CN209353221U - A kind of packaged type cantilever job platform for the construction of side guardrail - Google Patents

A kind of packaged type cantilever job platform for the construction of side guardrail Download PDF

Info

Publication number
CN209353221U
CN209353221U CN201821463854.3U CN201821463854U CN209353221U CN 209353221 U CN209353221 U CN 209353221U CN 201821463854 U CN201821463854 U CN 201821463854U CN 209353221 U CN209353221 U CN 209353221U
Authority
CN
China
Prior art keywords
cantilever
steel
construction
steel frame
job platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821463854.3U
Other languages
Chinese (zh)
Inventor
管世玉
高波
张晓俊
钱叶存
陈浩
陈云锋
程华敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Construction Co Ltd of China Construction Third Engineering Division
Original Assignee
First Construction Co Ltd of China Construction Third Engineering Division
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Construction Co Ltd of China Construction Third Engineering Division filed Critical First Construction Co Ltd of China Construction Third Engineering Division
Priority to CN201821463854.3U priority Critical patent/CN209353221U/en
Application granted granted Critical
Publication of CN209353221U publication Critical patent/CN209353221U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model relates to a kind of packaged type cantilever job platforms for the construction of side guardrail, including main steel frame, cantilever, electric block, steel roller and clump weight, steel roller is set to the bottom of main steel frame, one end of cantilever is connected to the one end at the top of main steel frame, the other end of cantilever stretches out the other end of main steel frame, cantilever is equipped with sliding rail along its length, and it is connect along the scroll wheel that sliding rail slides with electric block by opposite sides, to lift by crane and be moved to by guardrail steel form on the outside of guardrail, by the installation for manually carrying out template on cantilever.The utility model is not limited by place, can lifting transhipment template and safe cantilever job platform is provided for side crash barrier steel form installment work, it is horizontal to improve mechanized construction, accelerates construction progress, reduces security risk.

Description

A kind of packaged type cantilever job platform for the construction of side guardrail
Technical field
The utility model relates to technical field of building construction, more specifically to it is a kind of for the construction of side guardrail can Movable suspending arm job platform.
Background technique
In bridge floor anticollision barrier construction site, especially urban interchange, the construction of bridge deck concrete anticollision barrier is being carried out When, steel form is heavier, and Work sectors are longer, and automobile crane operation is inflexible, and it is costly, and place is required, though crane It is low to the small expense of site requirements, but job area is limited.
Utility model content
The technical problem to be solved by the present invention is to the construction equipment works in the prior art for the construction of side guardrail Industry is not flexible, and costly, therefore provides a kind of packaged type cantilever job platform for the construction of side guardrail, and operation can be improved Efficiency reduces cost.
The technical scheme adopted by the utility model to solve the technical problem is as follows: construct it is a kind of for side guardrail construction can Movable suspending arm job platform, which is characterized in that including main steel frame, cantilever, electric block, steel roller and clump weight, the steel Idler wheel is set to the bottom of main steel frame, and one end of the cantilever is connected to the one end at the top of main steel frame, the other end of the cantilever The other end of main steel frame is stretched out, the cantilever is equipped with sliding rail along its length, and sliding along sliding rail by opposite sides Dynamic scroll wheel is connect with electric block, and guardrail steel form is lifted by crane and is moved on the outside of guardrail, by manually enterprising in cantilever The installation of row template.
Preferably, the bottom of the main steel frame is equipped with telescopic legs far from the side of clump weight.
Preferably, the bottom of the main steel frame bottom beam parallel with cantilever is the first channel steel, set in first channel steel There is the second channel steel, second channel steel is equipped with supporting leg far from one end of clump weight, supporting leg is pulled to make the second channel steel along first Channel steel telescopic moving, to form the telescopic legs.
Preferably, the clump weight includes steel reinforcement cage and concrete block, the bottom of the steel reinforcement cage and main steel frame is connected, The concrete block is placed in steel reinforcement cage.
Preferably, the sliding rail is located at one end above clump weight equipped with limit steel bar, to prevent the sliding Wheel removes sliding rail.
A kind of packaged type cantilever job platform for the construction of side guardrail for implementing the utility model, has beneficial below Effect: the utility model is not limited by place, can lifting transhipment template and be the installment work of side crash barrier steel form mention For the cantilever job platform of safety, mechanized construction level is improved, accelerates construction progress, reduces security risk.
Detailed description of the invention
Below in conjunction with accompanying drawings and embodiments, the utility model is described in further detail, in attached drawing:
Fig. 1 is that a kind of stereochemical structure of packaged type cantilever job platform for the construction of side guardrail of the utility model is shown It is intended to;
Fig. 2 is a kind of operation signal of packaged type cantilever job platform for the construction of side guardrail of the utility model Figure.
Specific embodiment
For a clearer understanding of the technical features, objectives and effects of the utility model, now control attached drawing is detailed Illustrate specific embodiment of the present utility model.
It should be noted that in the description of the present invention, term " on ", "lower", "front", "rear", "left", "right", The orientation or positional relationship of the instructions such as "vertical", "horizontal", "top", "bottom", "inner", "outside" be orientation based on the figure or Positional relationship is merely for convenience of describing the present invention and simplifying the description, and is not the device or member of indication or suggestion meaning Part must have a particular orientation, be constructed and operated in a specific orientation, therefore should not be understood as limiting the present invention. In addition, term " first ", " second " etc. are used for descriptive purposes only and cannot be understood as indicating or suggesting relative importance.
As depicted in figs. 1 and 2, in a kind of packaged type cantilever job platform for the construction of side guardrail of the utility model Embodiment in, including main steel frame 1, cantilever 3, electric block 5, steel roller 7 and clump weight, steel roller 7 are set to the bottom of main steel frame 1 Portion, one end of cantilever 3 are connected to the one end at the top of main steel frame 1, and the other end of cantilever 3 stretches out the other end of main steel frame 1, cantilever 3 opposite sides along its length is equipped with sliding rail, and the scroll wheel 4 slided by opposite sides along sliding rail with it is electronic Cucurbit 5 connects, and guardrail steel form is lifted by crane and is moved on the outside of guardrail, by the installation for manually carrying out template on cantilever.
In the present embodiment, the bottom of main steel frame 1 is equipped with telescopic legs far from the side of clump weight.Specifically, main steel frame 1 The bottom bottom beam parallel with cantilever 3 be the first channel steel 11, be equipped with the second channel steel 10 in the first channel steel 11, the second channel steel 10 is separate One end of clump weight is equipped with supporting leg 6, and supporting leg 6 is pulled to make the second channel steel 10 along 11 telescopic moving of the first channel steel, can with formation Telescopic outrigger can increase the antidumping arm of force, increase the stability of structure.
In the present embodiment, clump weight includes steel reinforcement cage 8 and concrete block, and steel reinforcement cage 8 is connect with the bottom of main steel frame 1, is mixed Solidifying soil block is placed in steel reinforcement cage 8.
In the present embodiment, sliding rail is located at one end above clump weight equipped with limit steel bar, to prevent the removal of on-slip driving wheel Sliding rail.
It, will using 40 × 3 angle steel of ∠ by use channel steel shown in Fig. 1 and Fig. 2 by 1 firm welding of main steel frame in the present embodiment 3 firm welding of cantilever is connected between main steel frame 1 and cantilever 3 using bolt 9, and supporting leg 2 is connected using bolt 9.Using HW125 × For 125H fashioned iron as cantilever 3, No. 20 round steel are welded as limit steel bar in the end of cantilever 3, prevent scroll wheel 4 and its attachment sliding Sliding rail out.Pedestal is welded using Two bors d's oeuveres channel steel, and according to construction personnel's weight and safety coefficient requirement, weight is reasonably mixed Solidifying soil block is fixed in steel reinforcement cage 8, increases resistance to tipping moment.
Mobile base of one of the utility model for the packaged type cantilever job platform of side guardrail construction is solid Fixed multidirectional shifting roller, can also be quickly remote mobile under the mechanical engagements such as fork truck.
The utility model is reasonable by a kind of packaged type cantilever job platform design structure for the construction of side guardrail, real Show and has not been limited and can be moved freely on bridge floor by hoisting operation place, it can lifting transhipment template and for side anticollision barrier Steel form installment work provides the cantilever job platform of safety, improves mechanized construction level, accelerates construction progress, reduce Security risk.
A kind of packaged type cantilever job platform for the construction of side guardrail, application method following steps:
1, production, the assembled inspection that carries out an acceptance inspection first after the completion, carry out trial operation, trial operation is qualified again on inspection after qualification It can come into operation;
2, it manually pushes or under the mechanical engagements such as fork truck, cantilever job platform is moved to construction area;
3, guardrail steel form is lifted by crane by scroll wheel, sliding rail and electric block and is moved on the outside of guardrail;
4, operating personnel enters on cantilever cradle the installment work for carrying out template, before operating personnel enters cantilever cradle, draws Two sides telescopic legs are opened, and safety rope is fixed on the reliable position of bridge floor.
The embodiments of the present invention are described above in conjunction with attached drawing, but the utility model is not limited to The specific embodiment stated, the above mentioned embodiment is only schematical, rather than restrictive, this field it is common Technical staff is not departing from the utility model aims and scope of the claimed protection situation under the enlightenment of the utility model Under, many forms can be also made, these are belonged within the protection of the utility model.

Claims (5)

1. a kind of packaged type cantilever job platform for the construction of side guardrail, which is characterized in that including main steel frame, cantilever, electricity Dynamic cucurbit, steel roller and clump weight, the steel roller are set to the bottom of main steel frame, and one end of the cantilever is connected to main steel frame The one end at top, the other end of the cantilever stretch out the other end of main steel frame, and the cantilever is equipped with sliding rail along its length, And connect along the scroll wheel that sliding rail slides with electric block by opposite sides, guardrail steel form is lifted by crane and is moved to On the outside of guardrail, by the installation for manually carrying out template on cantilever.
2. a kind of packaged type cantilever job platform for the construction of side guardrail according to claim 1, which is characterized in that The bottom of the main steel frame is equipped with telescopic legs far from the side of clump weight.
3. a kind of packaged type cantilever job platform for the construction of side guardrail according to claim 2, which is characterized in that The bottom of the main steel frame bottom beam parallel with cantilever is the first channel steel, is equipped with the second channel steel in first channel steel, described the Two channel steels are equipped with supporting leg far from one end of clump weight, pull supporting leg to make the second channel steel along the first channel steel telescopic moving, with shape At the telescopic legs.
4. a kind of packaged type cantilever job platform for the construction of side guardrail according to claim 1, which is characterized in that The clump weight includes steel reinforcement cage and concrete block, and the bottom of the steel reinforcement cage and main steel frame connects, and the concrete block is placed in In steel reinforcement cage.
5. a kind of packaged type cantilever job platform for the construction of side guardrail according to claim 1, which is characterized in that The sliding rail is located at one end above clump weight equipped with limit steel bar, to prevent the scroll wheel from removing sliding rail.
CN201821463854.3U 2018-09-07 2018-09-07 A kind of packaged type cantilever job platform for the construction of side guardrail Active CN209353221U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821463854.3U CN209353221U (en) 2018-09-07 2018-09-07 A kind of packaged type cantilever job platform for the construction of side guardrail

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821463854.3U CN209353221U (en) 2018-09-07 2018-09-07 A kind of packaged type cantilever job platform for the construction of side guardrail

Publications (1)

Publication Number Publication Date
CN209353221U true CN209353221U (en) 2019-09-06

Family

ID=67779591

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821463854.3U Active CN209353221U (en) 2018-09-07 2018-09-07 A kind of packaged type cantilever job platform for the construction of side guardrail

Country Status (1)

Country Link
CN (1) CN209353221U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111661594A (en) * 2020-06-01 2020-09-15 王斌 Construction is with enclosing fender installation device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111661594A (en) * 2020-06-01 2020-09-15 王斌 Construction is with enclosing fender installation device
CN111661594B (en) * 2020-06-01 2021-03-30 广东联创建筑工程有限公司 Construction is with enclosing fender installation device

Similar Documents

Publication Publication Date Title
CN202186848U (en) Universal movable maintenance gantry crane
CN107990051A (en) It is a kind of to lift auxiliary device in place and method for jacking pipe joints
CN205294665U (en) Jack -up tower crane based on engineering mechanics
JPH0841828A (en) Bridge girder erection equipment
CN104863374B (en) Large-span steel slipping mechanism and its gliding method
CN106088609A (en) A kind of integral lifting method of large span steel structure vestibule
CN209353221U (en) A kind of packaged type cantilever job platform for the construction of side guardrail
CN103422662A (en) Integral mobile construction platform for cast-in-place of elevator shaft and method for using same
CN102190249A (en) Method for hoisting equipment positioned at bottom of multilayer frame platform
CN203173644U (en) Multifunctional lifting shaft working platform system
CN105569692A (en) Trolley for welding tunnel waterproof board hanging cloth
CN103274315A (en) Installing and hoisting device for side plate and upright of gas chamber
CN212559194U (en) Lifting frame for finite space drilling pile
CN203877780U (en) High-leg and low-leg handle gantry crane for road
CN212773376U (en) Protection platform encorbelments
CN201250058Y (en) Improved lifting trolley
CN110388066B (en) Unit type curtain wall plate construction machine
CN201083018Y (en) Mobile multipurpose fast mounting scaffold
JP2014047479A (en) Method for lifting demolishing heavy machine to building to be demolished
CN213653209U (en) Integrated construction movable platform for bridge flange plate
CN205369033U (en) Gallows formula bridge tool car
CN212425380U (en) Turning device suitable for prefabricated stand
CN211665577U (en) Folding arm type anti-flexibility stretching operation platform
CN202626840U (en) Hanging basket device used in construction of slag retaining wall of railway cast-in-situ edge beam
CN112627043A (en) Installation device and method for composite cable saddle of narrow cavern of suspension bridge in mountainous area

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant