CN208858135U - A kind of integral lifting construction of lift well job platform - Google Patents

A kind of integral lifting construction of lift well job platform Download PDF

Info

Publication number
CN208858135U
CN208858135U CN201821590792.2U CN201821590792U CN208858135U CN 208858135 U CN208858135 U CN 208858135U CN 201821590792 U CN201821590792 U CN 201821590792U CN 208858135 U CN208858135 U CN 208858135U
Authority
CN
China
Prior art keywords
girder steel
main girder
steel
job platform
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821590792.2U
Other languages
Chinese (zh)
Inventor
李宏良
陈家平
黄付强
李加宁
罗金
白永晨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Second Engineering Bureau Co Ltd
Original Assignee
China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Second Engineering Bureau Co Ltd filed Critical China Construction Second Engineering Bureau Co Ltd
Priority to CN201821590792.2U priority Critical patent/CN208858135U/en
Application granted granted Critical
Publication of CN208858135U publication Critical patent/CN208858135U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model provides a kind of integral lifting construction of lift well job platform, including main girder steel and time girder steel, main girder steel and time girder steel surround braced frame, braced frame is equipped with job platform, it is equipped with support steel beam in main girder steel, is also equipped with elastic device in main girder steel, the compression end of support steel beam is fixedly connected with elastic device, the projecting end of support steel beam stretches out main girder steel under the active force of elastic device, and support steel beam can compress under external force into main girder steel.When construction floor carries out operation, support steel beam can stretch out main girder steel under the action of the elastic means, to ride upon on construction floor, building for job platform is realized, when needing lifting to next floor, support steel beam can be compressed into main girder steel, main girder steel is gone up and down to next floor, support steel beam can stretch out main girder steel under the action of the elastic means, to ride upon on next floor, realize building for next floor job platform, job platform sets up time saving material-saving and stabilized structure.

Description

A kind of integral lifting construction of lift well job platform
Technical field
The utility model relates to elevator construction fields, and in particular to a kind of integral lifting construction of lift well job platform.
Background technique
Elevator shaft mouth is that a bite in four mouthfuls of Triratna and five face one side in side, is that safety accident takes place frequently ground.In height In journey major structure of construction concrete construction of lift well, elevator inner wall form is installed, traditional method be steel pipe scaffold from Basis starts to set up, until operation layer, or using steel pipe scaffold+fashioned iron layering unloading until operation layer, is primarily present following Problem:
(1) steel pipe scaffold expense material expense material is set up
Steel pipe scaffold is set up all the way up from basis needs a large amount of steel tube fastener foot handsheet etc., when being unloaded with layering, Pre-buried fashioned iron is also answered in corresponding floor, needs biggish material investment, takes material expense material;
(2) material platform is set up time-consuming
Steel pipe scaffold scaffolding height is higher when main structure construction, and bracket is more unstable, is easy unstability, there is biggish peace Full hidden danger;
(3) it is unfavorable for operator's construction
Material table top uses foot handsheet or template and bracket to bind substantially, is limited by laying plane materiel and laying personnel, quality It cannot be guaranteed, there are security risks, are unfavorable for operator's construction for status.
Utility model content
The technical problem to be solved by the utility model is to provide one kind to set up time saving material-saving, structurally stable whole promotion Formula construction of lift well job platform.
To achieve the above object, a kind of technical solution that the utility model is taken are as follows: integral lifting construction of lift well work Industry platform, including main girder steel and time girder steel, main girder steel and time girder steel surround braced frame, and braced frame is equipped with job platform, Main girder steel is hollow structure, and support steel beam, support steel beam and main girder steel slidable fit are equipped in main girder steel, is also installed in main girder steel The compression end of flexible device, support steel beam is fixedly connected with elastic device, the work of the projecting end of support steel beam in elastic device Firmly lower to stretch out main girder steel, support steel beam can compress under external force into main girder steel.
The limited post for carrying out limit block to elastic device is equipped in main girder steel, elastic device limit is assemblied in main steel In beam.
Elastic device is fixed in main girder steel.
Support steel beam compression end is fixedly connected with elastic device, and projecting end is equipped with the idler wheel that can be rolled along elevator shaft.
Main girder steel is welded by two opposite channel steels of opening direction, and support steel beam is matched I-steel Beam.
The inner wall of main girder steel is equipped with the first postive stop baffle, and the web of support steel beam is equipped with to be limited with the first postive stop baffle Second postive stop baffle of cooperation.
The projecting end of support steel beam is equipped with pull ring.
The projecting end of support steel beam is connected with spacer pin by wirerope, and the length of spacer pin is greater than the end ruler of main girder steel Very little, the projecting end of support steel beam is additionally provided with pin hole compatible with spacer pin.
Main girder steel is welded by two opposite channel steels of opening direction, and support steel beam is matched I-steel Beam, pin hole are located on the top plate and bottom plate of steel I-beam.
It is additionally provided on main girder steel and hangs liter pull ring and positioning column.
The integral lifting construction of lift well job platform of the utility model, including main girder steel and time girder steel, main girder steel and Secondary girder steel surrounds braced frame, and braced frame is equipped with job platform, and main girder steel is hollow structure, is equipped with supporting steel in main girder steel Beam, support steel beam and main girder steel slidable fit are also equipped with elastic device in main girder steel, and the compression end and elasticity of support steel beam fill It sets and is fixedly connected, the projecting end of support steel beam stretches out main girder steel under the active force of elastic device, and support steel beam can be in outer masterpiece It is retracted in main girder steel with pushing.When construction floor carries out operation, support steel beam can stretch out main steel under the action of the elastic means Beam realizes building for job platform to ride upon on construction floor, can be by support steel beam when needing lifting to next floor It compresses into main girder steel, main girder steel is gone up and down to next floor, support steel beam can stretch out main steel under the action of the elastic means Beam realizes building for next floor job platform to ride upon on next floor, and job platform sets up time saving material-saving and structure It is firm.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of specific embodiment of the utility model one;
Fig. 2 is the A-A direction view of Fig. 1;
Fig. 3 is the B-B direction view of Fig. 1.
Specific embodiment
The utility model is described in further detail with reference to the accompanying drawing.
The specific embodiment one of the integral lifting construction of lift well job platform of the utility model, as Fig. 1 into Fig. 3 institute Show, including main girder steel 1 and time girder steel, main girder steel 1 and time girder steel surround braced frame, and braced frame is equipped with job platform, main Girder steel 1 is hollow structure, is equipped with support steel beam 2 in main girder steel 1, main girder steel 1 by the opposite channel steel welding of two opening directions and At support steel beam 2 is matched steel I-beam, support steel beam 2 and main 1 slidable fit of girder steel, is also installed in main girder steel 1 Flexible device 3, elastic device 3 are spring energy storage block, certainly, in other embodiments, elastic device 3 can for spring etc. other Elastic device, the interior limited post 4 being equipped with for carrying out limit block to elastic device 3 of main girder steel 1, the limit assembly of elastic device 3 In main girder steel 1, the compression end of support steel beam 2 is fixedly connected with elastic device 3, and the projecting end of support steel beam 2 is in elastic device Active force under stretch out main girder steel 1, support steel beam 2 can be compressed under external force into main girder steel 1.
When construction floor carries out operation, support steel beam 2 can stretch out main girder steel 1 under the action of elastic device 3, to take It is located on construction floor, realizes building for job platform, when needing lifting to next floor, support steel beam 2 can be compressed into master In girder steel 1, then main girder steel 1 is gone up and down to next floor, in lifting process, support steel beam 2 is under the active force of elastic device 3 It contradicts on elevator shaft, support steel beam 2 and elevator shaft sliding friction, when going up and down to next floor, support steel beam 2 Main girder steel 1 is stretched out under the action of elastic device 3, to ride upon on next floor, realizes taking for next floor job platform It builds, job platform sets up time saving material-saving and stabilized structure.
Preferably, 2 compression end of support steel beam is fixedly connected with elastic device 3, and projecting end is equipped with and can roll along elevator shaft Idler wheel 5, can reduce main girder steel 1 lifting when support steel beam 2 and elevator shaft frictional resistance.
As shown in Figure 2, the inner wall of main girder steel 1 is equipped with the first postive stop baffle 6, the web of support steel beam 2 be equipped with Second postive stop baffle 7 of the first postive stop baffle 6 limit cooperation, is arranged the first postive stop baffle 6 and the second postive stop baffle 7, can avoid Support steel beam 2 is excessively retracted to main 1 internal pressure of girder steel under external force and damages to elastic device 3 and limited post 4.
As shown in Figure 3, the projecting end of support steel beam 2 is connected with spacer pin 9 by wirerope 8, and the length of spacer pin 9 is big In the end size of main girder steel 1, the projecting end of support steel beam 2 is additionally provided with pin hole compatible with spacer pin 9, and spacer pin 9 is arranged, Operation floor can be promoted in main girder steel 1, when support steel beam 2 stretches out main girder steel 1 and rides upon operation floor, to support steel beam 2 into Row limit, job platform falls caused by avoiding support steel beam 2 under external force in the main girder steel of compression and back 1, further, Since support steel beam 2 is i-beam structure, pin hole is arranged on the top plate and bottom plate of steel I-beam, it is ensured that spacer pin 9 is right The limit effect of support steel beam 2.
Preferably, be additionally provided on main girder steel 1 and hang liter pull ring 10 and positioning column 11, rise in order to hang to main girder steel 1 and Positioning.
The specific embodiment two of the integral lifting construction of lift well job platform of the utility model, and embodiment one Difference is that elastic device 3 is fixed in main girder steel 1, can simplify the structure of job platform, is convenient for assembly and disassembly.
The specific embodiment three of the integral lifting construction of lift well job platform of the utility model, and embodiment one Difference is that the projecting end of support steel beam 2 is equipped with pull ring, in order to pull out support steel beam 2 out of main girder steel 1.
Finally, it is stated that: above embodiments are merely intended for describing the technical solutions of the present application, but not for limiting the present application, this field Other modifications or equivalent replacement that those of ordinary skill makes the technical solution of the utility model, it is practical without departing from this The spirit and scope of new technique scheme should all cover in the scope of the claims of the utility model.

Claims (10)

1. a kind of integral lifting construction of lift well job platform, including main girder steel and time girder steel, main girder steel and time girder steel surround Braced frame, braced frame are equipped with job platform, it is characterised in that: main girder steel is hollow structure, is equipped with support in main girder steel Girder steel, support steel beam and main girder steel slidable fit are also equipped with elastic device, the compression end and elasticity of support steel beam in main girder steel Device is fixedly connected, and the projecting end of support steel beam stretches out main girder steel under the active force of elastic device, and support steel beam can be in external force Effect, which pushes, to be retracted in main girder steel.
2. integral lifting construction of lift well job platform according to claim 1, it is characterised in that: be equipped in main girder steel For carrying out the limited post of limit block to elastic device, elastic device limit is assemblied in main girder steel.
3. integral lifting construction of lift well job platform according to claim 1, it is characterised in that: elastic device is fixed In main girder steel.
4. integral lifting construction of lift well job platform according to claim 1, it is characterised in that: support steel beam compression End is fixedly connected with elastic device, and projecting end is equipped with the idler wheel that can be rolled along elevator shaft.
5. integral lifting construction of lift well job platform according to any one of claim 1 to 4, it is characterised in that: Main girder steel is welded by two opposite channel steels of opening direction, and support steel beam is matched steel I-beam.
6. integral lifting construction of lift well job platform according to claim 5, it is characterised in that: the inner wall of main girder steel It is equipped with the first postive stop baffle, the web of support steel beam is equipped with the second postive stop baffle with the limit cooperation of the first postive stop baffle.
7. integral lifting construction of lift well job platform according to claim 1, it is characterised in that: support steel beam hangs It stretches end and is equipped with pull ring.
8. integral lifting construction of lift well job platform according to claim 1, it is characterised in that: support steel beam hangs It stretches end and spacer pin is connected with by wirerope, the length of spacer pin is greater than the end size of main girder steel, the projecting end of support steel beam It is additionally provided with pin hole compatible with spacer pin.
9. integral lifting construction of lift well job platform according to claim 8, it is characterised in that: main girder steel is by two The opposite channel steel of opening direction is welded, and support steel beam is matched steel I-beam, and pin hole is located at steel I-beam On top plate and bottom plate.
10. integral lifting construction of lift well job platform according to claim 1, it is characterised in that: on main girder steel also Equipped with hanging liter pull ring and positioning column.
CN201821590792.2U 2018-09-28 2018-09-28 A kind of integral lifting construction of lift well job platform Expired - Fee Related CN208858135U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821590792.2U CN208858135U (en) 2018-09-28 2018-09-28 A kind of integral lifting construction of lift well job platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821590792.2U CN208858135U (en) 2018-09-28 2018-09-28 A kind of integral lifting construction of lift well job platform

Publications (1)

Publication Number Publication Date
CN208858135U true CN208858135U (en) 2019-05-14

Family

ID=66419703

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821590792.2U Expired - Fee Related CN208858135U (en) 2018-09-28 2018-09-28 A kind of integral lifting construction of lift well job platform

Country Status (1)

Country Link
CN (1) CN208858135U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111962909A (en) * 2020-10-21 2020-11-20 上海建工五建集团有限公司 Slidable supporting system suitable for vertical narrow space
CN114837396A (en) * 2022-05-12 2022-08-02 中国建筑第二工程局有限公司 Telescopic operation platform for light production well and construction method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111962909A (en) * 2020-10-21 2020-11-20 上海建工五建集团有限公司 Slidable supporting system suitable for vertical narrow space
CN114837396A (en) * 2022-05-12 2022-08-02 中国建筑第二工程局有限公司 Telescopic operation platform for light production well and construction method thereof

Similar Documents

Publication Publication Date Title
CN208858135U (en) A kind of integral lifting construction of lift well job platform
CN106348188A (en) Method for manufacturing gantry type building construction lifting device
CN207129872U (en) A kind of hanging lifting device of surface structures steel pipe
CN205773024U (en) A kind of convenient pipeline lifting auxiliary device
CN210313314U (en) Hoisting device for construction
CN203794533U (en) Light portable mobile lifting equipment
CN201786010U (en) Elevating platform for construction use
CN203462736U (en) Operating platform for lift shaft structural steel construction
CN208732486U (en) Roofing monorail crane
CN204299157U (en) The mounted lifting device in attached lifting scaffold side
CN208732495U (en) A kind of small gun carriage
CN206799012U (en) A kind of concrete batten transport of small space and installation tool group
CN206957175U (en) A kind of planar dimension and adjustable for height operating platform
CN206475294U (en) A kind of efficient safety-type tensioning baffle plate
CN202718380U (en) Hydraulic climbing frame for construction of high-rise building
CN211257761U (en) Lifting type elevator shaft operating platform
CN211257773U (en) Door type integral lifting steel platform
CN207774676U (en) A kind of storage tank installation lifting means
CN203654707U (en) Detachable gantry installation frame
CN208981355U (en) A kind of packaged type scaffold
CN209567730U (en) A kind of small-sized lattice dead man steel construction
CN209493262U (en) Construction site stone material handling apparatus
CN202990392U (en) Steel tube guide rail and multifunctional ring rail combined mechanism for overall lifting scaffold
CN207774680U (en) A kind of portable mechanism jacking apparatus
CN205894641U (en) Elevartor shaft lifting platform

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190514

Termination date: 20210928