CN105040726A - Method for applying circular prestress on fan foundation connection - Google Patents

Method for applying circular prestress on fan foundation connection Download PDF

Info

Publication number
CN105040726A
CN105040726A CN201510468612.8A CN201510468612A CN105040726A CN 105040726 A CN105040726 A CN 105040726A CN 201510468612 A CN201510468612 A CN 201510468612A CN 105040726 A CN105040726 A CN 105040726A
Authority
CN
China
Prior art keywords
steel
pilaster
prestress
discharge ring
backing plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510468612.8A
Other languages
Chinese (zh)
Other versions
CN105040726B (en
Inventor
冯又全
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Fengchang Civil Engineering Technology Co Ltd
Original Assignee
Shanghai Fengchang Civil Engineering Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Fengchang Civil Engineering Technology Co Ltd filed Critical Shanghai Fengchang Civil Engineering Technology Co Ltd
Priority to CN201510468612.8A priority Critical patent/CN105040726B/en
Publication of CN105040726A publication Critical patent/CN105040726A/en
Application granted granted Critical
Publication of CN105040726B publication Critical patent/CN105040726B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention provides a method for applying circular prestress on a fan foundation connector. The method can be used for reinforcing out-of-operation foundation circular connection of a built project put into operation, and can also be used for avoiding stress defects of foundation circular connection in a newly-built project. Steel pilasters and base plates are fixed to the outer side of a concrete pier, prestress steel strands penetrate through anchor plates of the steel pilasters and limiting rings of the base plates, prestress is applied to the two ends of each prestress steel strand, and special anchoring heads are installed at the two ends of each prestress steel strand. At last, thickened areas are arranged on the upper surface and the side face of the concrete pier, and are evenly provided with circular steel bars and vertical steel bars so as to protect the prestress steel strands, the steel pilasters, the special anchoring heads and the base plates in a wrapping manner. The multiple limiting rings are evenly welded to the base plates to limit the prestress steel strands. Each steel pilaster is composed of a pilaster base plate, rib plates and anchor plates, wherein the rib plates are evenly welded to the pilaster base plate, the anchor plates are welded to the pilaster base plate and the rib plates, each rib plate has the wide inside and the narrow outside, and therefore the two ends of each prestress steel strand perpendicularly act on the corresponding anchor plate.

Description

A kind of for connecting the method applying ring orientation prestress to blower foundation
Technical field
The invention belongs to generation power foundation of wind power technical field of structures, be specifically related to a kind of for connecting the method applying ring orientation prestress to blower foundation.
Background technology
At present, single tube wind power generation stepped connection with bottom reinforcement bars concrete foundation often adopts pre-embedded foundation ring, upper column cylinder and discharge ring in reinforced concrete foundation to be realized by Flange joint.But, because discharge ring length of embedment is shallow, and be non-prestressed structure, discharge ring connection upper column cylinder and base foundation is adopted to there is following defect: the existing reinforcing bar in discharge ring region has again discharge ring to strengthen, only reinforcing bar is had with lower area, because strength and stiffness sudden change causes the crack because of hardening of concrete contraction and stressed generation to concentrate between discharge ring and base plate, crack width increases; Discharge ring isolates inside and outside concrete, because steel are different with concrete bi-material performance, coefficient of thermal expansion is different, distortion can not be coordinated, and temperature action, load work, frost heave action etc. make discharge ring and concrete gap constantly increase, the anchorage effect of both deteriorations; Under blower fan reciprocating fatigue load action, discharge ring join domain distress in concrete, gap constantly increase development, and then make discharge ring vibrate in base concrete, rock, and produce concrete percussion.
Basis connects the stressed defect the existed project problems that causes putting into operation and breaks out gradually, has a strong impact on running quality and the security of operation of blower fan.And project that is newly-built, that still adopt discharge ring to connect still does not have good measure to evade this defect.
Summary of the invention
The object of the present invention is to provide a kind of for connecting the method applying ring orientation prestress to blower foundation, both can be used for the reinforcing of the built item base ring Joint failure that puts into operation, and may be used for again the stressed defect that grassroot project evades basis connection.
It is a kind of for connecting the method applying ring orientation prestress to blower foundation that the present invention proposes, described blower foundation ring connects and is made up of discharge ring 1, concrete stub 2 and discharge ring slit region 3, described discharge ring 1 inserts concrete stub 2, discharge ring slit region 3 is provided with between described discharge ring 1 and concrete stub 2, when connecting Shi Hanzhang to basis, concrete steps are: be first positioned at concrete stub 2 both sides partly at discharge ring 1 and drill through some oblique grout holes 6, make described grout hole 6 lead to discharge ring slit region 3; Then by oblique grout hole 6 pairs of discharge ring slit region 3 pressure groutings, discharge ring slit region 3 and grout hole 6 is made all to fill full high-strength grouting material; Then be fixed on outside concrete stub 2 by steel pilaster 8 and backing plate 10, prestress wire 5 successively through the anchor slab 15 of steel pilaster 8 and the spacing ring 11 of backing plate 10, installs special anchorage head 9 at prestress wire 5 two ends Shi Hanzhang.Finally in upper surface and the side surface layout thicker region 4 of concrete stub 2, described thicker region 4 is evenly arranged circumferential reinforcement and vertical reinforcement 7, for wrapping up protection prestress wire 5, steel pilaster 8, special anchorage head 9 and backing plate 10.Several spacing rings 11 of uniform welding on described backing plate 10, spacing for prestress wire 5.
In the present invention, described steel pilaster 8 is made up of pilaster backing plate 13, floor 14 and anchor slab 15, and floor 14 is uniform to be welded on pilaster backing plate 13, and anchor slab 15 welds with pilaster backing plate 13 and floor 14, described floor 14 inner wide and outer narrow, makes prestress wire 5 two ends vertically act on anchor slab 15.
Beneficial effect of the present invention is:
1. what the present invention proposed is a kind of for connecting the method applying ring orientation prestress to blower foundation, structure is simple, reasonable stress, easy construction, both can be used for the stressed defect that grassroot project evades discharge ring connection, may be used for again the reinforcing of the built item base ring Joint failure that puts into operation.
2. after backing plate and steel pilaster are fixed, to prestress wire Shi Hanzhang, make concrete stub region by hoop precompression, contribute to concrete clamping discharge ring outside stub, concrete is made to be in preloading condition, can reduce distress in concrete, between concrete and discharge ring gap development, improve concrete bearing capacity and anti-fatigue performance.
3. when the present invention is used for the reinforcing of the built item base ring Joint failure that puts into operation, thicken ring beam measure in conjunction with top, the buried depth of discharge ring can be increased, improve concrete to the binding effect of discharge ring, and do not destroy original structure.
4., under ring orientation prestress effect, in discharge ring, outside concrete clamping discharge ring, makes a discharge ring part be forced through discharge ring and concrete frictional force transmission, and the stress reduced bottom discharge ring is concentrated.
5. steel column floor inner wide and outer narrow of the present invention, makes anchor slab become certain inclination angle with radial direction, guarantees that prestress wire is orthogonal with anchor slab, steel strand are not bent.
6. prestress application of the present invention does not intersect with concrete construction and maintenance, simple operation, easy construction.
Accompanying drawing explanation
Fig. 1 is that basis of the present invention connects front view.
Fig. 2 is the front view that the present invention applies.
Fig. 3 is the top view that the present invention applies.
Fig. 4 is backing plate detail drawing of the present invention.
Fig. 5 is steel pilaster detail drawing of the present invention.
Number in the figure: based on 1, ring, 2 is ring slit region based on concrete stub, 3,4 is thicker region, 5 be prestress wire, 6 be grout hole, 7 be circumferential reinforcement and vertical reinforcement, 8 be steel pilaster, 9 be special anchorage head, 10 be backing plate, 11 be spacing ring, 12 be curved plate, 13 be pilaster backing plate, 14 be floor, 15 be anchor slab.
Detailed description of the invention
The present invention is further illustrated by reference to the accompanying drawings below by embodiment.
Embodiment 1:
As shown in Figure 1, during basic Joint failure, between discharge ring 1 and concrete stub 2, produce discharge ring gap area 3.
When the present invention is applied to basis connection Shi Hanzhang, is first positioned at concrete stub 2 both sides partly at discharge ring 1 and drills through some oblique grout holes 6, make described grout hole 6 lead to discharge ring slit region 3; Then by oblique grout hole 6 pairs of discharge ring slit region 3 pressure groutings, discharge ring slit region 3 and grout hole 6 is made all to fill full high-strength grouting material; Then be fixed on outside concrete stub 2 by steel pilaster 8 and backing plate 10, prestress wire 5 successively through the anchor slab 15 of steel pilaster 8 and the spacing ring 11 of backing plate 10, installs special anchorage head 9 at prestress wire 5 two ends Shi Hanzhang.Finally in upper surface and the side surface layout thicker region 4 of concrete stub 2, described thicker region 4 is evenly arranged circumferential reinforcement and vertical reinforcement 7, for wrapping up protection prestress wire 5, steel pilaster 8, special anchorage head 9 and backing plate 10.
Implementation step is as follows:
(1) discharge ring 1 liang of sidetracking grout hole 6, notes the discharge ring gap area 3 of setting-out cleaning discharge ring 1 both sides in both sides grout hole 6;
(2) use slip casing by pressure material along grout hole 6, fill discharge ring gap area 3;
(3) be fixed on outside concrete stub 2 by steel pilaster 8 and backing plate 10, prestress wire 5 is successively through the anchor slab 15 of steel pilaster 8 and the spacing ring 11 of backing plate 10;
(4) at prestress wire 5 two ends Shi Hanzhang special anchorage head 9 is installed;
(5) in upper surface and the side surface layout thicker region 4 of concrete stub 2, described thicker region 4 is evenly arranged circumferential reinforcement and vertical reinforcement 7, for wrapping up protection prestress wire 5, steel pilaster 8, special anchorage head 9 and backing plate 10.

Claims (2)

1. one kind applies the method for ring orientation prestress for connecting blower foundation, described blower foundation ring connects by discharge ring (1), concrete stub (2) and discharge ring slit region (3) composition, described discharge ring (1) inserts concrete stub (2), discharge ring slit region (3) is provided with between described discharge ring (1) and concrete stub (2), it is characterized in that when connecting Shi Hanzhang to basis, concrete steps are: be first positioned at concrete stub (2) both sides partly at discharge ring (1) and drill through some oblique grout holes (6), described grout hole (6) is made to lead to discharge ring slit region (3), then by oblique grout hole (6) to discharge ring slit region (3) pressure grouting, make discharge ring slit region (3) and grout hole (6) all fill full high-strength grouting material, then steel pilaster (8) and backing plate (10) are fixed on concrete stub (2) outside, prestress wire (5) successively through the anchor slab (15) of steel pilaster (8) and the spacing ring (11) of backing plate (10), installs special anchorage head (9) at prestress wire (5) two ends Shi Hanzhang, finally at upper surface and side surface layout thicker region (4) of concrete stub 2, described thicker region (4) is evenly arranged circumferential reinforcement and vertical reinforcement (7), for wrapping up protection prestress wire (5), steel pilaster (8), special anchorage head (9) and backing plate (10), upper several spacing rings of uniform welding (11) of described backing plate (10), spacing for prestress wire (5).
2. according to claim 1 for connecting the method applying ring orientation prestress to blower foundation, it is characterized in that described steel pilaster (8) is made up of pilaster backing plate (13), floor (14) and anchor slab (15), floor (14) is uniform to be welded on pilaster backing plate (13), anchor slab (15) welds with pilaster backing plate (13) and floor (14), described floor (14) inner wide and outer narrow, makes prestress wire (5) two ends vertically act on anchor slab (15).
CN201510468612.8A 2015-08-04 2015-08-04 A kind of method for applying ring orientation prestress is connected to blower foundation ring Active CN105040726B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510468612.8A CN105040726B (en) 2015-08-04 2015-08-04 A kind of method for applying ring orientation prestress is connected to blower foundation ring

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510468612.8A CN105040726B (en) 2015-08-04 2015-08-04 A kind of method for applying ring orientation prestress is connected to blower foundation ring

Publications (2)

Publication Number Publication Date
CN105040726A true CN105040726A (en) 2015-11-11
CN105040726B CN105040726B (en) 2017-03-08

Family

ID=54447672

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510468612.8A Active CN105040726B (en) 2015-08-04 2015-08-04 A kind of method for applying ring orientation prestress is connected to blower foundation ring

Country Status (1)

Country Link
CN (1) CN105040726B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106592622A (en) * 2016-12-19 2017-04-26 长安大学 Annular concrete based wind-driven generator foundation structure with vertical prestress
CN106638733A (en) * 2017-03-07 2017-05-10 长安大学 Method for reinforcing fan foundation through additionally-arranged horizontal steel bars
CN106836324A (en) * 2017-03-07 2017-06-13 长安大学 A kind of blower foundation reinforcement means for setting up oblique tension reinforcement
CN110565680A (en) * 2019-10-09 2019-12-13 兰州理工大学 Steel grating ring type wind power tower foundation ring facility and construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002122066A (en) * 2000-10-16 2002-04-26 Ps Corp Wind power generating tower
CN202265838U (en) * 2011-08-10 2012-06-06 同济大学建筑设计研究院(集团)有限公司 Multidirectional prestress foundation of wind driven generator
CN104088291A (en) * 2014-05-05 2014-10-08 安徽三建工程有限公司 Annular wedge combined concrete precast block tower crane foundation
CN104790424A (en) * 2015-04-17 2015-07-22 同济大学建筑设计研究院(集团)有限公司 Reinforcing system and reinforcing method of wind power generation tower foundation ring foundation

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002122066A (en) * 2000-10-16 2002-04-26 Ps Corp Wind power generating tower
CN202265838U (en) * 2011-08-10 2012-06-06 同济大学建筑设计研究院(集团)有限公司 Multidirectional prestress foundation of wind driven generator
CN104088291A (en) * 2014-05-05 2014-10-08 安徽三建工程有限公司 Annular wedge combined concrete precast block tower crane foundation
CN104790424A (en) * 2015-04-17 2015-07-22 同济大学建筑设计研究院(集团)有限公司 Reinforcing system and reinforcing method of wind power generation tower foundation ring foundation

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
沈春林等: "《建筑的渗漏与防治》", 30 September 2008, 中国建材工业出版社 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106592622A (en) * 2016-12-19 2017-04-26 长安大学 Annular concrete based wind-driven generator foundation structure with vertical prestress
CN106638733A (en) * 2017-03-07 2017-05-10 长安大学 Method for reinforcing fan foundation through additionally-arranged horizontal steel bars
CN106836324A (en) * 2017-03-07 2017-06-13 长安大学 A kind of blower foundation reinforcement means for setting up oblique tension reinforcement
CN110565680A (en) * 2019-10-09 2019-12-13 兰州理工大学 Steel grating ring type wind power tower foundation ring facility and construction method
CN110565680B (en) * 2019-10-09 2024-02-13 兰州理工大学 Steel grating ring type wind power tower foundation ring facility and construction method

Also Published As

Publication number Publication date
CN105040726B (en) 2017-03-08

Similar Documents

Publication Publication Date Title
CN102704491B (en) Sectional steel and reinforced concrete beam combination foundation pit supporting protection surrounding purlin and construction method of purlin
CN100567659C (en) The base configuration of iron tower
CN206396816U (en) A kind of blower foundation various dimensions ruggedized construction
CN207194146U (en) Prestressing force assembly concrete frame joint attachment structure
CN105040726A (en) Method for applying circular prestress on fan foundation connection
CN206844314U (en) A kind of new prefabricated assembled bean column node
CN210798990U (en) Corrugated steel lining combined member for tunnel
CN103306214A (en) Novel reinforcement device for reinforced concrete beam and floor slab and construction method thereof
CN104727318A (en) Foundation ditch composite concrete nail supporting structure and method
CN104499608B (en) The design and construction method of prestressing force section steel reinforcement shear wall
CN105756365B (en) A kind of method of rapid reinforcement beams of concrete
KR101337001B1 (en) Connector assembly for steel pipe strut
CN103291082A (en) Wood beam reinforcing body external pre-stress construction method
CN104234443B (en) A kind of corbel type reinforcement means of steel reinforced concrete member and newly-increased beam
RU196074U1 (en) Reinforced concrete foundation for a rocking machine
CN204849809U (en) A radial prestressing force subassembly for fan foundation ring is connected
CN204825954U (en) A subassembly for being directed at hoop prestressing force is applyed to basic connection of fan
KR101623377B1 (en) Reinforcing structure for pipe head
CN208777758U (en) A kind of steel roof truss lower boom reinforcing device
CN207484742U (en) A kind of prestressed building blocks wall between windows
CN105970963B (en) A kind of precast concrete channel plate pile head bracing means
KR20120100052A (en) Bridge leg correcting method using oil compressure jack and broken parts compensation structure
JP2012149399A (en) Slab reinforcement method using h-shaped steel
KR200455415Y1 (en) Head reinforcement assembly of concrete pile for foundation work
JP3826348B2 (en) Construction method of composite wall with mountain retaining core and underground outer wall

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant