CN209429084U - Cavern usual friendship fork structure - Google Patents

Cavern usual friendship fork structure Download PDF

Info

Publication number
CN209429084U
CN209429084U CN201821926596.8U CN201821926596U CN209429084U CN 209429084 U CN209429084 U CN 209429084U CN 201821926596 U CN201821926596 U CN 201821926596U CN 209429084 U CN209429084 U CN 209429084U
Authority
CN
China
Prior art keywords
usual friendship
fork structure
temporary diversion
cavern
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201821926596.8U
Other languages
Chinese (zh)
Inventor
谢金元
张清琼
陈军
吴东利
谷玲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Chengdu Engineering Co Ltd
Original Assignee
PowerChina Chengdu Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Chengdu Engineering Co Ltd filed Critical PowerChina Chengdu Engineering Co Ltd
Priority to CN201821926596.8U priority Critical patent/CN209429084U/en
Application granted granted Critical
Publication of CN209429084U publication Critical patent/CN209429084U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The utility model relates to field of water conservancy, especially a kind of fork structure is simple, the small difficulty of reconstruction project amount is low, it is remarkably improved the cavern usual friendship fork structure of reconstruction working security and simplicity, including temporary diversion hole and permanent tunnel, the temporary diversion hole and permanent tunnel intersect by usual friendship combination fork structure, and temporary diversion hole direction is provided with temporary diversion wall at the structure of usual friendship combination fork, interim rock plug water blocking plug is provided in the permanent tunnel.The utility model is that temporary diversion hole is allowed normally to play corresponding guide functions first, due to being provided with interim rock plug water blocking plug in permanent tunnel, ensure that water flow can not temporarily pass through from permanent tunnel.After reconstruction, only need to simply be constructed, when realize that water flow is flowed out via permanent tunnel, while also achieving the combination in temporary diversion hole and permanent tunnel.The utility model is particularly suitable in the construction scene that the later period needs temporary diversion hole and permanent tunnel to combine.

Description

Cavern usual friendship fork structure
Technical field
The utility model relates to field of water conservancy, especially a kind of cavern's usual friendship fork structure.
Background technique
In hydraulic and hydroelectric engineering, to make full use of the diversion tunnel temporarily used, often consider it in conjunction with permanent tunnel.It is right In the usual friendship fork for handing over trouble to combine using plane, generally reconstructed greatly after diversion tunnel use;It is first torn open when reconstruction Except the diversion tunnel liner structure that early period is formed at fork, explosion is carried out to cavern at fork and is digged, reconnected reinforcing bar and pour permanently Fork section lining cutting.
But under the mode that existing big reconstruction combines, the former big difficulty of diversion tunnel lining cutting dismounting amount is high;To hole at fork It is big to the existing building destruction in periphery when room progress explosion digs, and easily cause the safety accidents such as cavern's landslide;Fork section lining cutting The bodily form is more complex, and linking technique is cumbersome between reinforcing bar connection and New-old concrete, is not easy to guarantee construction quality.
Utility model content
The technical problem to be solved by the utility model is to provide a kind of fork structure is simple, the small difficulty of reconstruction project amount It is low, it is remarkably improved the cavern usual friendship fork structure of reconstruction working security and simplicity.
The technical scheme adopted by the utility model to solve the technical problem is as follows: cavern usual friendship fork structure, including it is interim Diversion tunnel and permanent tunnel, the temporary diversion hole and permanent tunnel intersect by usual friendship combination fork structure, the usual friendship Temporary diversion hole direction is provided with temporary diversion wall in conjunction at the structure of fork, interim rock plug gear is provided in the permanent tunnel Water blocking head.
Further, being provided with permeable hole on the temporary diversion wall.
Further, the permeable hole is uniformly distributed on temporary diversion wall metope.
Further, the central axis of the permeable hole is vertical with the metope of temporary diversion wall.
Further, the seam face at temporary diversion wall both ends is provided with both ends bituminous coating structure.
Further, the seam face in temporary diversion wall top portion is provided with top bituminous coating structure.
Further, the interim rock plug water blocking plug is set at the updrift side in permanent tunnel.
Further, being provided with permanent lining, secondary lining structure in the structure of usual friendship combination fork.
Further, usual friendship combination fork structure is primary excavation lining cutting molding structure.
Further, the metope in plane where temporary diversion wall and temporary diversion hole is to be coplanar with.
The beneficial effects of the utility model are: the utility model is in actual use, it is to make temporary diversion hole normal first The corresponding guide functions of performance, at this point, due to the presence of temporary diversion wall, water flow can steadily, smoothly flow to downstream. And at this time due to being provided with interim rock plug water blocking plug in permanent tunnel, it ensure that water flow temporarily can not be logical from permanent tunnel It crosses.After reconstruction, i.e., dismountable temporary diversion wall and interim rock plug water blocking plug, at this point, only need to simply be constructed Shi Shixian water flow is flowed out via permanent tunnel, while also achieving the combination in temporary diversion hole and permanent tunnel.The utility model It is particularly suitable in the construction scene that the later period needs temporary diversion hole and permanent tunnel to combine.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model.
Fig. 2 is the A-A cross-sectional view of Fig. 1.
In the figure, it is marked as permanent tunnel 1, interim rock plug water blocking plug 2, usual friendship combination fork structure 3, permeable hole 5, temporarily Training wall 6, permanent training wall 7, temporary diversion hole 8, both ends bituminous coating structure 9, top bituminous coating structure 10.
Specific embodiment
The present invention will be further described with reference to the accompanying drawing.
Cavern's usual friendship as shown in Figure 1 and Figure 2 fork structure, including temporary diversion hole 8 and permanent tunnel 1, it is described temporarily to lead It flows hole 8 and permanent tunnel 1 to intersect by usual friendship combination fork structure 3, along temporary diversion at usual friendship combination fork structure 3 8 direction of hole is provided with temporary diversion wall 6, and interim rock plug water blocking plug 2 is provided in the permanent tunnel 1.
The technological core thought of the utility model is to realize the cavern usual friendship fork structure of " facing combination forever ", wherein " is faced forever In conjunction with ", refer to permanent building and temporay building in construction and using above making overall plans.In the utility model, since structure is set Meter it is ingenious, realize temporary diversion hole 8 and permanent tunnel 1 well in construction and using above making overall plans.It is practical new at this In the scheme of type, firstly, the cavern of usual friendship combination fork structure 3 secondary need not dig, existing effect on building is substantially mitigated, Working security significantly improves;Secondly, a construction molding may be implemented in the main structure of usual friendship combination fork structure 3, reconstruction Dismantling concrete amount is few and boundary is controllable, and construction technology is simple, and quality control on construction difficulty significantly reduces;Finally, reconstruction project Simply, small, easy construction is interfered to constructions such as the plugs of diversion tunnel, coverage ratio is high.In conjunction with actual construction environment condition, generally The interim rock plug water blocking plug 2 is selected to be set at the updrift side in permanent tunnel 1.It can choose and allow temporary diversion wall institute Metope in plane 6 with temporary diversion hole 8 is to be coplanar with, thus smooth when guaranteeing water flow flowing.
In order to guarantee the hydraulic pressure relative equilibrium of 6 wall two sides of temporary diversion wall, it is excessive to wall to prevent a side hydraulic pressure Destruction, meanwhile, also for reduce the later period remove project amount and difficulty of construction, can choose on the temporary diversion wall 6 It is provided with permeable hole 5.As shown in Figure 1, the presence of permeable hole 5 ensure that the hydraulic balance of wall two sides, the work of construction is reduced Cheng Liang.Generally it is preferred to which the permeable hole 5 is uniformly distributed on 6 metope of temporary diversion wall, to obtain more uniform stress item Part.It is preferred that the central axis of the permeable hole 5 is vertical with the metope of temporary diversion wall 6, guarantee that influence of the hydraulic pressure to wall is down to Lowest range.
In order to guarantee the stability of structure when in use, and remove convenient for the later period.It can choose such scheme: interim The seam face at 6 top of seam face setting both ends bituminous coating structure 9 and temporary diversion wall at 6 both ends of training wall is provided with top drip Green coating structure 10.
In order to reduce construction in later period amount as far as possible, in conjunction with the technical advantage of the utility model, can choose in the usual friendship In conjunction with permanent lining, secondary lining structure is arranged in fork structure 3, so that the later period just no longer needs to do corresponding construction when reconstructing.Likewise, Can choose usual friendship combination fork structure 3 is primary excavation lining cutting molding structure, to improve the efficiency of construction.
It when the structure of the utility model is constructed in the early stage, is can choose first in Diversion Tunnel excavation early period, i.e., by usual friendship Molding is disposably excavated in conjunction with fork structure 3;And permanent tunnel 1 is excavated into certain length to fork upstream, upstream end is reserved to be faced Shi Yansai water blocking plug 2 is used as temporary water dash plug;Secondly, usual friendship combination fork is tied in 8 lining cutting of hole of temporary diversion early period Structure 3 is completed by permanent requirement lining cutting;Sideline is designed along temporary diversion hole 8 at the fork of usual friendship combination fork structure 3 and is arranged Temporary diversion wall 6 crosses hydraulics requirement during water to meet temporary diversion hole 8, permeable hole 5 is arranged on temporary diversion wall 6, temporarily Training wall 6 is in addition to bottom plate, equal parting between both ends and top and fork lining cutting, stitches face brushing pitch;8 use of temporary diversion hole terminates Afterwards, temporary diversion wall 6 is removed along parting face, pours permanent training wall 7;Remove interim rock plug water blocking plug 2, permanent tunnel lining Directly it is connected with completed fork lining cutting.The small difficulty of the utility model reconstruction project amount is low, is remarkably improved reconstruction construction peace Full property and simplicity, have very wide market promotion prospect.

Claims (10)

1. cavern usual friendship fork structure, including temporary diversion hole (8) and permanent tunnel (1), it is characterised in that: the temporary diversion Hole (8) and permanent tunnel (1) intersect by usual friendship combination fork structure (3), and edge is faced at usual friendship combination fork structure (3) When diversion tunnel (8) direction be provided with temporary diversion wall (6), is provided with interim rock plug water blocking plug in the permanent tunnel (1) (2)。
2. cavern's usual friendship as described in claim 1 fork structure, it is characterised in that: be provided on the temporary diversion wall (6) Permeable hole (5).
3. cavern's usual friendship as claimed in claim 2 fork structure, it is characterised in that: the permeable hole (5), which is uniformly distributed in, faces When training wall (6) metope on.
4. cavern's usual friendship as claimed in claim 2 fork structure, it is characterised in that: the central axis of the permeable hole (5) with The metope of temporary diversion wall (6) is vertical.
5. cavern's usual friendship as claimed in claim 1 or 2 fork structure, it is characterised in that: the seam face at temporary diversion wall (6) both ends It is provided with both ends bituminous coating structure (9).
6. cavern's usual friendship as claimed in claim 1 or 2 fork structure, it is characterised in that: the seam face at the top of temporary diversion wall (6) It is provided with top bituminous coating structure (10).
7. cavern's usual friendship as claimed in claim 1 or 2 fork structure, it is characterised in that: the interim rock plug water blocking plug (2) It is set at the updrift side in permanent tunnel (1).
8. cavern's usual friendship as claimed in claim 1 or 2 fork structure, it is characterised in that: usual friendship combination fork structure (3) Inside it is provided with permanent lining, secondary lining structure.
9. cavern's usual friendship as claimed in claim 1 or 2 fork structure, it is characterised in that: usual friendship combination fork structure (3) is one Secondary excavation lining cutting molding structure.
10. cavern's usual friendship as claimed in claim 1 or 2 fork structure, it is characterised in that: plane where temporary diversion wall (6) Metope with temporary diversion hole (8) is to be coplanar with.
CN201821926596.8U 2018-11-21 2018-11-21 Cavern usual friendship fork structure Withdrawn - After Issue CN209429084U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821926596.8U CN209429084U (en) 2018-11-21 2018-11-21 Cavern usual friendship fork structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821926596.8U CN209429084U (en) 2018-11-21 2018-11-21 Cavern usual friendship fork structure

Publications (1)

Publication Number Publication Date
CN209429084U true CN209429084U (en) 2019-09-24

Family

ID=67969257

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821926596.8U Withdrawn - After Issue CN209429084U (en) 2018-11-21 2018-11-21 Cavern usual friendship fork structure

Country Status (1)

Country Link
CN (1) CN209429084U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109356124A (en) * 2018-11-21 2019-02-19 中国电建集团成都勘测设计研究院有限公司 Cavern usual friendship fork structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109356124A (en) * 2018-11-21 2019-02-19 中国电建集团成都勘测设计研究院有限公司 Cavern usual friendship fork structure
CN109356124B (en) * 2018-11-21 2023-11-21 中国电建集团成都勘测设计研究院有限公司 Chamber level crossing fork structure

Similar Documents

Publication Publication Date Title
CN107460882B (en) A kind of retaining piles construction method of deep basal pit closing sealing
CN205012284U (en) Build dam dam foundation seepage prevention structure on overburden
CN108331597A (en) A kind of duct pieces of shield tunnel grouting behind shaft or drift lining construction method
CN106759250A (en) Unfavorable geologic body grouting method under the conditions of a kind of pressure-bearing seepage flow
CN209429084U (en) Cavern usual friendship fork structure
CN109763837A (en) A kind of TBM tunnel film bag cement stops paste structure and construction method
CN106638486B (en) High-tech zones cut-pff wall and gallery stage construction method
CN207063226U (en) Precast reinforced concrete shear wall
CN207498908U (en) A kind of diversion tunnel vertical cyclindrical shape stopper structure pattern
CN202440787U (en) Riverway diversion device
CN108316259A (en) Diversion tunnel sets up lock under interim plug joint gate and blocks arrangement and method
CN109356124A (en) Cavern usual friendship fork structure
CN105178268A (en) Construction method and structure achieving combination of diversion tunnel and flood discharging tunnel
CN205152918U (en) Structure that diversion tunnel and flood discharge hole combine
CN108330933A (en) The structure and its construction method and application that a kind of diversion tunnel and ecological drainage tunnel combine
CN202250109U (en) Back-stuck drainage water stop
CN210263095U (en) Full-tunnel section maintenance cofferdam structure of diversion tunnel in early and middle period
CN208604552U (en) For the stake woods dam under complex geological condition
CN112064601A (en) Diversion tunnel and emptying tunnel combined structure for extra-high rock-fill dam and construction method
CN208219579U (en) The structure that a kind of diversion tunnel and ecological drainage tunnel combine
CN207919510U (en) Diversion tunnel blocks arrangement using lock under permanent plug first section joint gate
CN207130701U (en) Compound water flowing out structure for Hydraulic and Hydro-Power Engineering
CN207111112U (en) High dam ecology water supply hole block section liner structure
CN207728377U (en) A kind of tunnel structure and stratum consolidation structure for metro shield section
CN203096696U (en) High and low composite backwater weir

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20190924

Effective date of abandoning: 20231121

AV01 Patent right actively abandoned

Granted publication date: 20190924

Effective date of abandoning: 20231121