CN109611150A - Tunnel water proofing discharge structure and tunnel water proofing water discharge method - Google Patents

Tunnel water proofing discharge structure and tunnel water proofing water discharge method Download PDF

Info

Publication number
CN109611150A
CN109611150A CN201910127194.4A CN201910127194A CN109611150A CN 109611150 A CN109611150 A CN 109611150A CN 201910127194 A CN201910127194 A CN 201910127194A CN 109611150 A CN109611150 A CN 109611150A
Authority
CN
China
Prior art keywords
tunnel
layer
pipe
blind pipe
water proofing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910127194.4A
Other languages
Chinese (zh)
Other versions
CN109611150B (en
Inventor
何元俊
刘田
刘广志
强旭宏
刘飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Tunnel Group Co Ltd CRTG
China Railway Tunnel Stock Co Ltd
Original Assignee
China Railway Tunnel Group Co Ltd CRTG
China Railway Tunnel Stock Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Tunnel Group Co Ltd CRTG, China Railway Tunnel Stock Co Ltd filed Critical China Railway Tunnel Group Co Ltd CRTG
Priority to CN201910127194.4A priority Critical patent/CN109611150B/en
Publication of CN109611150A publication Critical patent/CN109611150A/en
Application granted granted Critical
Publication of CN109611150B publication Critical patent/CN109611150B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a kind of tunnel water proofing discharge structure and water-proof drainage methods, the tunnel water proofing discharge structure includes the preliminary bracing layer that sets gradually of wall surface in tunneling, waterproof roll layer, the tunnel arch wall of secondary moulded lining layer composition, in tunneling bottom surface, the two sides of liner structure are respectively equipped with the lateral sulcus longitudinally extended, longitudinal blind pipe is embedded in tunnel arch wall bottom, the inward at both ends of longitudinal blind pipe, which is bent and is communicated between lateral sulcus preliminary bracing layer and waterproof roll layer, is equipped at intervals with circle draining plate, lateral spare tapping pipe is additionally provided in the bottom of tunnel arch wall, the outer end of spare tapping pipe is communicated to corresponding lateral sulcus, inner end is located at preliminary bracing layer, the present invention is by being arranged spare tapping pipe, after the concrete blocking that the two-port of longitudinal blind pipe is solidified, spare tapping pipe can be enabled, reduce the hydraulic pressure at the tunnel arch wall back side Power prevents from causing tunnel structure impaired since hydraulic pressure is excessively high.

Description

Tunnel water proofing discharge structure and tunnel water proofing water discharge method
Technical field
The present invention relates to technical field of tunnel construction, and in particular to a kind of tunnel water proofing discharge structure.
Background technique
In Tunnel Engineering, need to bury circle draining channel and longitudinal drainage channel, general ring in the tunnel wall constructed It is communicated to longitudinal drainage channel to drainage channel, circle draining channel and longitudinal drainage channel are permeable structure, serve as a contrast tunnel The ponding for building behind is discharged in the survey ditch of tunnel two sides by the outlet in longitudinal drainage channel, reduces liner structure behind hydraulic pressure Power.
When tunnel-liner backfills mortar depositing construction, since the concrete in injection trolley formwork has a certain pressure, when slip casting, is starched Liquid may enter longitudinal drainage channel and circle draining channel and flow out, need to be by longitudinal drainage channel to prevent slurries from flowing out Outlet obstruction, therefore a certain amount of cement grout can be accumulated in drainage pipeline to cause the discharge outlet in longitudinal drainage channel to occur stifled Plug, tunnel lining structure behind water cannot be smoothly discharged, and water pressure increase in liner structure behind can seriously affect tunnel structure The probability of stability, lining cutting infiltration greatly improves.
The Chinese patent literature of Publication No. CN104879164A discloses a kind of tunnel circle draining structure, the tunnel ring It is embedded between preliminary bracing layer and secondary lining layer to discharge structure using the perishable rope made of hemp, builds up initial stage in engineering, only It can be drained in a small amount by the water imbibition of the rope made of hemp, after need to waiting until that the rope made of hemp etches, natural drainage channel could be formed, in engineering Build up initial stage to the rope made of hemp corrosion interval time it is too long, tunnel wall back side water pressure is higher during this, and tunnel wall has biggish damage The risk of leak.
The Chinese patent literature of Publication No. CN207297089U describes a kind of suitable for ballastless track bed tunnel inverted arch Novel waterproof and water drainage system comprising the tunnel drainage system with tunnel lateral sulcus, tunnel Central drain, tunnel bottom structure includes inverted arch It is easy to happen blocking with longitudinal blind pipe of inverted arch preliminary bracing, tunnel waterproof system setting, the later period needs repairing, due to draining Mouth quantity is more, and maintenance cost is higher.
For these reasons, it is necessary to which later period maintenance cost can be reduced, can effectively arrange tunnel back side water by providing one kind Out to reduce the water-proof drainage structure of tunnel back side hydraulic pressure.
Summary of the invention
The present invention is intended to provide a kind of tunnel water proofing discharge structure and tunnel water proofing water discharge method, solve tunnel in the prior art The drainage hole in road is easy to happen blocking, so that tunnel lining structure back side water pressure increases, and then tunnel lining structure is caused to have The technical issues of damage risk.
In order to solve the above technical problems, the first aspect of the present invention is:
A kind of tunnel water proofing discharge structure is provided, the preliminary bracing layer that sets gradually including the wall surface in tunneling, waterproof roll The tunnel arch wall of material layer, secondary moulded lining layer composition, in tunneling bottom surface, the two sides of liner structure are respectively equipped with longitudinal prolong The lateral sulcus stretched is embedded with longitudinal blind pipe in tunnel arch wall bottom, and the inward at both ends of the longitudinal direction blind pipe is bent and is communicated to described Lateral sulcus is equipped at intervals with circle draining blind pipe or/and is equipped in construction joint two sides between the preliminary bracing layer and waterproof roll layer The both ends of circle draining plate, the circle draining plate or/and circle draining blind pipe are communicated to corresponding longitudinal blind pipe;In tunnel The bottom of road arch wall is additionally provided with lateral spare tapping pipe, and the outer end of the spare tapping pipe is communicated to the corresponding lateral sulcus, Inner end is located at the preliminary bracing layer.
Preferably, the inner end mouthful of the spare tapping pipe is sealed with adhesive tape, and external port binds geotextiles, described standby Spacer bar is set with sluicing bottom of the tube, tunnel wall surface is inserted into the inner end of the spacer bar.
Preferably, piece spare tapping pipe, tunnel circular construction joint are respectively set in the two sides of tunnel circular construction joint Adjacent two spare sluicing tube spacing 50-80cm of two sides.
Preferably, longitudinal blind pipe is punching bellows, and the longitudinal direction blind pipe is located at the preliminary bracing layer and waterproof Between coiled material layer, C15 non-sand concrete displacement hull is poured around the longitudinal direction blind pipe;It is wrapped outside the spare tapping pipe and longitudinal blind pipe One layer of geotextiles are wrapped up in, one layer of geotextiles are equipped between the preliminary bracing layer and waterproof roll layer.
Preferably, two sides are respectively equipped with the bottom discharge blind pipe longitudinally extended below the liner structure of tunneling bottom surface, Transverse drainage blind pipe is equipped between the bottom discharge blind pipe.
Preferably, the buried rubber fastening band in the middle part of the circular construction joint of tunnel arch wall and deformation construction joint is equipped with, Top, which is located at below the waterproof roll layer, is equipped with back sticking type rubber fastening band.
Preferably, it is equipped with back sticking type rubber fastening band in the bottom of the circular construction joint of tunnel inverted arch and deformation construction joint, Middle part be equipped in buried rubber fastening band;Also interval is embedded with longitudinal seamless steel pipe at the deformation construction joint of tunnel inverted arch, Butter is filled in the seamless steel pipe.
Preferably, it is equipped with pre- patch flexible porous tube along longitudinal direction below the top waterproof roll layer of tunnel arch wall, it is described pre- The one end for pasting flexible porous tube is equipped with vertical coating steel pipe, and it is flexible porous that one end of the coating steel pipe is communicated to the pre- patch Pipe, the other end are communicated to the lower surface of tunnel arch wall.
The second aspect of the present invention is:
A kind of tunnel water proofing water discharge method is designed, including,
Preliminary bracing layer, waterproof roll layer, secondary moulded lining layer are set gradually in the wall surface of tunneling, at tunneling bottom The lateral sulcus longitudinally extended is arranged in face, and in the embedded longitudinal blind pipe in tunnel arch wall bottom, the inward at both ends bending of the longitudinal direction blind pipe is simultaneously It is communicated to the lateral sulcus;
The interval setting circle draining plate between the preliminary bracing layer and waterproof roll layer, the both ends of the circle draining plate connect Lead to corresponding longitudinal blind pipe;
Lateral spare tapping pipe is buried in the bottom of tunnel arch wall, the outer end of the spare tapping pipe is communicated to corresponding described Lateral sulcus, inner end are located at the preliminary bracing layer.
Preferably, pre- patch flexible porous tube, the pre- patch are equipped with along longitudinal direction below the top waterproof roll of tunnel arch wall One end of flexible porous tube is equipped with vertical coating steel pipe, and it is flexible porous that one end of the coating steel pipe is communicated to the pre- patch Pipe, the other end are communicated to the lower surface of tunnel arch wall, inwardly inject cement mortar by the coating steel pipe, carry out lining cutting behind Slip casting is backfilled, when grouting pressure reaches 0.2Mpa, terminates slip casting.
The beneficial technical effect of the present invention lies in:
1. tunnel water proofing discharge structure provided by the invention is equipped with the spare tapping pipe of spare tapping pipe, in the two-port of longitudinal blind pipe After the concrete blocking being solidified, spare tapping pipe can be enabled, spare tapping pipe is straight tube, and outer end is close using adhesive tape Envelope, after tunnel arch wall pours, using cutter ring cutting adhesive tape can water flowing, reduce the tunnel arch wall back side water pressure, prevent Cause tunnel structure impaired since hydraulic pressure is excessively high.
2. not needing to repair it and get through, reduce dimension after the concrete blocking that the two-port of longitudinal blind pipe is solidified Expense is repaired, and reduces the risk of maintenance bring tunnel structure damage.
3. the deformation construction joint location of inverted arch is equipped with seamless steel pipe in tunnel, the deformation for being both suitable for structure longitudinal extension is wanted It asks, and the sedimentation of tunable deformation construction joint two sides, advantageously reduces differential settlement, reduce waterstop amount of tension, extension stops Water band service life, enhances waterproof effect.
4. the tunnel water proofing discharge structure is buried in each circular construction joint and deformation joint location equipped with back-adhering waterstop Formula waterstop, so that weaker tunnel circular construction joint and deformation joint location have preferable waterproof performance.
5. the bottom in tunnel is equipped with bottom longitudinal direction blind pipe, can will be outside tunnel lining structure bottom by bottom longitudinal direction blind pipe Water discharge, prevent tunnel lining structure bottom water pressure excessive.
Detailed description of the invention
Fig. 1 is the cross-sectional structure schematic diagram of 1 tunnel water proofing discharge structure of the embodiment of the present invention;
Fig. 2 is the portion the A enlarged drawing in Fig. 1;
Fig. 3 is the tiling schematic diagram of waterproof roll layer in 1 tunnel water proofing discharge structure of the embodiment of the present invention;
Fig. 4 is the fixed schematic diagram of installation of waterproof roll layer in 1 tunnel water proofing discharge structure of the embodiment of the present invention;
Fig. 5 is the scheme of installation of circumferential drain bar in 1 tunnel water proofing discharge structure of the embodiment of the present invention;
Fig. 6 is the mounting plane figure of spare drain hole in 1 tunnel water proofing discharge structure of the embodiment of the present invention;
Fig. 7 is the installation cross-sectional view of spare drain hole in 1 tunnel water proofing discharge structure of the embodiment of the present invention;
Fig. 8 is circular construction joint location in 1 tunnel water proofing discharge structure of the embodiment of the present invention and deforms the transversal of construction joint location Face structural schematic diagram;
Fig. 9 is the longitudinal cross-section structural schematic diagram in circular construction joint location in 1 tunnel water proofing discharge structure of the embodiment of the present invention;
Figure 10 is the longitudinal cross-section structural schematic diagram that construction joint location is deformed in 1 tunnel water proofing discharge structure of the embodiment of the present invention;
Figure 11 is that vault backfills slip casting schematic diagram behind in 1 tunnel water proofing discharge structure of the embodiment of the present invention;
Figure 12 is the longitudinal sectional drawing that vault backfills slip casting behind in 1 tunnel water proofing discharge structure of the embodiment of the present invention;
Figure 13 is the cross-sectional structure schematic diagram of 2 tunnel water proofing discharge structure of the embodiment of the present invention;
Figure 14 is the longitudinal cross-section knot in the circular construction joint location of tunnel inverted arch in 2 tunnel water proofing discharge structure of the embodiment of the present invention Structure schematic diagram;
Figure 15 is the longitudinal cross-section knot in the deformation construction joint location of tunnel inverted arch in 2 tunnel water proofing discharge structure of the embodiment of the present invention Structure schematic diagram;
Figure 16 is the flow chart of 3 tunnel water proofing water discharge method of the embodiment of the present invention.
In figure, each label signal are as follows: preliminary bracing layer 11, country rock 111, waterproof roll layer 12, geotextiles 121, riveting group Part 122, hot melt liner 1221, nailing 1222, metal washer 1223, abutment wall portion 123, crown portion 124, secondary moulded lining layer 13, secondary moulded lining layer root 131, longitudinal construction joint 132, in buried rubber fastening band 133, circular construction joint 134, trolley Template 135, template aperture 1351, in buried rubber fastening band 136, back sticking type rubber fastening band 137, deformation construction joint 138, de- Empty portion 139, bottom plate 141, back sticking type rubber fastening band 1411, discharge conduit 142, lateral sulcus 1421, side gutter 1422, filling Layer 143, railway roadbed 1431, in buried rubber fastening band 1432, longitudinal blind pipe 151, bending section 1511, C15 non-sand concrete displacement hull 1512, circle draining plate 16, spare tapping pipe 17, adhesive tape 171, spacer bar 172, pre- patch flexible porous tube 181, zinc-plated Steel pipe 182, internal rail top surface 192, preliminary bracing layer 21, waterproof roll layer 22, secondary moulded lining layer 23, becomes tunnel middle line 191 Shape construction joint 232, seamless steel pipe 233, bottom preliminary bracing layer 241, back sticking type rubber fastening band 2411, the secondary mould in bottom build lining Course 242, in buried rubber fastening band 2421, filled layer 243.
Specific embodiment
Illustrate a specific embodiment of the invention with reference to the accompanying drawings and examples, but following embodiment is used only in detail It describes the bright present invention in detail, does not limit the scope of the invention in any way.
During whole constructing tunnel, the form of construction work of tunnel lining structure, I, II grade of country rock are determined according to country rock grade Coating combination it is good, be generally not in unstable bolck, and the bite force of the structural plane of III, IV, V grade of country rock hole section is weak, With more unstable bolck, therefore, in I, II grade of country rock hole section, the bottom of tunnel lining structure is construction of bottom plates mode, In III, IV, V grade of country rock hole section, the bottom of tunnel lining structure needs to carry out inverted arch construction.
Embodiment 1:
A kind of tunnel water proofing discharge structure, also referring to Fig. 1 to Figure 12.
As depicted in figs. 1 and 2, tunnel water proofing discharge structure provided in this embodiment is for I, II grade of country rock hole section, the tunnel Road water-proof drainage structure includes wall surface the preliminary bracing layer 11, waterproof roll layer 12, the secondary mould that set gradually in tunneling Building lining layer 13, preliminary bracing layer 11 are to be injected in the concrete mud on tunneling wall surface or elder generation on tunneling wall surface Anchor pole fill-before-fire concrete mud is squeezed into, one layer of geotextiles 121 are equipped between preliminary bracing layer 11 and waterproof roll layer 12, Geotextiles 121 have good water permeability, and can be protected from waterproof roll layer 12, prevent it to be punctured, secondary mould builds lining Course 13 be by below geotextiles 121 supporting trolley formwork after-pouring concrete formed.By preliminary bracing layer 11, waterproof roll Material layer 12, secondary moulded lining layer 13 form tunnel arch wall.
As shown in Figure 3 and Figure 4, waterproof roll layer 12 is fixed on the initial stage branch poured on country rock 111 by riveting component 122 On sheath 11, the two sides up and down of waterproof roll layer 12 are abutment wall portion 123, and middle section is crown portion 124, and abutment wall portion 123 is corresponding In on the abutment wall for being laid on tunnel arch wall, crown portion 124, which corresponds to, to be laid on the vault of tunnel arch wall, in abutment wall portion 123 Riveting component 122 is more sparse, and the riveting component 122 in crown portion 124 is more dense.
Riveting component 122 includes 1221, nailing 1222, metal washer 1223 of hot melt liner, and fixed geotextiles 121, which use, penetrates Metal washer 1223 is pressed under nailing 1222 by nail gun, and hot melt liner 1221 is pressed under metal washer 1223, washer is heated Welding uses pressure welding device between 1221 and waterproof roll layer 12, and the welding of adjacent waterproof roll is using double slit heat on waterproof roll layer 12 Fusing soldering welder.
Tunneling bottom surface liner structure includes bottom plate 141 and discharge conduit 142, is equipped on the inside of discharge conduit 142 longitudinal The lateral sulcus 1421 of extension, outside are equipped with side gutter 1422, and bottom plate 141 is concrete lift, and top is filled layer 143, filled layer 143 uses C20 concrete placings, and it is railway roadbed at the top of filled layer 143 that the intensity of bottom plate 141, which is higher than filled layer 143, 1431, it is internal rail top surface 192 at the top of railway roadbed 1431, is laid with rubble on railway roadbed 1431, track is laid on rubble, entire tunnel is in tunnel Middle line 191 two sides in road are symmetrical.
Side gutter 1422 and the top surface of railway roadbed 1431 pass through transverse water drain pipe 1423 and are communicated to lateral sulcus 1421, laterally let out Water pipe 1423 is internal diameter 50mm pipeline, and the interval 3-5m is laid along longitudinal direction by lateral sulcus 1421.When draining, the water of internal rail top surface is arranged Enter side gutter 1422, the water in side gutter 1422 and railway roadbed 1431 is discharged into lateral sulcus 1421, eventually by lateral sulcus 1421 are discharged to outside tunnel.
It is embedded with longitudinal blind pipe 151 in tunnel arch wall bottom, wraps up one layer of geotextiles, longitudinal blind pipe 151 outside longitudinal blind pipe Both ends be bending section 1511, bending section 1511 curves inwardly and is communicated to lateral sulcus 1421, the bottom of secondary moulded lining layer 13 For secondary moulded lining layer root 131, between secondary moulded lining layer root 131 and the main body on secondary 13 top of moulded lining layer Equipped with longitudinal construction joint 132, be equipped among longitudinal construction joint 132 in buried rubber fastening band 133, longitudinal blind pipe 151 is embedded in Between preliminary bracing layer 11 and waterproof roll layer 12, one layer of geotextiles are wrapped up outside longitudinal blind pipe 151, longitudinal blind pipe 151 is interior The punching bellows of diameter 107mm pours C15 non-sand concrete displacement hull 1512, C15 non-sand concrete displacement hull around longitudinal blind pipe 151 1512 inside are coarse texture, have water permeability, and the water in country rock enters C15 without sand by the crack on preliminary bracing layer 11 Concrete displacement hull 1512, and eventually enter into longitudinal blind pipe 151 and be drained into lateral sulcus 1421.
As shown in figure 5, being respectively provided with a circumferential row in construction joint two sides between preliminary bracing layer 11 and waterproof roll layer 12 Water plate 16, the width L1 of each circle draining plate 16 are 50cm,
A longitudinal blind pipe 151, the end of the two 16 the same sides of circle draining plate are buried respectively in the two sides of each ring tunnel arch wall Head is communicated to corresponding longitudinal blind pipe 151, and the water in country rock enters circle draining plate 16 by the crack on preliminary bracing layer 11, Longitudinal blind pipe 151 is discharged by circle draining plate 16 again, is ultimately discharged into lateral sulcus 1421, to reduce the hydraulic pressure at the tunnel arch wall back side Power.
Further, in water abundant ground, the circle draining blind pipe of φ 50mm, the circumferential direction be there also is provided according to longitudinal pitch 2m The both ends of draining blind pipe are also communicated to corresponding longitudinal blind pipe.
Further, as shown in Fig. 6-1 and Fig. 6-2, lateral spare tapping pipe 17 is additionally provided in the bottom of tunnel arch wall, Specifically, about 10 meters of a ring tunnel arch wall length, about 9 meters of spacing between the two-port of longitudinal blind pipe 151, a ring tunnel arch wall exists The two sides of longitudinal blind pipe 151 are respectively provided with a spare tapping pipe 17, and spare tapping pipe 17 is located at same height with longitudinal blind pipe 151 Journey.The outer end of spare tapping pipe 17 be communicated to corresponding lateral sulcus 1421 and binding geotextiles, inner end be located at preliminary bracing layer 11 and It is sealed with adhesive tape 171.
Trolley formwork 135 corresponds to 1511 end of bending section of longitudinal blind pipe 151 and the outer end of spare tapping pipe 17 and is all provided with There is template aperture 1351, in pre-buried spare tapping pipe 17, wraps up one layer of geotextiles, spare tapping pipe 17 outside spare tapping pipe 17 Outer end pass through trolley formwork 135 template aperture 1351, spare 17 bottom of tapping pipe be arranged spacer bar 172, supporting steel In the preliminary bracing layer 11 and country rock of the inner end insertion tunnel wall surface of muscle 172,172 diameter 16mm of spacer bar, to guarantee to support It is firm.
It is circular construction joint 134 between adjacent two rings tunnel arch wall, in tunnel, the two sides of circular construction joint 134 are respectively arranged one The spare tapping pipe 17 of root, spacing 60cm between adjacent two spare tapping pipes 17 of 134 two sides of tunnel circular construction joint.
After the blocking of 1511 end of bending section of longitudinal blind pipe 151, water is accumulated in longitudinal blind pipe 151 leads to longitudinal blind pipe 151 hydraulic pressure increases nearby, and contact point hydraulic pressure is small between spare tapping pipe 17 and preliminary bracing layer 11, water can flow to from high pressure It is excluded at low pressure and along spare tapping pipe 17, prevents tunnel arch wall back side hydraulic pressure is excessive from causing liner structure unstable or damaging It is bad.
It is higher to waterproof ability requirement at the construction joint and deformation construction joint of two ring tunnel arch walls, therefore, such as Fig. 8 institute Show, at circular construction joint 134 or deformation construction joint 138, back sticking type rubber fastening band 1411 is equipped at the top of bottom plate 141, Buried rubber fastening band 1432 in being embedded in the middle part of filled layer 143.As shown in Figure 9 and Figure 10, in secondary moulded lining layer 13 Buried rubber fastening band 136 in being equipped with is located at below waterproof roll layer 12 at the top of secondary moulded lining layer 13 and is equipped with back patch Formula rubber fastening band 137, in buried rubber fastening band 136, in buried 1432 width L2 of rubber fastening band be 40cm.
Further, two sides are respectively equipped with the bottom discharge blind pipe longitudinally extended, bottom discharge blind pipe below bottom plate 141 Between be equipped with transverse drainage blind pipe, the water of the lower section of bottom plate 141 is discharged by bottom discharge blind pipe by transverse drainage blind pipe, is being passed through Water is discharged to outside tunnel by bottom discharge blind pipe, prevents 141 lower section hydraulic pressure of bottom plate excessive.
As is illustrated by figs. 11 and 12, when pouring secondary moulded lining layer 13, the top of secondary moulded lining layer 13 can be deposited In the portion of coming to nothing 139, leads to leakiness at the top of tunnel arch wall, be unfavorable for water-proof drainage, therefore, in the top waterproof roll of tunnel arch wall 12 lower section of material layer is equipped with pre- patch flexible porous tube 181 along longitudinal direction, and the pre- flexible porous tube 181 that pastes is close to trolley formwork end face 1352 One end is equipped with vertical coating steel pipe 182,182 internal diameter 30cm of coating steel pipe, and one end is communicated to pre- patch flexible porous tube 181, The other end is communicated to the lower surface of tunnel arch wall, can be soft to pasting in advance by coating steel pipe 182 after trolley formwork 135 is removed Water-permeable pipe 181 injects concrete grout, and concrete grout, full of portion 139 of entirely coming to nothing, makes tunnel arch wall along pre- patch flexible porous tube 181 Top filling is closely knit.
Embodiment 2
A kind of tunnel water proofing discharge structure, also referring to Figure 13 to Figure 15.
As shown in figure 13, tunnel water proofing discharge structure provided in this embodiment is for III, IV, V grade of country rock hole section, with reality The difference for applying example 1 is, is not only provided on the top of tunneling by preliminary bracing layer 21, waterproof roll layer 22, secondary mould The tunnel arch wall that building lining layer 23 forms also is equipped with tunnel inverted arch in the bottom of tunneling, and tunnel inverted arch includes bottom initial stage Branch sheath 241, the secondary moulded lining layer 242 in bottom and filled layer 243, to enhance the support capacity in entire tunnel.
As shown in figure 14, in 231 location of circular construction joint of tunnel inverted arch, among the secondary moulded lining layer 242 in bottom Buried rubber fastening band 2421 in being equipped with, in bottom, the lower surface of secondary moulded lining layer 242 is embedded with back sticking type rubber water-proof Band 2411, in buried rubber fastening band 2421 and 2411 width of back sticking type rubber fastening band in 40cm, prevent water from being applied by circumferential direction Work seam 231 penetrates into.
Further, as shown in figure 15, the bottom in 232 location of deformation construction joint of tunnel inverted arch be also spaced be embedded with it is vertical To seamless steel pipe 233, butter is filled in seamless steel pipe 233, prevents seamless steel pipe 233 from getting rusty, seamless steel pipe 233 plays connection The effect of two ring tunnel inverted arch, prevent tunnel inverted arch part deformation occurs destroy waterproof ability.
Embodiment 3
A kind of tunnel water proofing water discharge method, comprising:
(1) main water-proof drainage structure construction: preliminary bracing layer, waterproof roll layer, secondary is set gradually in the wall surface of tunneling The lateral sulcus longitudinally extended is arranged in tunneling bottom surface for moulded lining layer, longitudinal blind in the embedded longitudinal blind pipe in tunnel arch wall bottom The inward at both ends of pipe is bent and is communicated to lateral sulcus;Setting circle draining plate in interval between branch sheath and waterproof roll layer in the early stage, The both ends of circle draining plate are communicated to corresponding longitudinal blind pipe.
One layer of geotextiles are laid on waterproof roll layer to prevent from being punctured, waterproof roll layer constitutes the main waterproof of tunnel arch wall Structure, and the main discharge structure of tunnel arch wall is made up of above-mentioned circle draining plate and longitudinal blind pipe.
Further, it is equipped with pre- patch flexible porous tube along longitudinal direction below the top waterproof roll of tunnel arch wall, pastes in advance soft One end of formula water-permeable pipe is equipped with vertical coating steel pipe, and one end of coating steel pipe is communicated to pre- patch flexible porous tube, and the other end connects Cement mortar is inwardly injected by coating steel pipe in the lower surface for leading to tunnel arch wall, when grouting pressure reaches 0.2Mpa, terminates Slip casting.Due to tunnel arch wall secondary moulded lining layer at the top of can exist come to nothing, cause its top it is not closely knit enough, waterproof ability compared with Difference can increase the compactness at the top of arch wall by secondary grouting, enhance waterproof ability.
(2) spare discharge structure construction: burying lateral spare tapping pipe in the bottom of tunnel arch wall, spare tapping pipe Outer end is communicated to corresponding lateral sulcus, and inner end is located at preliminary bracing layer.
Since the two-port of longitudinal blind pipe is easy the concrete being solidified blocking, after later period tunnel comes into operation, part hole Section draining is difficult, and can exclude water by spare tapping pipe, has both reduced the water pressure at the tunnel arch wall back side, has prevented due to hydraulic pressure mistake It is impaired that height leads to tunnel structure, while avoiding and drilling through drain hole again, has saved cost.
The present invention is described in detail above in conjunction with drawings and examples, still, those of skill in the art Member is it is understood that without departing from the purpose of the present invention, can also carry out each design parameter in above-described embodiment Change, forms multiple specific embodiments, is common variation range of the invention, is no longer described in detail one by one herein.

Claims (10)

1. a kind of tunnel water proofing discharge structure, preliminary bracing layer, the waterproof roll set gradually including the wall surface in tunneling The tunnel arch wall of layer, secondary moulded lining layer composition, in tunneling bottom surface, the two sides of liner structure are respectively equipped with longitudinal extension Lateral sulcus, be embedded with longitudinal blind pipe in tunnel arch wall bottom, the inward at both ends of the longitudinal direction blind pipe is bent and is communicated to the side Ditch, which is characterized in that circle draining blind pipe is equipped at intervals between the preliminary bracing layer and waterproof roll layer or/and in construction joint Two sides are equipped with circle draining plate, and the both ends of the circle draining plate or/and circle draining blind pipe are communicated to the corresponding longitudinal direction Blind pipe;Lateral spare tapping pipe is additionally provided in the bottom of tunnel arch wall, the outer end of the spare tapping pipe is communicated to corresponding The lateral sulcus, inner end are located at the preliminary bracing layer.
2. tunnel water proofing discharge structure according to claim 1, which is characterized in that use the inner end mouthful of the spare tapping pipe Adhesive tape sealing, external port bind geotextiles, and spacer bar is arranged in the spare sluicing bottom of the tube, the spacer bar Tunnel wall surface is inserted into inner end.
3. tunnel water proofing discharge structure according to claim 1, which is characterized in that in tunnel, the two sides of circular construction joint are each A piece spare tapping pipe, adjacent two spare sluicing tube spacing 50-80cm of tunnel circular construction joint two sides are set.
4. tunnel water proofing discharge structure according to claim 1, which is characterized in that the longitudinal direction blind pipe is punching ripple Pipe, the longitudinal direction blind pipe pour C15 without sand around the longitudinal direction blind pipe between the preliminary bracing layer and waterproof roll layer Concrete displacement hull;One layer of geotextiles are wrapped up outside the spare tapping pipe and longitudinal blind pipe;The preliminary bracing layer and waterproof roll One layer of geotextiles are equipped between layer.
5. tunnel water proofing discharge structure according to claim 1, which is characterized in that tunneling bottom surface liner structure with Lower two sides are respectively equipped with the bottom discharge blind pipe longitudinally extended, are equipped with transverse drainage blind pipe between the bottom discharge blind pipe.
6. tunnel water proofing discharge structure according to claim 1, which is characterized in that tunnel arch wall circular construction joint and The middle part of deformation construction joint be equipped in buried rubber fastening band, top, which is located at below the waterproof roll layer, is equipped with back sticking type rubber Waterstop.
7. tunnel water proofing discharge structure according to claim 1, which is characterized in that in tunnel the circular construction joint of inverted arch and Deform construction joint bottom be equipped with back sticking type rubber fastening band, middle part be equipped in buried rubber fastening band;The change of inverted arch in tunnel Also interval is embedded with longitudinal seamless steel pipe at shape construction joint, fills butter in the seamless steel pipe.
8. tunnel water proofing discharge structure according to claim 1, which is characterized in that in the top waterproof roll of tunnel arch wall Layer lower section is equipped with pre- patch flexible porous tube along longitudinal direction, and one end of the pre- patch flexible porous tube is equipped with vertical coating steel pipe, institute The one end for stating coating steel pipe is communicated to the pre- patch flexible porous tube, and the other end is communicated to the lower surface of tunnel arch wall.
9. a kind of tunnel water proofing water discharge method, which is characterized in that including,
Preliminary bracing layer, waterproof roll layer, secondary moulded lining layer are set gradually in the wall surface of tunneling, at tunneling bottom The lateral sulcus longitudinally extended is arranged in face, and in the embedded longitudinal blind pipe in tunnel arch wall bottom, the inward at both ends bending of the longitudinal direction blind pipe is simultaneously It is communicated to the lateral sulcus;
The interval setting circle draining plate between the preliminary bracing layer and waterproof roll layer, the both ends of the circle draining plate connect Lead to corresponding longitudinal blind pipe;
Lateral spare tapping pipe is buried in the bottom of tunnel arch wall, the outer end of the spare tapping pipe is communicated to corresponding described Lateral sulcus, inner end are located at the preliminary bracing layer.
10. tunnel water proofing water discharge method according to claim 9, which is characterized in that in the top waterproof roll of tunnel arch wall Pre- patch flexible porous tube is equipped with below material along longitudinal direction, one end of the pre- patch flexible porous tube is equipped with vertical coating steel pipe, institute The one end for stating coating steel pipe is communicated to the pre- patch flexible porous tube, and the other end is communicated to the lower surface of tunnel arch wall, passes through institute It states coating steel pipe and inwardly injects cement mortar, carrying out lining cutting backfill slip casting behind terminates note when grouting pressure reaches 0.2Mpa Slurry.
CN201910127194.4A 2019-02-20 2019-02-20 Waterproof drainage structure and waterproof drainage method for tunnel Active CN109611150B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910127194.4A CN109611150B (en) 2019-02-20 2019-02-20 Waterproof drainage structure and waterproof drainage method for tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910127194.4A CN109611150B (en) 2019-02-20 2019-02-20 Waterproof drainage structure and waterproof drainage method for tunnel

Publications (2)

Publication Number Publication Date
CN109611150A true CN109611150A (en) 2019-04-12
CN109611150B CN109611150B (en) 2024-08-30

Family

ID=66019028

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910127194.4A Active CN109611150B (en) 2019-02-20 2019-02-20 Waterproof drainage structure and waterproof drainage method for tunnel

Country Status (1)

Country Link
CN (1) CN109611150B (en)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110145364A (en) * 2019-06-24 2019-08-20 中铁隧道局集团有限公司 A kind of construction method of tunnel water handling structure
KR102026874B1 (en) * 2019-04-16 2019-09-30 나두영 drain system for water flowing out of tunnel road
CN110410144A (en) * 2019-07-18 2019-11-05 中交第二公路勘察设计研究院有限公司 A kind of waterproof/drainage structure of shield tunnel
CN110486037A (en) * 2019-08-26 2019-11-22 中铁二局第一工程有限公司 A kind of constructing structure that railway tunnel vault prevents two lining vaults from coming to nothing and method
CN111810233A (en) * 2020-06-30 2020-10-23 中铁二院工程集团有限责任公司 Construction method for drainage hole of tunnel lining side wall
CN112360519A (en) * 2020-10-28 2021-02-12 中铁隧道局集团有限公司 Geotextile positioning method for positioning geotextile and improving tunnel waterproof plate laying quality
CN113062768A (en) * 2021-04-01 2021-07-02 重庆交通大学 Tunnel waterproof drainage structure and drainage method thereof
CN113374524A (en) * 2021-06-25 2021-09-10 中铁大桥勘测设计院集团有限公司武汉分公司 Longitudinal water-permeable supporting block for tunnel
CN113404533A (en) * 2021-06-28 2021-09-17 中铁大桥勘测设计院集团有限公司武汉分公司 Integrated longitudinal drainage blind pipe with water permeable supporting function for tunnel
CN114278375A (en) * 2021-12-18 2022-04-05 中建一局集团京通路桥建设有限公司 Tunnel hoop drainage system
CN114352308A (en) * 2022-01-13 2022-04-15 中化学交通建设集团有限公司 Tunnel entrance to a cave section is prevented drainage and reinforced structure
CN114592911A (en) * 2022-03-08 2022-06-07 中铁十六局集团第三工程有限公司 Waterproof and drainage structure of oversized span open-cut tunnel
CN115199306A (en) * 2022-07-06 2022-10-18 中铁二十一局集团第二工程有限公司 Waterproof equipment for water leakage in tunnel construction stage and application method
CN118390578A (en) * 2024-06-28 2024-07-26 中铁第六勘察设计院集团有限公司 Waterproof and drainage system for underwater tunnel connection position

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200195007Y1 (en) * 2000-03-21 2000-09-01 주식회사우대기술단 Tunnel draining system
CN203161255U (en) * 2012-08-22 2013-08-28 中铁二院工程集团有限责任公司 Tunnel network waterproof and drainage structure
CN205895312U (en) * 2016-05-16 2017-01-18 中铁第四勘察设计院集团有限公司 Be used for rich irrigated land section tunnel water handling system
CN206386150U (en) * 2016-12-16 2017-08-08 中铁二院工程集团有限责任公司 A kind of Underground Subway Station draining and examination and repair system
CN207297089U (en) * 2017-08-24 2018-05-01 中铁二院工程集团有限责任公司 A kind of new waterproof and water drainage system suitable for ballastless track bed tunnel inverted arch
CN108361065A (en) * 2018-05-07 2018-08-03 中铁工程设计咨询集团有限公司 A kind of tunnel inverted arch filling discharge structure
CN108729932A (en) * 2018-05-22 2018-11-02 中铁二院工程集团有限责任公司 Tunnel lining structure solid waterproof and water drainage system
CN208073501U (en) * 2017-12-27 2018-11-09 中铁二院工程集团有限责任公司 Foundation base type is without inverted arch type tunnel lining structure and its drainage system
CN109026079A (en) * 2018-07-28 2018-12-18 苏交科集团股份有限公司 Tunnel joint waterproof structure and waterproof construction method
CN209637782U (en) * 2019-02-20 2019-11-15 中铁隧道局集团有限公司 Tunnel water proofing discharge structure

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200195007Y1 (en) * 2000-03-21 2000-09-01 주식회사우대기술단 Tunnel draining system
CN203161255U (en) * 2012-08-22 2013-08-28 中铁二院工程集团有限责任公司 Tunnel network waterproof and drainage structure
CN205895312U (en) * 2016-05-16 2017-01-18 中铁第四勘察设计院集团有限公司 Be used for rich irrigated land section tunnel water handling system
CN206386150U (en) * 2016-12-16 2017-08-08 中铁二院工程集团有限责任公司 A kind of Underground Subway Station draining and examination and repair system
CN207297089U (en) * 2017-08-24 2018-05-01 中铁二院工程集团有限责任公司 A kind of new waterproof and water drainage system suitable for ballastless track bed tunnel inverted arch
CN208073501U (en) * 2017-12-27 2018-11-09 中铁二院工程集团有限责任公司 Foundation base type is without inverted arch type tunnel lining structure and its drainage system
CN108361065A (en) * 2018-05-07 2018-08-03 中铁工程设计咨询集团有限公司 A kind of tunnel inverted arch filling discharge structure
CN108729932A (en) * 2018-05-22 2018-11-02 中铁二院工程集团有限责任公司 Tunnel lining structure solid waterproof and water drainage system
CN109026079A (en) * 2018-07-28 2018-12-18 苏交科集团股份有限公司 Tunnel joint waterproof structure and waterproof construction method
CN209637782U (en) * 2019-02-20 2019-11-15 中铁隧道局集团有限公司 Tunnel water proofing discharge structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李超雄等: "高速铁路桥隧建筑物修理规则(试行)问与答", 中国铁道出版社, pages: 498 - 60 *

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102026874B1 (en) * 2019-04-16 2019-09-30 나두영 drain system for water flowing out of tunnel road
CN110145364A (en) * 2019-06-24 2019-08-20 中铁隧道局集团有限公司 A kind of construction method of tunnel water handling structure
CN110410144A (en) * 2019-07-18 2019-11-05 中交第二公路勘察设计研究院有限公司 A kind of waterproof/drainage structure of shield tunnel
CN110410144B (en) * 2019-07-18 2024-05-10 中交第二公路勘察设计研究院有限公司 Waterproof and drainage structure of shield tunnel
CN110486037A (en) * 2019-08-26 2019-11-22 中铁二局第一工程有限公司 A kind of constructing structure that railway tunnel vault prevents two lining vaults from coming to nothing and method
CN110486037B (en) * 2019-08-26 2024-04-05 中铁二局第一工程有限公司 Construction structure and method for preventing double-lining vault from being hollow for railway tunnel vault
CN111810233A (en) * 2020-06-30 2020-10-23 中铁二院工程集团有限责任公司 Construction method for drainage hole of tunnel lining side wall
CN112360519B (en) * 2020-10-28 2023-02-17 中铁隧道局集团有限公司 Geotextile positioning method for positioning geotextile and improving tunnel waterproof plate laying quality
CN112360519A (en) * 2020-10-28 2021-02-12 中铁隧道局集团有限公司 Geotextile positioning method for positioning geotextile and improving tunnel waterproof plate laying quality
CN113062768A (en) * 2021-04-01 2021-07-02 重庆交通大学 Tunnel waterproof drainage structure and drainage method thereof
CN113062768B (en) * 2021-04-01 2023-11-10 中交综合规划设计院有限公司 Tunnel waterproof drainage structure and drainage method thereof
CN113374524A (en) * 2021-06-25 2021-09-10 中铁大桥勘测设计院集团有限公司武汉分公司 Longitudinal water-permeable supporting block for tunnel
CN113404533A (en) * 2021-06-28 2021-09-17 中铁大桥勘测设计院集团有限公司武汉分公司 Integrated longitudinal drainage blind pipe with water permeable supporting function for tunnel
CN114278375A (en) * 2021-12-18 2022-04-05 中建一局集团京通路桥建设有限公司 Tunnel hoop drainage system
CN114352308A (en) * 2022-01-13 2022-04-15 中化学交通建设集团有限公司 Tunnel entrance to a cave section is prevented drainage and reinforced structure
CN114592911A (en) * 2022-03-08 2022-06-07 中铁十六局集团第三工程有限公司 Waterproof and drainage structure of oversized span open-cut tunnel
CN115199306A (en) * 2022-07-06 2022-10-18 中铁二十一局集团第二工程有限公司 Waterproof equipment for water leakage in tunnel construction stage and application method
CN118390578A (en) * 2024-06-28 2024-07-26 中铁第六勘察设计院集团有限公司 Waterproof and drainage system for underwater tunnel connection position

Also Published As

Publication number Publication date
CN109611150B (en) 2024-08-30

Similar Documents

Publication Publication Date Title
CN109611150A (en) Tunnel water proofing discharge structure and tunnel water proofing water discharge method
CN209637782U (en) Tunnel water proofing discharge structure
CN106120801B (en) Pipeline crosses the construction method at foundation ditch in water-rich sand layer
CN103410161B (en) Oblique control slip casting steel anchor tube framework and construction method thereof
CN109403371A (en) A kind of Steep Slope Embankment retaining structure and construction method
CN208280185U (en) A kind of post-cast strip advanced water-stopping construction
WO2016058275A1 (en) Underground steel-concrete structure pipeline with spiral composite reinforcement ring on inner wall thereof and manufacturing method thereof
CN102808422B (en) Bonded post-tensioned prestressed construction method for cast-in-place reinforced concrete structure
CN209368867U (en) A kind of Steep Slope Embankment retaining structure
CN102808414B (en) Bonded post-tensioned prestressed anchoring construction method for cast-in-place concrete structure
CN106939791A (en) One kind can prestress steel structure concrete pipe sheet and its construction method
CN101476470B (en) Water-proof drainage house cover process for tunnel
CN106838463B (en) The fastener inserts and usage of longitudinal overall stiffness after raising rectangular top plumber
CN101575859B (en) Anti-seepage joint of underground continuous walls and construction method thereof
CN204511513U (en) A kind of tunnel drainage blind pipe syndeton
CN107387092B (en) A kind of multiple rectangular top pipes are connected in parallel on the engineering method of the formation underground space under complex environment
CN112081607B (en) Tunnel primary support and waterproof and drainage combined system and construction method
CN212479325U (en) Drainage system for construction joint of underground excavation tunnel
CN217107046U (en) Corrugated steel plate self-plugging structure for highway tunnel transverse passage
CN105673933A (en) Waterproof sealing device for post-through-wall pipeline and construction method
CN205954632U (en) Pipeline crosses supporting construction of foundation ditch department in rich water sand layer
CN215105439U (en) New and old underpass links up waterproof construction
CN108521097A (en) A kind of prefabricated tunnel of electric power and its installation method
CN109140046B (en) Method for plugging end of pipe jacking pipe curtain
CN114525781A (en) Prestressed rod core bag grouting combined anti-floating component and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant