CN209557010U - A kind of full-automatic health trolley of Tunnel Second Lining - Google Patents

A kind of full-automatic health trolley of Tunnel Second Lining Download PDF

Info

Publication number
CN209557010U
CN209557010U CN201821615851.7U CN201821615851U CN209557010U CN 209557010 U CN209557010 U CN 209557010U CN 201821615851 U CN201821615851 U CN 201821615851U CN 209557010 U CN209557010 U CN 209557010U
Authority
CN
China
Prior art keywords
tunnel
water pipe
water
jack
full
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821615851.7U
Other languages
Chinese (zh)
Inventor
王亚雄
孟亚锋
吴定略
肖东辉
王前
谢兼量
李红杰
刘颖彦
王林
高红军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Changda Highway Engineering Co Ltd
Original Assignee
Guangdong Changda Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Changda Highway Engineering Co Ltd filed Critical Guangdong Changda Highway Engineering Co Ltd
Priority to CN201821615851.7U priority Critical patent/CN209557010U/en
Application granted granted Critical
Publication of CN209557010U publication Critical patent/CN209557010U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model discloses a kind of full-automatic health trolley of Tunnel Second Lining, including vehicle frame, idler wheel, motor and water tank are installed on the vehicle frame, water pump is installed in the water tank, the vehicle frame also on fixed bracket and jack are installed, it is equipped on the fixed bracket and arc water pipe similar in tunnel radian, arranged for interval has several water mist showers on the arc water pipe, the arc water pipe is connected by flexible water pipe with the water pump, and the jack connects and the fixed bracket is driven to stretch or to contract to extending out.This is novel by height adjusting system, automatic sprinkler system and automatically walk system, just propped up for tunnel and secondary lining provide it is more efficient, faster, more easily conserve approach.

Description

A kind of full-automatic health trolley of Tunnel Second Lining
Technical field
The utility model relates to tunnel maintenance device, specially a kind of full-automatic health trolley of Tunnel Second Lining.
Background technique
In combined type tunnel lining structure, first layer force structure of the first branch concrete as tunnel-liner will be main The load action of country rock is undertaken, so the size of its intensity will affect the force-bearing situation and stability to tunnel;Secondary lining is mixed Solidifying earth removal guarantees that tunnel permanent stabilization, safety, beauty in operation use are outer, while being also a kind of engineering of tunnel safety deposit Measure.So there should be enough intensity in conclusion propping up at the beginning of tunnel and serving as a contrast concrete with two, meet life requirement again, and The influence factor of concrete strength and durability, in addition to raw material, match ratio etc., there are one important influence factor-coagulations Soil maintenance.After concreting, cannot such as be conserved in time, the cement granules in concrete cannot abundant aquation, be converted into Stable crystalline solid, leads to that sheet occurs in concrete surface or powdery falls off, and influences the intensity of concrete structure.In addition, mixed When solidifying soil not yet has enough intensity, the premature evaporation of moisture can also generate biggish contraction distortion, desciccation crack, shadow occur Ring the durability and globality of concrete.
Currently, in constructing tunnel, just branch and two lining concrete curings mainly use water pipe directly sprinkle water or the progress of fog gun machine Health is influenced by tunnel headroom height and planform, it is more difficult to play the role of health, and due to water pipe water spray water compared with Greatly, hole internal water accumulation is serious, generates interference to in-cavity construction, and in addition hole top is often not achieved in the jetting height of water pipe and fog gun machine, Cause the health effect at the top of hole not reach requirement, directly affects concrete quality, there are security-hidden troubles.
Utility model content
In view of above-mentioned background technique, the utility model provides a kind of full-automatic health trolley of Tunnel Second Lining, leads to Cross height adjusting system, automatic sprinkler system and automatically walk system, just propped up for tunnel and secondary lining provide it is more efficient, faster Victory more easily conserves approach.
A kind of full-automatic health trolley of Tunnel Second Lining, including vehicle frame, be equipped on the vehicle frame idler wheel, motor and Water tank, is equipped with water pump in the water tank, the vehicle frame also on fixed bracket and jack are installed, pacify on the fixed bracket Equipped with arc water pipe similar in tunnel radian, arranged for interval has several water mist showers, the arc on the arc water pipe Water pipe is connected by flexible water pipe with the water pump, the jack connect and drive the fixed bracket to extend out stretch or to Contract.
The fixed bracket includes left support, right support and upper bracket, is led between the left support, right support and upper bracket Telescope support is crossed to be connected;The arc water pipe includes left arc water pipe, right arc water pipe and upper arc water pipe, the left arc water Pipe, right arc water pipe and upper arc water pipe are connected by flexible water pipe with the water pump respectively;The jack includes a left side thousand Jin top, right jack and upper jack, the left jack, right jack and upper jack are separately connected and drive the left branch Frame, right support and upper bracket are stretched or to contract to extending out.
The water tank is equipped with automatic feeding water valve port, the buoy of control water level line is additionally provided in the water tank, by automatic Water inlet valve port connect the height of the water level line in regulating tank with external water source, wherein the volume of the water tank is 60~80L.
The diameter of the idler wheel is 50~80cm, and the power of motor is 1kw/h.
The water mist shower is made of copper material, and the spacing of the two neighboring water mist shower is 20~30cm.
The power of the water pump is 1kw.
The beneficial effects of the utility model are:
1, the utility model is applicable to the first branch and secondary lining concrete curing in different head rooms and wide cut tunnel, While improving concrete curing efficiency, guarantee the intensity and durability of concrete.
2, simple and easy to operate, automatic sprinkler system, automatically walk system are basic to realize full-automation, and health process is not necessarily to Special messenger keeps an eye on, and saves labor cost.
3, structure is simple, easy to maintain, there is preferable promotion prospect.
Detailed description of the invention
Fig. 1 is the structural section schematic diagram of the utility model.
Specific embodiment
The utility model is further detailed with reference to the accompanying drawing.
A kind of full-automatic health trolley of Tunnel Second Lining is installed on the vehicle frame 22 as shown in Figure 1, including vehicle frame 22 There are idler wheel 1, motor 2, installation body frame 7, mounting bracket 15 and water tank, motor 2 to drive idler wheel 1 that vehicle frame 22 is realized automatically It is mobile;The water tank includes central water tank 16 and the left and right water tank 5 positioned at the left and right sides, and left and right water tank 5 is supported by water tank Pedestal 21 is fixed on 22 side of vehicle frame, central water tank 16 and left and right water tank 5 and is connected by aqueduct 18, peace in central water tank 16 Equipped with second level water pump 6-2, level-one water pump 6-1 is installed in left and right water tank 5;The mounting bracket 7 and the also upper peace of mounting bracket 15 Equipped with fixed bracket and jack, the fixed bracket includes left and right bracket 23 and upper bracket 24, and installation body frame 7 is equipped with solid Determine the upper beam 19 of upper bracket 24, is connected between the left and right bracket 23 and upper bracket 24 by telescope support 11;The arc Shape water pipe includes left arc water pipe, right arc water pipe 20 and upper arc water pipe 10, on the left and right bracket 23 and upper bracket 24 Be separately installed with arc water pipe similar in tunnel radian (left arc water pipe, right arc water pipe 20 and upper arc water pipe 10, it is described Arranged for interval has several water mist showers 8, the left arc on left arc water pipe, right arc water pipe 20 and upper arc water pipe 10 Water pipe, right arc water pipe 20 and upper arc water pipe 10 pass through flexible water pipe 13 and high-pressure water pipe 17 and the level-one water pump 6- respectively 1 is connected with second level water pump 6-2;The jack includes left jack, right jack 12 and upper jack 9, left jack, the right side The maximum top loading of jack 12 and upper jack 9 is 1t;The left jack, right jack 12 and upper jack 9 are separately connected And the left support, right support 23 and upper bracket 24 is driven to stretch or to contract to extending out.
The water tank is equipped with automatic feeding water valve port 14, and the buoy 4 of control water level line 3 is additionally provided in the water tank, is passed through Automatic feeding water valve port 14 connect the height of the water level line 3 in regulating tank with external water source, wherein and the volume of the water tank is 60~ 80L。
The diameter of the idler wheel 1 is 50~80cm, and the power of motor 2 is 1kw/h.
The water mist shower 8 is made of copper material, and the spacing of the two neighboring water mist shower 8 is 20~30cm.
The power of the level-one water pump 6-1 and second level water pump 6-2 are 1kw.
Working principle:
1, running fix-automatically walk system.When the power is turned on, motor is started to work, and trolley is moved to work Position;
2, height adjustment.Longitudinal jack and lateral jack are adjusted according to tunnel contour line after the completion of positioning, so that platform 8 20~30cm of apex distance tunnel contour line of vehicle water mist shower.
3, spraying health promotion-automatic sprinkler fire-extinguishing system.After the completion of trolley height adjustment, automatic feeding water valve port 14 open, water into Enter water tank, when buoy is more than maximum water level in water tank, automatic feeding water valve port 14 is closed, and water tank stops plus water;Level-one water pump It starts to work with second level water pump, left arc water pipe, right arc water pipe 20 and upper arc water pipe 10 is introduced the water into, finally by water mist Shower 8 props up at the beginning of being sprayed to tunnel or two serve as a contrast on concrete surfaces.When water level line is lower than lowest water level line in water tank, automatic water inlet valve Mouth is opened, and water tank adds water, realizes uninterrupted automatic spray.
Highway tunnel with large cross section tunneling boring provided by the utility model just props up, two serve as a contrast concrete health trolleys, only needs one man operation, Substantially reduce labor intensity and cost of labor.Water spray automation, maintenance efficiency significantly improve, and the amount of conserving water reduces maintenance The influence sprinkled water to constructing tunnel;Automatically walk, water spray, it is easy to operate, and tunneling boring watering, different parts can conserve Position, maintenance quality are high.
As described above, the only preferred embodiment of the utility model, when cannot be limited with this utility model implementation range, I.e. generally according to simple equivalent changes and modifications made by the utility model claim and novel description, it is new all still to belong to this In the range of type patent covers.

Claims (8)

1. a kind of full-automatic health trolley of Tunnel Second Lining, including vehicle frame, which is characterized in that be equipped with rolling on the vehicle frame Wheel, motor and water tank, are equipped with water pump in the water tank, the vehicle frame also on fixed bracket and jack are installed, it is described Be equipped on fixed bracket with arc water pipe similar in tunnel radian, arranged for interval has several water mists flower on the arc water pipe It spills, the arc water pipe is connected by flexible water pipe with the water pump, and the jack connects and drives the fixed bracket It stretches or to extending out to contract.
2. the full-automatic health trolley of a kind of Tunnel Second Lining according to claim 1, which is characterized in that the fixed branch Frame includes left support, right support and upper bracket, is connected between the left support, right support and upper bracket by telescope support;Institute Stating arc water pipe includes left arc water pipe, right arc water pipe and upper arc water pipe, the left arc water pipe, right arc water pipe and on Arc water pipe is connected by flexible water pipe with the water pump respectively;The jack include left jack, right jack and on Jack, the left jack, right jack and upper jack are separately connected and drive the left support, right support and upper bracket It stretches or to extending out to contract.
3. the full-automatic health trolley of a kind of Tunnel Second Lining according to claim 1, which is characterized in that on the water tank Equipped with automatic feeding water valve port, the buoy of control water level line is additionally provided in the water tank.
4. the full-automatic health trolley of a kind of Tunnel Second Lining according to claim 1, which is characterized in that the water tank Volume is 60~80L.
5. the full-automatic health trolley of a kind of Tunnel Second Lining according to claim 1, which is characterized in that the idler wheel Diameter is 50~80cm.
6. the full-automatic health trolley of a kind of Tunnel Second Lining according to claim 1, which is characterized in that the function of motor Rate is 1kw/h.
7. the full-automatic health trolley of a kind of Tunnel Second Lining according to claim 1, which is characterized in that the water mist flower It spills and is made of copper material, the spacing of the two neighboring water mist shower is 20~30cm.
8. the full-automatic health trolley of a kind of Tunnel Second Lining according to claim 1, which is characterized in that the water pump Power is 1kw.
CN201821615851.7U 2018-09-30 2018-09-30 A kind of full-automatic health trolley of Tunnel Second Lining Active CN209557010U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821615851.7U CN209557010U (en) 2018-09-30 2018-09-30 A kind of full-automatic health trolley of Tunnel Second Lining

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821615851.7U CN209557010U (en) 2018-09-30 2018-09-30 A kind of full-automatic health trolley of Tunnel Second Lining

Publications (1)

Publication Number Publication Date
CN209557010U true CN209557010U (en) 2019-10-29

Family

ID=68297822

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821615851.7U Active CN209557010U (en) 2018-09-30 2018-09-30 A kind of full-automatic health trolley of Tunnel Second Lining

Country Status (1)

Country Link
CN (1) CN209557010U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112282805A (en) * 2020-10-29 2021-01-29 中铁隧道局集团有限公司 Intelligent reinforcing trolley for mine method tunnel

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112282805A (en) * 2020-10-29 2021-01-29 中铁隧道局集团有限公司 Intelligent reinforcing trolley for mine method tunnel

Similar Documents

Publication Publication Date Title
CN107654240A (en) A kind of novel atomizing maintenance trolley
CN105065056B (en) A kind of underground coal mine multi-stage, energy-saving tunnel cleaning device
CN208619125U (en) A kind of tunnel secondary lining concrete curing trolley
CN205714217U (en) Two lining concrete curing trolleys
CN209557010U (en) A kind of full-automatic health trolley of Tunnel Second Lining
CN205277442U (en) A movable automatic spraying system for tunnel concrete maintenance
CN207987052U (en) A kind of Bridge High-pier automatic spray health preserving equipment
CN206916019U (en) A kind of basket-hanging continuous beam automatic spray maintenance of equipment
CN205818122U (en) A kind of high-speed railway large box girder concrete automatic spray curing system
CN108505446A (en) Bridge pier, continuous beam spray maintenance device
CN204690662U (en) A kind of building site atomizing de-dusting apparatus
CN205063284U (en) Watering curing means is decorated to building outer wall
CN206383822U (en) A kind of solar energy sprinkler with reel
CN211342935U (en) A lining concrete watering device for tunnel construction
CN210470578U (en) Novel watering robot
CN211472377U (en) Combined structure for preventing and treating water inrush leakage of hydraulic engineering tunnel
CN205893912U (en) Self -propelled case roof beam spraying maintenance machine
CN207109608U (en) High pier stud spraying health promotion system
CN204921020U (en) Colliery is multistage energy -conserving tunnel belt cleaning device in pit
CN220157246U (en) Water-saving water spray control device for landscaping
CN204126276U (en) Wall of High-building structure automatic spray curing system
CN218278123U (en) Urban garden afforestation water-saving irrigation device
CN206279488U (en) Excavating plant transport routes device for reducing dust
CN217751964U (en) Portable maintenance platform truck in highway beam yard
CN214758383U (en) Special water-saving spray set of afforestation

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant