CN209509022U - A kind of pipe gallery space releasing system improving space utilization rate - Google Patents
A kind of pipe gallery space releasing system improving space utilization rate Download PDFInfo
- Publication number
- CN209509022U CN209509022U CN201822232538.1U CN201822232538U CN209509022U CN 209509022 U CN209509022 U CN 209509022U CN 201822232538 U CN201822232538 U CN 201822232538U CN 209509022 U CN209509022 U CN 209509022U
- Authority
- CN
- China
- Prior art keywords
- pipe gallery
- pipeline
- concrete buttress
- buttress
- cushion block
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
The utility model provides a kind of pipe gallery space releasing system for improving space utilization rate, there is good practical value and promotional value;Its technical solution solved includes pipe gallery, concrete buttress is installed on the bottom plate of pipe gallery, the upper end of concrete buttress offers arc notch, water supply pipeline is installed in the arc notch of concrete buttress, it is interspersed with intermediate water pipeline on concrete buttress, energy consumption cushion block is equipped between water supply pipeline and intermediate water pipeline, the seam areas of pipeline is arranged in energy consumption cushion block, the upper and lower end face of energy consumption cushion block is respectively equipped with arc groove, is equipped with buffer layer in arc groove;The utility model materials are convenient, and low in cost, construction is simple is easy to spread.
Description
Technical field
The utility model belongs to pipe gallery building technology field, more particularly to a kind of synthesis for improving space utilization rate
Piping lane space releasing system.
Background technique
Pipe gallery is also known as common trench, it is the civilian infrastructure for being built in Urban Underground and laying all kinds of utility lines, real
Apply unified planning, design, construction and maintenance.Corridor pipeline will be entered orderly reasonably to be arranged in piping lane, and monitoring and maintenance are set
Mouthful, urban underground space can be rationally utilized, urban road is avoided to excavate repeatedly, monitors pipeline performance state in real time, greatly
Reduce influence of the destruction of life line system to social life.Umbrella of this structure as city lifeline system, due to
Its is with the obvious advantage, and domestic majority city has started to build on a large scale.
Although pipe gallery possesses plurality of advantages, the huge caused cost of its structural style is high, economy is lower
It is still the problem of can not properly settling so far, under especially current sustainable developing environment, all kinds of municipal pipelines enter corridor in succession,
It needs for the pipeline provided pipe position of corridor may be entered, so that the cabin number of piping lane increases, piping lane section increases.
When figure pipe support big in narthex is generally traditional concrete buttress, as the erection support construction of pipeline,
Main function is the displacement for preventing pipeline, and the height by setting up, to ensure normal plumbing.Although traditional concrete branch
Pier has played its due effect, but in the underground structure of this intensive style of pipe gallery, should rationally design piping lane and cut
Face, reasonable Arrangement corridor gut line improve piping lane useful space utilization rate, make as far as possible meeting various types pipeline functional requirement
Under the premise of with environment, strive for that space reasonable utilization rate reaches maximization in corridor.
Therefore, the utility model is directed to this problem, proposes and a kind of integrates Shang Shui, middle water, concrete buttress
Pipe gallery space releasing system combines water supply pipeline, intermediate water pipeline and pipe support, forms a kind of novel hollow coagulation
Native buttress has not only effectively saved piping lane space, and reduces the area of section of concrete buttress, greatlys save material,
Rationally to be offered reference using space in corridor.In addition, if piping lane be it is prefabricated assembled, to improve the prefabricated of pipe gallery have than also
There is important meaning.
Utility model content
For above situation, for the defect for overcoming the prior art, the utility model provides a kind of raising space utilization rate
Pipe gallery space releasing system, construction is simple is easy to spread, there is good practical value and promotional value.
Its technical solution solved includes pipe gallery, and concrete buttress, concrete are equipped on the bottom plate of pipe gallery
The upper end of buttress offers arc notch, and water supply pipeline is equipped in the arc notch of concrete buttress, is worn on concrete buttress
It is inserted with intermediate water pipeline, energy consumption cushion block is equipped between water supply pipeline and intermediate water pipeline, the seam areas of pipeline is arranged in energy consumption cushion block,
The upper and lower end face of energy consumption cushion block is respectively equipped with arc groove, is equipped with buffer layer in arc groove.
The utility model materials are convenient, and low in cost, construction is simple is easy to spread, there is good practical value and popularization
Value.
Detailed description of the invention
Fig. 1 is a kind of three-dimensional structure schematic diagram of piping lane space releasing system of the utility model.
Fig. 2 is the utility model concrete buttress portion is two when being prefabricated structural schematic diagram.
Fig. 3 is a kind of piping lane space releasing system concrete when piping lane is prefabricated pipe gallery that the utility model provides
Standard section 11, bellmouth section 9, the socket section 10 of buttress.
Fig. 4 is the utility model energy consumption cushion block schematic diagram.
Specific embodiment
Specific embodiment of the present utility model is described in further detail below in conjunction with attached drawing.
By Fig. 1-4 it is found that the utility model includes pipe gallery 1, concrete buttress is installed on the bottom plate of pipe gallery 1
2, the upper end of concrete buttress 2 offers arc notch 3, is equipped with water supply pipeline 4 in the arc notch 3 of concrete buttress 2, mixes
It is interspersed with intermediate water pipeline 5 on solidifying soil buttress 2, energy consumption cushion block 6 is equipped between water supply pipeline 4 and intermediate water pipeline 5, energy consumption cushion block 6 is set
The seam areas in pipeline is set, the upper and lower end face of energy consumption cushion block 6 is respectively equipped with arc groove 7, is equipped with buffer layer in arc groove 7
8。
For the ease of the convenience of construction, the concrete buttress 2 is unified in determining in formwork using temporary cushion block
5 position of waterpipe, the temporary cushion block is for temporary support intermediate water pipeline 5 and then completes coupled concrete buttress 2
Pour.
It is to be spliced using sealing ring flexibility, and prevented that the intermediate water pipeline 5 carries out splicing inside concrete buttress 2
Water seepage treatment.
The pipe gallery 1 can be prefabricated component, concrete buttress 2 when prefabricated portion be two, with piping lane it is prefabricated
Concrete buttress 2 together is fixed together by bell and spigot, does water-proofing treatment in interface.
The utility model is when specifically used, in the construction process, while 1 construction of bottom plates of pipe gallery, binds coagulation
The reinforcing bar and formwork of native buttress 2, casting concrete makes an entirety together with bottom plate.
When carrying out 2 formwork of concrete buttress, the position of intermediate water pipeline 5 is uniformly determined first with temporary cushion block, it is ensured that
Inconvenience of constructing because caused by pipeline location is improper is avoided the occurrence of in installation process.Pipeline splicing is carried out inside concrete buttress 2
The splicing of Shi Caiyong sealing ring flexibility, and carry out water-impervious processing.Water supply pipeline 4 and middle water pipe among two concrete buttress 2
Setting energy consumption cushion block 6, which avoids pipeline from colliding, between road 5 causes seam crossing to be staggered.
If piping lane is prefabricated pipe gallery 1, determine that intermediate water pipeline 5 highly carries out assembling reinforcement formwork, with piping lane bottom plate
It pours jointly.Buttress 2 is divided into two when prefabricated, bellmouth section 9, socket section 10 such as Fig. 3 concrete buttress 2, spells to piping lane
When connecing completion, buttress 2 also completes splicing.Using waterproof measure identical when being closed with piping lane at 2 closure of buttress.
The utility model has the following beneficial effects:
1, the utility model is the hole-opening in concrete buttress 2, and intermediate water pipeline 5 is placed wherein, collectively as top
The support of water supply pipeline 4 integrates 1 space releasing system of pipe gallery of Shang Shui, middle water, concrete buttress 2, improves pipe
Corridor useful space utilization rate.
2, the utility model is not only suitable for cast-in-place pipe gallery 1, and is suitable for the pipe gallery 1 of prefabrication and assembly construction;Buttress 2
It is prefabricated together with concrete segment, increase the globality of piping lane, while increasing the prefabricated ratio of concrete.
The utility model materials are convenient, and low in cost, construction is simple is easy to spread, there is good practical value and popularization
Value.
Claims (4)
1. a kind of pipe gallery space releasing system for improving space utilization rate, including pipe gallery (1), which is characterized in that comprehensive
It closes and is equipped with concrete buttress (2) on the bottom plate of piping lane (1), the upper end of concrete buttress (2) offers arc notch (3), mixes
It is equipped with water supply pipeline (4) in the arc notch (3) of solidifying soil buttress (2), intermediate water pipeline (5) is interspersed on concrete buttress (2),
Energy consumption cushion block (6) is equipped between water supply pipeline (4) and intermediate water pipeline (5), the seam areas of pipeline is arranged in energy consumption cushion block (6),
The upper and lower end face of energy consumption cushion block (6) is respectively equipped with arc groove (7), is equipped with buffer layer (8) in arc groove (7).
2. a kind of pipe gallery space releasing system for improving space utilization rate according to claim 1, which is characterized in that
The concrete buttress (2) uniformly determines intermediate water pipeline (5) position, the interim pad in formwork, using temporary cushion block
Block is for temporary support intermediate water pipeline (5) and then completes pouring for coupled concrete buttress (2).
3. a kind of pipe gallery space releasing system for improving space utilization rate according to claim 1, which is characterized in that
It is to be spliced using sealing ring flexibility, and carry out water-impervious that the intermediate water pipeline (5) carries out splicing inside concrete buttress (2)
Processing.
4. a kind of pipe gallery space releasing system for improving space utilization rate according to claim 1, which is characterized in that
The pipe gallery (1) can be prefabricated component, and concrete buttress (2) portion when prefabricated is two, prefabricated together with piping lane
Concrete buttress (2) be fixed together by bell and spigot, do water-proofing treatment in interface.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201822232538.1U CN209509022U (en) | 2018-12-28 | 2018-12-28 | A kind of pipe gallery space releasing system improving space utilization rate |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201822232538.1U CN209509022U (en) | 2018-12-28 | 2018-12-28 | A kind of pipe gallery space releasing system improving space utilization rate |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209509022U true CN209509022U (en) | 2019-10-18 |
Family
ID=68198055
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201822232538.1U Active CN209509022U (en) | 2018-12-28 | 2018-12-28 | A kind of pipe gallery space releasing system improving space utilization rate |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209509022U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113863366A (en) * | 2021-09-14 | 2021-12-31 | 北京市水利规划设计研究院 | Piping lane pipeline arrangement structure |
-
2018
- 2018-12-28 CN CN201822232538.1U patent/CN209509022U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113863366A (en) * | 2021-09-14 | 2021-12-31 | 北京市水利规划设计研究院 | Piping lane pipeline arrangement structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206052779U (en) | A kind of prefabricated pipe gallery splicing structure | |
CN103205979B (en) | Method for constructing large raft foundation under high temperature | |
CN206376276U (en) | A kind of prefabricated pipe gallery | |
CN207348091U (en) | A kind of assembled pipe gallery | |
CN106284412B (en) | A kind of prefabricated pipe gallery and construction method | |
CN108915734A (en) | A kind of corrugated steel-Combined concrete supporting construction and its construction method | |
CN205530344U (en) | Utility tunnel is pour to split type no mould | |
WO2017071113A1 (en) | Cement-soil mixing pile protected underground pipe gallery | |
CN205617426U (en) | Cast -in -place bottom plate of utility tunnel and prefabricated outer panel connection structure | |
CN207998860U (en) | A kind of assembled pipe gallery | |
CN207498985U (en) | A kind of partial precast assembly steel concrete combination underground pipe gallery for exempting from template | |
CN106381886A (en) | Partially-prefabricated assembled steel and concrete combined utility tunnel | |
CN209509022U (en) | A kind of pipe gallery space releasing system improving space utilization rate | |
CN208380578U (en) | Precast construction in a kind of roads and tunnels | |
CN204151825U (en) | Super-section prestressing force Urban Underground pipe gallery | |
CN205894103U (en) | Prefabricated parabola type utility tunnel | |
CN202247719U (en) | Corresponding corrugated pre-stressed anti-sedimentation culvert pipe for bridge | |
CN205369320U (en) | Basement post -cast strip leakage protective system | |
CN105926665A (en) | Large block assembled type prefabricated concrete drainage pipeline base and construction method thereof | |
CN204491663U (en) | Prestressed structure function formula underground pipe gallery combined system | |
CN202252422U (en) | Multifunctional pre-stress underground draining integrated pipeline of city | |
CN202324155U (en) | Adjustable corrugated prestress anti-pollution drainage culvert | |
CN106088758B (en) | A kind of bilayer assembled underground granary | |
CN204491662U (en) | Abnormity resistance to compression prestressed structure function formula underground pipe gallery | |
CN105887925A (en) | Comprehensive pipe rack of corrugated circular tube structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |