向的镀锌钢管182,镀锌钢管182内径30cm,其一端连通到预贴软式透水管181,另一端连通到隧道拱墙的下表面,当台车模板135移走后,可通过镀锌钢管182向预贴软式透水管181注入混凝土浆,混凝土浆沿预贴软式透水管181充满整个脱空部139,使隧道拱墙顶部填充密实。As shown in Figures 9 and 10, when pouring the secondary molded lining layer 13, there will be a void 139 on the top of the secondary molded lining layer 13, which will cause the top of the tunnel arch wall to be not dense, which is not conducive to waterproofing and drainage. , a pre-attached soft permeable pipe 181 is arranged longitudinally under the top waterproof coiled material layer 12 of the tunnel arch wall, and a vertical galvanized steel pipe 182 is provided at the end of the pre-attached soft permeable pipe 181 close to the end face 1352 of the formwork of the trolley, Galvanized steel pipe 182 with an inner diameter of 30cm, one end of which is connected to the pre-pasted soft permeable pipe 181, and the other end is connected to the lower surface of the tunnel arch wall. The permeable pipe 181 is injected with concrete slurry, and the concrete slurry fills the entire hollow part 139 along the pre-attached soft permeable pipe 181, so that the top of the tunnel arch wall is filled densely.
实施例2Example 2
一种隧道防水排水结构,请一并参阅图11至图12-2。A tunnel waterproof drainage structure, please refer to Figure 11 to Figure 12-2.
如图11所示,本实施例提供的隧道防水排水结构用于Ⅲ、Ⅳ、Ⅴ级围岩洞段,与实施例1的区别在于,不仅在开挖隧道的上部设置有由初期支护层21、防水卷材层22、二次模筑衬砌层23组成的隧道拱墙,还在开挖隧道的底部设有隧道仰拱,隧道仰拱包括底部初期支护层241、底部二次模筑衬砌层242和填充层243,以增强整个隧道的支护能力。As shown in Figure 11, the tunnel waterproof and drainage structure provided by this embodiment is used in the surrounding rock cave sections of grades III, IV, and V. 21. The tunnel arch wall composed of the waterproof membrane layer 22 and the secondary molded lining layer 23 is also equipped with a tunnel invert at the bottom of the excavated tunnel. The tunnel invert includes the bottom primary support layer 241 and the bottom secondary molded The lining layer 242 and the filling layer 243 are used to enhance the supporting capacity of the entire tunnel.
如图12-1所示,在隧道仰拱的环向施工缝231地段,在底部二次模筑衬砌层242中间设有中埋式橡胶止水带2421,在底部二次模筑衬砌层242的下表面埋设有背贴式橡胶止水带2411,中埋式橡胶止水带2421和背贴式橡胶止水带2411宽度均在40cm,防止水由环向施工缝231渗入。As shown in Figure 12-1, in the circular construction joint 231 section of the inverted arch of the tunnel, a mid-buried rubber waterstop 2421 is provided in the middle of the secondary molded lining layer 242 at the bottom, and a secondary molded lining layer 242 at the bottom The lower surface of the bottom surface is buried with a back-adhesive rubber waterstop 2411, and the width of the middle-buried rubber waterstop 2421 and the back-adhesive rubber waterstop 2411 is 40cm to prevent water from penetrating into the construction joint 231 from the ring.
进一步的,如图12-2所示,在隧道仰拱的变形施工缝232地段的底部还间隔埋设有纵向的无缝钢管233,无缝钢管233内填充黄油,防止无缝钢管233生锈,无缝钢管233起到连接两环隧道仰拱的作用,防止隧道仰拱局部发生形变破坏防水能力。Further, as shown in Figure 12-2, vertical seamless steel pipes 233 are buried at intervals at the bottom of the deformation construction joint 232 section of the inverted arch of the tunnel, and the seamless steel pipes 233 are filled with butter to prevent the seamless steel pipes 233 from rusting. The seamless steel pipe 233 plays the role of connecting the invert of the two-ring tunnel, preventing local deformation of the invert of the tunnel from damaging the waterproof ability.
由于纵向盲管的两端口容易被凝固的混凝土堵塞,后期隧道投入使用后,部分洞段排水困难,而通过备用泄水管可排除水,既降低隧道拱墙背面的水压力,防止由于水压过高导致隧道结构受损,同时避免了重新钻取泄水孔,节约了成本。Because the two ports of the longitudinal blind pipe are easily blocked by solidified concrete, after the tunnel is put into use later, it is difficult to drain water in some sections of the tunnel, and the water can be drained through the spare drain pipe, which not only reduces the water pressure on the back of the tunnel arch wall, but also prevents the tunnel from being damaged due to excessive water pressure. High damage to the tunnel structure while avoiding the need to re-drill the scuppers saves costs.
上面结合附图和实施例对本实用新型作了详细的说明,但是,所属技术领域的技术人员能够理解,在不脱离本实用新型宗旨的前提下,还可以对上述实施例中的各个具体参数进行变更,形成多个具体的实施例,均为本实用新型的常见变化范围,在此不再一一详述。The utility model has been described in detail above in conjunction with the accompanying drawings and embodiments, but those skilled in the art can understand that without departing from the purpose of the utility model, each specific parameter in the above-mentioned embodiments can also be adjusted. Changes and the formation of multiple specific embodiments are common variation ranges of the present utility model, and will not be described in detail here.
