CN209178989U - A kind of PHC tubular pole anti-freeze expansion processing unit - Google Patents

A kind of PHC tubular pole anti-freeze expansion processing unit Download PDF

Info

Publication number
CN209178989U
CN209178989U CN201820834965.4U CN201820834965U CN209178989U CN 209178989 U CN209178989 U CN 209178989U CN 201820834965 U CN201820834965 U CN 201820834965U CN 209178989 U CN209178989 U CN 209178989U
Authority
CN
China
Prior art keywords
drilling pipe
hollow drilling
tubular pole
phc tubular
processing unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820834965.4U
Other languages
Chinese (zh)
Inventor
刘利强
杨利剑
侯珺
苗红达
郭琦隆
张秋霞
杨帆
梁萍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan DR Construction Group Co Ltd
Original Assignee
Henan DR Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan DR Construction Group Co Ltd filed Critical Henan DR Construction Group Co Ltd
Priority to CN201820834965.4U priority Critical patent/CN209178989U/en
Application granted granted Critical
Publication of CN209178989U publication Critical patent/CN209178989U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model provides a kind of PHC tubular pole anti-freeze expansion processing unit, reduces mass deviation and project cost when the construction of PHC tubular pole anti-freeze expansion to a certain extent;Including hollow drilling pipe, the hollow drilling pipe lower ending opening setting, the hollow drilling pipe upper end is sealed set, is installed with connector in the center of the hollow drilling pipe upper surface, the connector, which is used to connect, provides the drive system of rotary force;It is installed with the helical blade at the middle part of the core drill drum outer wall and lower part, successively offers several holes of being unearthed from top to bottom on the top of the hollow drilling pipe.Utility model device structure is simply easy to use, and manufacturing cost is low.

Description

A kind of PHC tubular pole anti-freeze expansion processing unit
Technical field
The utility model relates to foundation of civil work engineering prefabricated tubular pile application fields, and in particular to a kind of PHC tubular pole anti-freeze expansion Processing unit.
Background technique
PHC tubular pole, i.e. PHC piles, existing PHC tubular pole frozen prevention measures mainly increase PHC pipe Pile length or subdrilling macropore be reserved to be changed and fills out non-frost heave material space and construct again PHC tubular pole, but such method is unable to control PHC tubular pole The levelness on basis, deviation is larger, and cost is excessively high.
Utility model content
In view of the deficiencies of the prior art, the utility model provides a kind of PHC tubular pole anti-freeze expansion processing unit, to a certain degree The upper mass deviation and project cost reduced when PHC tubular pole anti-freeze expansion is constructed.
A kind of PHC tubular pole anti-freeze expansion processing unit, it is characterised in that: including hollow drilling pipe, the hollow drilling pipe lower end is opened Mouth setting, is installed with helical blade around its outer wall in the hollow drilling pipe.
Further are as follows: the hollow drilling pipe upper end is sealed set, and the center in the hollow drilling pipe upper surface is solid Equipped with connector, the connector, which is used to connect, provides the drive system of rotary force.
Further are as follows: the helical blade is installed at the middle part of the core drill drum outer wall and lower part, described hollow The top of drilling pipe successively offers several holes of being unearthed from top to bottom.
Further are as follows: it is installed with the native plate of sweeping of the vertical hollow drilling pipe on the top of the hollow drilling pipe, it is described to sweep soil Plate is angle steel, and is fixedly connected by welding with the hollow drilling pipe.
The utility model has the beneficial effects that utility model device structure is simply easy to use, manufacturing cost is low;Practical Utility model is avoided that increasing reserved change of PHC tubular pole length or subdrilling macropore fills out non-frost heave material space and construct again PHC tubular pole, from And reduce project cost.
Detailed description of the invention
Fig. 1 is the front view of utility model device;
Fig. 2 is the top view of utility model device;
Fig. 3 is structural perspective of the utility model device in the first Construction State;
Fig. 4 is structural perspective of the utility model device in the second Construction State.
In figure: 1, sweeping native plate;2, connector;3, helical blade;4, unearthed hole;5, hollow drilling pipe;B, PHC tubular pole;C, Face.
Specific embodiment
It elaborates with reference to the accompanying drawing to the utility model.
As depicted in figs. 1 and 2, a kind of PHC tubular pole anti-freeze expansion processing unit, including hollow drilling pipe 5, the hollow drilling pipe 5 Lower ending opening setting, is installed with helical blade 3 around its outer wall in the hollow drilling pipe 5.
5 upper end of hollow drilling pipe is sealed set, is installed with connection in the center of hollow 5 upper surface of drilling pipe Part 2, the connector 2, which is used to connect, provides the drive system of rotary force.
Specifically, the helical blade 3 is installed at the middle part of hollow 5 outer wall of drilling pipe and lower part, described hollow The top of drilling pipe 5 successively offers several holes 5 of being unearthed from top to bottom.
It is installed with the native plate 1 of sweeping of the vertical hollow drilling pipe 5 on the top of the hollow drilling pipe 5, it is described to sweep native plate 1 as angle Steel, and be fixedly connected by welding with the hollow drilling pipe 5.
It is the use step of the utility model in conjunction with shown in Fig. 3 and Fig. 4:
Step 1: by hollow 5 loop of drilling pipe on the PHC tubular pole B to have constructed;
Step 2: making the hollow drilling pipe 5 along the PHC tubular pole B, C is rotated below to the ground, at this time the helical blade 3 precession is directed downward;
Step 3: being continued to rotate after so that 5 lower end of hollow drilling pipe is parked in ground C certain depth below, pass through the spiral shell Soil around the PHC tubular pole B is turned to ground C or more by vane piece 3;
Step 4: when the helical blade 3 being located at ground is no longer unearthed, taking out the hollow drilling pipe 5 upwards;Make There are the filled layers of tubular around the ground C PHC tubular pole B below;
Step 5: being filled in the filled layer and tamp non-frost heave material.
In the step 4, when taking out the hollow drilling pipe 5 upwards, the hollow drilling pipe 5 is reversely rotated.
The utility model General Implementing process is as follows:
One, hollow boring bit is made
It is made according to PHC tubular pole diameter dimension using seamless steel pipe or other rigid materials more slightly larger than PHC tubular pole hollow Drilling pipe (causes the distortion of PHC tubular pole to destroy) when size being avoided closely to be rotated down;Two sides are opened in two sides above hollow drilling pipe Shape hole, so as to the unearthed hole as soil extra in hollow drilling pipe;An angle steel is welded above hollow drilling pipe, as sweeps soil Plate facilitates and the soil routed up is put down;
Helical blade outside hollow drilling pipe needs material identical with steel pipe model, to guarantee helical blade and hollow drilling pipe It combines closely, helical blade will be fully welded with hollow drilling pipe, to guarantee that utility model device possesses enough rigidity, in any soil Desired effect is attained by the case of matter;
Two, hollow drilling pipe and backacter are assembled
It is assembled by the driving rotary head of the connector and backacter of hollow drilling pipe upper end.
Three, it checks mechanical
After the acceptance(check) of construction site, set drills through check whether each component and instrument are sensitive effectively after native machine is marched into the arena, really Protecting equipment operation safety can use after normal.
Four, set drills through soil
Hollow drilling pipe is inserted on the PHC tubular pole constructed, machinery start slowly be rotated down, with hollow drilling pipe to Reverse rotation when lower rotation and extraction, soil can be turned to earth's surface with helical blade, two sides of two sides above hollow drilling pipe Shape hole so as to the unearthed hole as soil extra in hollow drilling pipe, and sees whether to reach the absolute altitude for changing the demand of filling out;In hollow drilling pipe Angle steel at top facilitates and the soil routed up is put down.
Five, it changes and fills out non-frost heave material
It takes to change after soil around PHC tubular pole below ground using utility model device and fills out non-frost heave material, using Pressure rams the compacting factor for reaching design and related specification requirement.
The basic principles and main features of the present invention and the advantages of the present invention have been shown and described above.Current row The technical staff of industry is described in above embodiments and description it should be appreciated that the present utility model is not limited to the above embodiments Only illustrate the principles of the present invention, on the premise of not departing from the spirit and scope of the utility model, the utility model is also It will have various changes and improvements, these various changes and improvements fall within the scope of the claimed invention.The utility model Claimed range is defined by the appending claims and its equivalent thereof.

Claims (4)

1. a kind of PHC tubular pole anti-freeze expansion processing unit, it is characterised in that: including hollow drilling pipe, the hollow drilling pipe lower ending opening Setting, is installed with helical blade around its outer wall in the hollow drilling pipe.
2. a kind of PHC tubular pole anti-freeze expansion processing unit according to claim 1, it is characterised in that: in the hollow drilling pipe End is sealed set, is installed with connector in the center of the hollow drilling pipe upper surface, the connector is mentioned for connecting For the drive system of rotary force.
3. a kind of PHC tubular pole anti-freeze expansion processing unit according to claim 2, it is characterised in that: in the hollow drilling pipe The middle part and lower part of outer wall are installed with the helical blade, successively offer from top to bottom on the top of the hollow drilling pipe several A unearthed hole.
4. a kind of PHC tubular pole anti-freeze expansion processing unit according to claim 2, it is characterised in that: in the hollow drilling pipe Top be installed with the vertical hollow drilling pipe sweep native plate.
CN201820834965.4U 2018-05-31 2018-05-31 A kind of PHC tubular pole anti-freeze expansion processing unit Active CN209178989U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820834965.4U CN209178989U (en) 2018-05-31 2018-05-31 A kind of PHC tubular pole anti-freeze expansion processing unit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820834965.4U CN209178989U (en) 2018-05-31 2018-05-31 A kind of PHC tubular pole anti-freeze expansion processing unit

Publications (1)

Publication Number Publication Date
CN209178989U true CN209178989U (en) 2019-07-30

Family

ID=67357213

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820834965.4U Active CN209178989U (en) 2018-05-31 2018-05-31 A kind of PHC tubular pole anti-freeze expansion processing unit

Country Status (1)

Country Link
CN (1) CN209178989U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108442369A (en) * 2018-05-31 2018-08-24 河南省第二建设集团有限公司 A kind of PHC pile piles anti-freeze expansion processing unit and method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108442369A (en) * 2018-05-31 2018-08-24 河南省第二建设集团有限公司 A kind of PHC pile piles anti-freeze expansion processing unit and method

Similar Documents

Publication Publication Date Title
US11299864B2 (en) Jetting, expansion and extrusion combined pile, construction method thereof and spiral jetting, expansion and extrusion drilling rig used in method
CN102691296A (en) Pipe pile foundation for static-pressure grouting on pile side and rotary jet grouting at pile bottom and construction method thereof
CN103669365A (en) External diagonal-pulling and internal diagonal-bracing herringbone foundation pit supporting pile and construction method thereof
CN104141305A (en) Multi-layer spiral blade self-drilling-type soil anchor rod and constructing method thereof
CN103556628B (en) Spiral conical soil compaction pile construction method
CN113431490B (en) Large-diameter tubular pile construction equipment and method for karst area
CN106917404A (en) A kind of prefabricated screw stake
CN112281829A (en) Composite pile foundation structure and construction method thereof
WO2024007591A1 (en) Rock-socketed monopile construction method based on double-casing pile stabilizing platform
CN109667537B (en) Drilling process for surveying and filling pebble soil karst cave
CN106968147A (en) A kind of composite road bed structure of cast-in-situ bored pile and its construction method
CN102011548A (en) Three-layer rock-socketed tube drill of rotary drilling rig
CN203569561U (en) Novel pile forming device of steel pipe protection wall cast-in-place piles following up drill
CN209178989U (en) A kind of PHC tubular pole anti-freeze expansion processing unit
CN208605162U (en) A kind of shield tunnel geological prospecting borehole hole sealing structure
CN106759295A (en) The quiet combined pile and its construction method for boring extruding-enlarging branch tray and pile tube
CN109826226A (en) Historical building timber strengthening of foundation method
CN201763243U (en) Three-layer rock-socketed cylindrical drill for rotary drilling rig
CN204225100U (en) The construction equipment of concrete pile
CN204252120U (en) The construction equipment of concrete pile
CN206246052U (en) Soil compaction rotary-jetting bottom-expanding pile shaped device
CN104895066B (en) The construction method of overlength churning strength core built pile
CN208220632U (en) A kind of assembly type drilling tool
CN108442369A (en) A kind of PHC pile piles anti-freeze expansion processing unit and method
CN106401466A (en) Soil-squeezing jet grouting pedestal pile forming device and construction method thereof

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant