- Prior art keywords
- out device
- pile construction
- bored pile
- strut
- sludge pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Treatment Of Sludge (AREA)
Abstract
The utility model provides a kind of bored pile construction mud draw-out device.Bored pile construction mud draw-out device includes the first sludge pipe;Sucker mechanism;Connecting sleeve;Supporting mechanism;Second sludge pipe;Slush pump;Storage bin;Sealing mechanism, the sealing mechanism include hopper, link, cover board and position-limit mechanism, and the side wall of the cover board is equipped with the position-limit mechanism, and the position-limit mechanism includes strut, spring and retaining ring;One end of the spring is fixedly connected with the cover board, and the other end of the spring is fixedly connected with the strut;The end of the strut is equipped with the retaining ring, and the retaining ring is fastened and connected the link;Idler wheel, and the idler wheel is fixedly connected with the rotation motor;Handle.Bored pile construction provided by the utility model mud draw-out device, equipment installation and transportation are easy, and centralized collection and quickly discharge can be carried out to mud.
Description
Technical field
The utility model relates to technical field of buildings more particularly to a kind of bored pile construction mud draw-out devices.
Background technique
Bored concrete pile system refers in engineering site through means such as machine drilling, steel pipe soil compaction or manpower excavations in foundation soil
Stake holes is formed, and places steel reinforcement cage, concrete perfusion and the stake being made into it, according to forming hole method difference, bored concrete pile again may be used
It is divided into several classes such as driven cast-in-place pile, cast-in-situ bored pile and digging hole filling pile.
It in bored pile construction, needs for the mud in stake holes to be pumped into out, current mud extraction equipment conduit, place
It is more to manage equipment, takes up a large area, on-the-spot environmental requirements can not be well adapted to, so that the installation period of equipment is longer, it cannot
It is enough that mud is quickly transferred to centralized processing region.
Therefore, it is necessary to provide a kind of new bored pile construction mud draw-out device solution above-mentioned technical problem.
Utility model content
The drilling that the technical issues of the utility model solves is to provide a kind of install convenient, can quickly be shifted to mud
Filling pile construction mud draw-out device.
In order to solve the above technical problems, bored pile construction provided by the utility model mud draw-out device, comprising:
First sludge pipe;Sucker mechanism, the sucker mechanism are installed on the arrival end of first sludge pipe;Connecting sleeve, the company
Female connector pipe is installed on the outlet end of first sludge pipe;Supporting mechanism, the supporting mechanism are installed on first sludge pipe
Bottom;Second sludge pipe, cooperate connection between the arrival end and the connecting sleeve of second sludge pipe;Take out mud
Pump, the slush pump are connect with the outlet end of second sludge pipe;Storage bin, the surface of the storage bin are equipped with the pumping
Dredge pump, and the outlet end of the slush pump is connected to the inside of the storage bin;Sealing mechanism, the sealing mechanism include discharge
Bucket, link, cover board and position-limit mechanism, and the hopper is installed on the side wall of the storage bin;The side wall of the hopper
It is rotatablely connected the cover board, and the two sidewalls of the hopper are equipped with the link;The side wall of the cover board is equipped with the limit
Mechanism, and the position-limit mechanism includes strut, spring and retaining ring;One end of the spring is fixedly connected with the cover board, and institute
The other end for stating spring is fixedly connected with the strut;The end of the strut is equipped with the retaining ring, and the retaining ring is fastened and connected
The link;Idler wheel, the idler wheel is set to the bottom of the storage bin, and the idler wheel is fixedly connected with rotation motor;Handle, institute
State the side wall that handle is installed on the storage bin.
Preferably, the supporting mechanism includes strut, limits knob, supporting sleeve and bottom plate, and the top of the strut
End is fixedly connected with first sludge pipe;The bottom end of the strut is socketed with the supporting sleeve, and the supporting sleeve and institute
It states between strut through limit knob connection;The bottom end of the supporting sleeve is equipped with the bottom plate.
Preferably, the sucker mechanism includes into bucket and extension pipe, and the extension pipe is socketed on first spoil disposal
The inside of pipe;The bottom end of the extension pipe is fixedly connected with described into bucket.
Preferably, the side wall of first sludge pipe is fixed with the top of electric pushrod, and the bottom end of the electric pushrod
It is fixedly connected with the side wall into bucket.
Preferably, the sucker mechanism further includes rabbling mechanism and driving mechanism, and the rabbling mechanism includes shaft, tooth
Ring and stirring rod;The shaft is fixed on described into the bottom surface of bucket, and the shaft is rotatablely connected the ring gear;The tooth
The stirring rod is distributed in the bottom surface of ring;The driving mechanism includes driving motor, transmission shaft and driving gear, and the drive
Dynamic motor is fixed on the side wall into bucket;The driving motor is fixedly connected with the transmission shaft, and the end of the transmission shaft
Portion is fixed with the driving gear;The driving gear engagement connects the ring gear.
Preferably, the stirring rod circular array distribution, and the bottom surface of ring gear described in the equal vertical welding of the stirring rod.
Preferably, the transmission shaft and described into arranged in parallel between bucket, and the transmission shaft, electric pushrod it
Between be symmetrically set.
Preferably, the driving gear and the ring gear are located at same level, and the diameter of the driving gear is less than institute
State the diameter of ring gear.
Compared with the relevant technologies, bored pile construction provided by the utility model mud draw-out device has as follows
The utility model has the advantages that
The utility model provides a kind of bored pile construction mud draw-out device, by mud suction part and storage unit
Divide and be separately provided, it is more convenient to may make that draw-out device carries, concentration storage is carried out to mud using the storage bin, and in institute
The bottom for stating storage bin is equipped with the idler wheel, side wall is equipped with the handle, can be convenient for worker after mud extracts
The storage bin is quickly transferred to centralized processing region, structure is simple, and occupied area is small;Second sludge pipe can be plugged into
In first sludge pipe, the two connection is quick, and the bottom of first sludge pipe is equipped with the supporting mechanism, Neng Gouyou
The stability of the raising structure of effect accelerates installation speed;When needing that mud is discharged, worker draws the strut outside, so that described
Spring elongation, then deducts the retaining ring, produces the cover board, and mud can quickly be discharged from the hopper.
Detailed description of the invention
Fig. 1 is a kind of knot of preferred embodiment of bored pile construction mud draw-out device provided by the utility model
Structure schematic diagram;
Fig. 2 is the sealing mechanism structural schematic diagram that Fig. 1 is provided;
Fig. 3 is the sucker mechanism structural schematic diagram that Fig. 1 is provided.
Figure label: 1, sucker mechanism, 11, into bucket, 12, rabbling mechanism, 121, shaft, 122, ring gear, 123, stirring
Bar, 13, extension pipe, 14, driving mechanism, 141, driving motor, 142, transmission shaft, 143, driving gear, 2, electric pushrod, 3, the
One sludge pipe, 31, connecting sleeve, 4, supporting mechanism, 41, strut, 42, limit knob, 43, supporting sleeve, 44, bottom plate, 5, pumping
Dredge pump, 6, storage bin, 7, sealing mechanism, 71, hopper, 72, link, 73, cover board, 74, position-limit mechanism, 741, strut, 742,
Spring, 743, retaining ring, 8, connecting sleeve, the 9, second sludge pipe, 9a, idler wheel, 91a, rotation motor, 9b, handle.
Specific embodiment
The utility model is described in further detail with embodiment with reference to the accompanying drawing.
Please refer to Fig. 1, Fig. 2 and Fig. 3, wherein Fig. 1 is bored pile construction mud provided by the utility model
Starch a kind of structural schematic diagram of preferred embodiment of draw-out device;Fig. 2 is the sealing mechanism structural schematic diagram that Fig. 1 is provided;Fig. 3 is
The sucker mechanism structural schematic diagram that Fig. 1 is provided.Bored pile construction mud draw-out device includes: the first sludge pipe 3;Sucking
Mechanism 1, the sucker mechanism 1 are installed on the arrival end of first sludge pipe 3;Connecting sleeve 8, the connecting sleeve 8 are installed
In the outlet end of first sludge pipe 3;Supporting mechanism 4, the supporting mechanism 4 are installed on the bottom of first sludge pipe 3;
Second sludge pipe 9, cooperate connection between the arrival end and the connecting sleeve 8 of second sludge pipe 9;Slush pump 5, institute
Slush pump 5 is stated to connect with the outlet end of second sludge pipe 9;The surface of storage bin 6, the storage bin 6 is equipped with the pumping
Dredge pump 5, and the outlet end of the slush pump 5 is connected to the inside of the storage bin 6;Sealing mechanism 7, the sealing mechanism 7
Including hopper 71, link 72, cover board 73 and position-limit mechanism 74, and the hopper 71 is installed on the side of the storage bin 6
Wall;The side wall of the hopper 71 is rotatablely connected the cover board 73, and the two sidewalls of the hopper 71 are equipped with the link 72;
The side wall of the cover board 73 is equipped with the position-limit mechanism 74, and the position-limit mechanism 74 includes strut 741, spring 742 and buckles
Ring 743;One end of the spring 742 is fixedly connected with the cover board 73, and the other end of the spring 742 is fixedly connected with the branch
Bar 741;The end of the strut 741 is equipped with the retaining ring 743, and the retaining ring 743 is fastened and connected the link 72;Idler wheel
9a, the idler wheel 9a are set to the bottom of the storage bin 6, and the idler wheel 9a is fixedly connected with rotation motor 91a;Handle 9b, institute
State the side wall that handle 9b is installed on the storage bin 6.
In order to effectively be supported to sludge pipe, so that connection is more convenient, the supporting mechanism 4 includes strut 41, limit
Position knob 42, supporting sleeve 43 and bottom plate 44, and the top of the strut 41 is fixedly connected with first sludge pipe 3;It is described
The bottom end of strut 41 is socketed with the supporting sleeve 43, and passes through limit knob between the supporting sleeve 43 and the strut 41
42 connections;The bottom end of the supporting sleeve 43 is equipped with the bottom plate 44.
In order to realize the suction of mud, the sucker mechanism 1 includes into bucket 11 and extension pipe 13, and the extension pipe
13 are socketed on the inside of first sludge pipe 3;The bottom end of the extension pipe 13 is fixedly connected with described into bucket 11.
In order to which the extension elongation to the extension pipe 13 is adjusted, the side wall of first sludge pipe 3 is fixed with electronic
The top of push rod 2, and the bottom end of the electric pushrod 2 is fixedly connected with the side wall into bucket 11.
In order to be stirred to mud, so that inhalant effect is more preferable, the sucker mechanism 1 further includes rabbling mechanism 12 and drives
Motivation structure 14, and the rabbling mechanism 12 includes shaft 121, ring gear 122 and stirring rod 123;The shaft 121 is fixed on institute
It states into the bottom surface of bucket 11, and the shaft 121 is rotatablely connected the ring gear 122;The bottom surface of the ring gear 122 is distributed with described
Stirring rod 123;The driving mechanism 14 includes driving motor 141, transmission shaft 142 and driving gear 143, and the driving is electric
Machine 141 is fixed on the side wall into bucket 11;The driving motor 141 is fixedly connected with the transmission shaft 142, and the transmission
The end of axis 142 is fixed with the driving gear 143;The engagement of driving gear 143 connects the ring gear 122.
In order to enable mixing effect is more preferable, 143 circular array of the stirring rod distribution, and the stirring rod 143 hangs down
Directly weld the bottom surface of the ring gear 122.
In order to enable 143 stable rotation of stirring rod, the transmission shaft 142 and described it is parallel to each other between bucket 11
Setting, and be symmetrically set between the transmission shaft 142, electric pushrod 2.
In order to realize the driving for the ring gear 122, the driving gear 143 is located at same water with the ring gear 122
The diameter of plane, the driving gear 143 is less than the diameter of the ring gear 122.
The use principle of bored pile construction provided by the utility model mud draw-out device are as follows: during installation, first
By the supporting mechanism 4 be placed in from stake holes not far from, the bottom plate 44 is fixed together with ground, the inhalation machine
Structure 1 is placed in stake holes, and the storage bin 6 is then pushed into extracting region again, adjusts the height of the strut 41, so that described
Two sludge pipes 9 are closely combined together with first sludge pipe 3, can complete to assemble;When slurry-sucking, start described electronic
Push rod 2, driving is described to be moved downward into bucket 11 until extending into mud, the overhanging movement of the extension pipe 13, the pumping mud
Pump 5 extracts mud out, by described into bucket 11, the extension pipe 13, first sludge pipe 3 and second sludge pipe
9 enter eventually into the storage bin 6;The electric pushrod 2 be can control in extraction process to change the extension pipe 13
Extension elongation so that described be always positioned in mud into bucket 11, the driving motor 141 drives the transmission shaft 142, institute
It states driving gear 143 to rotate, and then drives the ring gear 122 to rotate around the shaft 121 by engagement force, the stirring rod
123 can realize rotation, are stirred to the mud of inhalation area, prevent blocked inlet;After extraction, it can pull out described
Storage bin 6, second sludge pipe 3 are separated with the connecting sleeve 31, and the storage bin 6 can be pushed into concentrated area by worker,
Then outer to draw the strut 741, so that the spring 742 extends, the retaining ring 743 is then deducted, it can be by the cover board 73
It produces, mud can be discharged from the hopper 71.
Compared with the relevant technologies, bored pile construction provided by the utility model mud draw-out device has as follows
The utility model has the advantages that
The utility model provides a kind of bored pile construction mud draw-out device, by mud suction part and storage unit
It point is separately provided, it is more convenient to may make that draw-out device carries, concentration storage is carried out to mud using the storage bin 6, and
The bottom of the storage bin 6 is equipped with the idler wheel 9a, side wall is equipped with the handle 9b, can extract convenient for worker in mud
After quickly by the storage bin 6 be transferred to centralized processing region, structure is simple, and occupied area is small;Second sludge pipe 9
It can be plugged into first sludge pipe 3, the two connection is quick, and the bottom of first sludge pipe 3 is equipped with the support
Mechanism 4 can effectively improve the stability of structure, accelerate installation speed;When needing that mud is discharged, worker draws the branch outside
Then bar 741 deducts the retaining ring 743, produces the cover board 73, mud can be quick so that the spring 742 extends
It is discharged from the hopper 71.
The above description is only the embodiments of the present invention, and therefore it does not limit the scope of the patent of the utility model, all
Equivalent structure or equivalent flow shift made based on the specification and figures of the utility model, is applied directly or indirectly in
Other relevant technical fields, are also included in the patent protection scope of the utility model.
Claims (8)
1. a kind of bored pile construction mud draw-out device characterized by comprising
First sludge pipe;
Sucker mechanism, the sucker mechanism are installed on the arrival end of first sludge pipe;
Connecting sleeve, the connecting sleeve are installed on the outlet end of first sludge pipe;
Supporting mechanism, the supporting mechanism are installed on the bottom of first sludge pipe;
Second sludge pipe, cooperate connection between the arrival end and the connecting sleeve of second sludge pipe;
Slush pump, the slush pump are connect with the outlet end of second sludge pipe;
Storage bin, the surface of the storage bin is equipped with the slush pump, and the outlet end of the slush pump is connected to the storage
Deposit the inside of case;
Sealing mechanism, the sealing mechanism includes hopper, link, cover board and position-limit mechanism, and the hopper is installed on
The side wall of the storage bin;The side wall of the hopper is rotatablely connected the cover board, and the two sidewalls of the hopper are equipped with institute
State link;The side wall of the cover board is equipped with the position-limit mechanism, and the position-limit mechanism includes strut, spring and retaining ring;Institute
The one end for stating spring is fixedly connected with the cover board, and the other end of the spring is fixedly connected with the strut;The end of the strut
Portion is equipped with the retaining ring, and the retaining ring is fastened and connected the link;
Idler wheel, the idler wheel is set to the bottom of the storage bin, and the idler wheel is fixedly connected with rotation motor;
Handle, the handle are installed on the side wall of the storage bin.
2. bored pile construction according to claim 1 mud draw-out device, which is characterized in that the supporting mechanism
Including strut, limit knob, supporting sleeve and bottom plate, and the top of the strut is fixedly connected with first sludge pipe;Institute
The bottom end for stating strut is socketed with the supporting sleeve, and passes through limit knob connection between the supporting sleeve and the strut;
The bottom end of the supporting sleeve is equipped with the bottom plate.
3. bored pile construction according to claim 1 mud draw-out device, which is characterized in that the sucker mechanism
Including into bucket and extension pipe, and the extension pipe is socketed on the inside of first sludge pipe;The bottom end of the extension pipe is solid
Surely it is connected with described into bucket.
4. bored pile construction according to claim 3 mud draw-out device, which is characterized in that first spoil disposal
The side wall of pipe is fixed with the top of electric pushrod, and the bottom end of the electric pushrod is fixedly connected with the side wall into bucket.
5. bored pile construction according to claim 3 mud draw-out device, which is characterized in that the sucker mechanism
It further include rabbling mechanism and driving mechanism, and the rabbling mechanism includes shaft, ring gear and stirring rod;The shaft is fixed on
The bottom surface into bucket, and the shaft is rotatablely connected the ring gear;The stirring rod is distributed in the bottom surface of the ring gear;Institute
Stating driving mechanism includes driving motor, transmission shaft and driving gear, and the driving motor be fixed on it is described into the side of bucket
Wall;The driving motor is fixedly connected with the transmission shaft, and the end of the transmission shaft is fixed with the driving gear;The drive
Moving gear engagement connects the ring gear.
6. bored pile construction according to claim 5 mud draw-out device, which is characterized in that the stirring rod is in
Annular array distribution, and the bottom surface of ring gear described in the equal vertical welding of the stirring rod.
7. bored pile construction according to claim 5 mud draw-out device, which is characterized in that the transmission shaft with
It is described into arranged in parallel between bucket, and be symmetrically set between the transmission shaft, electric pushrod.
8. bored pile construction according to claim 5 mud draw-out device, which is characterized in that the driving gear
It is located at same level with the ring gear, the diameter of the driving gear is less than the diameter of the ring gear.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820857668.1U CN209227514U (en) | 2018-06-05 | 2018-06-05 | A kind of bored pile construction mud draw-out device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820857668.1U CN209227514U (en) | 2018-06-05 | 2018-06-05 | A kind of bored pile construction mud draw-out device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209227514U true CN209227514U (en) | 2019-08-09 |
Family
ID=67496738
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820857668.1U Active CN209227514U (en) | 2018-06-05 | 2018-06-05 | A kind of bored pile construction mud draw-out device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209227514U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110657081A (en) * | 2019-10-09 | 2020-01-07 | 潘显敏 | Slurry pumping equipment for river channel environment treatment |
-
2018
- 2018-06-05 CN CN201820857668.1U patent/CN209227514U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110657081A (en) * | 2019-10-09 | 2020-01-07 | 潘显敏 | Slurry pumping equipment for river channel environment treatment |
CN110657081B (en) * | 2019-10-09 | 2021-08-03 | 中际晟丰环境工程技术集团有限公司 | Slurry pumping equipment for river channel environment treatment |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110409421B (en) | Ultra-deep pile ground is wall construction system even | |
CN110409422B (en) | Diaphragm wall construction method and diaphragm wall construction system | |
CN104358927A (en) | Push pipe construction method and push pipe device | |
CN109989396A (en) | In conjunction with the novel extruding-enlarging branch tray molding machine and its operating method of post grouting process | |
CN209227514U (en) | A kind of bored pile construction mud draw-out device | |
CN108755685A (en) | A kind of building piling machine | |
JP2004263561A (en) | Cast-in-place pile and its work execution method | |
KR101170515B1 (en) | Device for dredge dredging soil managing sewer-pipe | |
CN217870662U (en) | Drainage desilting device for road construction | |
JP2615096B2 (en) | Drilling method | |
KR101818949B1 (en) | Construction method of pile type groundwater collector | |
KR100690396B1 (en) | An installation method of the drain pipe filter for collector wells using flexible hose | |
CN104514505A (en) | Drilling device | |
CN208330239U (en) | A kind of reacting cycle hole cleaning device | |
CN102409679A (en) | Pore-forming high-pressure slurry pipe reel for piling | |
CN218550610U (en) | Plant planting equipment for municipal administration | |
CN205314142U (en) | Pile foundation is hook for experiment | |
CN219710360U (en) | Foundation pit maintenance-free drainage dewatering well | |
CN112144519A (en) | Drilling tool, cement-soil stirring pile sinking all-in-one machine and construction method of composite pile | |
CN114592518B (en) | Mountain land hard rock geological pile foundation construction device and application method thereof | |
CN217105093U (en) | Steel-pipe column mud pumping equipment | |
CN207672726U (en) | A kind of inspection shaft oil slick automatic collecting device | |
CN220580957U (en) | Rectangular deep hole drilling machine with horizontal cantilever and step-by-step type structure adapting to soil stratum | |
JP2013204404A (en) | Construction method of steel pipe pile | |
CN102493454A (en) | Ultrahigh-pressure aerodynamic force water-flushing pile extracting method of vibration-free flexible sleeve |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |