CN206157913U CN201621242386.8U CN201621242386U CN206157913U CN 206157913 U CN206157913 U CN 206157913U CN 201621242386 U CN201621242386 U CN 201621242386U CN 206157913 U CN206157913 U CN 206157913U
Authority
CN
China
Prior art keywords
steel
concrete
tubular column
square tubular
filled
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621242386.8U
Other languages
Chinese (zh)
Inventor
霍静思
刘汗青
王海涛
魏振
周磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huaqiao University
Original Assignee
Huaqiao University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huaqiao University filed Critical Huaqiao University
Priority to CN201621242386.8U priority Critical patent/CN206157913U/en
Application granted granted Critical
Publication of CN206157913U publication Critical patent/CN206157913U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)
  • Rod-Shaped Construction Members (AREA)

Abstract

The utility model discloses an assembled square steel tube concrete post and girder steel connected node, including square steel tube concrete post prefab, steel beam member and a plurality of connecting piece, the square steel tube concrete post adopts prefabricated form, goes up trompil and pre -buried corrugated metal pipe, the other side's steel -pipe column concreting formation square steel tube concrete post again in square steel tube support connnection side, H shaped steel roof beam tip welding steel end plate, inject the high performance and pack and insert the connecting piece wherein and fix again in corrugated metal pipe, treat that high performance filler intensity reaches the designing requirement after, carry out the erection joint with H shaped steel roof beam and square steel tube concrete post through bolt connection, just easily realize the dismantlement and the change of H shaped steel roof beam and square steel tube concrete post. Roof beam column component is all prefabricated at the interplant, only is in the milk to square steel tube concrete post preformed hole at the scene, only needs during the assembly to assemble the member, fastens connecting the position, and the efficiency of construction is high, and the dismouting is convenient, adapts to assembly structure's development.

Description

A kind of assembled concrete-filled steel square tubular column and steel beam connecting joint
Technical field
The utility model is related to technical field of structural engineering, more particularly to a kind of assembled concrete-filled steel square tubular column and steel Beam connecting node.
Background technology
Because steel core concrete column compares reinforced column, with high capacity, plasticity and ductility is good, fire resistance is good And the advantages of good economical benefit, the every field in civil engineering is widely used in recent years.At the same time, China carries energetically Advocate building industrialization and green building.And cast-in-place concrete structure environmental pollution is big, material and energy resource consumption are high, construction material Recoverable rate is low, has not met the Architecture Policies of country-driven " being suitable for, economic, green is attractive in appearance ".Due to assembled Combining structure has an energy-conserving and environment-protective, and speed of application is fast, industrialization degree height etc., and it is low to solve China's building industrialization level, room Room construction effort productivity ratio is low and the low problems of conventional house product quality, adapts to the development of China's building trade.
Assembled concrete-filled steel square tubular column-steel-beam combination structure as the important branch in assembled combined structure system, Also there is every feature of assembled combining structure.Nowadays it is also applicable among Practical Project, and existing square steel tube coagulation Earth pillar is complex with steel beam connecting joint working procedure, and construction technology difficulty is larger, considerably increases difficulty of construction, is unfavorable for Speed of application is improved, while directly affecting the speed and assembling degree of structure construction.
Utility model content
The utility model proposes concrete-filled steel square tubular column and steel beam connecting joint, its mesh in a kind of assembled combining structure Be the defect for overcoming prior art, meet node items mechanical property, and realize the assembling of structure, improve the spelling of component Dress speed, fully adapts to requirement and the feature of assembled combined structure system.
For achieving the above object, the utility model proposes technical scheme be a kind of assembled concrete-filled steel square tubular column and steel Beam connecting node, including concrete-filled steel square tubular column prefabricated component, girder steel element and some connectors;Concrete-filled steel square tubular column is prefabricated Part includes the concrete-filled steel square tubular column formed by square steel tube casting concrete and some metal bellows, and metal bellows is pre-buried For pore-forming in quadrate steel pipe column in concrete-filled steel square tubular column, and hole one end open is located at concrete-filled steel square tubular column and connects side On;Girder steel element includes H profile steel beam and steel end plate;High-performance filler is filled with metal bellows, connector is corresponded Insertion metal bellows in it is fixed, after high-performance filling intensity reaches design requirement, by connector and steel end plate fasten from And realize the connection of concrete-filled steel square tubular column and H profile steel beam.
Some bolts hole are provided with the steel end plate, bolt hole is correspondingly arranged with connector position;The connector one One it is corresponding through bolt hole and and appended claims, the mode being bolted realizes concrete-filled steel square tubular column and H profile steel The installation connection of beam.
The connector is screw rod or threaded reinforcing bar;The 3~7 of a diameter of connector diameter of the metal bellows Times.
The securing member includes nut and pad.
Respectively by being welded and fixed between the metal bellows and concrete-filled steel square tubular column, steel end plate and H profile steel beam.
The high-performance filler is ungauged regions self-compacting high-strength concrete.
Compared to prior art, the utility model has the advantages that:
1st, assembled concrete-filled steel square tubular column described in the utility model and steel beam connecting joint first will in work progress Beam column component is prefabricated in the factory batch production out, and metal bellows is embedded in into square steel tube when factory makes quadrate steel pipe column In post, concrete grouting is carried out to quadrate steel pipe column in factory, form concrete-filled steel square tubular column;Steel end plate is welded on H profile steel beam-ends Portion;Then by girder steel component and it is embedded with the concrete-filled steel square tubular column of metal bellows and is transported to job site, at the scene to gold Category bellows carries out pouring into for high-performance filler, is inserted into connector and fixes, and treats that the high-performance filler in metal bellows reaches To after requirement of strength design, then each girder steel component and concrete-filled steel square tubular column are carried out into bolt connection by connector, really done Arrive prefabrication, the architectural process of on-site consolidation, so as to effectively improve the speed of construction, and safety and reliability is obtained To significantly being lifted.
2nd, when girder steel component suffers damage, due to convenient dismounting, so as to effectively improve the feasibility of later period maintenance, and And allow the recuperability of the structure using this scheme to be greatly improved.
3rd, built-in metal bellows is conducive to being attached the positioning of part, high-performance can be poured in metal bellows and is filled out Material, compared to the type of attachment for not adopting metal bellows, connector can be effectively improved in square steel using metal bellows Adhesion strength in pipe concrete column.
The utility model is described in further detail below in conjunction with drawings and Examples;But a kind of dress of the present utility model Embodiment is not limited to formula concrete-filled steel square tubular column and steel beam connecting joint.
Description of the drawings
Fig. 1 is the connecting node dimensional structure diagram of an embodiment;
Fig. 2 is the connecting node assembling schematic diagram of an embodiment;
Fig. 3 is the connecting node front view of an embodiment;
Fig. 4 is the girder steel element schematic diagram of an embodiment;
Fig. 5 is the connecting node part-structure schematic diagram of an embodiment;
Fig. 6 is the connecting node part-structure schematic diagram of another embodiment.
Specific embodiment
Embodiment 1
Refer to shown in Fig. 1 to Fig. 5, a kind of assembled concrete-filled steel square tubular column is mixed including square steel tube with steel beam connecting joint Solidifying earth pillar prefabricated component 1, connector 3 and girder steel element 4.Concrete-filled steel square tubular column prefabricated component includes the He of concrete-filled steel square tubular column 1 Metal bellows 2.Concrete-filled steel square tubular column adopts preformed patterns, perforate 11 and built-in metal ripple on quadrate steel pipe column connection side Line pipe 2, casting concrete is carried out to quadrate steel pipe column and forms concrete-filled steel square tubular column 1.Girder steel element 4 include H profile steel beam 41 and Steel end plate 42, the end of H profile steel beam 41 is welded with steel end plate 42, perforate 421 on steel end plate 42.High property is poured into metal bellows 2 Connector 3 is inserted in metal bellows 2 correspondingly and is fixed by energy filler again, treats that cementing material intensity reaches design After requirement, girder steel element 4 is connected on concrete-filled steel square tubular column 1 by nut 5 and pad 6 mode with bolts. In the present embodiment, connector 3 be screw rod, 3~7 times of a diameter of screw diameter of metal bellows 2.
If need to dismantle with girder steel element 4 to prefabricated concrete-filled steel square tubular column 1, the nut on dismounting connector can be passed through 5 and pad 6 so that prefabricated concrete-filled steel square tubular column 1 and the overall separation of girder steel element 4.Step before repeating, you can complete node It is assembled again.
Embodiment 2
Fig. 6 is refer to, embodiment 2 is that its connector 3 ' is threaded reinforcing bar, and metal with the difference of embodiment 1 3~7 times of a diameter of bar diameter of bellows 2.Remaining structure refer to embodiment 1, and not in this to go forth.
Above-described embodiment is only used for further illustrating a kind of assembled concrete-filled steel square tubular column of the present utility model and girder steel Connecting node, but the utility model is not limited to embodiment, it is every to implement to more than according to technical spirit of the present utility model Any simple modification, equivalent variations and modification that example is made, each fall within the protection domain of technical solutions of the utility model.

Claims (6)

1. a kind of assembled concrete-filled steel square tubular column and steel beam connecting joint, it is characterised in that:It is pre- including concrete-filled steel square tubular column Product, girder steel element and some connectors;Concrete-filled steel square tubular column prefabricated component includes what is formed by square steel tube casting concrete Concrete-filled steel square tubular column and some metal bellows, metal bellows is embedded in advance in concrete-filled steel square tubular column for quadrate steel pipe column Interior pore-forming, and hole one end open is on concrete-filled steel square tubular column connection side;Girder steel element includes H profile steel beam and steel end plate; High-performance filler is filled with metal bellows, connector is inserted correspondingly fixed in metal bellows, treat high-performance Filling intensity is reached after design requirement, and connector and steel end plate are fastened so as to realize concrete-filled steel square tubular column with H profile steel beam Connection.
2. assembled concrete-filled steel square tubular column according to claim 1 and steel beam connecting joint, it is characterised in that:The steel Some bolts hole are provided with end plate, bolt hole is correspondingly arranged with connector position;The connector passes through correspondingly spiral shell Keyhole and and appended claims, the mode being bolted realizes that concrete-filled steel square tubular column is connected with the installation of H profile steel beam.
3. assembled concrete-filled steel square tubular column according to claim 2 and steel beam connecting joint, it is characterised in that:The company Fitting is screw rod or threaded reinforcing bar;3~7 times of a diameter of connector diameter of the metal bellows.
4. assembled concrete-filled steel square tubular column according to claim 2 and steel beam connecting joint, it is characterised in that:It is described tight Firmware includes nut and pad.
5. assembled concrete-filled steel square tubular column according to claim 1 and steel beam connecting joint, it is characterised in that:The gold Respectively by being welded and fixed between category bellows and concrete-filled steel square tubular column, steel end plate and H profile steel beam.
6. assembled concrete-filled steel square tubular column according to claim 1 and steel beam connecting joint, it is characterised in that:The height Performance filler is ungauged regions self-compacting high-strength concrete.
CN201621242386.8U 2016-10-31 2016-10-31 Assembled square steel tube concrete post and girder steel connected node Expired - Fee Related CN206157913U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621242386.8U CN206157913U (en) 2016-10-31 2016-10-31 Assembled square steel tube concrete post and girder steel connected node

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621242386.8U CN206157913U (en) 2016-10-31 2016-10-31 Assembled square steel tube concrete post and girder steel connected node

Publications (1)

Publication Number Publication Date
CN206157913U true CN206157913U (en) 2017-05-10

Family

ID=58660723

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621242386.8U Expired - Fee Related CN206157913U (en) 2016-10-31 2016-10-31 Assembled square steel tube concrete post and girder steel connected node

Country Status (1)

Country Link
CN (1) CN206157913U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106320537A (en) * 2016-10-31 2017-01-11 华侨大学 Prefabricated concrete-filled square steel tube column and steel girder connecting joint
CN107965055A (en) * 2017-12-15 2018-04-27 北京万兴建筑集团有限公司 A kind of connecting node and the practice of H profile steel beam and girder with rolled steel section en cased in concrete
CN109577492A (en) * 2018-12-12 2019-04-05 东华理工大学 A kind of steel sections package concrete column and reinforced beam node connecting structure
CN113323135A (en) * 2021-06-01 2021-08-31 台州学院 Assembly type steel pipe column and concrete beam connecting component

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106320537A (en) * 2016-10-31 2017-01-11 华侨大学 Prefabricated concrete-filled square steel tube column and steel girder connecting joint
CN107965055A (en) * 2017-12-15 2018-04-27 北京万兴建筑集团有限公司 A kind of connecting node and the practice of H profile steel beam and girder with rolled steel section en cased in concrete
CN107965055B (en) * 2017-12-15 2023-10-03 北京万兴建筑集团有限公司 Connecting node of H-shaped steel beam and steel reinforced concrete beam and manufacturing method
CN109577492A (en) * 2018-12-12 2019-04-05 东华理工大学 A kind of steel sections package concrete column and reinforced beam node connecting structure
CN113323135A (en) * 2021-06-01 2021-08-31 台州学院 Assembly type steel pipe column and concrete beam connecting component

Similar Documents

Publication Publication Date Title
WO2018214477A1 (en) Prefabricated dual-steel-tube concrete shear wall, and assembly method therefor
CN107143034A (en) A kind of assembly concrete frame structure beam column rigid connection node
CN204023778U (en) The connected node of prefabricated assembled concrete beam column
CN107254884A (en) A kind of detachable prefabricated assembled concrete-filled steel square tubular column pin node
CN205777098U (en) A kind of detachable assembling type concrete-filled circular steel tube column
CN206157913U (en) Assembled square steel tube concrete post and girder steel connected node
CN105544801A (en) Bolted connection technique for prefabricated large plate shear wall provided with concealed bracing and construction method
CN107905363B (en) A kind of full assembled concrete nodal point connecting and connection method based on energy consumption with shearing resistance
CN106320537A (en) Prefabricated concrete-filled square steel tube column and steel girder connecting joint
CN104818801A (en) Pre-fabricated section steel reinforced concrete beam and pillar and manufacturing method
CN109372129A (en) The novel full assembly concrete frame joint of one kind and its construction method
CN107023076A (en) A kind of assembly concrete pole steel beam connecting node and preparation method thereof
CN102071747A (en) Joint of square steel tube concrete column and reinforced concrete floor and production method thereof
CN106869567A (en) A kind of energy-dissipating type cold-formed thin-walled steel pipe concrete Lateral Resistant System
CN108775084B (en) Steel-concrete combined precast beam and precast column connecting structure and construction method
CN108301531A (en) Assembled built-in heat insulation layer concrete composite wall-light steel frame-floor connecting node
CN210086553U (en) Dry-type connected precast concrete wall and foundation connection node
CN106088401A (en) A kind of assembled light steel frame insulation anti-side panel structure being applicable to villages and small towns multi-storey building and the practice
CN106592777B (en) Assembled steel-is mixed to combine beam-column node structure and its implementation method
CN108086471A (en) Detachable prefabricated assembled concrete-filled steel square tubular column and girder steel combined joint
CN208534081U (en) A kind of reconstruction structure of old building constructional column
CN206428805U (en) A kind of concrete prefabricated balcony of assembled steel
CN106592630A (en) Cast-in-situ and prefabricated combination comprehensive pipe rack structure and construction method thereof
CN110241915A (en) A kind of assembly concrete beam column L-type muscle integrated connection node and application method
CN204023777U (en) The connected node of prefabricated assembled concrete beam column

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170510

CF01 Termination of patent right due to non-payment of annual fee