CN209025072U - Reinforced concrete sleeve stake - Google Patents

Reinforced concrete sleeve stake Download PDF

Info

Publication number
CN209025072U
CN209025072U CN201821602676.8U CN201821602676U CN209025072U CN 209025072 U CN209025072 U CN 209025072U CN 201821602676 U CN201821602676 U CN 201821602676U CN 209025072 U CN209025072 U CN 209025072U
Authority
CN
China
Prior art keywords
stake
pile
outer tube
interior
diameter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821602676.8U
Other languages
Chinese (zh)
Inventor
柴清
陈天镭
张�杰
王兆辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Lanzhou Engineering and Research Institute of Nonferrous Metallurgy Co Ltd
Original Assignee
Lanzhou Engineering and Research Institute of Nonferrous Metallurgy Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Lanzhou Engineering and Research Institute of Nonferrous Metallurgy Co Ltd filed Critical Lanzhou Engineering and Research Institute of Nonferrous Metallurgy Co Ltd
Priority to CN201821602676.8U priority Critical patent/CN209025072U/en
Application granted granted Critical
Publication of CN209025072U publication Critical patent/CN209025072U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a kind of reinforced concrete sleeve stakes, belong to civil engineering field, to solve the problem of that existing tube-in-tube pile can not be applied and higher cost in big, intermediate diameter pile foundation engineering.Including outer tube, interior stake;The interior stake indulges muscle by stake, the built-in concrete of pile ring muscle encloses, the lower part stake diameter of interior stake is big, and the top stake diameter of interior stake is small, is connected between lower part stake and top stake by down big up small reducer, top stake is outer to be arranged outer tube, and discrete material layer is equipped between outer tube and stake holes.Pile-side negative friction can be greatly decreased to the adverse effect of pile foundation in the utility model, easy to operate, improve the bearing capacity of pile foundation, reduce sedimentation, extend durability.The utility model convenient construction, it is environment friendly and pollution-free.

Description

Reinforced concrete sleeve stake
Technical field
The utility model belongs to civil engineering field, and in particular to Yi Zhong great, intermediate diameter are that armored concrete fills Infuse stake.
Background technique
The effect of pile foundation is that load is reached to the good soil layer of underground higher depth load-carrying properties, to meet bearing capacity and sedimentation Requirement.The bearing capacity of pile foundation is high, can bear Vertical Load, can also bear horizontal loading, can resist uplift load and also can Oscillatory load is born, is most widely used deep foundation form.Pile foundation is since applied widely, bearing capacity is high, settling amount It is small, it is widely used in the engineerings such as building, bridge, harbour.
Pile foundation is classified by bearing characters, can be divided into Piles for Friction Piles, type stake is held at end.Piles for Friction Piles can be divided into friction pile, Point friction pile, under ultimate limit states, stake top vertical load is born friction pile by pile side resistance, and end resistance is small to be arrived It is negligible;Under ultimate limit states, stake top vertical load is mainly born by pile side resistance point friction pile.It holds at end Type stake is divided into end-bearing pile, friction end-bearing pile, and under ultimate limit states, stake top vertical load is held end-bearing pile by end resistance By pile side resistance is small to negligible;End-bearing pile rub under ultimate limit states, stake top vertical load is mainly by stake End resistance is born.Friction pile, point friction pile, friction side hold stake top vertical load whole, main or part pile side resistance is held By.
But China region is wide, and engineering geological condition is complicated, collapsible loess, banket, the special soils such as frozen soil, salinized soil it is wide General distribution.Stake top vertical load cannot not only be born by pile side resistance in these Special soil foundations, and stake side can generate it is negative Frictional resistance has an adverse effect to Pile Bearing Capacity and sedimentation.
There is cavity between existing tube-in-tube pile outer tube and interior stake, interior stake, can not be in big, intermediate diameter since slenderness ratio limits It is applied in pile foundation engineering, and interior stake is mostly steel, higher cost.
Utility model content
The purpose of this utility model provides a kind of reinforced concrete sleeve stake, can not be big or middle to solve existing tube-in-tube pile It is applied in equal diameter pile foundation engineering, and the problem of higher cost.
The technical solution adopted in the utility model is: a kind of reinforced concrete sleeve stake, including outer tube, interior stake;It is described Interior stake indulges muscle by stake, the built-in concrete of pile ring muscle encloses, and the lower part stake diameter of interior stake is big, and the top stake diameter of interior stake is small, under It is connected between portion's stake and top stake by down big up small reducer, top stake is outer to be arranged outer tube, sets between outer tube and stake holes There is discrete material layer.
The lower part of the outer tube is in down big up small bell mouth shape as a further improvement of the utility model,.
As a further improvement of the utility model,
As a further improvement of the utility model, the discrete material layer with a thickness of 50mm-200mm.
The stake upper diameter is 250mm-1100mm as a further improvement of the utility model,.
The stake lower diameter is 350mm-1200mm as a further improvement of the utility model,.
The utility model is applied to tube-in-tube pile in big, intermediate diameter pile foundation engineering by foundation treatment mode expansion, reduces Cost, can be greatly decreased pile-side negative friction to the adverse effect of pile foundation, easy to operate, improve the bearing capacity of pile foundation, subtract Small sedimentation extends durability.The utility model convenient construction, it is environment friendly and pollution-free.
Compared with the prior art, the utility model has the following advantages:
1. the utility model pass through collapsible loess, banket, the special soil layer such as frozen soil, salinized soil when, since stake diameter becomes It is small, reduce pile-side negative friction;
2. outer tube is arranged in special soil layer, the durability of pile foundation is extended, housing tube wall is smooth, further subtracts Small adverse effect of the stake side force of negative friction to pile foundation;
3. filling discrete material between outer tube and stake holes, adverse effect of the isolation pile side foundation soil to tube-in-tube pile.
4. utility model can be widely used in collapsible loess, banket, the Special soil foundations such as frozen soil, salinized soil, to durable In the high pile foundation of property, settlement request.
Detailed description of the invention
Fig. 1 is a kind of reinforced concrete sleeve stake schematic diagram;
Fig. 2 is A-A view in Fig. 1;
Fig. 3 is B-B view in Fig. 1.
Appended drawing reference meaning is as follows: muscle is indulged in stake;2-pile ring muscle;3-concrete;4-outer tubes;5- discrete material layer; 6-pile framings;7- stake holes;The stake of the lower part 8-;The stake of the top 9-;C- reducer.
Specific embodiment
The technical solution of the utility model is described in further detail with reference to the accompanying drawing.
As shown, a kind of reinforced concrete sleeve stake, including outer tube 4, interior stake;Interior stake indulges muscle 1, pile ring muscle 2 by stake Built-in concrete 3 encloses, and the lower part of interior stake 8 diameters of stake are big, and top 9 diameters of stake of interior stake are small, lower part stake 8 and top stake 9 it Between be connected by down big up small reducer C, outer tube 4 is set outside top stake 9, discrete material is equipped between outer tube 4 and stake holes 7 Layer 5.The lower part of outer tube 4 is in down big up small bell mouth shape.Outer tube the plastic material pipe or metal material smooth using surface Matter pipe.
Specific implementation step are as follows:
1, scene passes through surveying setting-out spacer bar concrete jacket tubular pole;
2, by mechanical equipment or it is artificially formed stake holes 7;
3, the interior stake that muscle 1 is indulged in stake, pile ring muscle 2 forms is sunk at clear bottom after pore-forming;
4, at casting concrete to stake section reducer C, it is put into outer tube 4, casting concrete to stake top, pile framing 6 Lower section;
5, outer tube is further decreased to the filler for inserting coarse sand or other discrete materials isolation negative friction between stake holes Adverse effect of the pile-side negative friction to stake.
Embodiment 1
The arrangement of stake, stake diameter and stake are long by specifically designing determination in present embodiment.
1, vertical bearing capacity of single pile characteristic value is calculated:
(1) according to the empirical relation between the physical index of soil and carrying force parameter, ultimate bearing capacity of single pile standard is determined Value:
Qsk: total ultimate frictional resistance standard value;
Qpk: total standard ultimate bearing capacity;
qsik: the native ultimate frictional resistance standard value in i-th layer of stake side only counts neutral point or less part side resistance value;
qpk: ultimate end resistance of pile standard value;
Ψsi、ψp: side, end resistance dimensions effect coefficient, calculating is shown in Table 1;
U: stake lower perimeter;
Quk: vertical bearing capacity of single pile;
Li: i-th layer of native thickness;
Ap: stake end area.
(2) vertical bearing capacity of single pile characteristic value RaIt should determine as the following formula:
Ra: vertical bearing capacity of single pile characteristic value
K: safety coefficient takes K=2.
(3) type foundation pile is held for end and is considered as the downdrag that negative friction causes foundation pile, and checking computations foundation pile is held as the following formula Carry power:
Nk: foundation pile vertical bearing capacity.
Since the utility model is when passing through the special soil layer that can generate pile-side negative friction, stake diameter becomes smaller, outer tube pipe Wall is smooth, and discrete material layer is isolated so that pile-side negative friction reduces or even eliminates, constant in vertical bearing capacity of single pile characteristic value In the case where, improve foundation pile vertical bearing capacity.
2, the negative friction of outer tube is measured by testing.
3, by designing, calculating acquires a diameter size and stake is long.
4, production and site operation.
As the case may be, discrete material layer with a thickness of 50mm-200mm.Stake upper diameter is 250mm-1100mm.Stake Lower diameter is 350mm-1200mm, and stake end can do enlarged footing.Stake is long to be greater than 6m, with specific reference to geological state, upper load etc. It is determined by design.The length of outer tube 4 is determined according to special the thickness of the layer etc. by design.

Claims (5)

1. a kind of reinforced concrete sleeve stake, including outer tube, interior stake;It is characterized by: the interior stake indulges muscle (1), stake by stake Stirrup (2) built-in concrete (3) encloses, and lower part stake (8) diameter of interior stake is big, and top stake (9) diameter of interior stake is small, lower part stake (8) be connected between top stake (9) by down big up small reducer, outer tube (4) are arranged outside in top stake (9), outer tube (4) and Discrete material layer (5) are equipped between stake holes (7).
2. reinforced concrete sleeve stake according to claim 1, it is characterised in that: under the lower part of the outer tube (4) is in Small bell mouth shape upper greatly.
3. reinforced concrete sleeve stake according to claim 1 or 2, it is characterised in that: the thickness of the discrete material layer For 50mm-200mm.
4. reinforced concrete sleeve stake according to claim 3, it is characterised in that: the stake upper diameter is 250mm- 1100mm。
5. reinforced concrete sleeve stake according to claim 4, it is characterised in that: the stake lower diameter is 350mm- 1200mm。
CN201821602676.8U 2018-09-29 2018-09-29 Reinforced concrete sleeve stake Active CN209025072U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821602676.8U CN209025072U (en) 2018-09-29 2018-09-29 Reinforced concrete sleeve stake

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821602676.8U CN209025072U (en) 2018-09-29 2018-09-29 Reinforced concrete sleeve stake

Publications (1)

Publication Number Publication Date
CN209025072U true CN209025072U (en) 2019-06-25

Family

ID=66905198

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821602676.8U Active CN209025072U (en) 2018-09-29 2018-09-29 Reinforced concrete sleeve stake

Country Status (1)

Country Link
CN (1) CN209025072U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108951615A (en) * 2018-09-29 2018-12-07 兰州有色冶金设计研究院有限公司 Reinforced concrete sleeve stake and its construction method
CN115162318A (en) * 2022-07-13 2022-10-11 中国电建集团昆明勘测设计研究院有限公司 Open-close type isolation pile for controlling influence of vacuum preloading environment and isolation method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108951615A (en) * 2018-09-29 2018-12-07 兰州有色冶金设计研究院有限公司 Reinforced concrete sleeve stake and its construction method
CN115162318A (en) * 2022-07-13 2022-10-11 中国电建集团昆明勘测设计研究院有限公司 Open-close type isolation pile for controlling influence of vacuum preloading environment and isolation method thereof

Similar Documents

Publication Publication Date Title
CN108951615A (en) Reinforced concrete sleeve stake and its construction method
Lv et al. Field tests on bearing characteristics of X-section pile composite foundation
CN102080373A (en) Construction method for jointly treating collapsibility of loess foundation by using DDC (Downhole Dynamic Compaction) pile and pile foundation
CN108385673A (en) Miniature top filling ball sleeve pile pile and its construction method
CN109457698A (en) Eliminate the casing prefabricated pile and its construction method of breathing soil layer frictional force
CN209025072U (en) Reinforced concrete sleeve stake
CN105200983A (en) PVC pipe and thick wall steel tube composite hollow recycled concrete pile
CN203160263U (en) Rigid piles and soft piles adopted composite foundation for resisting side displacement and soil squeeze of saturated soft soils
CN108824471A (en) A kind of deep water drift net multi-column pier foundation and its construction method
CN204112318U (en) A kind of technique device improving CFG guncreting pile bearing capacity
CN100513708C (en) Method for transversal reinforcement and grouting underpinning of ready construction foundation
CN209538174U (en) Eliminate the casing prefabricated pile of breathing soil layer frictional force
CN206503157U (en) The embedding rock mixing pile foundation of offshore wind farm
CN207092083U (en) Pile protection pile tube in miniature fixed type steel
CN209538173U (en) Eliminate the prefabricated pile of breathing soil layer frictional force
CN104047285A (en) Technical device and construction method for improving bearing capacity of CFG pressure pouring piles
CN104179190A (en) Composite pile foundation for offshore wind power and construction method thereof
CN209891202U (en) Anti-floating anchor rod
CN204000856U (en) The anti-side changeable ridigity pile of inner support grouting formula level base
CN207109805U (en) Wear the compound isolation pile of bridge pier in a kind of tunnel side
CN209603127U (en) Eliminate the bored concrete pile of breathing soil layer frictional force
Jiang et al. A new large step-tapered hollow pile and its bearing capacity
CN202247910U (en) Soil retaining structure with different inclination angles of anti-skid cement soil pile
CN109695242A (en) Eliminate the prefabricated pile and its construction method of breathing soil layer frictional force
CN109457697A (en) Eliminate the bored concrete pile of breathing soil layer frictional force

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant