CN208605162U - A kind of shield tunnel geological prospecting borehole hole sealing structure - Google Patents

A kind of shield tunnel geological prospecting borehole hole sealing structure Download PDF

Info

Publication number
CN208605162U
CN208605162U CN201821162780.XU CN201821162780U CN208605162U CN 208605162 U CN208605162 U CN 208605162U CN 201821162780 U CN201821162780 U CN 201821162780U CN 208605162 U CN208605162 U CN 208605162U
Authority
CN
China
Prior art keywords
sealing structure
pile body
shield tunnel
shield
tunnel geological
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821162780.XU
Other languages
Chinese (zh)
Inventor
王海波
王树英
胡钦鑫
张细宝
曾凡轩
杨鹏
阳军生
刘朋飞
傅金阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Central South University
Original Assignee
Central South University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Central South University filed Critical Central South University
Priority to CN201821162780.XU priority Critical patent/CN208605162U/en
Application granted granted Critical
Publication of CN208605162U publication Critical patent/CN208605162U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

本实用新型公开了一种盾构隧道地质勘探钻孔封孔结构,在勘探钻孔内从下到上依次施工有盾构废弃渣土填充层、与勘探钻孔螺旋配合的螺旋桩体和回填层。本实用新型整个封堵结构非常简单,所消耗的水泥浆量较少且采用盾构废弃渣土进行回填,实现了废物利用、节能环保,降低了成本;采用螺旋桩体结构实现勘探钻孔的封堵,螺旋桩体与勘探钻孔螺旋配合,增加了桩体与地层间的相互作用,桩体承载力。

The utility model discloses a hole sealing structure for a shield tunnel geological exploration borehole. A shield waste slag filling layer, a screw pile body screwed with the exploration borehole and a backfill are sequentially constructed in the exploration borehole from bottom to top. Floor. The whole plugging structure of the utility model is very simple, the consumption of cement slurry is small, and shield waste slag is used for backfilling, which realizes waste utilization, energy saving and environmental protection, and reduces costs; For plugging, the screw pile body cooperates with the exploration borehole screw, which increases the interaction between the pile body and the stratum, and the bearing capacity of the pile body.

Description

A kind of shield tunnel geological prospecting borehole hole sealing structure
Technical field
The utility model belongs to Shield Construction Technique field more particularly to a kind of shield tunnel geological prospecting borehole sealing of hole knot Structure.
Background technique
For shield machine as machinery common in subway work, its basic principle is by applying certain pressure to excavation face Power maintains its stabilization, and it is different to apply stressed mode according to it, can be divided into slurry type shield, earth pressure balanced shield etc., and General set pressure is in 2bar or more.Before shield tunneling, need to the geology progress detailed exploration along it, and geology After exploration, the sealing pores of drilling are often weak link.The method for mostly using clay ball that cement slurry is added to backfill at present, but due to The reason of aperture is shunk, actual effect is often bad.
When shield tunneling to drill hole, under the jacking effect of high pressure, sealing material is easy to be extruded, immediately shield mud The modifying agent (foaming agent, bentonite slurry etc.) in mud or native storehouse in sump is gushed from drill hole.Particularly, for The underwater shield-tunneling construction of rivers, Hu Hai are passed through, the mud gushed out can not only impact ecological environment, but also increase shield The risk of structure construction.In addition, the drilling of failure also results in the decline of shield Caused by Backfill Grouting Pressure and the loss of slurries, it is serious In the case of can jeopardize shield safe construction.
Patent 201210563813.2 " exploratory hole method for blocking above solvable karst cave " is proposed using flexible cup type bolt Plug, to can lava area meet solution cavity in the case of exploratory hole method for blocking.In addition, 201410391580.1 " underwater exploration of patent Hole hole-sealing technology " proposes that a kind of top is equipped with hook, and bottom is nose cone, and outer wall is equipped with the stake plug of bulge loop, passes through accelerated cement Slurry and the cooperation of stake plug block underwater exploration hole.Both above-mentioned closure mainly for underwater exploration hole, consumed cement slurry compared with More, plugging structure is more single, does not give full play to the bearing capacity on side friction and stratum, and the computation model blocked is not bright enough Really.
Utility model content
The application aims to solve at least one of the technical problems existing in the prior art.For this purpose, the purpose of this utility model One of be to provide a kind of shield tunnel geological prospecting borehole hole sealing structure that plugging effect is good, at low cost, adaptable.
In order to solve the above technical problems, the utility model adopts the following technical solution:
A kind of shield tunnel geological prospecting borehole hole sealing structure, successively construction has shield useless from top to bottom in exploratory bore-hole The spiral pile body and backfill layer of waste soil filled layer and exploratory bore-hole threaded engagement.
Further, the bottom and top in prospecting bit hole positioned at the spiral pile body are respectively formed with shield and discard dregs Filled layer and the backfill layer backfilled by the principle of " with native earth backing, with sand also sand ".
Further, the spiral pile body is made of sequentially connected upper pile body and lower pile body, and lower pile body is spinning So as to visit the threaded drillpipe that drill hole inner wall forms screw thread in exploratory bore-hole, upper pile body is to be filled in exploratory bore-hole thread segment Interior cement slurry obturator.
Further, the shield discards between dregs filled layer and the threaded drillpipe and is additionally provided with cement injection layer.
Further, the drilling rod is made of one or more sequentially connected drill rod assemblies, and the drill rod assemblies include Periphery wall is formed with the body of rod of helical blade, is equipped in the body of rod and leads mud hole, the mud hole of leading on adjacent drill pipes component mutually interconnects It is logical.
Further, described to lead mud hole and constituted by being embedded in the intracorporal PVC mud guiding tube of bar.
Further, the body of rod is made of concrete or rubber.
Further, the arrangement of reinforcement being circular layout is embedded in the body of rod.
Further, the plug that adjacent two drill rod assemblies are formed with slot at docking and match with the slot, phase Adjacent two drill rod assemblies realize connection by extending transversely through the pin shaft of the plug and slot.
Compared with prior art, the utility model has the following beneficial effects:
1, entire plugging structure is simple, and consumed cement slurry volume is less and is backfilled using the discarded dregs of shield, real Show waste utilization, energy conservation and environmental protection, reduced costs, realizes the closure of exploratory bore-hole, spiral using spiral pile body structure for the first time Pile body and exploratory bore-hole threaded engagement increase the interaction of pile body and ground interlayer, pile body bearing capacity.
2, spiral pile body is made of threaded drillpipe and cement slurry obturator, and threaded drillpipe can carry out splicing and combining use, is led to The plug construction cooperation bolt for crossing upper socket and lower part realizes that threaded drillpipe is provided centrally with mud guiding tube, downward precession process In, muddy water is discharged from pipe, to reduce penetration resistance, improves injection efficiency.
Detailed description of the invention
Fig. 1 is the schematic diagram of hole sealing structure;
Fig. 2 is the structural schematic diagram of auger stem;
Fig. 3 is auger stem size marking schematic diagram;
Fig. 4 is the assembled schematic diagram of auger stem.
Specific embodiment
The utility model is further described below in conjunction with the drawings and specific embodiments.
Referring to figures 1-4, in one embodiment, a kind of shield tunnel geological prospecting borehole hole sealing structure, in exploratory bore-hole Inside successively construction has shield to discard dregs filled layer 2 and exploratory bore-hole threaded engagement from top to bottom spiral pile body 1 and backfill layer 3.Wherein, it is preferred that backfill layer 2 is backfilled by the principle of " with native earth backing, with sand also sand ", and shield discards dregs using packed Mode be filled.Entire plugging structure is simple in the present embodiment, and consumed cement slurry volume is less and discarded using shield Dregs is backfilled, and is realized waste utilization, energy conservation and environmental protection, is reduced costs, and realizes exploratory bore-hole using spiral pile body structure Closure, spiral pile body and exploratory bore-hole threaded engagement increase the interaction of pile body and ground interlayer, pile body bearing capacity, when To drill hole, sealing material is not easy to be extruded shield tunneling, and plugging effect is good.
- Fig. 4 referring to fig. 2, in another embodiment, spiral pile body 1 are made of sequentially connected upper pile body 4 and lower pile body 5, Lower pile body 5 is that diameter is greater than drill bit bore internal diameter, to form the threaded bore of screw thread in exploratory bore-hole inner wall in spinning progradation Bar, upper pile body 4 are the cement slurry obturator being filled in exploratory bore-hole thread segment.Dregs filled layer 2 and screw thread are discarded in shield Cement injection layer (not identifying in figure) is additionally provided between drilling rod.
Preferably, drilling rod is made of one or more sequentially connected drill rod assemblies 6, and drill rod assemblies 6 include periphery wall one Body forms the body of rod 6-1 that (can also use split type) has helical blade 7, is equipped in body of rod 6-1 and leads mud hole 6-2, adjacent drill pipes The mud hole 6-2 that leads on component 6 is interconnected.It is constituted specifically, leading mud hole 6-2 by being embedded in the intracorporal PVC mud guiding tube of bar.When adopting When with multiple drill rod assemblies, adjacent two drill rod assemblies 6 are formed with slot 8 and the plug matched with slot 89, phase at docking Adjacent two drill rod assemblies 6 realize connection by extending transversely through the pin shaft 10 of plug 9 and slot 8.
The specific size of drill rod assemblies 6 are as follows: top diameter D1 is equal to 1.2 times of prospecting bit bore dias, intermediate mud guiding tube diameter D2 It is equal to the 1/2 of top diameter D1 equal to 3cm, lower plug diameter D3, lower plug height h is equal to 5cm, top rim of a cup depth d Equal to 3cm, overall height H is equal to 3 times of top diameter D1, and the size of periphery wall screw thread meets n:m:k=4:3:1.
The present embodiment, drilling rod can carry out splicing and combining use, cooperate latch structure by upper socket and the plug of lower part It realizes;It is provided centrally with mud guiding tube, during downward precession, muddy water is discharged from pipe, to reduce penetration resistance, improves injection Efficiency;When the body of rod is by concrete for making, it is adaptable to the closure of soil layer drilling, when using rubber production, is adaptable to rock The closure of layer drilling, is the intensity of drilling rod, the arrangement of reinforcement being circular layout also is embedded in the body of rod.
The work progress of the utility model hole sealing structure is as follows:
(1) auger stem is prefabricated: shell injection molded material makes auger stem using concrete or rubber according to demand;
(2) drilling lower part backfill: packed shield is discarded into dregs as lower part sealing material and carries out sealing of hole, packed shield is useless Waste soil packed height is at the 1m of shield machine top;
(3) prepared by cement slurry: preparing the cement slurry that the ratio of mud is 0.8;
(4) once grouting: will lead slurry pipe and be put into drilling, by leading slurry pipe in prepared cement slurry injection hole, Marginal not slurry side, which is promoted, leads slurry pipe, and cement mortar perfusion height first stops slip casting when reaching 1m, slurry pipe is led in extraction;
(5) it places auger stem: prefabricated spiral drilling rod is screwed in 0.5m above packed shield dregs;
(6) secondary grouting: will lead slurry pipe again and be put into drilling, until continuing grout injection to desired height, slip casting After the completion, it is lifted out and leads slurry pipe, and make cement slurry sets 30min;
(7) sealing quality inspection: sealing quality is checked according to corresponding specification;
(8) drilling top backfill: after sealing of hole detection is qualified, upper overburden layer by " with native earth backing, with sand also sand " principle into Row backfill.
Above-described embodiment is only to clearly demonstrate examples for clearly illustrating the present invention, rather than the restriction to embodiment. For those of ordinary skill in the art, other various forms of variations can also be made on the basis of the above description Or it changes.Here without can not be also exhaustive to all embodiments.And the obvious variation thus amplified out Or it changes among still in the protection scope of the utility model.

Claims (9)

1.一种盾构隧道地质勘探钻孔封孔结构,其特征在于:在勘探钻孔内从下到上依次施工有盾构废弃渣土填充层、与勘探钻孔螺旋配合的螺旋桩体和回填层。1. a shield tunnel geological exploration borehole sealing structure is characterized in that: in the exploration borehole, from bottom to top, the shield waste slag filling layer, the screw pile body and the helical pile body that is screwed with the exploration borehole are constructed successively. backfill layer. 2.根据权利要求1所述的盾构隧道地质勘探钻孔封孔结构,其特征在于:在回填层按“以土还土,以砂还砂”的原则进行回填。2. The shield tunnel geological exploration drilling hole sealing structure according to claim 1 is characterized in that: backfill is carried out in the backfill layer according to the principle of "return soil with sand, and return sand with sand". 3.根据权利要求1或2所述的盾构隧道地质勘探钻孔封孔结构,其特征在于:所述螺旋桩体由顺次连接的上桩体和下桩体组成,所述下桩体为旋装在勘探钻孔中以使勘探钻孔内壁形成螺纹的螺纹钻杆,所述上桩体为填充在勘探钻孔螺纹段内的水泥浆填充体。3. The shield tunnel geological exploration drilling hole sealing structure according to claim 1 or 2, characterized in that: the spiral pile body is composed of an upper pile body and a lower pile body connected in sequence, and the lower pile body is composed of For a threaded drill pipe screwed into an exploration borehole to form threads on the inner wall of the exploration borehole, the upper pile body is a cement slurry filling body filled in the threaded section of the exploration borehole. 4.根据权利要求3所述的盾构隧道地质勘探钻孔封孔结构,其特征在于:所述盾构废弃渣土填充层与所述螺纹钻杆之间还设有水泥注浆层。4 . The shield tunnel geological exploration drilling hole sealing structure according to claim 3 , wherein a cement grouting layer is further provided between the shield waste slag filling layer and the threaded drill pipe. 5 . 5.根据权利要求3所述的盾构隧道地质勘探钻孔封孔结构,其特征在于:所述钻杆由一个或多个顺次连接的钻杆组件组成,所述钻杆组件包括外周壁形成有螺旋叶片的杆体,所述杆体中设有导泥孔,相邻钻杆组件上的导泥孔相互连通。5 . The shield tunnel geological exploration drilling hole sealing structure according to claim 3 , wherein the drill pipe is composed of one or more drill pipe assemblies connected in sequence, and the drill pipe assembly includes an outer peripheral wall. 6 . A rod body with a helical blade is formed, the rod body is provided with mud guide holes, and the mud guide holes on adjacent drill rod assemblies communicate with each other. 6.根据权利要求5所述的盾构隧道地质勘探钻孔封孔结构,其特征在于:所述导泥孔由预埋在杆体内的PVC导泥管构成。6 . The hole sealing structure for shield tunnel geological exploration according to claim 5 , wherein the mud guiding hole is formed by a PVC mud guiding pipe pre-buried in the rod body. 7 . 7.根据权利要求6所述的盾构隧道地质勘探钻孔封孔结构,其特征在于:所述杆体由混凝土或橡胶制成。7 . The drilling and sealing structure for shield tunnel geological exploration according to claim 6 , wherein the rod body is made of concrete or rubber. 8 . 8.根据权利要求7所述的盾构隧道地质勘探钻孔封孔结构,其特征在于:所述杆体内预埋有环形布置的配筋。8 . The shield tunnel geological exploration drilling hole sealing structure according to claim 7 , wherein the rod body is pre-embedded with annularly arranged reinforcing bars. 9 . 9.根据权利要求5所述的盾构隧道地质勘探钻孔封孔结构,其特征在于:相邻两钻杆组件在对接处形成有插槽和与所述插槽相配合的插头,相邻两钻杆组件通过横向贯穿所述插头和插槽的销轴实现连接。9. The shield tunnel geological exploration drilling hole sealing structure according to claim 5, characterized in that: a slot and a plug matched with the slot are formed at the butt joint of two adjacent drill pipe assemblies, adjacent to the The two drill rod assemblies are connected by a pin shaft transversely passing through the plug and the socket.
CN201821162780.XU 2018-07-23 2018-07-23 A kind of shield tunnel geological prospecting borehole hole sealing structure Active CN208605162U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821162780.XU CN208605162U (en) 2018-07-23 2018-07-23 A kind of shield tunnel geological prospecting borehole hole sealing structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821162780.XU CN208605162U (en) 2018-07-23 2018-07-23 A kind of shield tunnel geological prospecting borehole hole sealing structure

Publications (1)

Publication Number Publication Date
CN208605162U true CN208605162U (en) 2019-03-15

Family

ID=65669699

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821162780.XU Active CN208605162U (en) 2018-07-23 2018-07-23 A kind of shield tunnel geological prospecting borehole hole sealing structure

Country Status (1)

Country Link
CN (1) CN208605162U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110005367A (en) * 2019-03-26 2019-07-12 无锡市政设计研究院有限公司 A kind of device of drilling and sealing
CN112610181A (en) * 2020-12-30 2021-04-06 武汉中科岩土工程有限责任公司 Underwater tunnel engineering exploration hole plugging structure and plugging method thereof
CN114876405A (en) * 2022-06-20 2022-08-09 中煤科工集团重庆研究院有限公司 Spiral drill rod type hole packer

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110005367A (en) * 2019-03-26 2019-07-12 无锡市政设计研究院有限公司 A kind of device of drilling and sealing
CN110005367B (en) * 2019-03-26 2024-04-09 华昕设计集团有限公司 Device for hole sealing of drilling holes
CN112610181A (en) * 2020-12-30 2021-04-06 武汉中科岩土工程有限责任公司 Underwater tunnel engineering exploration hole plugging structure and plugging method thereof
CN114876405A (en) * 2022-06-20 2022-08-09 中煤科工集团重庆研究院有限公司 Spiral drill rod type hole packer
CN114876405B (en) * 2022-06-20 2023-07-21 中煤科工集团重庆研究院有限公司 Spiral drill rod type hole packer

Similar Documents

Publication Publication Date Title
CN102691296B (en) Pipe pile foundation for static-pressure grouting on pile side and rotary jet grouting at pile bottom and construction method thereof
CN104453913B (en) A kind of Shaft Stopes front pre-grouting method
CN103089275B (en) Control method of surrounding rocks in water-rich very-broken surrounding rock tunnel collapse sections
CN107975375B (en) A kind of miniature steel pipe pile reinforced soft foundation construction method of city tunnel
CN103382847A (en) Prestressed drilling, anchoring and grouting anchor cable and supporting method
CN106917627B (en) The advanced support method of pilot tunnel under a kind of water rich strata boring construction
CN208605162U (en) A kind of shield tunnel geological prospecting borehole hole sealing structure
CN107605498A (en) Rich water sand-pebble layer shield tunnel termination horizontal grouting ruggedized construction construction method
CN110185413A (en) A method of stable slip casting channel is formed on easy collapse hole stratum
CN102418536A (en) Large-aperture pretension bottom plate hollow grouting device
CN108756809B (en) A kind of sealing method for shield tunnel geological exploration borehole
CN108708743A (en) A method of using grouting treatment Tunnel Collapse
CN105756700A (en) Construction method and hole sealing structure for super-large section tunnel for traversing coal measure strata section
CN102777185A (en) Inclined well shaft construction technology
CN106906840A (en) The method of offshore wind farm rock-socketed steel pipe piles and the outer grouting construction of stake
CN206625831U (en) A kind of Karst grouting automatic monitored control system
CN107313745A (en) A kind of cementing method for crossing the intensive grouting and reinforcing coal bed gas well of many nodes in goaf
CN205152941U (en) City subway passes through weak sand bed drilling grouting dado structure in karst region
CN105909265B (en) Pass through the anti-protuberance retrusive deep hole grouting system and method for existing shield tunnel
CN205558943U (en) Country rock fault slip casting stock in pit
CN204252934U (en) Test boring device for plugging
CN205576957U (en) Stake end pilework
CN103114576A (en) Post grouting construction method for cast-in-place concrete pile
CN207406345U (en) Rich water sand-pebble layer shield tunnel end horizontal grouting ruggedized construction
CN108729461A (en) For the constructing structure and construction method on aerial leakage stratum in deep hole impervious wall construction