CN208797546U - A kind of cable trough - Google Patents
A kind of cable trough Download PDFInfo
- Publication number
- CN208797546U CN208797546U CN201821017428.7U CN201821017428U CN208797546U CN 208797546 U CN208797546 U CN 208797546U CN 201821017428 U CN201821017428 U CN 201821017428U CN 208797546 U CN208797546 U CN 208797546U
- Authority
- CN
- China
- Prior art keywords
- cable trough
- bracket
- cable
- ontology
- drain hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Laying Of Electric Cables Or Lines Outside (AREA)
Abstract
The utility model discloses a kind of cable troughs, the cable trough ontology including cable trough bracket and above the cable trough bracket.The utility model has the following beneficial effects: the step of eliminating excavation pit, reduces workload, and it ensure that the integrality of bedding;Width of the subgrade surface is reduced, project cost is reduced;It avoids moisture from entering within bedding by the gap between cable trough and foundation pit, causes to rise soil, the subgrade defects such as frost heave;Later maintenance, replacement are convenient, without excavating again, disturbing bedding.
Description
Technical field
The utility model relates to railway bed adjunct technical fields, and in particular to a kind of cable trough.
Background technique
Cable trough is the laying channel of signal cable and power cable in rail track, plays the role of protecting cable.Mesh
Before, cable trough is generally layed in road shoulder position, and is embedded in surface layer of subgrade bed, and cable trough upper opening is held with surface layer of subgrade bed upper surface
It is flat.It carries out cable trough installation exercise again after the completion of roadbed main body construction, when construction, compares cable trough in design position excavation first
Slightly larger groove, and base treatment is carried out to groove, then prefabricated cable trough is installed in groove and is adjusted to design
Position, finally sealing materials such as gap fill concrete between cable trough both sides and roadbed.
In existing design, cable trough is set in surface layer of subgrade bed, increases width of the subgrade surface and project amount, improves engineering
Cost.Cable trench is excavated again after the completion of roadbed filling, certain disturbance is caused to roadbed, destroys roadbed globality,
Gap after backfill between cable trough and roadbed is the weak link easily to seep water, and top moisture penetrates into cable trench bottom and such as can not
It excludes in time, will penetrate into roadbed and cause a series of subgrade defects, seriously affect roadbed working condition, and then influence column
Vehicle operation security, even if being laid with one layer of sand bedding course or blotter as drainage blanket in cable trench bottom, moisture also can not be complete
It is discharged outside bedding.
In order to reduce width of the subgrade surface, project cost is reduced, is avoided because excavating the weak infiltration formed after cable trough foundation pit
Position, the utility model provide a kind of novel railway cable trough structure type.Novel cable slot occupies less or even is not take up road
Base width does not excavate the roadbed for filling completion, avoids a series of diseases caused by moisture intrusion, has reduction road bed wide
Degree reduces Engineering Task amount, does not destroy roadbed globality, reduces the advantages that project cost, can be used in the roadbeds such as high-speed railway.
Utility model content
It is layed in road shoulder position to solve cable trough in the prior art, and is embedded in surface layer of subgrade bed, roadbed is increased
Face width and project amount, improve project cost;Cable trench is excavated again after the completion of roadbed filling, and roadbed is caused centainly
Disturbance, destroy roadbed globality, top moisture penetrates into cable trench bottom and can not such as exclude in time, causes a series of roadbeds
Disease seriously affects roadbed working condition, and then influences technical problems, the utility model such as train operation safety and provide a kind of electricity
Cable slot, is able to solve above-mentioned technical problem, has and reduces width of the subgrade surface, reduce project amount, reduce project cost, do not destroy road
Base integrality, the advantages that avoiding top moisture from entering bedding.
To achieve the above object, the technical solution adopted in the utility model are as follows:
A kind of cable trough, the cable trough ontology including cable trough bracket and above the cable trough bracket.
The cable trough includes cable trough bracket and the cable trough ontology above the cable trough bracket.So that described
Cable trough ontology is set to above the surface layer of subgrade bed, is reduced width of the subgrade surface and project amount, is reduced project cost.In roadbed
When filling certain elevation, after the completion of burying cable trough bracket or roadbed integral construction, then embedded cable trough bracket.It will not
Roadbed is caused to disturb, roadbed globality will not be destroyed, it is not easy to seep water.
Preferably, cover board is equipped with above the cable trough ontology.The design of the cover board can be convenient the inspection of later period cable
It repairs.
Preferably, the cable trough body bottom portion is provided with drain hole.
Preferably, position corresponding with the drain hole is equipped with drainage tube below the cable trough ontology.
After water leaking-in in cable trough ontology, it can be discharged by the drain hole of bottom, and then drained by drainage tube
The positions such as skeleton slope protection avoid water from directly being flowed down by the drain hole on cable trough ontology and wash out surface layer of subgrade bed.
Preferably, pan arrest is equipped between the cable trough ontology and the cable trough bracket.
Preferably, position corresponding with the drain hole is provided with through-hole on the pan arrest.
Preferably, the through-hole that the drainage tube top passes through on the pan arrest is connected with the drain hole.
The utility model has the following beneficial effects: the step of eliminating excavation pit, reduces workload, bedding ensure that
Integrality.Width of the subgrade surface is reduced, project cost is reduced.Moisture is avoided to enter by the gap between cable trough and foundation pit
It within bedding, causes to rise soil, the subgrade defects such as frost heave.Later maintenance, replacement are convenient, without excavating again, disturbing bedding.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the cable trough of the utility model first embodiment;
Fig. 2 is the structural schematic diagram of the cable trough of the utility model second embodiment;
Fig. 3 is the structural schematic diagram of the cable trough of the utility model 3rd embodiment.
In figure,
1- cable trough ontology;11- drain hole;2- drainage tube;3- cable trough bracket;31- cable trough stent strut;4- contact
Net pillar;5- cover board;6- pan arrest;61- through-hole;7- surface layer of subgrade bed.
Specific embodiment
Explanation is explained in detail to the structure of the utility model with reference to the accompanying drawing.
As shown in Figure 1, a kind of cable trough that the utility model first embodiment provides, including cable trough bracket 3 and be set to
The cable trough ontology 1 of 3 top of cable trough bracket.Cover board 5 is equipped with above the cable trough ontology 1.The cable trough ontology 1
And its cover board 5 is prefabricated by pre-fabricated factory according to design requirement, when prefabricated, the length of each cable trough ontology 1 can be according to practical feelings
Condition flexibly determines, can also be cast-in-place.The cable trough bracket 3 can be prefabricated also cast-in-place, one or more settable cable trough bracket
Pillar 31,31 arrangement form of cable trough stent strut are unrestricted;When roadbed filling is to certain elevation, bury described
After the completion of cable trough bracket 3 or roadbed integral construction, then bury the cable trough bracket 3.
A kind of cable trough that the utility model first embodiment provides, 1 bottom of cable trough ontology is provided with drain hole
11.Position corresponding with the drain hole 11 is equipped with drainage tube 2 below the cable trough ontology 1, and the drainage tube 2 is using resistance to
The long good flexible or rigid material of property is made, and connect with the drain hole 11 on the cable trough ontology 1, by the cable trough ontology
Water in 1 drains into the positions such as skeleton slope protection, avoids water from directly being flowed down by the drain hole 11 of cable trough ontology 1 and washes out surface layer of subgrade bed
7.The cable trough ontology 1 can also be discharged by other relevant ways in water.The cable trough ontology 1 and the cable trough bracket
It is equipped with pan arrest 6 between 3, is fixed between the cable trough bracket 3 and the pan arrest 6 by cement mortar or other binding materials.
Position corresponding with the drain hole 11 is provided with through-hole 61 on the pan arrest 6.2 top of drainage tube passes through the pan arrest 6
On through-hole 61 be connected with the drain hole 11.
A kind of cable trough that the utility model first embodiment provides, the cable trough bracket 3 are set up at road shoulder, are had
Body process of deployment is as follows:
1. when roadbed filling to 3 end designed elevation of cable trough bracket, cable trough bracket 3 being buried at road shoulder, is then pressed
Continue according to construction plan filling roadbed.
2. after the completion of roadbed filling, cable trough ontology 1 to be placed in the card slot pallet 6 on 3 top of cable trough bracket
In, it is installed in place.
3. installing drainage tube 2, the outlet of drainage tube 2 is fixed at skeleton slope protection drainage channel.
As shown in Fig. 2, a kind of cable trough that the utility model second embodiment provides, including cable trough bracket 3 and be set to
The cable trough ontology 1 of 3 top of cable trough bracket.Cover board 5 is equipped with above the cable trough ontology 1.The cable trough ontology 1
And its cover board 5 is prefabricated by pre-fabricated factory according to design requirement, when prefabricated, the length of each cable trough ontology 1 can be according to practical feelings
Condition flexibly determines, can also be cast-in-place.The cable trough bracket 3 can be prefabricated also cast-in-place, one or more settable cable trough bracket
Pillar 31,31 arrangement form of cable trough stent strut are unrestricted;When roadbed filling is to certain elevation, bury described
After the completion of cable trough bracket 3 or roadbed integral construction, then bury the cable trough bracket 3.
A kind of cable trough that the utility model second embodiment provides, 1 bottom of cable trough ontology is provided with drain hole
11.Position corresponding with the drain hole 11 is equipped with drainage tube 2 below the cable trough ontology 1, and the drainage tube 2 is using resistance to
The long good flexible or rigid material of property is made, and connect with the drain hole 11 on the cable trough ontology 1, by the cable trough ontology
Water in 1 drains into the positions such as skeleton slope protection, avoids water from directly being flowed down by the drain hole 11 of cable trough ontology 1 and washes out surface layer of subgrade bed
7.The cable trough ontology 1 can also be discharged by other relevant ways in water.The cable trough ontology 1 and the cable trough bracket
It is equipped with pan arrest 6 between 3, is fixed between the cable trough bracket 3 and the pan arrest 6 by cement mortar or other binding materials.
Position corresponding with the drain hole 11 is provided with through-hole 61 on the pan arrest 6.2 top of drainage tube passes through the pan arrest 6
On through-hole 61 be connected with the drain hole 11.
A kind of cable trough that the utility model second embodiment provides, the cable trough bracket 3 are set up in road shoulder and side slope
Intersection, specific process of deployment are as follows:
1. when roadbed filling to 3 end designed elevation of cable trough bracket, burying cable trough branch in side slope and road shoulder junction
Frame 3 makes a catenary mast 4 of cable trough bracket 3 on road shoulder, another is located in side slope, then according to construction plan
Continue filling roadbed.
2. after the completion of roadbed filling, cable trough ontology 1 being placed in the pallet 6 of frame upper, is installed in place.
3. installing drainage tube 2, the outlet of drainage tube 2 is fixed at skeleton slope protection drainage channel.
As shown in figure 3, a kind of cable trough that the utility model 3rd embodiment provides, including cable trough bracket 3 and be set to
The cable trough ontology 1 of 3 top of cable trough bracket.Cover board 5 is equipped with above the cable trough ontology 1.The cable trough ontology 1
And its cover board 5 is prefabricated by pre-fabricated factory according to design requirement, when prefabricated, the length of each cable trough ontology 1 can be according to practical feelings
Condition flexibly determines, can also be cast-in-place.The cable trough bracket 3 can be prefabricated also cast-in-place, one or more settable cable trough bracket
Pillar 31,31 arrangement form of cable trough stent strut are unrestricted;When roadbed filling is to certain elevation, bury described
After the completion of cable trough bracket 3 or roadbed integral construction, then bury the cable trough bracket 3.
A kind of cable trough that the utility model 3rd embodiment provides, 1 bottom of cable trough ontology is provided with drain hole
11.Position corresponding with the drain hole 11 is equipped with drainage tube 2 below the cable trough ontology 1, and the drainage tube 2 is using resistance to
The long good flexible or rigid material of property is made, and connect with the drain hole 11 on the cable trough ontology 1, by the cable trough ontology
Water in 1 drains into the positions such as skeleton slope protection, avoids water from directly being flowed down by the drain hole 11 of cable trough ontology 1 and washes out surface layer of subgrade bed
7.The cable trough ontology 1 can also be discharged by other relevant ways in water.The cable trough ontology 1 and the cable trough bracket
It is equipped with pan arrest 6 between 3, is fixed between the cable trough bracket 3 and the pan arrest 6 by cement mortar or other binding materials.
Position corresponding with the drain hole 11 is provided with through-hole 61 on the pan arrest 6.2 top of drainage tube passes through the pan arrest 6
On through-hole 61 be connected with the drain hole 11.
A kind of cable trough that the utility model 3rd embodiment provides, the cable trough bracket 3 are set up at side slope, are had
Body process of deployment is as follows:
1. when roadbed filling to 3 end designed elevation of cable trough bracket, bury cable trough bracket 3 in side slope, then according to
Construction plan continues filling roadbed.
2. after the completion of roadbed filling, cable trough ontology 1 being placed in the pallet 6 of frame upper, is installed in place.
3. installing drainage tube 2, the outlet of drainage tube 2 is fixed at skeleton slope protection drainage channel.
The above is only the preferred embodiments of the present utility model only, is not intended to limit the utility model, all practical at this
Made any modification, equivalent replacement and simple modifications etc., should be included in the protection of the utility model in novel substantive content
Within the scope of.
Claims (7)
1. a kind of cable trough, which is characterized in that including the cable trough bracket (3) being arranged on railway bed and be set to the cable
Cable trough ontology (1) above slot bracket (3), the cable trough bracket (3) are used for cable trough ontology (1) frame from railway
Roadbed setting height, the cable trough bracket (3) are located at the side of catenary mast (4).
2. cable trough according to claim 1, which is characterized in that be equipped with cover board (5) above the cable trough ontology (1).
3. cable trough according to claim 1, which is characterized in that cable trough ontology (1) bottom is provided with drain hole
(11)。
4. cable trough according to claim 3, which is characterized in that cable trough ontology (1) lower section and the drain hole
(11) corresponding position is equipped with drainage tube (2).
5. cable trough according to claim 4, which is characterized in that the cable trough ontology (1) and the cable trough bracket
(3) pan arrest (6) are equipped between.
6. cable trough according to claim 5, which is characterized in that opposite with the drain hole (11) on the pan arrest (6)
The position answered is provided with through-hole (61).
7. cable trough according to claim 6, which is characterized in that drainage tube (2) top passes through on the pan arrest (6)
Through-hole (61) be connected with the drain hole (11).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821017428.7U CN208797546U (en) | 2018-06-28 | 2018-06-28 | A kind of cable trough |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821017428.7U CN208797546U (en) | 2018-06-28 | 2018-06-28 | A kind of cable trough |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208797546U true CN208797546U (en) | 2019-04-26 |
Family
ID=66201679
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821017428.7U Active CN208797546U (en) | 2018-06-28 | 2018-06-28 | A kind of cable trough |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208797546U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110350464A (en) * | 2019-06-19 | 2019-10-18 | 中国铁道科学研究院集团有限公司铁道建筑研究所 | A method of laying cable trough on roadbed |
CN110364958A (en) * | 2019-06-19 | 2019-10-22 | 中国铁道科学研究院集团有限公司铁道建筑研究所 | A method of laying cable trough on roadbed |
-
2018
- 2018-06-28 CN CN201821017428.7U patent/CN208797546U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110350464A (en) * | 2019-06-19 | 2019-10-18 | 中国铁道科学研究院集团有限公司铁道建筑研究所 | A method of laying cable trough on roadbed |
CN110364958A (en) * | 2019-06-19 | 2019-10-22 | 中国铁道科学研究院集团有限公司铁道建筑研究所 | A method of laying cable trough on roadbed |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105863671B (en) | Frame-type subdrain system tunnel lining structure | |
CN104695289B (en) | A kind of put line construction for middle the low of low speed magnetic suspension traffic engineering embankment location | |
CN105927272A (en) | Floor anchoring constraint tunnel lining structure | |
CN203188065U (en) | Ballastless track railway expansion soil cutting bedding and slope protection structure | |
CN201835198U (en) | Drainage roadbed for high underground water level | |
CN106437748A (en) | Separated maintainable tunnel lining structure | |
CN105256876A (en) | Siphon type draining system of superhigh excavation section of road | |
CN103147614B (en) | Pool with multi-layer structure and building method thereof | |
CN203546514U (en) | Totally enclosed drainage prevention foundation bed structure of railway expansive soil cutting | |
CN208797546U (en) | A kind of cable trough | |
WO2016138776A1 (en) | Lowly disposed line structure used in medium-low speed magnetic levitation traffic engineering fill section | |
CN204455725U (en) | A kind ofly put line construction for middle the low of low speed magnetic suspension traffic engineering embankment location | |
CN108560586A (en) | Half prefabricated assembled pipe gallery and its construction method | |
CN101914882B (en) | Low embankment structure in phreatic high slity soil region and construction method thereof | |
CN210262555U (en) | Light soil road structure | |
CN206016853U (en) | Base plate anchors restricted type tunnel lining structure | |
CN101148886B (en) | Drainage treatment structure for unbuilt or abuilding landfill slope underground water | |
CN108222060A (en) | High-speed railway, highway pile foundation joist buttress type pallet subgrade support retainer structure | |
CN105089072A (en) | Anti-seepage structure of basement bottom board and construction method | |
CN205134481U (en) | Highway superelevation excavation highway section hydrocone type drainage system | |
CN206016821U (en) | Frame-type subdrain system tunnel lining structure | |
CN204940338U (en) | A kind of leakage preventing structure of basement bottom board | |
CN111809470A (en) | Structure and method for preventing cracks of road base layer and road subbase layer | |
CN205662802U (en) | Gutter and french drain integration drainage system | |
CN215055647U (en) | Cover drainage system that covers on vehicle |