- CN209620299U CN209620299U CN201822070668.XU CN201822070668U CN209620299U CN 209620299 U CN209620299 U CN 209620299U CN 201822070668 U CN201822070668 U CN 201822070668U CN 209620299 U CN209620299 U CN 209620299U
- Authority
- CN
- China
- Prior art keywords
- wallboard
- sleeve
- shear wall
- overlapped shear
- wall plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Working Measures On Existing Buildindgs (AREA)
Abstract
The utility model provides a kind of overlapped shear wall plate and overlapped shear wall, is related to construction engineering technical field, and overlapped shear wall plate includes the first wallboard, the second wallboard and first sleeve;First wallboard and the second wallboard relative spacing are arranged, and first sleeve is mounted between the first wallboard and the second wallboard, and the end of first sleeve passes through the first wallboard, has insulating layer in the second wallboard.Wherein, it being capable of roughing-in in first sleeve, when live roughing-in, by pipeline laying into first sleeve, can be prefabricated in the factory stage reserved first sleeve, avoid opening up tube seat when site operation on overlapped shear wall plate, and saving of work and time, saving material simultaneously reduce building waste pollution, construction efficiency is substantially increased, and the convenience of roughing-in is higher;In addition later period maintenance replacement pipeline does not need to destroy existing metope yet, directly extraction pipeline, and the overlapped shear wall plate has heat insulation function.
Description
Technical field
The utility model relates to construction engineering technical fields, more particularly, to a kind of overlapped shear wall plate and a kind of tool
There is the overlapped shear wall of the overlapped shear wall plate.
Background technique
When traditional architecture is constructed, the installation of feedwater piping usually opens up tube seat by scene on wall on wall, then exists
Feedwater piping is laid in tube seat, is blocked again with packing material after fixed, is finally completed the laying of the feedwater piping on wallboard.
With the fast development of building industrialization, more and more construction walls use prefabrication wallboard, on-site consolidation
The mode of prefabricated panel carries out, pipeline laying tube seat be also prefabricated in the factory wallboard when it is reserved complete, greatly facilitate site operation.
The advantages of overlapped shear wall integrates traditional cast-in-place structural and assembled arthitecutral structure due to it, and component matter
Amount is light, is readily transported, lifts and installs, and is more and more applied in assembled architecture.
But since overlapped shear wall is superposed type (hollow shape), be different from integral prefabricated concrete wall (solid shape),
Overlapped shear wall plate only has 50mm thickness, if opening up tube seat (generally wide 30mm, depth 20mm) again, can reduce the strong of local wall
Degree may cause the problem of cracking in transport and hoisting process, and since its special overturning production method is also uncomfortable
It closes and opens up tube seat in factory, therefore be difficult to default tube seat in overlapped shear wall, lead to the effect of the roughing-in in overlapped shear wall
Rate is lower, convenience is poor.
Utility model content
The purpose of this utility model is to provide a kind of overlapped shear wall plates, in the prior art in overlapping shearing to solve
The technical problem that the efficiency of roughing-in is lower in wall, convenience is poor.
Overlapped shear wall plate provided by the utility model, including the first wallboard, the second wallboard and first sleeve;
First wallboard and the second wallboard relative spacing are arranged, and the first sleeve is mounted on first wallboard
Between second wallboard, and the end of the first sleeve passes through first wallboard;
There is insulating layer in second wallboard.
Further, the overlapped shear wall plate further includes steel reinforcement cage;
The both ends of the steel reinforcement cage are fixed with first wallboard and second wallboard respectively;
It is fixed in the middle part of the first sleeve on the steel reinforcement cage.
Further, the first sleeve and the steel reinforcement cage weld.
Further, the first sleeve is bundled on the steel reinforcement cage.
Further, the first wallboard is equipped with the second casing;
Respectively with first wallboard through setting, the end of the first sleeve passes through institute at the both ends of second casing
State the second casing.
Further, plugging material is equipped between the first sleeve and second casing.
Further, the section of second casing is rectangle or circle.
Further, the first sleeve includes the first tube body and two the second tube bodies;
Two second tube bodies are connect with the both ends of first tube body respectively, and two second tube bodies respectively with
First tube body is vertically arranged;
First tube body is mounted between first wallboard and second wallboard, two the second tube body difference
Across first wallboard.
Further, first tube body is connect with second tube body by elbow.
The purpose of this utility model, which also resides in, provides a kind of overlapped shear wall, including overlapping described in the utility model shearing
Wallboard.
Overlapped shear wall plate provided by the utility model, including the first wallboard, the second wallboard and first sleeve;Described first
Wallboard and the second wallboard relative spacing are arranged, the first sleeve be mounted on first wallboard and second wallboard it
Between, and the end of the first sleeve passes through first wallboard.Wherein, in first sleeve can roughing-in, when scene apply
If when pipeline, by pipeline laying into first sleeve, the stage that can be prefabricated in the factory reserves first sleeve, scene is avoided to apply
Working hour opens up tube seat on overlapped shear wall plate, and saving of work and time saves material and reduces building waste pollution, substantially increases
Construction efficiency, and the convenience of roughing-in is higher;In addition later period maintenance replacement pipeline does not need overlapped shear wall plate yet, directly
Extract pipeline out, and the overlapped shear wall plate has heat insulation function.
Detailed description of the invention
It, below will be right in order to illustrate more clearly of specific embodiment of the present invention or technical solution in the prior art
Specific embodiment or attached drawing needed to be used in the description of the prior art are briefly described, it should be apparent that, it is described below
In attached drawing be that some embodiments of the utility model are not paying creativeness for those of ordinary skill in the art
Under the premise of labour, it is also possible to obtain other drawings based on these drawings.
Fig. 1 be overlapped shear wall plate provided by the embodiment of the utility model structural schematic diagram (feed pipe in furred ceiling apply
If when);
Fig. 2 is the partial enlarged view of Fig. 1;
Fig. 3 be overlapped shear wall plate provided by the embodiment of the utility model structural schematic diagram (feed pipe in bed course apply
If when).
Icon: 1- first sleeve;The first tube body of 11-;The second tube body of 12-;The first wallboard of 2-;The second wallboard of 3-;
4- steel reinforcement cage;The toilet 5- furred ceiling;6- accomodation ground;The toilet 7- bed course;The second casing of 8-;9- plugging material.
Specific embodiment
The technical solution of the utility model is clearly and completely described below in conjunction with attached drawing, it is clear that described
Embodiment is the utility model a part of the embodiment, instead of all the embodiments.Based on the embodiments of the present invention, originally
Field those of ordinary skill every other embodiment obtained without making creative work belongs to practical
Novel protected range.
In the description of the present invention, it should be noted that such as occur term " center ", "upper", "lower", " left side ",
" right side ", "vertical", "horizontal", "inner", "outside" etc., indicated by orientation or positional relationship be orientation based on the figure or
Positional relationship is merely for convenience of describing the present invention and simplifying the description, rather than the device or member of indication or suggestion meaning
Part must have a particular orientation, be constructed and operated in a specific orientation, therefore should not be understood as limiting the present invention.
In addition, such as there is term " first ", " second ", being used for descriptive purposes only and cannot be understood as indicating or suggesting relative importance.
Wherein, term " first position " and " second position " are two different positions.
In the description of the present invention, it should be noted that unless otherwise clearly defined and limited, term " is pacified
Dress ", " connected ", " connection " shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or integrally
Connection;It can be mechanical connection, be also possible to be electrically connected;Can be directly connected, can also indirectly connected through an intermediary,
It can be the connection inside two elements.For the ordinary skill in the art, above-mentioned art can be understood with concrete condition
The concrete meaning of language in the present invention.
The utility model provides a kind of overlapped shear wall plate and overlapped shear wall, and multiple embodiments are given below to this reality
It is described in detail with the overlapped shear wall plate and overlapped shear wall of novel offer.
Embodiment 1
Overlapped shear wall plate provided in this embodiment, as shown in Figure 1 to Figure 2, including the first wallboard 2, the second wallboard 3 and
Sleeve 1;First wallboard 2 and 3 relative spacing of the second wallboard are arranged, and first sleeve 1 is mounted on the first wallboard 2 and the second wallboard 3
Between, and the end of first sleeve 1 passes through the first wallboard 2, has insulating layer in the second wallboard 3.
Since the end of first sleeve 1 passes through the first wallboard 2, pipeline can be extended into or out by the end of first sleeve 1
First sleeve 1, so that being capable of roughing-in in first sleeve 1.
When live roughing-in, by pipeline laying into first sleeve 1, which can be in factory
The overlapped shear wall plate stage reserves first sleeve 1, solves the difficult point that overlapped shear wall is not easy reserved tube seat, avoids site operation
When open up tube seat on overlapped shear wall plate, saving of work and time saves material and simultaneously reduces building waste pollution, substantially increases and applies
Work efficiency rate, and the convenience of roughing-in is higher;In addition later period maintenance replacement pipeline does not need to destroy existing metope yet, directly takes out
Pipeline out.
There is insulating layer in second wallboard 3, make the second wallboard 3 that there is thermal insulation property, so that overlapped shear wall plate be made to have
Heat insulation function, wherein insulating layer can be set in the inside of the second wallboard 3, form heat preservation sandwich layer, which can be with
It is used as exterior wall.
Wherein, the both ends of first sleeve 1 can be cast in the first wallboard 2, so that first sleeve 1 is mounted on the first wallboard
2 and second between wallboard 3, and first sleeve 1 can also be fixed on the steel reinforcement cage between the first wallboard 2 and the second wallboard 3.
In the present embodiment, overlapped shear wall plate further includes steel reinforcement cage 4;The both ends of steel reinforcement cage 4 respectively with the first wallboard 2 and
Two wallboards 3 are fixed;The middle part of first sleeve 1 is fixed on steel reinforcement cage 4, and the end of first sleeve 1 is cast in the first wallboard 2
It is interior.
Specifically, the both ends of steel reinforcement cage 4 pour together with the first wallboard 2 and the second wallboard 3 respectively, so that the first wallboard
2, the second wallboard 3 and steel reinforcement cage 4 form the overlapped shear wall plate of hollow shape.
When making overlapped shear wall plate, steel reinforcement cage 4 is arranged in first on the mold of the second wallboard 3 of production, then in advance
The second wallboard 3 is made, after the completion of the second wallboard 3 is prefabricated, the middle part of first sleeve 1 is fixed on steel reinforcement cage 4, then by second
Wallboard 3 is overturn, and steel reinforcement cage 4 is made to be located at the lower section of the second wallboard 3, then begins to the first wallboard 2 of production, is making the first wallboard 2
When, the reserved through hole on the first wallboard 2 makes the first wallboard 2 so that the end of first sleeve 1 passes through the first wallboard 2 by through-hole
It pours and is integrated with the other end of steel reinforcement cage 4, finally carrying out maintenance to overlapped shear wall plate can be completed manufacturing process.
Wherein, it when first sleeve 1 is fixed on steel reinforcement cage 4, can be welded on steel reinforcement cage 4, reinforcing bar can also be bundled in
Any suitable mode such as on cage 4.
Further, the first wallboard 2 is equipped with the second casing 8;The both ends of second casing 8 respectively with first wallboard 2
Through setting, the end of the first sleeve 1 passes through second casing 8.
When producing the first wallboard 2, the diameter of pre-buried second casing 8 in the first wallboard 2, the second casing 8 is greater than first
The diameter of casing 1, after capable of overturning convenient for the second wallboard 3, first sleeve 1 passes through the second casing 8, to realize across the first wall
The purpose of plate 2 improves convenience.
Also, pre-buried second casing 8 in the first wallboard 2 can be improved when making the first wallboard 2 reserved through hole just
Victory improves production efficiency.
In the present embodiment, the diameter of the second casing 8 can be DN100mm.
Further, plugging material 9 is equipped between first sleeve 1 and the second casing 8.Utilize the filling of plugging material 9 first
The sealing performance of the first wallboard 2 is improved in gap between casing 1 and the second casing 8.
Further, the section of the second casing 8 can be rectangle or circle, to adapt to first sleeve 1 of different shapes, the
The shape in the section of two casings 8 can be set according to actual needs.
First sleeve 1 has at least two ends, such as first sleeve 1 is substantially U-shaped, and there are two ends for the tool of first sleeve 1
Portion, first sleeve 1 is generally t-shaped, and first sleeve 1 then has there are three end.The shape of first sleeve 1 and the quantity of end can
To be arranged according to pipeline laying situation.
In the present embodiment, first sleeve 1 includes the first tube body 11 and two the second tube bodies 12;Two the second tube body 12 difference
It is connect with the both ends of the first tube body 11, and two the second tube bodies 12 are vertically arranged with the first tube body 11 respectively;First tube body 11 is solid
It is scheduled on the first wallboard 2, two the second tube bodies 12 are each passed through the first wallboard 2.
Specifically, the axial direction of two the second tube bodies 12 is axially vertical with the first tube body 11 respectively, and two second pipes
Body 12 is connect with the both ends of the first tube body 11 respectively, to form first sleeve 1.
First tube body 11 is fixed on steel reinforcement cage, and two the second tube bodies 12 are cast in respectively in the first wallboard 2, and two
The end of second tube body 12 passes through the first wallboard 2, and the end of two the second tube bodies 12 can be concordant with the first wallboard 2, can also be with
Protrude from the first wallboard 2.
For the smooth transition for realizing the first tube body 11 and the second tube body 12, the first tube body 11 and the second tube body 12 pass through elbow
Connection, to facilitate scene roughing-in in it.
Overlapped shear wall plate provided in this embodiment, first sleeve 1 can be the steel sleeve of caliber DN40mm, and elbow uses
45 ° of elbows can lay PP-R feedwater piping in first sleeve 1, be used to assemble the shear wall of toilet in overlapped shear wall plate
When, when feed pipe is laid in furred ceiling, as shown in Figure 1,1 top of first sleeve is reserved at 5 top 150mm of toilet furred ceiling,
H2 is sanitary apparatus water supply interface height, and 1 bottom end of first sleeve is reserved to be arranged referring to sanitary apparatus water supply interface requirement for height;Pipe
The flexible feed pipe of PP-R material etc. that diameter is DN15-DN20mm can the laying installation in first sleeve 1, it is convenient and efficient;Water supply
When pipe is laid in toilet bed course 7, as shown in Fig. 2, 1 top of first sleeve is reserved in 6 top of accomodation ground, h2+h3 is
The thickness of toilet bed course 7,1 bottom end of first sleeve are reserved in toilet bed course 7;Caliber is the PP-R of DN15-DN20mm
Material etc. flexibility feed pipe can the laying installation in first sleeve 1, it is convenient and efficient.
Overlapped shear wall plate provided in this embodiment, in first sleeve 1 can roughing-in, when live roughing-in,
By pipeline laying into first sleeve 1, the stage that can be prefabricated in the factory reserves first sleeve 1, when avoiding site operation
Tube seat is opened up on overlapped shear wall plate, saving of work and time saves material and reduces building waste pollution, substantially increases construction effect
Rate, and the convenience of roughing-in is higher;In addition later period maintenance replacement pipeline does not need the prefabricated existing metope of destruction yet, directly takes out
Pipeline out.
Embodiment 2
Overlapped shear wall provided in this embodiment, the overlapped shear wall plate provided including embodiment 1.Wherein, first sleeve 1
In can roughing-in, when live roughing-in, by pipeline laying into first sleeve 1, can be prefabricated in the factory rank
The reserved first sleeve 1 of section, avoids opening up tube seat when site operation on overlapped shear wall plate, and saving of work and time is saved material and subtracted
Few building waste pollution, substantially increases the construction efficiency of overlapped shear wall, and the convenience of roughing-in is higher;In addition the later period
Maintenance replacement pipeline does not need to destroy existing metope yet, directly extraction pipeline.
Finally, it should be noted that the above various embodiments is only to illustrate the technical solution of the utility model, rather than it is limited
System;Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should
Understand: it is still possible to modify the technical solutions described in the foregoing embodiments, or to some or all of
Technical characteristic is equivalently replaced;And these are modified or replaceed, it does not separate the essence of the corresponding technical solution, and this is practical new
The range of each embodiment technical solution of type.
Claims (10)
1. a kind of overlapped shear wall plate, which is characterized in that including the first wallboard (2), the second wallboard (3) and first sleeve (1);
First wallboard (2) and the second wallboard (3) relative spacing are arranged, and the first sleeve (1) is mounted on described the
Between one wallboard (2) and second wallboard (3), and the end of the first sleeve (1) passes through first wallboard (2);
There is insulating layer in second wallboard (3).
2. overlapped shear wall plate according to claim 1, which is characterized in that the overlapped shear wall plate further includes steel reinforcement cage
(4);
The both ends of the steel reinforcement cage (4) are fixed with first wallboard (2) and second wallboard (3) respectively;
It is fixed on the steel reinforcement cage (4) in the middle part of the first sleeve (1).
3. overlapped shear wall plate according to claim 2, which is characterized in that the first sleeve (1) and the steel reinforcement cage
(4) it welds.
4. overlapped shear wall plate according to claim 2, which is characterized in that the first sleeve (1) is bundled in the steel
On muscle cage (4).
5. overlapped shear wall plate according to claim 1, which is characterized in that the first wallboard (2) is equipped with the second casing
(8);
The both ends of second casing (8) are respectively with first wallboard (2) through setting, the end of the first sleeve (1)
Across second casing (8).
6. overlapped shear wall plate according to claim 5, which is characterized in that the first sleeve (1) and described second set
It manages and is equipped with plugging material (9) between (8).
7. overlapped shear wall plate according to claim 5, which is characterized in that the section of second casing (8) is rectangle
Or it is round.
8. overlapped shear wall plate described in any one of -7 according to claim 1, which is characterized in that first sleeve (1) packet
Include the first tube body (11) and two the second tube bodies (12);
Two second tube bodies (12) connect with the both ends of first tube body (11) respectively, and two second tube bodies
(12) it is vertically arranged respectively with first tube body (11);
First tube body (11) is mounted between first wallboard (2) and second wallboard (3), two second pipes
Body (12) is each passed through first wallboard (2).
9. overlapped shear wall plate according to claim 8, which is characterized in that first tube body (11) and second pipe
Body (12) is connected by elbow.
10. a kind of overlapped shear wall, which is characterized in that including overlapped shear wall plate of any of claims 1-9.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201822070668.XU CN209620299U (en) | 2018-12-11 | 2018-12-11 | Overlapped shear wall plate and overlapped shear wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201822070668.XU CN209620299U (en) | 2018-12-11 | 2018-12-11 | Overlapped shear wall plate and overlapped shear wall |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209620299U true CN209620299U (en) | 2019-11-12 |
Family
ID=68445482
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201822070668.XU Active CN209620299U (en) | 2018-12-11 | 2018-12-11 | Overlapped shear wall plate and overlapped shear wall |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209620299U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109339286A (en) * | 2018-12-11 | 2019-02-15 | 三筑工科技有限公司 | Overlapped shear wall plate, overlapped shear wall and overlapped shear wall board manufacturing method |
-
2018
- 2018-12-11 CN CN201822070668.XU patent/CN209620299U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109339286A (en) * | 2018-12-11 | 2019-02-15 | 三筑工科技有限公司 | Overlapped shear wall plate, overlapped shear wall and overlapped shear wall board manufacturing method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2018214737A1 (en) | Construction method for inner structure of single-bore double-track composite lining shield tunnel | |
WO2017206411A1 (en) | Full-prefabricated superimposed assembly-type underground pipe gallery and connection node thereof | |
CN106245674A (en) | Hollow wallboard mixes prefabricated assembled pipe gallery and construction method thereof | |
CN205276316U (en) | Modular prefabricated piping lane | |
CN108149706A (en) | A kind of cast-in-place hidden girder and the prefabricated assembled pipe gallery and its construction method of superimposed sheet splicing | |
CN106760054B (en) | Prefabricated reinforced concrete shear wall | |
CN109537851A (en) | A kind of method for prefabricating of assembled pipe well | |
CN206616585U (en) | One kind splits element precast formula pipe gallery | |
CN105735532A (en) | Method for assembling prefabricated uperimposed slab shear wall structure | |
CN109680841A (en) | Hybrid prefabricated multi-cavity reinforced concrete wall, underground space structure system and construction method | |
CN210597399U (en) | Post-cast strip structure applied to basement outer wall | |
CN108086353A (en) | A kind of hollow wallboard spliced with cast-in-place hidden girder mixes prefabricated assembled pipe gallery and its construction method | |
CN108166525A (en) | A kind of half prefabricated assembled pipe gallery spliced with cast-in-place hidden girder and its construction method | |
CN106638686B (en) | Pipe gallery with corrugated steel shear wall and its construction method | |
CN109914644A (en) | A kind of assembled heat insulation masonry wall and preparation method thereof | |
CN113293802A (en) | Construction method of inspection well | |
CN209620299U (en) | Overlapped shear wall plate and overlapped shear wall | |
CN206157913U (en) | Assembled square steel tube concrete post and girder steel connected node | |
CN208633847U (en) | A kind of corrugated steel supporting construction suitable for circular arch stalk formula tunnel full-section excavation | |
CN108457208A (en) | Whole assembly overlapping box culvert and construction method | |
CN209620300U (en) | Overlapped shear wall plate and overlapped shear wall | |
CN104314105A (en) | Connecting vertical seaming structure for basement external wall boards and cast-in-situ buttress column and construction method of connecting vertical seaming structure | |
CN202117320U (en) | Floating-resistant device for inner circle mold of circulation water pipe trench | |
CN204151835U (en) | The vertical piece structure of connection of the basement wall and cast-in-place buttress | |
CN207846241U (en) | Whole assembly overlapping box culvert |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP03 | Change of name, title or address |
Address after: 102200 1st floor, building 6, No.8 Beiqing Road, Huilongguan town, Changping District, Beijing Patentee after: Sany Construction Technology Co.,Ltd. Address before: 410000 Sany industrial city, Sany Road, Changsha Economic and Technological Development Zone, Hunan Province Patentee before: SANY CONSTRUCTION TECHNOLOGY Co.,Ltd. |
|
CP03 | Change of name, title or address |