CN106703831A - Method for assembling segments of shield tunnels with internal water pressures - Google Patents

Method for assembling segments of shield tunnels with internal water pressures Download PDF

Info

Publication number
CN106703831A
CN106703831A CN201611083361.2A CN201611083361A CN106703831A CN 106703831 A CN106703831 A CN 106703831A CN 201611083361 A CN201611083361 A CN 201611083361A CN 106703831 A CN106703831 A CN 106703831A
Authority
CN
China
Prior art keywords
hydraulic pressure
anchor
anchor slab
shield tunnel
jurisdiction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611083361.2A
Other languages
Chinese (zh)
Inventor
温竹茵
孙巍
官林星
沈奕
侯剑锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Original Assignee
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Municipal Engineering Design Insitute Group Co Ltd filed Critical Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority to CN201611083361.2A priority Critical patent/CN106703831A/en
Publication of CN106703831A publication Critical patent/CN106703831A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • E21D11/083Methods or devices for joining adjacent concrete segments

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a method for assembling segments of shield tunnels with internal water pressures. The method is implemented by the aid of a pair of connector embedded components. The connector embedded components comprise anchor plates and a plurality of connecting anchor bars, and the connecting anchor bars are perpendicularly distributed on the outer sides of the anchor plates. The method includes steps of S1, symmetrically arranging the pair of connector embedded components, connecting one of the connecting anchor bars with one segment and connecting another connecting anchor bar with another segment; S2, connecting the two anchor plates to completely assemble the two corresponding segments. The method has the advantages that the integral strength and rigidity of connectors of the tunnels can be improved, and adverse load impact due to the internal water pressures born on the water delivery, water storage and water drainage tunnels and the like can be resisted.

Description

A kind of pipe sheet assembling method for the shield tunnel for having interior hydraulic pressure
Technical field
The present invention relates to pipe sheet assembling method, more particularly to a kind of pipe sheet assembling side for the shield tunnel for having interior hydraulic pressure Method.
Background technology
At present, during optimization water source supply and propulsion sponge city, the water delivery of China's shield construction, water storage, Outlet tunnel is more and more, based on use armored concrete prefabricated pipe section.Traditional shield tunnel joint is with straight bolt or tiltedly The method that bolt butt joint is directly attached is not particularly suited for the tunnel joint of interior influence of hydraulic pressure.To reduce interior hydraulic pressure to tunnel The influence of road structure, frequently with double-deck lining cutting, but the construction period is long and high cost.
The content of the invention
It is an object of the invention to provide a kind of pipe sheet assembling method for the shield tunnel for having interior hydraulic pressure, improve tunnel and connect The bulk strength and rigidity of head, resist the unfavorable load influence that the suffered interior hydraulic pressure such as water delivery, water storage, outlet tunnel brings.
In order to realize the above object the present invention is achieved by the following technical solutions:
A kind of pipe sheet assembling method for the shield tunnel for having interior hydraulic pressure, it utilizes a pair of joint built-in fitting, described joint Built-in fitting is included:Anchor slab, vertical distribution are characterized in several connection dowels in the outside of anchor slab, comprise the following steps:
S1, a pair of joint built-in fitting is symmetrical arranged, and the connection dowel described in one of them is connected with one piece of section of jurisdiction, another institute The connection dowel stated is connected with another piece of section of jurisdiction;
S2, the anchor slab of connect setting two completes two pieces of assembly of section of jurisdiction.
Two anchor slabs are symmetrical arranged in described step S1.
It is specially in described step S2:Several bolts hole are offered in anchor slab, by bolt passing through bolt hole, makes one Anchor slab is connected.
Described connection dowel is connected by bearing with anchor slab.
The thickness of described anchor slab determines according to its distribution of force.
Also included before described step S1:In the process segment, joint built-in fitting is fixed on section of jurisdiction hand hole location.
The present invention compared with prior art, with advantages below:
1st, the bulk strength and rigidity of tunnel joint can be improved, the suffered interior hydraulic pressure such as water delivery, water storage, outlet tunnel is resisted and is brought Unfavorable load influence.
2nd, it is special based on the shield tunnel stress by interior influence of hydraulic pressure from the angle for improving duct piece connector stress performance Point, it is proposed that this is this kind of to can be used for the joint pre-embedded device of single shell lining.
3rd, poured using cast iron, quickly and easily carry out reinforced concrete segment connecting between block, so as to obtain height The assembled shield tunnel ring of quality.
Brief description of the drawings
Fig. 1 is inventive joint built-in fitting elevation;
Fig. 2 is inventive joint built-in fitting side view;
The anchor ring location drawing of Fig. 3 joint built-in fittings in section of jurisdiction;
Cross-section location figure of Fig. 4 joint built-in fittings in section of jurisdiction;
Fig. 5 is used for the installation diagram of the shield tunnel piecing devices for having interior hydraulic pressure.
Specific embodiment
Below in conjunction with accompanying drawing, by describing a preferably specific embodiment in detail, the present invention is further elaborated.
As shown in Figure 1, 2, a kind of shield tunnel piecing devices for there is interior hydraulic pressure, for connecting section of jurisdiction 1, joint dress Put comprising a pair of joint built-in fitting 2, the joint built-in fitting 2 described in each is included:Anchor slab 21;Several connection dowels 22, it hangs down The straight outside for being distributed in anchor slab 21;Connection dowel 22 described in one of them is connected with one piece of section of jurisdiction 1, the connection described in another Dowel 22 is connected with another piece of section of jurisdiction 1, the anchor slab 21 of connect setting two so that two pieces of sections of jurisdiction 1 complete assembly.
Each anchor slab 21 offers several bolts hole 211, and according to the actual requirements, the present invention uses four bolts hole. Anchor slab 21 described in each pair is symmetrical arranged, and passes through bolt hole 211 by four bolts 212, a pair of anchor slabs 21 is connected.It is described Connection dowel 22 be connected with anchor slab 21 by bearing 23.The thickness of described anchor slab 21 determines according to its distribution of force.
As shown in figure 3, in the component process segment, joint built-in fitting 2 is anchored near section of jurisdiction hand hole 11.Fig. 4 gives and connects Position of the head built-in fitting in the cross section of section of jurisdiction 1,2 built-in fittings are used per endless tube piece 1.The ring assembly stage in section of jurisdiction, such as Fig. 5 institutes Show, bolt can be pierced into by embedded part bolt hole by artificial or equipment and nut is tightened into completion assembly again.
As shown in Fig. 1 ~ 5, a kind of pipe sheet assembling method for the shield tunnel for having interior hydraulic pressure, it utilizes a pair of joint pre- Embedded part, described joint built-in fitting is included:Anchor slab, vertical distribution the outside of anchor slab several connection dowels, comprising as follows Step:
S1, a pair of joint built-in fitting is symmetrical arranged, and the connection dowel described in one of them is connected with one piece of section of jurisdiction, another institute The connection dowel stated is connected with another piece of section of jurisdiction;
S2, the anchor slab of connect setting two completes two pieces of assembly of section of jurisdiction.
Two anchor slabs are symmetrical arranged in described step S1.
It is specially in described step S2:Several bolts hole are offered in anchor slab, by bolt passing through bolt hole, makes one Anchor slab is connected.
Described connection dowel is connected by bearing with anchor slab.
The thickness of described anchor slab determines according to its distribution of force.
Also included before described step S1:In the process segment, joint built-in fitting is fixed on section of jurisdiction hand hole location.
In sum, a kind of pipe sheet assembling method for the shield tunnel for having interior hydraulic pressure of the invention, improves tunnel joint Bulk strength and rigidity, resisting the unfavorable load that the suffered interior hydraulic pressure such as water delivery, water storage, outlet tunnel brings influences.
Although present disclosure is discussed in detail by above preferred embodiment, but it should be appreciated that above-mentioned Description is not considered as limitation of the present invention.After those skilled in the art have read the above, for of the invention Various modifications and substitutions all will be apparent.Therefore, protection scope of the present invention should be limited to the appended claims.

Claims (6)

1. a kind of pipe sheet assembling method for the shield tunnel for having interior hydraulic pressure, it utilizes a pair of joint built-in fitting, and described connects Head built-in fitting is included:Several connection dowels of anchor slab, vertical distribution in the outside of anchor slab, it is characterised in that comprising following step Suddenly:
S1, a pair of joint built-in fitting is symmetrical arranged, and the connection dowel described in one of them is connected with one piece of section of jurisdiction, another institute The connection dowel stated is connected with another piece of section of jurisdiction;
S2, the anchor slab of connect setting two completes two pieces of assembly of section of jurisdiction.
2. as claimed in claim 1 for the pipe sheet assembling method of the shield tunnel for having interior hydraulic pressure, it is characterised in that described Two anchor slabs are symmetrical arranged in step S1.
3. as claimed in claim 2 for the pipe sheet assembling method of the shield tunnel for having interior hydraulic pressure, it is characterised in that described It is specially in step S2:Several bolts hole are offered in anchor slab, by bolt passing through bolt hole, a pair of anchor slabs is connected.
4. as claimed in claim 1 for the pipe sheet assembling method of the shield tunnel for having interior hydraulic pressure, it is characterised in that described Connection dowel is connected by bearing with anchor slab.
5. as claimed in claim 1 for the pipe sheet assembling method of the shield tunnel for having interior hydraulic pressure, it is characterised in that described The thickness of anchor slab determines according to its distribution of force.
6. the pipe sheet assembling method for the shield tunnel for having interior hydraulic pressure as described in claim any one of 1-5, its feature exists In also being included before described step S1:In the process segment, joint built-in fitting is fixed on section of jurisdiction hand hole location.
CN201611083361.2A 2016-11-30 2016-11-30 Method for assembling segments of shield tunnels with internal water pressures Pending CN106703831A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611083361.2A CN106703831A (en) 2016-11-30 2016-11-30 Method for assembling segments of shield tunnels with internal water pressures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611083361.2A CN106703831A (en) 2016-11-30 2016-11-30 Method for assembling segments of shield tunnels with internal water pressures

Publications (1)

Publication Number Publication Date
CN106703831A true CN106703831A (en) 2017-05-24

Family

ID=58934304

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611083361.2A Pending CN106703831A (en) 2016-11-30 2016-11-30 Method for assembling segments of shield tunnels with internal water pressures

Country Status (1)

Country Link
CN (1) CN106703831A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107798166A (en) * 2017-09-18 2018-03-13 广东省水利水电科学研究院 Load structure collective effect computational methods under Shield tunnel composite lining internal water pressure
CN109184740A (en) * 2018-10-19 2019-01-11 中铁隧道局集团有限公司 Assembled tube coupling and preparation method thereof
CN109184735A (en) * 2018-10-25 2019-01-11 上海市政工程设计研究总院(集团)有限公司 A kind of method for blocking having interior hydraulic pressure shield tunnel seam hand hole

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101289938A (en) * 2008-06-12 2008-10-22 北京城建设计研究总院有限责任公司 Subway shield tunnel enlarging station special area and station structure connecting method
CN101435334A (en) * 2008-12-16 2009-05-20 上海隧道工程股份有限公司 In-and-out hole segment pipe sheet connecting structure of shield method and construction method thereof
CN201705365U (en) * 2010-04-07 2011-01-12 中国石油天然气集团公司 Duct piece structure of shield tunnel through mouth
CN104405413A (en) * 2014-10-20 2015-03-11 上海市城市建设设计研究总院 Segment joint device and segment joint structure of rectangular shield tunnel
CN104612724A (en) * 2015-01-09 2015-05-13 同济大学 Splicing structure for pipe pieces of ellipse-like shield tunnel with stand column
CN106499436A (en) * 2016-11-25 2017-03-15 上海市政工程设计研究总院(集团)有限公司 There is assembling method in the shield tunnel joint built-in fitting and shield tunnel ring of interior hydraulic pressure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101289938A (en) * 2008-06-12 2008-10-22 北京城建设计研究总院有限责任公司 Subway shield tunnel enlarging station special area and station structure connecting method
CN101435334A (en) * 2008-12-16 2009-05-20 上海隧道工程股份有限公司 In-and-out hole segment pipe sheet connecting structure of shield method and construction method thereof
CN201705365U (en) * 2010-04-07 2011-01-12 中国石油天然气集团公司 Duct piece structure of shield tunnel through mouth
CN104405413A (en) * 2014-10-20 2015-03-11 上海市城市建设设计研究总院 Segment joint device and segment joint structure of rectangular shield tunnel
CN104405413B (en) * 2014-10-20 2016-06-08 上海市城市建设设计研究总院 The duct piece connector device in rectangular shield tunnel and duct piece connector structure
CN104612724A (en) * 2015-01-09 2015-05-13 同济大学 Splicing structure for pipe pieces of ellipse-like shield tunnel with stand column
CN106499436A (en) * 2016-11-25 2017-03-15 上海市政工程设计研究总院(集团)有限公司 There is assembling method in the shield tunnel joint built-in fitting and shield tunnel ring of interior hydraulic pressure

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107798166A (en) * 2017-09-18 2018-03-13 广东省水利水电科学研究院 Load structure collective effect computational methods under Shield tunnel composite lining internal water pressure
CN107798166B (en) * 2017-09-18 2021-03-30 广东省水利水电科学研究院 Method for calculating combined action of load structure under water pressure in composite lining of shield tunnel
CN109184740A (en) * 2018-10-19 2019-01-11 中铁隧道局集团有限公司 Assembled tube coupling and preparation method thereof
CN109184735A (en) * 2018-10-25 2019-01-11 上海市政工程设计研究总院(集团)有限公司 A kind of method for blocking having interior hydraulic pressure shield tunnel seam hand hole

Similar Documents

Publication Publication Date Title
CN103243815B (en) End-anchored composite beam structure and corresponding reinforcing construction method
CN105155685B (en) A kind of assembled beam-column node and its construction method
CN108589971A (en) A kind of closed-section steel deck combined concrete shear wall connecting node and production method
CN106168057A (en) A kind of assembled steel lath band combined concrete shear wall and making construction method thereof
CN106703831A (en) Method for assembling segments of shield tunnels with internal water pressures
CN104929148B (en) The upside-down mounting hardened system of generation power foundation of wind power ring group plinth and reinforcement means thereof
CN105133793A (en) Space constraint multi-cavity pipe-in-pipe steel bar concrete huge column and construction method
KR20160005257A (en) Precast Coping, the Combination Structure of Column and Coping, and its Construction Method
CN107882232A (en) A kind of assembly concrete is mated formation the node connector and attaching method thereof of building cover board in advance
CN108194116A (en) A kind of integral prefabricated rail in subway station road assembling structure against the wind
CN109811965A (en) It is a kind of to be bolted high strength steel plate spliced girder-concrete slab combination beam entirely
CN103912288A (en) High-bearing-capacity segment joint structure
CN103924740A (en) H-shaped steel bone-confined concrete column with round steel draw bars and fabrication method of column
CN103953363A (en) Method for connecting shield tunnel pipe sheet and transverse passage structure
CN110284702A (en) A kind of constructing device and construction method of hyperboloid arc mixed mud wall
CN105040726A (en) Method for applying circular prestress on fan foundation connection
CN207749409U (en) Detachable assembling type reinforced concrete bridge pier cushion cap connection structure
CN206267856U (en) A kind of shield tunnel piecing devices for there is interior hydraulic pressure
CN203514528U (en) Composite connection structure of concrete filled steel tubular column and thin steel plate shear wall
CN203320703U (en) Connecting node of reinforced concrete column and newly added steel beam
CN205577153U (en) Installation node of wallboard connecting piece and wallboard
CN207750094U (en) A kind of integral prefabricated rail in subway station road assembling structure against the wind
CN104060714A (en) Construction method for seamless building sandwich composite wall body
CN109184741A (en) A kind of high-bearing capacity shield tunnel segment joint structure
CN203796280U (en) Segment joint structure high in bearing capacity

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170524

RJ01 Rejection of invention patent application after publication