CN209385146U - Tunnel double-lining concrete construction is without door frame formwork jumbo - Google Patents
Tunnel double-lining concrete construction is without door frame formwork jumbo Download PDFInfo
- Publication number
- CN209385146U CN209385146U CN201821364124.8U CN201821364124U CN209385146U CN 209385146 U CN209385146 U CN 209385146U CN 201821364124 U CN201821364124 U CN 201821364124U CN 209385146 U CN209385146 U CN 209385146U
- Authority
- CN
- China
- Prior art keywords
- arc template
- sliding slot
- fixed
- lifting
- oil cylinder
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn - After Issue
Links
- 238000010276 construction Methods 0.000 title claims abstract description 26
- 238000009415 formwork Methods 0.000 title claims abstract description 14
- 238000009434 installation Methods 0.000 claims description 6
- 230000003028 elevating effect Effects 0.000 claims description 5
- 238000009423 ventilation Methods 0.000 abstract description 2
- 230000003014 reinforcing effect Effects 0.000 description 4
- 239000012530 fluid Substances 0.000 description 3
- 238000005266 casting Methods 0.000 description 2
- 239000003500 flue dust Substances 0.000 description 2
- 240000007594 Oryza sativa Species 0.000 description 1
- 235000007164 Oryza sativa Nutrition 0.000 description 1
- 230000001154 acute effect Effects 0.000 description 1
- 238000009412 basement excavation Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000018109 developmental process Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 230000007115 recruitment Effects 0.000 description 1
- 235000009566 rice Nutrition 0.000 description 1
- 230000011218 segmentation Effects 0.000 description 1
- 239000000779 smoke Substances 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
Abstract
Tunnel double-lining concrete construction is without door frame formwork jumbo, it is placement traveling wheel in orbit and fixed lifting traveller, lifting cylinder is fixed in the upper end, lifting cylinder is fixed on bottom beam, sliding slot in side is set between bottom beam, oil cylinder in tune is inlayed in side sliding slot, its telescopic end affixed side sliding column is simultaneously sleeved in side sliding slot, setting driving platform and step of getting on the bus on bottom beam, upper arc template and side arc template are hinged, upper arc template sets transverse beam below, vertical columns between transverse beam and upper arc template, cantilever mounted beam and operation platform in the arc template of side, side arc oil cylinder is fixed in transverse beam, arc oil cylinder 7 telescopic end in side is hinged on a cantilever beam.The utility model is structurally reasonable, stable mechanical performance, easy to operate, fast and accurate for positioning, stability is good, and integral mold plate rigid is high, and deflection is small, and channel available space is big, Construction traffic operation is smooth, and ventilation strip can pass through, and improve the construction environment in tunnel.
Description
Technical field
The utility model relates to a kind of tunnel double-lining concrete blinding trolley, specifically a kind of tunnel double-lining concrete construction
Without door frame formwork jumbo, belong to road and bridge construction field.
Background technique
With the fast development that national basis is built, more strict requirements are proposed to construction quality and safety.
Especially the construction quality of Railway Tunnel concrete is required more to standardize, tunnel double-lining concreting generally uses 12
Rice formwork jumbo segmentation successively pours, and inevitably there are construction joints between every section, by every section of construction joint of job specfication requirement
It should be smooth smooth.And code requirement is extremely difficult in practice of construction, especially ground face upward 2 meters or so seam crossing most
It is easy to appear concrete height faulting of slab ends, and faulting of slab ends degree is larger, generally taken to eliminate faulting of slab ends in faulting of slab ends position erection construction
The concrete being higher by is polished flat on platform with sanding machine suitable by platform, construction personnel;There are also be exactly small abutment wall and lower arc template
Lower part lap-joint is also easy to appear faulting of slab ends, and main cause is that the bottom of formwork jumbo lower part camber template is added with screw rod and ground
Gu the angle of two fulcrums is generally acute angle, the pressure of concrete casting and the impact force of concrete vibrating are easy template
Now float shrink or tension and relaxation and there is faulting of slab ends, if screw rod to reinforce it is not firm, it is possible that spillage and run mould, go out concrete
It now sheds tears line, voids and pits, serious influence concrete solid quality;Due to the particularity of constructing tunnel, two lining concrete moulds
Pallet vehicle must assure that Construction traffic is passed through from trolley door frame, so the door frame bottom of formwork jumbo cannot achieve rigidity branch
Support, the pressure when being poured concrete can make two sides door frame to central reduction, also be easy that concrete seam is made faulting of slab ends occur.Separately
The reinforcing screw rod of outer this formwork jumbo is especially more, has lower arc template to the reinforcing screw rod of door frame, has lower arc template to ground
Screw rod is reinforced, screw rod is exactly to require construction personnel to reinforce rotation to hold out against reinforcings, more than recruitment and large labor intensity, simultaneously because area
Face, which is excavated, mostly uses big machinery to carry out excavation construction, so flue dust is larger in tunnel, since two lining formwork jumbos are there are door frame,
Oil smoke is not easy that tunnel is discharged, and seriously affects construction.There is presently no a kind of rigidity, and strong, environmentally friendly and structurally reasonable tunnel double-lining mixes
Solidifying soil construction formwork trolley.
Utility model content
The utility model aim is the current tunnel double-lining concrete blinding trolley defect present in construction of solution, thus
A kind of tunnel double-lining concrete construction is disclosed without door frame formwork jumbo.
The technical solution of the utility model is as follows:
Two tracks are placed on the ground of tunnel longitudinal direction, two traveling wheels are placed on every track, on each traveling wheel
Fixed lifting traveller respectively, in lifting sliding slot, lifting sliding slot perforation is embedded on bottom beam lifting slide rod sleeve, is gone up and down on traveller
End is fixed on lifting cylinder telescopic end, and lifting cylinder fixing end is fixed on bottom beam, is set a side between three foundation beams respectively and is pushed away
Sliding slot is connected with each other between bottom beam and side sliding slot by attachment beam, and oil in a tune is respectively inlayed in each side sliding slot both ends
Cylinder, oil cylinder telescopic end fixes a side sliding column respectively in tune, and sliding column sleeve in side is in side sliding slot, fixer on attachment beam
Case is pressed, step of getting on the bus is respectively set in setting driving platform on bottom beam, driving platform both ends, and guardrail is arranged in driving platform two sides, even
Beam side installation elevating screw is connect, lead screw is reinforced in installation between bottom beam and side arc template, and upper arc template and side arc template pass through hinge
Even pin is hinged, and upper arc template sets several transverse beams below, and instrument in adjusting, every transverse beam and upper arc are installed in the middle part of the transverse beam of front end
A plurality of uprights are fixed between template, and a cantilever beam and two operation platforms, side arc oil cylinder are fixed in every piece of side arc template
Fixing end is fixed in transverse beam, and arc oil cylinder 7 telescopic end in side is hinged on a cantilever beam.
The utility model design structure is reasonable, and stable mechanical performance is easy to operate, and centering uses infrared ray adjustment dress
It sets, fast and accurate for positioning, whole trolley surrounding and bottom form closed structure, and stability is good, and integral mold plate rigid is high,
Deflection is small, and channel available space is big, and Construction traffic operation is smooth, and ventilation strip can pass through, the more advantageous tunnel of channel large space
The flue dust of road front end face is discharged, and improves the construction environment in tunnel, so reaching one meets quality safety requirement
Tunnel double-lining concrete construction is without door frame formwork jumbo.
Detailed description of the invention
Attached drawing 1 is the schematic view of the front view of the utility model.
Attached drawing 2 be the utility model attached drawing 1 along A-A to left view the schematic diagram of the section structure.
The reference numerals are as follows: upper arc template 1, side arc template 2, hinge pin 3, column 4, transverse beam 5, cantilever beam 6, side
Arc oil cylinder 7, operation platform 8, track 9, traveling wheel 10, lifting cylinder 11 go up and down traveller 12, go up and down sliding slot 13, bottom beam 14, in tune
Oil cylinder 15 reinforces lead screw 16, attachment beam 17, side sliding column 18, side sliding slot 19, instrument 20 in tune, hydraulic fluid tank 21, step of getting on the bus
22, platform 23 of driving a vehicle, guardrail 24, elevating screw 25.
Specific embodiment
The utility model is described in further detail below in conjunction with attached drawing:
Two tracks 9 are placed on the ground of tunnel longitudinal direction, two traveling wheels 10 are placed on every track 9, in each walking
Fixed lifting traveller 12, lifting traveller 12 are sleeved in lifting sliding slot 13 respectively on wheel 10, and the lifting perforation of sliding slot 13 is embedded in bottom
On beam 14, lifting 12 upper end of traveller is fixed on 11 telescopic end of lifting cylinder, and 11 fixing end of lifting cylinder is fixed on bottom beam 14, and three
A side sliding slot 19 is set between foundation beam 14 respectively, is connected with each other between bottom beam 14 and side sliding slot 19 by attachment beam 17,
Oil cylinder 15 in a tune is respectively inlayed in each 19 both ends of side sliding slot, 15 telescopic end of oil cylinder fixes a side sliding column respectively in tune
18, side sliding column 18 is sleeved in side sliding slot 19, fixed hydraulic case 21 on attachment beam 17, setting driving platform on bottom beam 14
23, step 22 of getting on the bus is respectively set in driving 23 both ends of platform, and guardrail 24, the installation of 17 side of attachment beam is arranged in driving 23 two sides of platform
Elevating screw 25, lead screw 16 is reinforced in installation between bottom beam 14 and side arc template 2, and upper arc template 1 passes through the pin that is hinged with side arc template 2
3 are hinged, and upper arc template 1 sets five transverse beams 5 below, in the middle part of front end transverse beam 5 installation adjust in instrument 20, every transverse beam 5 with it is upper
Three root posts 4 are fixed between arc template 1, fix a cantilever beam 6 and two operation platforms 8, side arc in every piece of side arc template 2
7 fixing end of oil cylinder is fixed in transverse beam 5, and arc oil cylinder 7 telescopic end in side is hinged on cantilever beam 6.
When the utility model is used, two tracks are laid in tunnel ground level first, trolley is placed in orbit, is led to
It crosses traveling wheel and pushes to the position that need to be poured concrete, open hydraulic fluid tank, oil cylinder in tune is adjusted by instrument in adjusting and is stretched, really
It is consistent with tunnel middle line to determine trolley middle line, lifting cylinder extends to jack trolley to specified altitude assignment and stop, rotation and lifting lead screw, silk
Thick stick extends top to ground, and oil cylinder, which extends, in tune drives sliding capital in side to stretch lower arc template to designated position stopping, rotating reinforcing wire
Thick stick is reinforced lead screw extension opposite side arc template and is reinforced, is laid with step of getting on the bus, starts casting concrete, after concrete setting,
Remove step of getting on the bus, close hydraulic fluid tank, come loose and reinforce lead screw and elevating screw, trolley resets, and so on enter next section to apply
Work.
Claims (2)
1. tunnel double-lining concrete construction is without door frame formwork jumbo, it is characterised in that: place two rails on the ground of tunnel longitudinal direction
Two traveling wheels (10) are placed in road (9) on every track (9), fixed lifting traveller (12) respectively on each traveling wheel (10),
Lifting traveller (12) is sleeved in lifting sliding slot (13), and lifting sliding slot (13) perforation is embedded on bottom beam (14), goes up and down traveller
(12) upper end is fixed on lifting cylinder (11) telescopic end, and lifting cylinder (11) fixing end is fixed on bottom beam (14), three foundation beams
(14) a side sliding slot (19) is set between respectively, is mutually interconnected between bottom beam (14) and side sliding slot (19) by attachment beam (17)
It connects, oil cylinder (15) in a tune is respectively inlayed in each side sliding slot (19) both ends, oil cylinder (15) telescopic end fixes one respectively in tune
A side sliding column (18), side sliding column (18) are sleeved in side sliding slot (19), fixed hydraulic case (21), bottom on attachment beam (17)
Setting driving platform (23) on beam (14), driving platform (23) both ends are respectively set step of getting on the bus (22), platform (23) two of driving a vehicle
Guardrail (24) are arranged in side, and elevating screw (25) are installed in attachment beam (17) side, and installation adds between bottom beam (14) and side arc template (2)
Gu lead screw (16), upper arc template (1) and side arc template (2) are hinged by the pin (3) that is hinged, upper arc template (1) sets several below
Transverse beam (5), instrument (20) in tune is installed at front end transverse beam (5) middle part, fixed between every transverse beam (5) and upper arc template (1)
A plurality of uprights (4) fix a cantilever beam (6) and two operation platforms (8), side arc oil cylinder on every piece of side arc template (2)
(7) fixing end is fixed on transverse beam (5), and side arc oil cylinder (7) telescopic end is hinged on cantilever beam (6).
2. tunnel double-lining concrete construction according to claim 1 is without door frame formwork jumbo, it is characterised in that: upper arc template
(1) five transverse beams (5) are set below, fixes three root posts (4) between every transverse beam (5) and upper arc template (1).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821364124.8U CN209385146U (en) | 2018-08-23 | 2018-08-23 | Tunnel double-lining concrete construction is without door frame formwork jumbo |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821364124.8U CN209385146U (en) | 2018-08-23 | 2018-08-23 | Tunnel double-lining concrete construction is without door frame formwork jumbo |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209385146U true CN209385146U (en) | 2019-09-13 |
Family
ID=67869298
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821364124.8U Withdrawn - After Issue CN209385146U (en) | 2018-08-23 | 2018-08-23 | Tunnel double-lining concrete construction is without door frame formwork jumbo |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209385146U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108868832A (en) * | 2018-08-23 | 2018-11-23 | 中铁二十局集团第三工程有限公司 | Tunnel double-lining concrete construction is without door frame formwork jumbo |
-
2018
- 2018-08-23 CN CN201821364124.8U patent/CN209385146U/en not_active Withdrawn - After Issue
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108868832A (en) * | 2018-08-23 | 2018-11-23 | 中铁二十局集团第三工程有限公司 | Tunnel double-lining concrete construction is without door frame formwork jumbo |
CN108868832B (en) * | 2018-08-23 | 2024-03-19 | 中铁二十一局集团第三工程有限公司 | Portal-free template trolley for tunnel secondary lining concrete construction |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101230785B (en) | Construction method for large section and multiple sections tunnel lining | |
CN104594918B (en) | Split integrated underground passage steel mold plate trolley and construction method thereof | |
CN103967050A (en) | Construction system of subway station | |
CN101302739B (en) | Prestress concrete box girder hydraulic internal mold vehicle as well as hydraulic internal mold system | |
CN106089253A (en) | A kind of all-hydraulic template system poured for culvert | |
CN107387122A (en) | A kind of formwork jumbo and its construction method for the construction of piping lane tunneling boring | |
CN108103945B (en) | A kind of whole landing mould bases of cast-in-situ box girder | |
CN104499434A (en) | Movable formwork for casting of wide-body box girder and construction method | |
CN106812541A (en) | A kind of adjustable bore tunnel construction platform car and adjusting method | |
CN108868832A (en) | Tunnel double-lining concrete construction is without door frame formwork jumbo | |
CN104453951B (en) | Combined type subway station lining template trolley for baffle | |
CN209385146U (en) | Tunnel double-lining concrete construction is without door frame formwork jumbo | |
CN202412422U (en) | Template system for prefabricating simply-supported box girder | |
CN109629439B (en) | Construction method of single-tower cable-stayed bridge | |
CN103388305A (en) | Railway T-beam cast-in-site bridge deck forming machine | |
CN203248170U (en) | Lining trolley for secondary lining construction of pedestrian crosswalk | |
CN104110002A (en) | Method for replacing bridge deck slabs of steel truss girder bridge | |
CN102268858A (en) | Cradle for suspension pouring of arch-type bridge | |
KR20050108867A (en) | A method for changing plate-girder bridge of railway bridge into slab bridge by using temporary construction bents. | |
CN211762304U (en) | Self-propelled hydraulic integral T-beam template device | |
CN102528910A (en) | Template system of prefabricated simply support box beam | |
CN205243529U (en) | Tunnel secretly digs lining construction platform truck | |
CN108098978A (en) | A kind of assembled underground pipe gallery epimere producing device and production method | |
CN212335790U (en) | Large cantilever bent cap construction trolley | |
CN105178197B (en) | Support frame for bearing formworks of initial blocks of bridge box girder and initial block construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
AV01 | Patent right actively abandoned |
Granted publication date: 20190913 Effective date of abandoning: 20240319 |
|