CN209585131U - There is the waterproof construction between the basement roof of earthing and main structure - Google Patents
There is the waterproof construction between the basement roof of earthing and main structure Download PDFInfo
- Publication number
- CN209585131U CN209585131U CN201821814273.XU CN201821814273U CN209585131U CN 209585131 U CN209585131 U CN 209585131U CN 201821814273 U CN201821814273 U CN 201821814273U CN 209585131 U CN209585131 U CN 209585131U
- Authority
- CN
- China
- Prior art keywords
- waterproof
- layer
- basement roof
- main structure
- barricade
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
The utility model relates to a kind of waterproof constructions having between the basement roof of earthing and main structure, it includes basement roof, main structure side plate, one layer of balcony slab, waterproof barricade, the overburden layer being provided on the outside of waterproof barricade above the basement roof are provided with below one layer of balcony slab;The waterproof barricade is extended downwardly and is contradicted with basement roof, and one layer of balcony slab, basement roof, main structure side plate and waterproof barricade are enclosed cavity.The utility model has the backfill amount and water repellent area for reducing the earthwork, reduces the effect of the leakage hidden trouble for generation not in place of constructing.
Description
Technical field
The utility model relates to housing construction technical field, more particularly, to a kind of basement roof for having earthing with
Waterproof construction between main structure.
Background technique
Referring to Fig. 4, the waterproof construction between the conventional basement roof 1 for having earthing and main structure side plate 2 is to be close to
What main structure side plate 2 was done, but in one layer of 3 lower part of balcony slab of house, since space is smaller, difficulty of construction is big, causes to construct
It is not in place, backfill leakiness, therefore there are the hidden danger of percolating water.
Utility model content
The purpose of the utility model is to provide a kind of waterproof construction having between the basement roof of earthing and main structure,
With the backfill amount and water repellent area for reducing the earthwork, the advantages of reducing the leakage hidden trouble for generation not in place of constructing.
The above-mentioned purpose of utility model of the utility model has the technical scheme that
A kind of waterproof construction having between the basement roof of earthing and main structure, including basement roof, main body knot
Structure side plate, one layer of balcony slab, one layer of balcony slab lower section are provided with waterproof barricade, are provided with position above the basement roof
Overburden layer on the outside of waterproof barricade;
The waterproof barricade is extended downwardly and is contradicted with basement roof, one layer of balcony slab, basement roof, main body
Structure side plate and waterproof barricade are enclosed cavity.
By using above-mentioned technical proposal, site operation is greatly facilitated, and reduces the backfill amount and waterproof surface of the earthwork
Product, reduces the hidden danger of the leak for generation not in place of constructing, final save the cost.
The utility model is further arranged to: being flushed outside the waterproof barricade and one layer of balcony.
By using above-mentioned technical proposal, site operation is facilitated, reduces the backfill amount of the earthwork.
The utility model is further arranged to: the overburden layer roof is provided with the draining for being fitted in water blocking barricade outer wall
Ditch.
By using above-mentioned technical proposal, drains, reduce between basement roof and column structure side plate convenient for aproll
The possibility of infiltration.
The utility model is further arranged to: the waterproof barricade outer wall fitting is fixed with waterproof roll layer, the waterproof
Coiled material layer extends fitting straight down and is fixed on basement roof roof.
By using above-mentioned technical proposal, the waterproof performance of waterproof barricade is improved, reduces the possibility that moisture enters cavity.
The utility model is further arranged to: it is provided with concrete cover between the overburden layer and basement roof,
The concrete cover is arranged above waterproof roll layer;
Waterproof protective layer is provided on the outside of the waterproof roll layer.
By using above-mentioned technical proposal, the being completely embedded property of waterproof roll layer and basement roof is improved, to waterproof
Coiled material layer plays pressing fixed function, and waterproof protective layer is used to further increase the waterproof performance of waterproof barricade, and plays pressing
The effect of fixed waterproof roll.
The utility model is further arranged to: it is close that the junction of the waterproof protective layer and basement roof is provided with first
Sealing.
By using above-mentioned technical proposal, the sealing for further improving waterproof barricade and basement roof junction is made
With reducing the leakage phenomenon of moisture.
The utility model is further arranged to: the gutter bottom wall is provided with concrete cushion, the gutter side wall
Waterproof slope, second seal and third sealing element are from top to bottom disposed with waterproof protective layer junction.
By using above-mentioned technical proposal, reduce the possibility that moisture is leaked along waterproof protective layer outer wall, to gutter side
Sealing waterproof action is played in wall and waterproof protective layer junction.
The utility model is further arranged to: the junction of the waterproof protective layer side wall and concrete cover is provided with
One end of water-swellable part, the water-swellable part is embedded in concrete cover, and the other end is connected to outside waterproof protective layer
Side wall offers the T-type card slot for the engaging of water-swellable part on the waterproof protective layer outer wall.
By using above-mentioned technical proposal, the waterproof performance of concrete cover Yu waterproof protective layer junction is improved,
It is further reduced possibility of the Water deep leaching in basement roof and cavity.
In conclusion the advantageous effects of the utility model are as follows:
1. using the waterproof barricade and cavity for extending to basement roof, it can play and reduce backfilling of earthwork amount and prevent
The effect of water area;
2. using gutter, the effect of diversion aproll can be played;
3. using waterproof roll layer, the first sealant, the second sealant, third sealant and water-swellable part, energy
Enough play the effect for improving waterproof performance.
Detailed description of the invention
Fig. 1 is the overall structure diagram of the utility model.
Fig. 2 is the partial enlargement diagram of part A in Fig. 1.
Fig. 3 is the partial enlargement diagram of part B in Fig. 1.
Fig. 4 is the overall structure diagram of the prior art.
In figure, 1, basement roof;2, main structure side plate;3, one layer of balcony slab;4, waterproof barricade;41, waterproof roll
Layer;42, first seal;43, water-swellable part;44, T-type card slot;5, overburden layer;6, cavity;7, gutter;71, concrete
Bed course;72, waterproof slope;73, second seal;74, third sealing element;8, concrete cover;9, waterproof protective layer.
Specific embodiment
The utility model is described in further detail below in conjunction with attached drawing.
It referring to Fig.1, is a kind of waterproof having between the basement roof of earthing and main structure disclosed by the utility model
Structure, including 2, one layers of basement roof 1, main structure side plate balcony slab 3 are provided with waterproof barricade below one layer of balcony slab 3
4, it flushes outside waterproof barricade 4 and one layer of balcony, waterproof barricade 4 is extended downwardly and contradicted with basement roof 1.One layer of balcony
Plate 3, basement roof 1, main structure side plate 2 and waterproof barricade 4 are enclosed cavity 6.It is provided with above basement roof 1
Overburden layer 5 positioned at 4 outside of waterproof barricade.The setting of waterproof barricade 4 greatly facilitates site operation, and reduces returning for the earthwork
The amount of filling out and water repellent area reduce the hidden danger of the leak for generation not in place of constructing, final save the cost.
It referring to Fig.1, is the waterproof performance for improving waterproof barricade 4, the fitting of 4 outer wall of waterproof barricade is fixed with waterproof roll layer
41, waterproof roll layer 41 extends to 1 top of basement roof and is bonded to each other with basement roof 1.To further increase waterproof
The waterproof performance of barricade 4 is fixed with waterproof protective layer 9 in the fitting of 41 lateral wall of waterproof roll layer, and waterproof protective layer 9 is on the one hand right
Waterproof roll layer 41 plays pressing protective effect, causes the possibility of damage when on the other hand reducing backfill to waterproof barricade 4.
Waterproof protective layer 9 is made of waterproof material, such as cement-base infiltration crystallization type sealant;9 bottom wall of waterproof protective layer and underground simultaneously
Junction between ceiling plate 1 is provided with the first seal 42(of clay filleting composition referring to fig. 2), the setting of clay filleting makes
It obtains waterproof protective layer 9 and basement roof 1 generates flexible connection, play better waterproof effect.
Referring to Fig.1, to realize being bonded for waterproof roll layer 41, concrete guarantor is provided with above waterproof roll coiled material layer
Sheath 8, the setting of concrete cover 8 while the waterproof performance for improving basement roof 1 reduce moisture penetration and enter underground
Ceiling plate 1.
Referring to Fig. 2, to realize the close connection between concrete cover 8 and waterproof protective layer 9, in concrete cover
Water-swellable part 43 is provided between waterproof protective layer 9, one end of water-swellable part 43 is embedded in concrete cover 8,
The other end is connected to 9 lateral wall of waterproof protective layer, and the T-type engaged for water-swellable part 43 is offered on 9 outer wall of waterproof protective layer
Card slot 44.
Referring to Fig. 3, for convenience of one layer of balcony slab 3(referring to Fig. 1) outside draining, 5 roof of overburden layer be provided be fitted in it is anti-
The gutter 7 of 4 outer wall of water barricade, 7 bottom wall of gutter are provided with concrete cushion 71, for reduce 7 bottom wall of gutter cracking and
The generation of sedimentation phenomenon.It is provided with the waterproof slope 72 being connected with waterproof barricade 4 above 7 side wall of gutter, is dissipated for realizing diversion
Water function.The junction of 7 side wall of gutter and waterproof barricade 4 is provided with caulking sealing part comprising from top to bottom sets gradually
Second seal 73 and third sealing element 74, second seal 73 be made of Bituminous hemp fiber, third sealing element 74 is by filleting glue
It constitutes, second seal 73 and third sealing element 74 realize the sealing waterproof action at abutment joint jointly, reduce the leakage of moisture
Phenomenon occurs.
The implementation principle of the present embodiment are as follows: anti-between the conventional basement roof 1 for having earthing and main structure side plate 2
Water-bound is close to main structure side plate 2 and is done, but in one layer of 3 lower part of balcony slab of house, since space is smaller, difficulty of construction
Greatly, cause to construct not in place, backfill leakiness, therefore there are the hidden danger of percolating water.The waterproof barricade of one layer of 3 lower section of balcony slab
4 do to outside one layer of balcony slab 3 put down, make between one layer of 3 lower part of balcony slab and basement roof 1 formed cavity 6, significantly facilitate
Site operation, and reduce the backfill amount and water repellent area of the earthwork, reduce the hidden danger of the leak for generation not in place of constructing, most
Whole save the cost.
The embodiment of present embodiment is the preferred embodiment of the utility model, and not limitation is originally practical new according to this
The protection scope of type, therefore: the equivalence changes that all structures, shape, principle according to the utility model are done should all be covered by practical
Within novel protection scope.
Claims (8)
1. a kind of waterproof construction having between the basement roof of earthing and main structure, it is characterised in that: including underground ceiling
Plate (1), main structure side plate (2), one layer of balcony slab (3), one layer of balcony slab (3) lower section are provided with waterproof barricade (4), institute
State the overburden layer (5) being provided on the outside of waterproof barricade (4) above basement roof (1);
The waterproof barricade (4) extends downwardly and contradicts with basement roof (1), one layer of balcony slab (3), basement roof
(1), main structure side plate (2) and waterproof barricade (4) are enclosed cavity (6).
2. the waterproof construction according to claim 1 having between the basement roof of earthing and main structure, feature exist
In: it is flushed outside the waterproof barricade (4) and one layer of balcony.
3. the waterproof construction according to claim 2 having between the basement roof of earthing and main structure, feature exist
The gutter (7) for being fitted in water blocking barricade outer wall is provided in: overburden layer (5) roof.
4. the waterproof construction according to claim 3 having between the basement roof of earthing and main structure, feature exist
In: waterproof barricade (4) the outer wall fitting is fixed with waterproof roll layer (41), and the waterproof roll layer (41) extends straight down
Fitting is fixed on basement roof (1) roof.
5. the waterproof construction according to claim 4 having between the basement roof of earthing and main structure, feature exist
In: it is provided with concrete cover (8) between the overburden layer (5) and basement roof (1), the concrete cover (8)
Setting is above waterproof roll layer (41);
Waterproof protective layer (9) are provided on the outside of the waterproof roll layer (41).
6. the waterproof construction according to claim 5 having between the basement roof of earthing and main structure, feature exist
In: the junction of waterproof protective layer (9) bottom wall and basement roof (1) is provided with first seal (42).
7. the waterproof construction according to claim 3 having between the basement roof of earthing and main structure, feature exist
In: gutter (7) bottom wall is provided with concrete cushion (71), and gutter (7) side wall is connect with waterproof protective layer (9)
Place is from top to bottom disposed with waterproof slope (72), second seal (73) and third sealing element (74).
8. the waterproof construction according to claim 6 having between the basement roof of earthing and main structure, feature exist
In: the junction of waterproof protective layer (9) side wall and concrete cover (8) is provided with water-swellable part (43), the chance
One end of water expansion piece (43) is embedded in concrete cover (8), and the other end is connected to waterproof protective layer (9) lateral wall, institute
State the T-type card slot (44) offered on waterproof protective layer (9) outer wall for water-swellable part (43) engaging.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821814273.XU CN209585131U (en) | 2018-11-03 | 2018-11-03 | There is the waterproof construction between the basement roof of earthing and main structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821814273.XU CN209585131U (en) | 2018-11-03 | 2018-11-03 | There is the waterproof construction between the basement roof of earthing and main structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209585131U true CN209585131U (en) | 2019-11-05 |
Family
ID=68376187
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821814273.XU Active CN209585131U (en) | 2018-11-03 | 2018-11-03 | There is the waterproof construction between the basement roof of earthing and main structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209585131U (en) |
-
2018
- 2018-11-03 CN CN201821814273.XU patent/CN209585131U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201695408U (en) | Basement baseplate integrating water-proofing and drainage functions | |
CN105421497A (en) | Water-proof construction method for connected nodes of foundation slab and ground wall in composite surround system | |
CN104234089B (en) | The construction method that a kind of basement guarded drainage combines | |
US2050798A (en) | Art of waterproofing building cellar foundation walls | |
CN212641729U (en) | High-strength basement side wall heat-insulation waterproof structure with water guide groove | |
CN202706060U (en) | Waterproof structure for base plate deformation joint with width of 50 mm | |
CN209585131U (en) | There is the waterproof construction between the basement roof of earthing and main structure | |
CN207228173U (en) | A kind of underground project waterproof structure | |
CN211735533U (en) | Waterproof structure of post-cast strip of underground chamber roof | |
CN203716064U (en) | Roadbed sewer convenient for dredging | |
CN216552098U (en) | U-shaped cover plate drainage-prevention combined seepage-prevention structure arranged at deformation joint of basement top plate | |
CN213952157U (en) | Multi-material composite ecological environment-friendly pine pile channel | |
CN204551378U (en) | Seepage-proofing structure of upstream surface layer of rock-fill dam | |
CN212405025U (en) | Rockfill dam with simplified construction partitions | |
CN104372770B (en) | Rubber panel rock-fill dams and construction method thereof | |
CN100370088C (en) | Constructing method for preventing toilet and kitchen from leakage | |
TW451019B (en) | Water-proof and damp-proof method for basement side wall | |
CN203668912U (en) | Structure for embedding drain pipe in concrete | |
CN107882350A (en) | Roofing mending-leakage technique and corresponding roof structure | |
CN209082689U (en) | A kind of waterproof construction between kitchen lavatory at pipe root | |
CN109930703A (en) | A kind of construction technology of toilet warterproof beam | |
CN1074501A (en) | Construction of slope drain in geologically unstable area | |
CN216405508U (en) | Waterproof structure of outer wall of underground building structure | |
CN204081152U (en) | A kind of waterproof construction of metope inner corner trim node | |
CN217001898U (en) | Structure is administered in seepage of duplex arch tunnel |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |