CN209413171U - A kind of prefabricated component stair of light silencing - Google Patents
A kind of prefabricated component stair of light silencing Download PDFInfo
- Publication number
- CN209413171U CN209413171U CN201920001000.1U CN201920001000U CN209413171U CN 209413171 U CN209413171 U CN 209413171U CN 201920001000 U CN201920001000 U CN 201920001000U CN 209413171 U CN209413171 U CN 209413171U
- Authority
- CN
- China
- Prior art keywords
- bearing
- waist slab
- stair
- insulation board
- hinge pin
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Steps, Ramps, And Handrails (AREA)
Abstract
The utility model relates to a kind of prefabricated component stair of light silencing, belong to building engineering field.The stair include at the bearing of waist slab upper end, tread plate, lifting built-in fitting, sliding hinge pin key hole to be provided, fixed hinge pin key hole to be provided, waist slab, at the bearing of waist slab lower end, plugging wire insulation board reserve grout hole, cant beam, plugging wire insulation board, reinforcing bar at reinforcing bar, concrete topping steel wire, cant beam reinforcing bar and the bearing of waist slab lower end at the bearing of waist slab upper end;The utility model be a kind of quick construction, short time limit, light-weight, excellent earthquake resistance, low cost, walk sound-absorbing prefabricated component stair.
Description
Technical field
The utility model relates to a kind of prefabricated component stair of light silencing, belong to building engineering field.
Background technique
Stair are divided into cast-in-situ steel reinforced concrete stair and two kinds of precast stair.Cast-in-situ steel reinforced concrete stair are whether board-like
Stair or stringer type stairway are required to a large amount of live formworks when constructing, after assembling reinforcement after-pouring concrete conserves 14~21 days again
Demoulding molding, construction is complicated, long in time limit, and cost is high.Precast stair pours in factory's formwork in advance according to size, after maintenance is good
It is transported to construction site, need to only complete lifting splicing at the scene, easy construction, short time limit, cost is lower than cast-in-place, but mesh
Preceding precast stair weight is big, calculates according to the most commonly used ST-30-25 model precast stair in national standard, and single flight weight is up to 2.1
~2.4 tons, be more than the tolerance zone of 1.5 tons of small-sized tower crane, it is necessary to use large-scale tower crane equipment, bring to transporting with lifting
It is inconvenient.And current stair whether it is cast-in-place or it is prefabricated be all using armored concrete, cause people walk stair when unavoidably
Noise can be generated, while precast stair generally uses fixed-hinged support to connect in bench with cast-in-situ stair at platform, causes just
It spends bigger than normal, is unfavorable for antidetonation.
Utility model content
The utility model is that the existing cast-in-situ stair construction of solution is complicated, long in time limit, cost is high, and precast stair weight is big, transports
The technical issues of defeated lifting inconvenience, poor seismic behavior, walking generate noise, its purpose is to provide a kind of quick constructions, duration
Short, light-weight, excellent earthquake resistance, low cost, walk sound-absorbing prefabricated component stair.
The utility model to achieve the above object, adopts the following technical scheme that
A kind of prefabricated component stair of light silencing, which includes at the bearing of waist slab upper end, tread plate, lifting are pre-buried
Part, sliding hinge pin key hole to be provided, fixed hinge pin key hole to be provided, waist slab, at the bearing of waist slab lower end, plugging wire insulation board is reserved fills
Starch hole, cant beam, plugging wire insulation board, at the bearing of waist slab upper end under reinforcing bar, concrete topping steel wire, cant beam reinforcing bar and waist slab
Hold reinforcing bar at bearing;
Respectively there are a cant beam bearing in two sides below the waist slab of the stair, place cant beam reinforcing bar in cant beam, waist slab
The plugging wire insulation board of concrete topping is wrapped up in plate for surrounding, placed concrete topping steel wire in surrounding package concrete topping
Net, at the bearing of waist slab upper end with there are two fixed hinge pin key hole to be provided and sliding hinge pin key are pre- respectively at the bearing of waist slab lower end
Box out, wherein at the bearing of waist slab upper end be fixed hinge pin key hole to be provided and it is internal place reinforcing bar at the bearing of waist slab upper end,
It is reinforcing bar at sliding hinge pin key hole to be provided and internal placement waist slab lower end bearing at the bearing of waist slab lower end.
Further, tread plate is on every layer mark time, and mark time it is interior reserved lifting built-in fitting, each mark time down
Plugging wire insulation board be all provided with there are two plugging wire insulation board reserve grout hole.
Further, it is 40~60mm that plugging wire insulation board, which reserves the diameter of grout hole,.
Further, surrounding package concrete topping plugging wire insulation board with a thickness of 40~50mm.
Further, the material of insulation board is material containing polystyrene thermal insulation plate in plugging wire insulation board.
A kind of preparation method of the prefabricated component stair of light silencing, this method include the following:
A, the oblique beam steel bar colligation in downside is put into the mold of precast stair well first;
B, the plugging wire insulation board for including plugging wire insulation board concrete grouting hole is fixed, and surrounding places the coagulation bound
Native surface layer steel fabric sheet;
C, by reinforcing bar binding and fixing at the bearing of waist slab upper end at the bearing of waist slab upper end, at the bearing of waist slab lower end steel
Muscle binding and fixing are at the bearing of waist slab lower end;
D, close casting concrete, wait conserve after demoulding, transport is to construction site;
E, stair temporary support, fixed upper and lower ends landing are set;
F, hoisting prefabricated component stair make to be individually positioned at the bearing of waist slab upper end, at the bearing of waist slab lower end up and down
On the landing of both ends, and it is directed at the fixation hinge pin key hole to be provided at the bearing of waist slab upper end and the cunning at the bearing of waist slab lower end
Dynamic hinge pin key hole to be provided;
G, it installs at the upper end bearing of stair waist slab: the bolt being embedded in platform board is inserted at the bearing of waist slab upper end
Fixation hinge pin key hole to be provided in;
H, it installs at the lower end bearing of stair waist slab: the bolt being embedded in platform board is inserted at the bearing of waist slab lower end
Sliding hinge pin key hole to be provided in;
Further, precast stair is that armored concrete includes polystyrene thermal insulation plate material.
Further, in step B, surrounding, which is placed, reserves concrete surface around the concrete topping steel fabric sheet bound
Layer is 40~50mm.
Further, in step G, the level at platform board and the bearing of waist slab upper end stays 20~30mm with vertically lapped place
Overlapping the slot, filled with polyphenyl, then by C30~C40 grades of grouting materials of the fixation hinge pin key hole to be provided at the bearing of waist slab upper end
Filling, the hole top for finally fixing hinge pin key hole to be provided stay the height of 20~30mm to block for mortar.
Further, in step H, the overlapping the slot of 20~30mm is stayed by lap-joint at platform board and the bearing of waist slab lower end, uses
Polyphenyl filling, after the height that 40~50mm is reserved in the hole upper end of sliding hinge pin key hole to be provided places gasket, by bolt and admittedly
Determine nut to be connected, gasket lower part is left a blank chamber, and gasket top is blocked with mortar.
Working principle is as follows:
Plugging wire insulation board is put into stair waist slab, instead of the weight of stair a big chunk concrete, and in ladder
Section plate surrounding reserves the concrete topping of 40~50mm thickness, and concrete topping steel wire is put into it, fixed when prefabricated to insert
Casting concrete, concrete can be filled from plugging wire insulation board is reserved in mold after silk insulation board and concrete topping steel wire position
Slurry flows into hole, so that concrete topping and internal plugging wire insulation board become an entirety, then the two sides below waist slab up and down
It is respectively arranged a cant beam, using stair stringer sandwich heat preservation technology, allows the stair for mitigating weight that can still bear normal use pole
Limit state load, specific reinforcing bar arrangement of reinforcement are calculated according to the practical specification of stair.At the bearing of waist slab upper end with waist slab lower end branch
Hold place and be provided with fixed hinge pin key hole to be provided and sliding hinge pin key hole to be provided, at the bearing of waist slab upper end with upper end platform,
At the bearing of waist slab lower end with the overlap joint of lower end platform.Stair can be produced using lower end sliding hinged-support when coming earthquake
Raw certain free run, discharges destructive power of the earthquake and is unlikely to generate structure destruction.Width at the bearing of bench upper end
A small distance longer than width at waist slab and the bearing of bench lower end, so that at the bearing of bench upper end and at the bearing of bench lower end
After the splicing of upper and lower platform board, meeting self-assembling formation stair shaft between stair activity, that section of distance grown is stair shaft width.
The precast stair of the utility model has the following beneficial effects:
Using factory's punching block one-pass molding, concreting in corresponding stairway die, transported after it meets intensity
The position subscribed to building site, in place by crane lifting, then with other building members splice, lifting construction efficiency, reduce construction
Duration reduces wet construction, energy-saving and emission-reduction, and for the stair of same gauge size, and the Novel staircase is more pre- than common
The weight saving of stair processed 30%~40%, avoids using large-scale tower crane equipment hoisting, also mitigates transport bring burden,
Inside setting plugging wire insulation board not only reduces weight, also saves material, reduces cost, and bring, which is marked time, when reducing walking stair makes an uproar
Sound.Stair waist slab is connect using lower end sliding hinged-support with platform simultaneously, can be avoided the formation of gangboard support, be weakened rigidity,
When being destroyed by seismic force, discharges destructive power of the earthquake and be unlikely to generate malformation even destruction.
Detailed description of the invention
Fig. 1 is the effect picture of one preferred embodiment of precast stair provided by the utility model;
Fig. 2 is the top view of one preferred embodiment of precast stair provided by the utility model;
Fig. 3 is the A-A sectional view of one preferred embodiment of precast stair provided by the utility model;
Fig. 4 is the reinforcing bar effect picture of one preferred embodiment of precast stair provided by the utility model.
In figure: 1, at the bearing of waist slab upper end;2, tread plate;3, built-in fitting is lifted;4, sliding hinge pin key hole to be provided;5, solid
Determine hinge pin key hole to be provided;6, waist slab;7, at the bearing of waist slab lower end;8, insulation board reserves grout hole;9, cant beam;10, plugging wire
Insulation board;11, reinforcing bar at the bearing of waist slab upper end;12, concrete topping steel wire;13, cant beam reinforcing bar;14, waist slab lower end
Reinforcing bar at bearing.
Specific embodiment
Below in conjunction with the attached drawing in the embodiments of the present invention, to the technical scheme in the embodiment of the utility model into
Row clearly and completely describes, it is clear that and described embodiment is only a part of the embodiment of the utility model, rather than all
Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are not making creative work premise
Under all other embodiment obtained, belong to the utility model patent protection range.
Embodiment 1
Referring to attached drawing 1 to 4, embodiment 1 is the technical solution of the prefabricated component stair of light silencing:
A kind of prefabricated component stair of light silencing, the stair include 1, tread plate 2 at the bearing of waist slab upper end, lifting it is pre-buried
Part 3, sliding hinge pin key hole to be provided 4, fixed hinge pin key hole to be provided 5, waist slab 6,7, plugging wire insulation board at the bearing of waist slab lower end
Reserved grout hole 8, cant beam 9, plugging wire insulation board 10, reinforcing bar 11, concrete topping steel wire 12, cant beam at the bearing of waist slab upper end
Reinforcing bar 14 at reinforcing bar 13 and the bearing of waist slab lower end;
Two sides respectively have a cant beam 9 to support to the waist slab 6 of the stair below, and cant beam reinforcing bar 13, bench are placed in cant beam 9
The plugging wire insulation board 10 of concrete topping is wrapped up in the plate of plate 6 for surrounding, placed concrete in surrounding package concrete topping
Surface layer steel wire 12,1 there are two fixed hinge pin key hole to be provided 5 respectively at the bearing of waist slab lower end 7 at the bearing of waist slab upper end
With sliding hinge pin key hole to be provided 4, wherein 1 it is fixed hinge pin key hole to be provided 5 and internal places bench at the bearing of waist slab upper end
Reinforcing bar 11 at the bearing of plate upper end 7 for sliding hinge pin key hole to be provided 4 and internal places waist slab lower end branch at the bearing of waist slab lower end
Hold place's reinforcing bar 14.
Tread plate 2 on every layer mark time, and mark time it is interior reserved lifting built-in fitting 3, the plugging wire under each marking time
Insulation board 10 be all provided with there are two plugging wire insulation board reserve grout hole 8.
The diameter that plugging wire insulation board reserves grout hole 8 is 40~60mm.
Surrounding wrap up concrete topping plugging wire insulation board 10 with a thickness of 40~50mm.
The material of insulation board is material containing polystyrene thermal insulation plate in plugging wire insulation board 10.
Embodiment 2
Referring to attached drawing 1 to 4, embodiment 2 is the technical solution of the preparation method of the prefabricated component stair of light silencing:
Precast stair is that armored concrete includes polystyrene thermal insulation plate material, first binds downside cant beam reinforcing bar 13
It is put into precast stair mold.
The plugging wire insulation board 10 that plugging wire insulation board concrete grouting hole 8 will be included is fixed, and surrounding places mixing of bind
Reserving concrete topping around solidifying soil surface layer steel fabric sheet 12(is 40~50mm).
By 11 binding and fixing of reinforcing bar at the bearing of waist slab upper end at the bearing of waist slab upper end at 1, waist slab lower end bearing
14 binding and fixing of reinforcing bar are 7 at the bearing of waist slab lower end
Close casting concrete, wait conserve after demoulding, transport is to construction site.
Stair temporary support, fixed upper and lower ends landing are set.
Hoisting prefabricated component stair make 1 at the bearing of waist slab upper end, 7 are individually positioned in up and down at the bearing of waist slab lower end
On the landing of both ends, and be aligned at the bearing of waist slab upper end 1 fixation hinge pin key hole to be provided 5 and the bearing of waist slab lower end at 7
Sliding hinge pin key hole to be provided 4.
The fixed hinge of 1(at the upper end bearing of stair waist slab is installed): the bolt being embedded in platform board is inserted on waist slab
It holds at bearing in 1 fixation hinge pin key hole to be provided 5, the overlapping the slot of 20~30mm is stayed at two modular levels and vertically lapped place, with poly-
Benzene filling, then by the C30~C40 grades of grouting material fillings of at the bearing of waist slab upper end 1 fixation hinge pin key hole to be provided 5, finally admittedly
The height of 20~30mm is stayed to block for mortar in the hole top for determining hinge pin key hole to be provided 5.
7(sliding hinge at the lower end bearing of stair waist slab is installed): the bolt being embedded in platform board is inserted under waist slab
It holds at bearing in 7 sliding hinge pin key hole to be provided 4, the overlapping the slot of 20~30mm is stayed by two component lap-joints, is filled with polyphenyl, in cunning
After the height that 40~50mm is reserved in the hole upper end of dynamic hinge pin key hole to be provided 4 places gasket, bolt is connected with fixture nut, is padded
Piece lower part is left a blank chamber, and gasket top is blocked with mortar.
Working principle:
Plugging wire insulation board 10 is put into stair waist slab 6, instead of the weight of stair a big chunk concrete, and
6 surrounding of waist slab reserves the concrete topping of 40~50mm thickness, and concrete topping steel wire 12 is put into it, consolidates when prefabricated
Determine behind 12 position of plugging wire insulation board 10 and concrete topping steel wire that casting concrete, concrete can be kept the temperature from plugging wire in mold
Plate is reserved to be flowed into grout hole 8, so that concrete topping and internal plugging wire insulation board 10 become an entirety up and down, then in bench
Plate 6 is respectively arranged a cant beam 9 in two sides below, using stair stringer sandwich heat preservation technology, the stair for mitigating weight can still be held
By serviceability limit state load, specific reinforcing bar arrangement of reinforcement is calculated according to the practical specification of stair.At the bearing of waist slab upper end 1 with
7 are provided with fixed hinge pin key hole to be provided 5 and sliding hinge pin key hole to be provided 4 at the bearing of waist slab lower end, are used for waist slab upper end branch
Hold place 1 and at upper end platform, the bearing of waist slab lower end 7 and the overlap joint of lower end platform.Stair use lower end sliding hinged-support can be with
Certain free run when coming earthquake, is being generated, destructive power of the earthquake is being discharged and is unlikely to generate structure destruction.Bench
Long a small distance of width of 1 width than at waist slab 6 and the bearing of bench lower end 7 at the bearing of upper end, so that bench upper end branch
Hold place 1 with the bearing of bench lower end at 7 upper and lower platform board splicing after, between stair activity can self-assembling formation stair shaft, grow that
Section distance is stair shaft width.
The above description is only the embodiments of the present invention, and therefore it does not limit the scope of the patent of the utility model, all
Equivalent structure or equivalent flow shift made based on the specification and figures of the utility model, is applied directly or indirectly in
Other relevant technical fields similarly include in the utility model patent protection scope.
Claims (5)
1. a kind of prefabricated component stair of light silencing, it is characterised in that: the stair include (1) at the bearing of waist slab upper end, anti-skidding
Item (2), lifting built-in fitting (3), sliding hinge pin key hole to be provided (4), fixed hinge pin key hole to be provided (5), waist slab (6), waist slab
(7) at the bearing of lower end, plugging wire insulation board reserve grout hole (8), cant beam (9), plugging wire insulation board (10), at the bearing of waist slab upper end
Reinforcing bar (14) at reinforcing bar (11), concrete topping steel wire (12), cant beam reinforcing bar (13) and the bearing of waist slab lower end;
Respectively there are cant beam (9) bearing in two sides to the waist slab (6) of the stair below, place cant beam reinforcing bar (13) in cant beam (9),
The plugging wire insulation board (10) of concrete topping is wrapped up in the plate of waist slab (6) for surrounding, surrounding is wrapped up in concrete topping and being placed
Concrete topping steel wire (12), (7) there are two fixed respectively at (1) and the bearing of waist slab lower end at the bearing of waist slab upper end
Hinge pin key hole to be provided (5) and sliding hinge pin key hole to be provided (4), wherein (1) is that fixed hinge pin key is pre- at the bearing of waist slab upper end
Box out (5) and it is internal place reinforcing bar (11) at the bearing of waist slab upper end, (7) are that sliding hinge pin key is reserved at the bearing of waist slab lower end
Reinforcing bar (14) at hole (4) and internal placement waist slab lower end bearing.
2. the prefabricated component stair of light silencing according to claim 1, it is characterised in that: tread plate (2) is positioned at every layer
On marking time, and mark time it is interior reserved lifting built-in fitting (3), the plugging wire insulation board (10) under each marking time is all provided with there are two plugging wire
Insulation board reserves grout hole (8).
3. the prefabricated component stair of light silencing according to claim 2, it is characterised in that: plugging wire insulation board reserves grout hole
(8) diameter is 40~60mm.
4. the prefabricated component stair of light silencing according to claim 1, it is characterised in that: surrounding wraps up concrete topping
Plugging wire insulation board (10) with a thickness of 40~50mm.
5. the prefabricated component stair of light silencing according to claim 1, it is characterised in that: heat preservation in plugging wire insulation board (10)
The material of plate is material containing polystyrene thermal insulation plate.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920001000.1U CN209413171U (en) | 2019-01-02 | 2019-01-02 | A kind of prefabricated component stair of light silencing |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920001000.1U CN209413171U (en) | 2019-01-02 | 2019-01-02 | A kind of prefabricated component stair of light silencing |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209413171U true CN209413171U (en) | 2019-09-20 |
Family
ID=67942383
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201920001000.1U Active CN209413171U (en) | 2019-01-02 | 2019-01-02 | A kind of prefabricated component stair of light silencing |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209413171U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112663883A (en) * | 2020-12-22 | 2021-04-16 | 浙江省建筑设计研究院 | Prefabricated staircase with pore channels and installation method thereof |
-
2019
- 2019-01-02 CN CN201920001000.1U patent/CN209413171U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112663883A (en) * | 2020-12-22 | 2021-04-16 | 浙江省建筑设计研究院 | Prefabricated staircase with pore channels and installation method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103388357B (en) | Shatter-proof, prefabricated steel tube shear Temperature Variation In Buildings of Mixed Structures thing | |
CN206707005U (en) | A kind of prefabricated PC concrete frame structure | |
CN107254933A (en) | The high-rise single through hole precast shear wall of assembled and its assembling structure and construction method | |
CN109648696A (en) | Side slope precast lattice beam of reinforcing bar connection and preparation method thereof and construction method | |
CN107882052A (en) | A kind of prefabricated assembled sinking basis of additional building elevator | |
CN108775084A (en) | Steel-concrete combines precast beam and prefabricated post connection structure and construction method | |
CN209413171U (en) | A kind of prefabricated component stair of light silencing | |
CN206769199U (en) | After wear formula post stretching vertical prestressing cast-in-place concrete rod structure | |
CN107100322B (en) | Post stretching vertical prestressing cast-in-place concrete rod structure and construction method | |
CN206769200U (en) | First wear formula post stretching vertical prestressing cast-in-place concrete rod structure | |
CN211312950U (en) | Assembled integral elevator shaft prefabricated part | |
CN113027021A (en) | Support-free prefabricated floor slab with bracket | |
CN105952044B (en) | Fully-prefabricated prestressed concrete floor structure and prestressed assembly method | |
CN209293197U (en) | Wall and floor connection structure and assembled arthitecutral structure system | |
CN208907228U (en) | A kind of prestressing force modular retaining wall | |
CN217204165U (en) | Assembled anchor rod frame beam | |
CN207891904U (en) | A kind of prefabricated basic component of additional elevator of existing building | |
CN109680833A (en) | The prefabricated reinforcing bar concrete panel component of self-bearing type, wall, structural system and production method | |
CN106013200A (en) | Prefabricated assembly type strip foundation and construction technology | |
CN206529881U (en) | The constructing device of cushion cap and ground girder construction | |
CN113279423B (en) | Prefabricated column pier and post-cast strip foundation beam assembly integral construction method | |
CN205382595U (en) | Integral shear force wall of steel pipe concrete edge constraint coincide | |
CN212452765U (en) | Two-in-one underground pipe gallery structure | |
CN110512776B (en) | Construction method of assembled steel structure multi-cavity steel plate composite shear wall | |
CN209670221U (en) | A kind of hollow stair of limited destructing preformed rigid connection structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |