CN209323023U - A kind of tin plating production line of cable end cold process - Google Patents

A kind of tin plating production line of cable end cold process Download PDF

Info

Publication number
CN209323023U
CN209323023U CN201822168072.3U CN201822168072U CN209323023U CN 209323023 U CN209323023 U CN 209323023U CN 201822168072 U CN201822168072 U CN 201822168072U CN 209323023 U CN209323023 U CN 209323023U
Authority
CN
China
Prior art keywords
cable
support roller
tin plating
cable end
production line
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201822168072.3U
Other languages
Chinese (zh)
Inventor
罗英宝
仲华
姜正权
周黎黎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Zhengdao Technology Co ltd
Original Assignee
ZHEJIANG ZHENGDAO LAN CABLE Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG ZHENGDAO LAN CABLE Co Ltd filed Critical ZHEJIANG ZHENGDAO LAN CABLE Co Ltd
Priority to CN201822168072.3U priority Critical patent/CN209323023U/en
Application granted granted Critical
Publication of CN209323023U publication Critical patent/CN209323023U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Electroplating Methods And Accessories (AREA)

Abstract

The utility model relates to cable processing technique fields, specially a kind of tin plating production line of cable end cold process, including the exposed winding type cable in both ends, with the support roller of winding type cable socket, the conveying mechanism for driving the support roller to advance, descaling bath, pot and the rinse bath set gradually along the conveying mechanism direction of advance, it is separately positioned on the support roller elevating mechanism of the descaling bath, pot and rinse bath two sides, the descaling bath, pot and rinse bath are located at support roller direction of advance bottom.The tin plating production line of the cold process of the application can carry out pickling, tin plating and cleaning and drying to cable end automatically, liberate labour, and improve the tin plating efficiency and tin plating effect of cable end.

Description

A kind of tin plating production line of cable end cold process
Technical field
The utility model relates to cable processing technique field, specially a kind of tin plating production line of cable end cold process.
Background technique
Some special cable construction occasions, need to use short-range multi-cable line, and every cable both ends need It is tin plating to carry out to cut off the end of a thread.Thread end is stripped by manual operation at present, then uses electric iron manual soldering, which behaviour Make very complicated, time-consuming and laborious, and conducting wire is too thin, scolding tin inefficiency, scolding tin defect rate is high.And it is accidentally connect when artificial tin plating Touching tin plating solution is also easy to hurt hand, and long-term operation can impact the health of operator.
Utility model content
In view of the problems of the existing technology the utility model, proposes a kind of tin plating production line of cable end cold process.
The technical scheme adopted by the utility model to solve the technical problem is as follows: a kind of tin plating production of cable end cold process Line, including the exposed winding type cable in both ends, the support roller being socketed with the winding type cable drives the support roller to advance Conveying mechanism, descaling bath, pot and the rinse bath set gradually along the conveying mechanism direction of advance are separately positioned on described The support roller elevating mechanism of descaling bath, pot and rinse bath two sides, the descaling bath, pot and rinse bath are located at the branch Support roller direction of advance bottom.
Preferably, the conveying mechanism includes the conveying assembly for being symmetricly set on the support roller axial ends, it is described Conveying assembly includes circulating conveyer belt, is tensioned the idler roller of the conveyer belt, drives the driving motor of the idler roller rotation, And several support sleeve mouths of the conveyor belt surface are set.
Preferably, the support roller elevating mechanism includes the support roller liter for being symmetricly set on the support roller axial ends Come down to a lower group part, the support roller lifting assembly includes base, the elevating lever at the top of the base, and with the elevating lever top The support frame of portion's connection.
Preferably, the support roller includes the roll body for being socketed the winding type cable, it is set to the roll body axial ends The support sleeve being used cooperatively with support frame, and the telescopic rod for connecting with the support sleeve and running-on being supported to be used cooperatively.
Preferably, the roll body is equipped with the separation protrusion for separating the winding type cable.
Preferably, the support roller is additionally provided with positioning element, the positioning element includes being set to the support sleeve bottom RF transmitter, and the infrared receiver at the top of base.
Preferably, the winding type cable is equipped with cable end grip block, the cable end grip block includes frame Shape frame plate, the frame plate include frame plate top body and the following body of frame plate, and frame plate top body, which is equipped with, allows cable end Accommodation groove on the cable passed through, accommodation groove has been separately equipped with rotary type cable clamp on the cable, and the following body of frame plate is set There is accommodation groove under the cable for allowing cable end to pass through, accommodation groove is equipped with a rotary type joint current clamping plate under the cable.
Preferably, the cable clamp free end is clamped by clamping protrusion and the clamping groove of frame plate top body, And the cable clamp free end is equipped with finger gripping slot.
The utility model has the beneficial effects that the tin plating production line of the cold process of the application can carry out acid to cable end automatically It washes, is tin plating, cleaning and drying, having liberated labour, and improve the tin plating efficiency and tin plating effect of cable end.
Detailed description of the invention
Fig. 1 is a kind of structural schematic diagram of the tin plating production line of cable end cold process of the utility model;
Fig. 2 is the structural schematic diagram of conveying mechanism;
Fig. 3 is the structural schematic diagram of support roller elevating mechanism;
The structural schematic diagram of Fig. 4 cable end grip block;
Fig. 5 is the partial enlarged view of cable end grip block in Fig. 4;
Wherein, 1, winding type cable, 2, support roller, 3, conveying mechanism, 31, conveyer belt, 32, idler roller, 33, support sleeve Mouthful, 4, support roller elevating mechanism, 41, base, 42, elevating lever, 43, support frame, 51, frame plate, 52, cable clamp, 53, total Cable clamp, 54, finger gripping slot, 55, clamping protrusion, 56, clamping groove.
Specific embodiment
Further illustrate the technical solution of the utility model below with reference to the accompanying drawings and specific embodiments.
As shown in Figures 1 to 5, a kind of tin plating production line of cable end cold process, including the exposed winding type cable 1 in both ends, With the support roller 2 of the winding type cable 1 socket, the conveying mechanism 3 for driving the support roller 2 to advance, along the conveying mechanism 3 Descaling bath, pot and the rinse bath that direction of advance is set gradually are separately positioned on the descaling bath, pot and rinse bath two The support roller elevating mechanism 4 of side, the descaling bath, pot and rinse bath are located at the 2 direction of advance bottom of support roller.
The conveying mechanism 3 includes the conveying assembly for being symmetricly set on 2 axial ends of support roller, the conveying assembly Including circulating conveyer belt 31, it is tensioned the idler roller 32 of the conveyer belt 31, the driving motor for driving the idler roller 32 to rotate, And several support sleeve mouths 33 on 31 surface of conveyer belt are set.
The support roller elevating mechanism 4 includes the support roller lifting assembly for being symmetricly set on 2 axial ends of support roller, The support roller lifting assembly includes base 41, the elevating lever 42 set on 41 top of the base, and with the elevating lever 42 The support frame 43 of top connection.
The support roller 2 includes the roll body for being socketed the winding type cable 1, is set to the roll body axial ends and support frame 43 support sleeves 21 being used cooperatively, and the telescopic rod 22 for connecting with the support sleeve 21 and running-on 33 being supported to be used cooperatively.Institute It states roll body and is equipped with the separation protrusion 23 for separating the winding type cable 1.The support roller 2 is additionally provided with positioning element, the positioning Component includes the RF transmitter 24 set on 21 bottom of support sleeve, and the infrared receiver set on 41 top of base 25。
The winding type cable 1 is equipped with cable end grip block, and the cable end grip block includes frame plate 51, The frame plate 51 includes frame plate top body and the following body of frame plate, and frame plate top body is equipped with what permission cable end passed through Accommodation groove on cable, accommodation groove has been separately equipped with rotary type cable clamp 52 on the cable, and the following body of frame plate, which is equipped with, to be permitted Perhaps accommodation groove under the cable that cable end passes through, accommodation groove is equipped with a rotary type joint current clamping plate 53 under the cable.It is described 52 free end of cable clamp is clamped by clamping protrusion 55 and the clamping groove 56 of frame plate top body, and the cable clamp 52 Free end is equipped with finger gripping slot 54, and the free end structure of joint current clamping plate 53 is identical as the free end structure of cable clamp 52.
Specific tin plating process is as follows, and by 1 set of winding type cable in support roller 2, the quantity of winding type cable 1 can be 10 It is a and substantially separated by separating protrusion 23, separate protrusion 23 and play positioning and position-limiting action, and two telescopic rods 22 are set respectively In on corresponding support running-on 33.
Then the both ends cable clip of winding type cable 1 is handled respectively by two cable end grip blocks, so that coiling The end vertical of formula cable 1 is downward, in order to which cable end is cleaned and tin plating processing automatically.Then manually by cable end Grip block cable end shell below is cut off, is removed.
Then start driving motor, drive support roller 2 to advance by conveyer belt 31, when support roller 2 is delivered to descaling bath bottom When portion, the infrared receiver 25 on base 41 corresponding with descaling bath can receive the RF transmitter of 21 bottom of support sleeve 24 infrared rays issued, at this point, control mechanism receives the signal, and issuing signal keeps driving motor out of service, then makes Elevating lever 42 rises to support frame 43 and contacts with support sleeve 21 and will lift certain distance on support sleeve 21, then controls telescopic rod 22 It shrinks, then controlling elevating lever 42 and dropping to makes cable end enter descaling bath, carries out pickling by descaling bath.When cable end acid It washes into later, control mechanism controls elevating lever 42 again and support roller 2 is risen to elemental height, the elongation of telescopic rod 22 to support sleeve Mouth 33, elevating lever 42 reset, and then control driving motor and continue to run so that support roller 2 to be fed forward.
25 meeting of infrared receiver when support roller 2 is delivered to tin plating trench bottom, on base 41 corresponding with pot The infrared ray that the RF transmitter 24 of 21 bottom of support sleeve issues is received, at this point, control mechanism receives the signal, concurrently Signal keeps driving motor out of service out, so that elevating lever 42 is risen to support frame 43 and contacts with support sleeve 21 and by support sleeve Certain distance is lifted on 21, is then controlled telescopic rod 22 and is shunk, then controlling elevating lever 42 and dropping to makes cable end enter pot, It is tin plating that cold process is carried out by the nanometer liquid in pot.After cable end tin plating completion, control mechanism controls elevating lever again Support roller 2 is risen to elemental height by 42, and the elongation of telescopic rod 22 to support running-on 33, elevating lever 42 resets, then control driving Motor is continued to run so that support roller 2 to be fed forward.
25 meeting of infrared receiver when support roller 2 is delivered to bottom of rinse bath, on base 41 corresponding with rinse bath The infrared ray that the RF transmitter 24 of 21 bottom of support sleeve issues is received, at this point, control mechanism receives the signal, concurrently Signal keeps driving motor out of service out, so that elevating lever 42 is risen to support frame 43 and contacts with support sleeve 21 and by support sleeve Certain distance is lifted on 21, is then controlled telescopic rod 22 and is shunk, then controlling elevating lever 42 and dropping to makes cable end enter rinse bath, Cable end is cleaned up by rinse bath.Judge that standard that cable cleans up can be the time span of cleaning.Work as electricity After cable-end portion cleans up, control mechanism controls elevating lever 42 again and support roller 2 is risen to elemental height, and telescopic rod 22 extends To support running-on 33, elevating lever 42 resets, and then controls driving motor and continues to run so that support roller 2 to be fed forward.
Support roller 2 is dried in remaining transmission process by the warm wind that heater completes cable end, when support roller 2 When being moved to the end of conveying mechanism 3, manually support roller 2 is removed from conveying mechanism 3 to complete the tin plating of cable end.
Embodiment described above is only that preferred embodiments of the present invention are described, not practical new to this The conception and scope of type is defined.Without departing from the design concept of the present utility model, ordinary people in the field is to this The all variations and modifications that the technical solution of utility model is made, should fall within the protection scope of the present utility model, this is practical Novel claimed technology contents, are all described in the claims.

Claims (8)

1. a kind of tin plating production line of cable end cold process, it is characterised in that: including the exposed winding type cable (1) in both ends, with institute The support roller (2) for stating winding type cable (1) socket, the conveying mechanism (3) for driving the support roller (2) to advance, along the conveying Descaling bath, pot and the rinse bath that mechanism (3) direction of advance is set gradually, be separately positioned on the descaling bath, pot and The support roller elevating mechanism (4) of rinse bath two sides, the descaling bath, pot and rinse bath are located at the support roller (2) advance Direction bottom.
2. a kind of tin plating production line of cable end cold process according to claim 1, it is characterised in that: the conveying mechanism It (3) include the conveying assembly for being symmetricly set on the support roller (2) axial ends, the conveying assembly includes circulating conveyer belt (31), it is tensioned the idler roller (32) of the conveyer belt (31), the driving motor for driving the idler roller (32) to rotate, and setting Several support sleeve mouths (33) on the conveyer belt (31) surface.
3. a kind of tin plating production line of cable end cold process according to claim 1, it is characterised in that: the support roller lifting Mechanism (4) includes the support roller lifting assembly for being symmetricly set on the support roller (2) axial ends, the support roller lifting assembly Including base (41), the elevating lever (42) being set at the top of the base (41), and connect with the elevating lever (42) top Support frame (43).
4. a kind of tin plating production line of cable end cold process according to claim 1, it is characterised in that: the support roller (2) Roll body including being socketed the winding type cable (1) is set to the branch that the roll body axial ends is used cooperatively with support frame (43) Support set (21), and the telescopic rod (22) for connecting with the support sleeve (21) and running-on (33) being supported to be used cooperatively.
5. a kind of tin plating production line of cable end cold process according to claim 4, it is characterised in that: the roll body, which is equipped with, to be divided It is raised (23) every the separation of the winding type cable (1).
6. a kind of tin plating production line of cable end cold process according to claim 4, it is characterised in that: the support roller (2) It is additionally provided with positioning element, the positioning element includes the RF transmitter (24) set on the support sleeve (21) bottom, and is set Infrared receiver (25) at the top of base (41).
7. a kind of tin plating production line of cable end cold process according to claim 1, it is characterised in that: the winding type cable (1) it is equipped with cable end grip block, the cable end grip block includes frame plate (51), frame plate (51) packet Frame plate top body and the following body of frame plate are included, frame plate top body is equipped with accommodation groove on the cable for allowing cable end to pass through, institute It states accommodation groove on cable to be separately equipped with rotary type cable clamp (52), the following body of frame plate, which is equipped with, allows cable end to pass through Cable under accommodation groove, accommodation groove is equipped with a rotary type joint current clamping plate (53) under the cable.
8. a kind of tin plating production line of cable end cold process according to claim 7, it is characterised in that: the cable clamp (52) free end is clamped by being clamped the clamping groove (56) of raised (55) and frame plate top body, and the cable clamp (52) Free end is equipped with finger gripping slot (54).
CN201822168072.3U 2018-12-24 2018-12-24 A kind of tin plating production line of cable end cold process Active CN209323023U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822168072.3U CN209323023U (en) 2018-12-24 2018-12-24 A kind of tin plating production line of cable end cold process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822168072.3U CN209323023U (en) 2018-12-24 2018-12-24 A kind of tin plating production line of cable end cold process

Publications (1)

Publication Number Publication Date
CN209323023U true CN209323023U (en) 2019-08-30

Family

ID=67728182

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822168072.3U Active CN209323023U (en) 2018-12-24 2018-12-24 A kind of tin plating production line of cable end cold process

Country Status (1)

Country Link
CN (1) CN209323023U (en)

Similar Documents

Publication Publication Date Title
CN109576750A (en) A kind of tin plating production technology of cable end cold process
CN209323023U (en) A kind of tin plating production line of cable end cold process
CN108611673A (en) A kind of automatic electroplating machine that can be used for irregular part and facilitate clamping
CN205056523U (en) Full -automatic cleaning machine
CN204849083U (en) VCP electricity plate wire's feed mechanism
CN205308976U (en) A automation equipment for rinsing wire drawing mould
CN203482835U (en) Full-automatic bean stick production system
CN207712900U (en) Module transfer machine
CN215301998U (en) Machine of retrieving is picked to full-automatic suspender auricularia auriculajudae
CN205967726U (en) Full -automatic data line wire cutting tin sticky machine
CN106655024B (en) A kind of line hanging mechanism
CN209814925U (en) Conveyor is used in production of connector contact pin
CN216072840U (en) Convenient to use's robot production is with lifting device
CN209396539U (en) A kind of ribbon lap machine send bobbin device automatically
CN207381378U (en) A kind of Wafer Cleaning automatic lifting-pulling apparatus
CN209939844U (en) A switching equipment for glass cup diversion
CN202290621U (en) Device for cleaning and dewatering bottom of storage battery
CN208098669U (en) Electric power operation stick cleaning device
CN206843024U (en) A kind of bottle placer with automatic fixer
CN206735694U (en) A kind of transporting device for being electrolysed cloudy plate electrode plate
CN205312459U (en) A centre gripping equipment for enameled trough subassembly board
CN206166771U (en) Cooking pot subassembly
CN212210299U (en) Power supply pole wire lifting mechanism
CN220200633U (en) Copper bar automatic feeding mechanism
CN215976098U (en) High-efficient electroplating treatment device of pendant

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 313000 No. 18, Hu Yan Road, Nanxun Town, Nanxun City, Zhejiang

Patentee after: Zhejiang Zhengdao Technology Co.,Ltd.

Address before: 313000 No. 18, Hu Yan Road, Nanxun Town, Nanxun City, Zhejiang

Patentee before: ZHEJIANG ZHENGDAO LAN CABLE Co.,Ltd.