CN209613581U - A kind of steel pipe sorter pulley-type pusher platform - Google Patents

A kind of steel pipe sorter pulley-type pusher platform Download PDF

Info

Publication number
CN209613581U
CN209613581U CN201822102162.2U CN201822102162U CN209613581U CN 209613581 U CN209613581 U CN 209613581U CN 201822102162 U CN201822102162 U CN 201822102162U CN 209613581 U CN209613581 U CN 209613581U
Authority
CN
China
Prior art keywords
pulley
traction rope
movable pulley
fixed
steel pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201822102162.2U
Other languages
Chinese (zh)
Inventor
忽少宏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Liulian Machinery Technology Co.,Ltd.
Original Assignee
Hangzhou Six Joint Machinery And Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Six Joint Machinery And Equipment Co Ltd filed Critical Hangzhou Six Joint Machinery And Equipment Co Ltd
Priority to CN201822102162.2U priority Critical patent/CN209613581U/en
Application granted granted Critical
Publication of CN209613581U publication Critical patent/CN209613581U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Discharge Of Articles From Conveyors (AREA)

Abstract

The utility model discloses a kind of steel pipe sorter pulley-type pusher platforms, set on steel pipe sorter front end, including discharging platform, the discharging platform is equipped with push plate and pulley gearing, sliding groove is additionally provided on the discharging platform, the discharging platform bottom is equipped with pulley motion space, the pulley gearing includes at least one fixed pulley, one movable pulley, engine, load-bearing traction rope, reset traction rope, the movable pulley and push plate are fixed to each other across sliding groove, the movable pulley or/and push plate are equipped with moving track, the load-bearing traction rope other end passes through movable pulley, it is fastened on engine after fixed pulley, described reset traction rope one end is fixed with movable pulley, the reset traction rope other end is fastened with engine, the load-bearing traction rope, reset winding side of the traction rope on engine To opposite.The utility model is structurally reasonable, securely and reliably, steel pipe can be pushed to building steel tube sorter.

Description

A kind of steel pipe sorter pulley-type pusher platform
Technical field
The utility model relates to a kind of construction equipment technical field more particularly to a kind of steel pipe sorter pulley-types Pusher platform.
Background technique
During architectural engineering carries out, especially skyscraper needs to use a large amount of building steel tube and builds scaffold, After the completion of architectural engineering, scaffold is removed, during withdraw from the arena sorting of a large amount of building steel tube after Practical Completion arranges, Taxonomic revision must be carried out by length specification to steel pipe, this work mostly uses greatly now artificial sorting to arrange, working efficiency is low, Cost is high, and employee work intensity is big, and length sorting precision is also inadequate, for this purpose, having had already appeared the automatic place of steel pipe sorting Manage equipment.
Existing building steel tube sorter in use, after steel pipe is unloaded from haulage vehicle, mixes, anyhow It is irregular, it cannot directly be unloaded on steel pipe sorter, need first to be discharged on platform, before entering sorter and arranging sorting, Sorter sorting onto is shifted steel pipe using driving means.
Summary of the invention
The utility model is to solve to need powered to enter asking for building steel tube sorter after steel pipe unloading is stacked Topic, provides a kind of structurally reasonable, and securely and reliably, the steel pipe sorter pulley-type that steel pipe can be pushed to building steel tube sorter pushes away Expect platform.
To achieve the goals above, the utility model uses a kind of following technical scheme: steel pipe sorter pulley-type pusher Platform is set to steel pipe sorter front end, including discharging platform, and the discharging platform is equipped with push plate and pulley drive fills It sets, sliding groove is additionally provided on the discharging platform, the discharging platform bottom is equipped with pulley motion space, the pulley drive Device include at least one fixed pulley, a movable pulley, engine, load-bearing traction rope, reset traction rope, the fixed pulley, Movable pulley is set in pulley motion space, and the fixed pulley is fixed in pulley motion space, and the movable pulley can be in cunning It is moved in wheel space, the movable pulley and push plate are fixed to each other across sliding groove, and the movable pulley or/and push plate are equipped with and move Dynamic rail road, described load-bearing traction rope one end are fixed in pulley motion space, and the load-bearing traction rope other end passes through dynamic slide It is fastened on engine after wheel, fixed pulley, described reset traction rope one end is fixed with movable pulley, the reset traction rope The other end is fastened with engine, and the winding direction of the load-bearing traction rope, reset traction rope on engine is opposite.We In case, the effect of discharging platform is to stack the steel pipe directly unloaded from vehicle in pusher platform, is then passed with push plate and pulley Dynamic device pushes steel pipe to steel pipe sorter in batches, after having pushed, push plate homing, then receive next group steel pipe;It is dynamic to slide Wheel needs the power of both direction to realize that reciprocating motion, the traction of the load-bearing as described in this programme and reset traction are respectively completed, hold When drawing again, load-bearing traction rope is recycled toward engine, and is resetted traction rope and released from engine, when reset then on the contrary, load-bearing and The same engine can be used in reset, can also be used two, and engine is equipped with winding plant, for elevator load-bearing traction rope, Reset traction rope;Using movable pulley, stress can be also reduced, changes power thrusts.
Preferably, further including movable pulley fixed frame, movable pulley moving guide rail, the movable pulley moving guide rail is fixed on In pulley motion space, the movable pulley fixed frame can move linearly on movable pulley moving guide rail, and the movable pulley is solid It is scheduled on movable pulley fixed frame.This programme by moving guide rail be arranged in discharging platform bottom pulley space, can and steel Pipe separation guarantees to move along a straight line and then determine that pulley Impact direction is constant, and push plate directly pushes steel pipe on discharging platform, can Increase pulley blocks service life.
Preferably, the discharging platform is equipped with track, the push plate is L shape, and the push plate bottom is equipped with can The wheel rolled in orbit.It is bigger to the impact of discharging platform when steel pipe discharging, the track (rail of the not easily damaged deformation of use Road intensity itself is high), push plate extra bus wheel forms trolley and moves in orbit, it is ensured that pulley blocks Impact direction will not change.
Preferably, the push plate is equipped with multiple points of push plates, described divides push plate to be respectively equipped with pulley gearing.By In length of steel pipe longest up to 6 meters, steel pipe component is than heavier, also all to the requirement for making and using using single pulley blocks It is relatively high, multiple pulley blocks can be used, corresponding multiple push plates, the strength that pulley blocks each in this way are born is lighter, pulley blocks production With it is easy to use.
Preferably, the push plate front end is equipped with arc tooth pushing.Steel pipe be it is circular, arc tooth pushing is easier from steel Bottom of the tube insertion, and steel pipe itself can be slided or be rolled along arc tooth pushing, to reduce resistance, facilitate promotion.
Therefore, the utility model has the following beneficial effects: (1) is structurally reasonable, securely and reliably;(2) steel pipe can be pushed To building steel tube sorter.
Detailed description of the invention
Fig. 1 is a kind of overlooking structure diagram of the utility model.
Fig. 2 is a kind of structural schematic diagram of the utility model embodiment one.
Fig. 3 is a kind of structural schematic diagram of the utility model embodiment two.
Fig. 4 is the pulley gearing structural schematic diagram of the utility model.
In figure: 1, steel pipe sorter 2, discharging platform 3, push plate 4, sliding groove
5, pulley motion space 6, fixed pulley 7, movable pulley 8, engine
9, load-bearing traction rope 10, reset traction rope 11, arc tooth pushing
12, movable pulley fixed frame 13, movable pulley moving guide rail 14, track 15, wheel.
Specific embodiment
The utility model is further described with reference to the accompanying drawing.
As shown in Figures 1 to 4, a kind of steel pipe sorter pulley-type pusher platform is set to 1 front end of steel pipe sorter, packet Discharging platform 2 is included, discharging platform 2 is equipped with push plate 3 and pulley gearing, is additionally provided with sliding groove 4, discharging on discharging platform 2 2 bottom of platform is equipped with pulley motion space 5, and pulley gearing includes 6, movable pulleys 7, engine of at least one fixed pulley 8, load-bearing traction rope 9, reset traction rope 10, fixed pulley 6, movable pulley 7 are set in pulley motion space 5, and fixed pulley 6 is fixed on cunning It takes turns in space 5, movable pulley 7 can move in pulley motion space 5, and movable pulley 7 and push plate 3 pass through sliding groove 4 mutually admittedly Fixed, 9 one end of load-bearing traction rope is fixed in pulley motion space 5, and 9 other end of load-bearing traction rope passes through movable pulley 7, fixed pulley 6 After be fastened on engine 8, it is fixed to reset 10 one end of traction rope and movable pulley 7, resets 10 other end of traction rope and power Machine 8 is fastened, and the winding direction of load-bearing traction rope 9, reset traction rope 10 on engine 8 is opposite;
Push plate 3 is equipped with multiple points of push plates, and push plate is divided to be respectively equipped with pulley gearing;
3 front end of push plate is equipped with arc tooth pushing 11;
Embodiment one further includes movable pulley fixed frame 12, movable pulley moving guide rail 13, movable pulley moving guide rail 13 such as Fig. 2 It is fixed in pulley motion space 5, movable pulley fixed frame 12 can move linearly on movable pulley moving guide rail 13, and movable pulley 7 is solid It is scheduled on movable pulley fixed frame 12;
Embodiment two, such as Fig. 3, discharging platform 2 is equipped with track 14, and push plate 3 is L shape, and 3 bottom of push plate is equipped with can be in track The wheel 15 rolled on 14.
Specifically used process is that the steel pipe directly unloaded from vehicle is stacked on discharging platform 2, then with push plate 3 (or Point push plate) and pulley gearing steel pipe is pushed in batches to steel pipe sorter 1, after having pushed, 3 homing of push plate, discharging Receive next group steel pipe on platform 2 again;
Load-bearing traction rope 9 and reset traction rope 10 are respectively completed the reciprocating motion of movable pulley 7, and when load-bearing is drawn, load-bearing is led Messenger 9 is recycled toward engine 8, and is resetted traction rope 10 and released from engine 8, and when reset is then opposite.

Claims (5)

1. a kind of steel pipe sorter pulley-type pusher platform is set to steel pipe sorter front end, which is characterized in that flat including discharging Platform, the discharging platform are equipped with push plate and pulley gearing, are additionally provided with sliding groove, the discharging on the discharging platform Mesa base is equipped with pulley motion space, and the pulley gearing includes at least one fixed pulley, movable pulley, a power Machine, load-bearing traction rope reset traction rope, and the fixed pulley, movable pulley are set in pulley motion space, and the fixed pulley is solid It is scheduled in pulley motion space, the movable pulley can move in pulley motion space, and the movable pulley and push plate are passed through and slided Dynamic slot is fixed to each other, and the movable pulley or/and push plate are equipped with moving track, and described load-bearing traction rope one end is fixed on pulley fortune In dynamic space, the load-bearing traction rope other end is fastened on engine after passing through movable pulley, fixed pulley, the reset Traction rope one end is fixed with movable pulley, and the reset traction rope other end is fastened with engine, and the load-bearing traction rope is answered Winding direction of the position traction rope on engine is opposite.
2. a kind of steel pipe sorter pulley-type pusher platform according to claim 1, which is characterized in that further include movable pulley Fixed frame, movable pulley moving guide rail, the movable pulley moving guide rail are fixed in pulley motion space, and the movable pulley is solid Determining frame can move linearly on movable pulley moving guide rail, and the movable pulley is fixed on movable pulley fixed frame.
3. a kind of steel pipe sorter pulley-type pusher platform according to claim 1, which is characterized in that the discharging is flat Platform is equipped with track, and the push plate is L shape, and the push plate bottom is equipped with the wheel that can be rolled in orbit.
4. a kind of steel pipe sorter pulley-type pusher platform according to claim 1 or 3, which is characterized in that described pushes away Plate is equipped with multiple points of push plates, and described divides push plate to be respectively equipped with pulley gearing.
5. a kind of steel pipe sorter pulley-type pusher platform according to claim 1 or 3, which is characterized in that described pushes away Front edge of board is equipped with arc tooth pushing.
CN201822102162.2U 2018-12-14 2018-12-14 A kind of steel pipe sorter pulley-type pusher platform Active CN209613581U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822102162.2U CN209613581U (en) 2018-12-14 2018-12-14 A kind of steel pipe sorter pulley-type pusher platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822102162.2U CN209613581U (en) 2018-12-14 2018-12-14 A kind of steel pipe sorter pulley-type pusher platform

Publications (1)

Publication Number Publication Date
CN209613581U true CN209613581U (en) 2019-11-12

Family

ID=68445850

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822102162.2U Active CN209613581U (en) 2018-12-14 2018-12-14 A kind of steel pipe sorter pulley-type pusher platform

Country Status (1)

Country Link
CN (1) CN209613581U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114054803A (en) * 2021-11-15 2022-02-18 江西金百成五金制品有限公司 Axle center punching equipment is used in window pulley production

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114054803A (en) * 2021-11-15 2022-02-18 江西金百成五金制品有限公司 Axle center punching equipment is used in window pulley production
CN114054803B (en) * 2021-11-15 2024-04-26 江西金百成五金制品有限公司 Axle center perforation equipment is used in window pulley production

Similar Documents

Publication Publication Date Title
CN101293624A (en) Stacking machine
CN209613581U (en) A kind of steel pipe sorter pulley-type pusher platform
CN204342016U (en) A kind of full-automatic ceramic tile flow production line
CN203581979U (en) Automatic plate supplying machine
CN106428848A (en) Workbin conveying mechanism and battery sorting collector
CN104276410A (en) Automatic bar-stacking machine
CN116256240A (en) Precast slab on-line measuring device
CN202464773U (en) Automatic gripping protective backing plate device
CN201228216Y (en) Stacking machine
CN105507632A (en) Double-shaft vertical lifting garage
CN204937611U (en) Rod shaped materials arranges counting assembly
CN209718120U (en) A kind of insulation blocks cutting machine
CN206842330U (en) Automatic conveyer
CN201013088Y (en) Down-loading vehicle board for solid parking equipment
CN114211764B (en) Automatic system suitable for installation of aerated brick production line net cage buckle
CN209393578U (en) A kind of steel pipe sorter screw feeding platform
CN103241513B (en) Automatic parking charging device for rail trolleys
CN101972743B (en) Automatic sorter
CN101774307B (en) Dual-rail dual-head laser marking mechanism
CN204310513U (en) Automatic heap rod machine
CN211366045U (en) Automatic feeding device for roller
CN203268946U (en) Automatic position-stopping and charging device for rail trolley
CN102881775A (en) Stack
CN209306290U (en) A kind of rail type lane stacker of plate fitment flexible production line
CN208856436U (en) Steel pipe sorter charging gear

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 310000 room 803-1, building 1, Xingcheng development building, Xiacheng District, Hangzhou City, Zhejiang Province

Patentee after: Hangzhou Liulian Machinery Technology Co.,Ltd.

Address before: 310000 1217 room 1217, No. 10, Yueshuai bridge, xiachai bridge, Xiacheng City, Zhejiang Province

Patentee before: HANGZHOU LIULIAN MACHINERY EQUIPMENT Co.,Ltd.