Claims (8)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201920216810.9U CN209637782U (en) | 2019-02-20 | 2019-02-20 | Tunnel waterproof and drainage structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201920216810.9U CN209637782U (en) | 2019-02-20 | 2019-02-20 | Tunnel waterproof and drainage structure |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN209637782U true CN209637782U (en) | 2019-11-15 |
Family
ID=68493925
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201920216810.9U Expired - Fee Related CN209637782U (en) | 2019-02-20 | 2019-02-20 | Tunnel waterproof and drainage structure |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN209637782U (en) |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109611150A (en) * | 2019-02-20 | 2019-04-12 | 中铁隧道局集团有限公司 | Tunnel water proofing discharge structure and tunnel water proofing water discharge method |
| CN111088996A (en) * | 2020-01-15 | 2020-05-01 | 四川省交通勘察设计研究院有限公司 | A kind of drainage structure for highway tunnel circumferential construction joints |
| CN114908903A (en) * | 2022-03-14 | 2022-08-16 | 中建二局装饰工程有限公司 | A curtain wall in northern Shaanxi style |
| CN114941258A (en) * | 2022-06-23 | 2022-08-26 | 中铁十八局集团有限公司 | Anti-cracking construction method for concrete track bed slab of CRTS I type double-block ballastless track of high-speed railway tunnel |
-
2019
- 2019-02-20 CN CN201920216810.9U patent/CN209637782U/en not_active Expired - Fee Related
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109611150A (en) * | 2019-02-20 | 2019-04-12 | 中铁隧道局集团有限公司 | Tunnel water proofing discharge structure and tunnel water proofing water discharge method |
| CN109611150B (en) * | 2019-02-20 | 2024-08-30 | 中铁隧道局集团有限公司 | Waterproof drainage structure and waterproof drainage method for tunnel |
| CN111088996A (en) * | 2020-01-15 | 2020-05-01 | 四川省交通勘察设计研究院有限公司 | A kind of drainage structure for highway tunnel circumferential construction joints |
| CN114908903A (en) * | 2022-03-14 | 2022-08-16 | 中建二局装饰工程有限公司 | A curtain wall in northern Shaanxi style |
| CN114941258A (en) * | 2022-06-23 | 2022-08-26 | 中铁十八局集团有限公司 | Anti-cracking construction method for concrete track bed slab of CRTS I type double-block ballastless track of high-speed railway tunnel |
| CN114941258B (en) * | 2022-06-23 | 2023-05-23 | 中铁十八局集团有限公司 | A construction method for anti-cracking of CRTS Ⅰ type double-block ballastless track concrete track bed slab in high-speed railway tunnel |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN109611150B (en) | Waterproof drainage structure and waterproof drainage method for tunnel | |
| CN204098937U (en) | Tunnel deformation joint waterproof construction and constructing tunnel structure | |
| CN209637782U (en) | Tunnel waterproof and drainage structure | |
| CN206874310U (en) | Be applicable to high-pressure rich water district tunnel decompression drainage device | |
| CN106120801B (en) | Pipeline crosses the construction method at foundation ditch in water-rich sand layer | |
| CN105927272A (en) | Floor anchoring constraint tunnel lining structure | |
| CN208280185U (en) | A kind of post-cast strip advanced water-stopping construction | |
| CN206386150U (en) | A kind of Underground Subway Station draining and examination and repair system | |
| CN109488371B (en) | Waterproof system of full-enclosed waterproof station and dynamic setting and quantity-limiting drainage method | |
| CN207597428U (en) | Prefabricated piping lane is connected waterproof construction with cast-in-place piping lane | |
| CN101575859B (en) | Anti-seepage Joint of Underground Diaphragm Wall and Its Construction Method | |
| CN111594184A (en) | A main hole excavation method for a biased tunnel at the entrance | |
| CN115012452A (en) | Post-casting belt construction technology and basement drainage and pressure relief structure | |
| CN103321246A (en) | Construction Method of Foundation Pit Using Underground Diaphragm Wall | |
| CN107401413A (en) | Tunnel structure for expansive stratum | |
| CN110374138A (en) | The waterproof construction and construction method of station main body and accessory channel interface | |
| CN201538975U (en) | Underground Diaphragm Wall Anti-seepage Joint | |
| CN115949437A (en) | Shallow cold-proof heat preservation, drainage structure that buries bias voltage tunnel | |
| CN117072236A (en) | Tunnel longitudinal drainage blind pipe turn-up gravel forming structure and construction method | |
| CN115749939B (en) | Active suspension protection system for tunnel underpass flexible joint drain pipe and construction method | |
| CN111733894A (en) | Anti-floating system of deep foundation pit underground structure and construction process | |
| CN113186977B (en) | A reverse sequence construction method for underground comprehensive utility gallery | |
| CN207568626U (en) | A kind of tunnel structure for expansive stratum | |
| CN206768745U (en) | A water-stop structure for the inner corridor joints of the core wall of a high core rockfill dam | |
| CN105133719B (en) | The dislocation of a kind of quick improvement rain pipe is leaked sand, is gushed the construction method of sand |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20191115 |