CN209469888U - A kind of super-section assembled air hose - Google Patents
A kind of super-section assembled air hose Download PDFInfo
- Publication number
- CN209469888U CN209469888U CN201920167328.0U CN201920167328U CN209469888U CN 209469888 U CN209469888 U CN 209469888U CN 201920167328 U CN201920167328 U CN 201920167328U CN 209469888 U CN209469888 U CN 209469888U
- Authority
- CN
- China
- Prior art keywords
- air hose
- super
- wind pipe
- pipe wall
- plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
Abstract
The utility model discloses a kind of super-section assembled air hose, including 4 pieces of wind pipe walls, wind pipe wall are steel plate, and the wind pipe wall length direction first and last end is respectively in-flanges and flanging, is connected between wind pipe wall by in-flanges and flanging.It is difficult to install that the utility model can solve the problems, such as that super-section air hose causes since construction site and transport channel are limited, and welding process can generate volume of smoke pollution environment, while avoiding super-section air hose when installing because self gravity leads to bending.
Description
Technical field
The utility model relates to a kind of super-section assembled air hoses, belong to construction site air hose mounting technique field.
Background technique
With the development of science and technology, easy, regularization become modern construction technological operation and have to the spy considered
Sign.At the construction field (site), how to become the important leverage of engineering construction progress according to the faster and better construction of process.Due to traditional
Air duct flange is live splicing mostly, and processing is installed on the spot after being welded.And the air hose of super-section, because of construction site and transport
Channel is limited, causes difficult to install.Secondly, site welding is processed, air hose surfacing will affect, while generating a large amount of flue dust
Nuisance generates pollution to environment, does not meet low-carbon, green construction.
Utility model content
Technical problem to be solved by the utility model is: providing a kind of super-section assembled air hose, cut with solving super large
For face air hose since the limited problem of construction site and transport channel causes difficult to install, welding process can generate volume of smoke pollution
The problems such as environment.
The technical solution of the utility model is: a kind of super-section assembled air hose, including 4 pieces of wind pipe walls, wind pipe wall are
Steel plate, the wind pipe wall width direction first and last end are respectively in-flanges and flanging, pass through in-flanges between wind pipe wall and turn up
While being connected.
The super-section assembled air hose head and end be equipped with flange, flange include 4 angle steel, angle steel it is one of
Plate is bolted to connection in wind pipe wall outer surface edge.
The super-section assembled air hose further includes L-type connecting plate, and one block of plate in L-type connecting plate is close to and passes through spiral shell
Bolt is fixedly connected on angle steel in the horizontal direction, and another block of plate in L-type connecting plate is close to and is bolted to connection vertical
On the angle steel of direction.
The super-section assembled air hose further includes strong steel plate, and reinforcing steel plate includes one block of horizontal direction steel plate and one piece
Vertical direction steel plate, the middle part for being fixedly connected with the wide one side of steel plate in the horizontal direction on one side in vertical direction steel plate width direction,
Reinforce steel plate horizontal direction steel plate to be bolted to connection in the middle part of wind pipe wall length direction.
The super-section assembled air duct flange further includes X-type bearing diagonal, and X-type bearing diagonal is made of two supports, and two
Root support is separately connected four pieces of wind pipe wall inner surfaces facing each other, and two support infalls are bolted, two supports
For angle steel.
Connecting component is equipped between the support and wind pipe wall, connecting component is angle steel, and one block of plate of connecting component is close to
Wind pipe wall is simultaneously bolted to connection, and another block of plate of connecting component is bolted in support.
The utility model also provides a kind of construction method of super-section assembled air hose, comprising the following steps:
S1, reinforcement steel plate is aligned with bolt hole in the middle part of wind pipe wall, is anchored, can be played using bolt and wind pipe wall
The outer support of single side air hose acts on;
S2, the bolt on angle steel is aligned with air hose end bolt hole, is anchored using bolt and wind pipe wall, formed single
Face air duct flange;
S3,4 pieces of wind pipe walls are spliced by in-flanges and flanging head and the tail occlusion,
S4, the two boards that L-type connects are respectively fixedly connected on two pieces of adjacent wind pipe walls by bolt;
S5, reinforce steel plate end joint using steel plate structure glue sticking;
S6, the connecting component wind pipe wall on X-type bearing diagonal is bolted and fixed, single-unit air hose is consequently formed;
S7, splice between air hose section using lifting equipment, sealing is filled between the flange that air hose section connects with air hose
Filler;
S8, it is done at sealing at the bolt that air hose flanging and in-flanges junction, flange, support and wind pipe wall connect
Reason.
The beneficial effects of the utility model are: compared with prior art, the utility model is carried out by fabricated mode
Air hose installation, can effectively solve the environment that inconvenient super-section air hose transport, narrow field processing difficulties and welding generate influences
The problem of.Additionally, due to the sequence for carrying out the splicing of air hose section after first progress single side wind pipe wall, support, flange are installed is used, keep away
Exempt to cause because supporting after first processing wind pipe wall wind pipe wall because of self gravity caused by be bent the problem of.The utility model is being installed
Fast installation can be realized under the premise of guaranteeing bonding strength in the process, saves time and cost.Overall structure is simple, installation side
Just speed is fast, and installation process will not generate dust polluting environment, is particularly suitable for using in the installation of super-section air hose.
Detailed description of the invention
Fig. 1 is the perspective view of the utility model;
Fig. 2 is enlarged drawing at Fig. 1 G of the utility model;
Fig. 3 is that the utility model reinforces steel plate structure schematic diagram;
Fig. 4 is the utility model L-type connecting board structure schematic diagram;
Fig. 5 is the utility model L-type steel plate connecting-piece structure schematic diagram;
In attached drawing, steel plate, 3 flanges, 301 angle steel, 302 L-type connecting plates, 4 X-type bearing diagonals, 401 are reinforced in 1 wind pipe wall, 2
Support, 402 connecting components.
Specific embodiment
With reference to the accompanying drawing and utility model is described further in specific embodiment:
As shown in Fig. 1 to 5, a kind of super-section assembled air hose, including 4 pieces of wind pipe walls 1, wind pipe wall 1 is steel plate, described
1 length direction first and last end of wind pipe wall is respectively in-flanges and flanging, is connected between wind pipe wall 1 by in-flanges and flanging occlusion
It connects.When installation, the in-flanges of two pieces of wind pipe walls 1 and flanging are mutually inserted from 1 width direction of wind pipe wall and are interlocked, according to
It is secondary that 4 pieces of wind pipe walls 1 are joined together to form air hose section according to this method.4 pieces of wind pipe walls 1 are passed through into interior flanging occlusion peace
Dress, the environment that can effectively solve the problems, such as that inconvenient super-section air hose transport, narrow field processing difficulties and welding generate influence.
The super-section assembled air hose head and end is equipped with flange 3, and flange 3 includes 4 angle steel 301, angle steel 301
One of plate is bolted to connection in 1 outer surface edge of wind pipe wall.In use, the flange 3 of two air hoses is passed through spiral shell
It tethering and connects an available longer air hose, flange 3 may make super-section assembled duct length that can freely customize, and
Flange 3 is to be bolted, and does not use welding procedure, assembly is more convenient, also more environmentally-friendly.
The super-section assembled air hose further includes L-type connecting plate 302, and one block of plate in L-type connecting plate 302 is close to simultaneously
It is bolted to connection on angle steel 302 in the horizontal direction, another block of plate in L-type connecting plate 302 is close to and is consolidated by bolt
Surely it is connected on vertical direction angle steel 301.L-type connecting plate 302 plays the role of the connection reinforced between wind pipe wall 1, so that wind
The connection of tube wall 1 is firmer.
The super-section assembled air hose further includes strong steel plate 2, and reinforcing steel plate 2 includes two blocks of horizontal direction steel plates and one
Block vertical direction steel plate, vertical direction steel plate width direction are fixedly connected on one side in the wide one side of steel plate in the horizontal direction
Portion reinforces 2 horizontal direction steel plate of steel plate and is bolted to connection in the middle part of 1 length direction of wind pipe wall.Since super-section fills
Bore with formula air hose is quite huge, and 1 width of wind pipe wall is also comparatively wide, is easy to generate shape under gravity or ambient pressure
Become, the ability of anti-deformation of 1 width direction of wind pipe wall can be increased by reinforcing steel plate 2.
The super-section assembled air duct flange further includes X-type bearing diagonal 4, and X-type bearing diagonal 4 supports 401 groups by two
At two supports 401 are separately connected four pieces of 1 inner surfaces of wind pipe wall facing each other, and two 401 infalls of support are connected by bolt
It connects, two supports 401 are angle steel.Since the bore of big section assembling air hose is quite huge, under the effect of gravity wind pipe wall by
It is easy to generate deformation in itself huge gravity, X-type diagonal brace 4 is supported as air hose, and lateral 401 both ends of support pass through respectively
Two pieces of wind pipe walls, 1 inside of the connections such as bolt transverse direction, longitudinal support 401 are fixedly connected on by bolt etc. two pieces longitudinal respectively
1 inside of wind pipe wall.When two pieces of wind pipe walls 1 in transverse direction are due to being made air hose by the compressing of self gravity and top wind pipe wall 1
When section changes from rectangle to parallelogram, since two 401 middle parts of support are bolted to connection, 4 pieces of 1 Hes of wind pipe wall
4 small 4 side shapes are constituted between 2 supports, are formed relative to the wind pipe wall 1 for being fitted without X-type bearing diagonal 401 big by parallel four
Side shape, structure is more firm to be unlikely to deform, and can effectively solve the problems, such as that super-section air hose deforms.
Connecting component 402 is equipped between the X-type bearing diagonal 4 and wind pipe wall 1, connecting component 402 is angle steel, connecting component
402 one block of plate is close to wind pipe wall and is bolted to connection, and the another of connecting component 402 is bolted in X-type bearing diagonal 4
One block of plate.It can realize that support 401 is more convenient more easily using wind pipe wall 1 is bolted by connecting component 402
Installation.
The utility model also provides a kind of construction method of super-section assembled air hose, comprising the following steps:
S1, reinforcement steel plate 2 is aligned with 1 middle part bolt hole of wind pipe wall, is anchored using bolt and wind pipe wall, Ke Yiqi
Outer support to single side air hose acts on;
S2, the bolt on angle steel 301 is aligned with air hose end bolt hole, is anchored using bolt and wind pipe wall 1, shape
At single side air duct flange 3;
S3,4 pieces of wind pipe walls 1 are spliced by in-flanges and flanging head and the tail occlusion,
S4, the two boards of L-type connection 302 are respectively fixedly connected on two pieces of adjacent wind pipe walls 1 by bolt;
S5, reinforce 2 end joint of steel plate using steel plate structure glue sticking;
S6,402 wind pipe wall of connecting component on X-type bearing diagonal 4 is bolted and fixed, single-unit wind is consequently formed
Pipe;
S7, splice between air hose section using lifting equipment, sealing is filled between the flange 3 that air hose section connects with air hose
Filler;
S8, done at the bolts that air hose flanging and in-flanges junction, flange 3, support 401 are connect with wind pipe wall 1 it is close
Envelope processing.
Above-mentioned air hose construction procedure, step S1 first using the reinforcing wind pipe wall 1 of steel plate 2 is reinforced, make wind pipe wall 1 in installation process
In be not easy to deform;Step S5 reinforces 2 end of steel plate using structure glue sticking, so that even if the bolt reinforced on steel plate 2 slips,
Reinforcing steel plate 2 can also lean on the bonding of structure glue to play the role of reinforcing wind pipe wall 1;Step S7 and S8 carry out close after finishing assembly
Envelope processing, can be to avoid in an assembling process to the damage of sealing filler.
It, cannot the above content is specific preferred embodiment further detailed description of the utility model is combined
Assert that the specific implementation of the utility model is only limited to these instructions.For the ordinary skill of the utility model technical field
For personnel, without departing from the concept of the premise utility, a number of simple deductions or replacements can also be made, should all regard
To belong to the protection scope of the utility model.
Claims (6)
1. a kind of super-section assembled air hose, including 4 pieces of wind pipe walls (1), wind pipe wall (1) is steel plate, it is characterised in that: described
Wind pipe wall (1) width direction first and last end is respectively in-flanges and flanging, and wind pipe wall is stung between (1) by in-flanges and flanging
Close connection.
2. super-section assembled air hose according to claim 1, it is characterised in that: the super-section assembled air hose
Head and end is equipped with flange (3), and flange (3) includes 4 angle steel (301), and one of plate of angle steel (301) is bolted
It is connected to wind pipe wall (1) outer surface edge.
3. super-section assembled air hose according to claim 2, it is characterised in that: the super-section assembled air hose
It further include L-type connecting plate (302), one block of plate in L-type connecting plate (302) is close to and is bolted to connection in the horizontal direction
On angle steel (301), another block of plate in L-type connecting plate (302) is close to and is bolted to connection in vertical direction angle steel
(301) on.
4. super-section assembled air hose according to claim 3, it is characterised in that: the super-section assembled air hose
It further include strong steel plate (2), reinforcing steel plate (2) includes one block of horizontal direction steel plate and one block of vertical direction steel plate, vertical direction steel
Steel plate (2) horizontal direction steel plate is reinforced at the middle part for being fixedly connected with the wide one side of steel plate in the horizontal direction on one side in board width direction
It is bolted to connection in the middle part of wind pipe wall (1) length direction.
5. super-section assembled air hose according to claim 4, it is characterised in that: the super-section assembled air hose
Flange further includes X-type bearing diagonal (4), and X-type bearing diagonal (4) is made of two supports (401), and two supports (401) are separately connected
Four pieces of wind pipe wall (1) inner surfaces facing each other, two support (401) infalls are bolted, and two supports (401) are
Angle steel.
6. super-section assembled air hose according to claim 5, it is characterised in that: the X-type bearing diagonal (4) and air hose
Connecting component (402) are equipped between wall (1), connecting component (402) is angle steel, and one block of plate of connecting component (402) is close to air hose
Wall is simultaneously bolted to connection, and another block of plate of connecting component (402) is bolted in support (401).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920167328.0U CN209469888U (en) | 2019-01-30 | 2019-01-30 | A kind of super-section assembled air hose |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920167328.0U CN209469888U (en) | 2019-01-30 | 2019-01-30 | A kind of super-section assembled air hose |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209469888U true CN209469888U (en) | 2019-10-08 |
Family
ID=68094380
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201920167328.0U Active CN209469888U (en) | 2019-01-30 | 2019-01-30 | A kind of super-section assembled air hose |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209469888U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109538838A (en) * | 2019-01-30 | 2019-03-29 | 中铁五局集团建筑工程有限责任公司 | A kind of super-section assembled air hose and construction method |
CN110848503A (en) * | 2019-11-29 | 2020-02-28 | 徐州华显凯星信息科技有限公司 | Board-sharing flange ventilation pipe additional strengthening |
-
2019
- 2019-01-30 CN CN201920167328.0U patent/CN209469888U/en active Active
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109538838A (en) * | 2019-01-30 | 2019-03-29 | 中铁五局集团建筑工程有限责任公司 | A kind of super-section assembled air hose and construction method |
CN110848503A (en) * | 2019-11-29 | 2020-02-28 | 徐州华显凯星信息科技有限公司 | Board-sharing flange ventilation pipe additional strengthening |
CN110848503B (en) * | 2019-11-29 | 2021-12-28 | 徐州华显凯星信息科技有限公司 | Board-sharing flange ventilation pipe additional strengthening |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109538838A (en) | A kind of super-section assembled air hose and construction method | |
CN209469888U (en) | A kind of super-section assembled air hose | |
CN101298768A (en) | Arrangement of multiple sheet pile components and welding profile therefor | |
CN104500095B (en) | Class rectangular shield duct piece connector structure | |
CN107447858A (en) | PC fabricated construction dry type column foot connecting structures | |
CN109339250A (en) | Joint strengthening type steel-pipe assembly concrete connecting structure and its construction method | |
CN205329858U (en) | Pre -buried muscle positioner of cast -in -place layer or prefabricated wallboard and connection structure thereof | |
CN202899640U (en) | Collar flitch reinforced steel pipe joint | |
CN218969809U (en) | Quick assembled closed box culvert structure | |
CN106703831A (en) | Method for assembling segments of shield tunnels with internal water pressures | |
CN107893480A (en) | A kind of assembled connecting node of lattice beam and post | |
CN206681017U (en) | A kind of steel pipe support tie-rod | |
CN213900232U (en) | Vertical ventilation pipe for installation in narrow ventilation shaft | |
CN205531363U (en) | Auxiliary device pours in core section of thick bamboo beam column steel -pipe column | |
CN207597591U (en) | A kind of assembled connecting node of lattice beam and column | |
CN206363731U (en) | Billboard | |
CN107152026B (en) | A kind of the mud jacking pipe support and its distribution method of steel-pipe pile | |
CN206829355U (en) | A kind of crossbeam of cross wall plate and the attachment structure of pillar | |
CN207436545U (en) | A kind of pin-connected panel building hoist returns back to top device | |
CN201296995Y (en) | Combined connecting structure of corrugated steel web plate in box beam bridge | |
CN220013994U (en) | Building steel structure with reinforced joint | |
CN205976151U (en) | Side fascia installation node | |
CN105544764B (en) | Big axle power buckling restrained brace and connection node device and its installation method | |
CN205976141U (en) | Side fascia installation node | |
CN205531018U (en) | Steel -pipe column welding is with supporting protective structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |