CN208792158U - A kind of Double Column Piers curing means - Google Patents
A kind of Double Column Piers curing means Download PDFInfo
- Publication number
- CN208792158U CN208792158U CN201820999975.3U CN201820999975U CN208792158U CN 208792158 U CN208792158 U CN 208792158U CN 201820999975 U CN201820999975 U CN 201820999975U CN 208792158 U CN208792158 U CN 208792158U
- Authority
- CN
- China
- Prior art keywords
- sheave
- lantern ring
- double column
- pillar
- column piers
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Abstract
A kind of Double Column Piers curing means, including twin drum winch, two groups of spraying racks and two groups of support frames, spraying rack housing is outside Double Column Piers pillar, support frame is arranged on Double Column Piers pillar top, two groups of spraying racks pass through more connecting rod connections, two groups of support frames are equipped with two assembly guidances, two wirerope are connect with two groups of spraying racks respectively after bypassing two assembly guidances on twin drum winch by two hanging beam connections on two hanging beams;The utility model is high low with operating efficiency for solving the problems, such as existing Double Column Piers spray maintenance large labor intensity, security risk.
Description
Technical field
The utility model relates to a kind of Double Column Piers curing means.
Background technique
Double Column Piers are made of two pillars and a bent cap being mounted on two pillars, pour completion in pillar
Afterwards, it needs to spray pillar and conserve, artificial wet curing is generallyd use to the maintenance process of two pillars at present, but with road and bridge
The extension of construction scale has been unable to meet demand using artificial wet curing method, is also easy to appear omission maintenance phenomenon, makes
Bridge pier pier shaft cracks, and generates security risk, affects construction quality, reduce the service life of bridge pier;In addition artificial right
When pillar is sprayed water, since pillar is higher, worker is difficult on the ground by water slug to pillar top, therefore often has worker to stand
Post top portion sprays water to pillar upper end, and the safeguards such as typically no fence of post top portion, causes worker to exist and falls
Risk;In addition because Double Column Piers are tools there are two pillar, existing spray mode cannot simultaneously spray two pillars
Water, so spray is inefficient, labor intensity of workers is big.
Summary of the invention
The technical problem to be solved by the present invention is to provide a kind of Double Column Piers curing means, for solving existing twin columns
Bridge pier spray maintenance large labor intensity, the high problem low with operating efficiency of security risk.
In order to solve the above-mentioned technical problem, the technical solution of the utility model are as follows:
A kind of Double Column Piers curing means, including twin drum winch, two groups of spraying racks and two groups of support frames, spraying rack housing
Outside Double Column Piers pillar, support frame setting is connected in Double Column Piers pillar top, two groups of spraying racks by more connecting rods, and two groups
Support frame is equipped with two assembly guidances, two wirerope on twin drum winch by two hanging beam connections on two hanging beams
Around being connect respectively with two groups of spraying racks after two assembly guidances;
The spraying rack includes the circular ring shape spray tube sequentially coaxially arranged from top to bottom and multiple first lantern rings, spray tube
It is fixedly connected by more connection straps between each first lantern ring between the first lantern ring, is respectively mounted on the inside of each first lantern ring
There are multiple idler wheels, outside Double Column Piers pillar, each idler wheel one end is resisted against for circular ring shape spray tube and multiple equal housings of first lantern ring
In pillar outside wall surface, the injection direction of each nozzle is communicated in spray tube one end into water towards spray tube hub on spray tube
Pipe;
Support frame as described above includes the second lantern ring that an internal diameter is greater than Double Column Piers pillar outer diameter and an internal diameter less than double
The third lantern ring of column bridge pier outer diameter, third lantern ring are co-axially located above the second lantern ring, are led between the second lantern ring and third lantern ring
Excessive root gib block connection;
Guiding device includes the first sheave and the second sheave being mounted between two hanging beams, the first sheave and the second sheave
It is located in the middle part of hanging beam one end and hanging beam, wirerope one end is connect after bypassing the second sheave and the first sheave with spraying rack.
Guiding device further includes the third sheave and the 4th sheave being mounted between two hanging beams, and the setting of third sheave is the
One sheave side, the 4th sheave are arranged in the second sheave side, wirerope one end sequentially pass through the second sheave and the 4th sheave it
Between gap, connect with spraying rack behind the gap between third sheave and the first sheave.
Support frame as described above further includes the 4th lantern ring being arranged between the second lantern ring and third lantern ring, the 4th lantern ring surrounding with
Each is fixedly connected to gib block, and the 4th lantern ring outer diameter is equal to Double Column Piers pillar outer diameter.
Further include PLC controller and be mounted on each water inlet pipe solenoid, PLC controller control twin drum winch and
Solenoid valve.
The beneficial effects of the utility model are: during installation, truck crane can be used two groups of spraying racks and two groups of supports
Frame is installed on two pillars of bridge pier, is climbed on pillar and is installed without worker, and safety when installation is improved;The present apparatus can generation
For manually spray maintenance is carried out simultaneously to two pillars, while reducing the labor intensity of worker, safety when spray is improved
And reliability;Meanwhile, it is capable to carry out comprehensive spray to pillar, spraying effect is improved;On the other hand, PLC controller, energy are utilized
Spray time is enough adjusted, realizes the automatic spray to pillar, and then further increases spraying effect and reduces labor intensity of workers.
Detailed description of the invention
The utility model is described further with reference to the accompanying drawing:
Fig. 1 is the schematic view of the front view of the utility model,
Fig. 2 is the schematic diagram of the section structure of the utility model about spraying rack,
Fig. 3 is overlooking structure diagram of the utility model about spraying rack,
Fig. 4 is the schematic diagram of the section structure of the utility model about support frame,
Fig. 5 is overlooking structure diagram of the utility model about support frame,
Fig. 6 is the connection relationship diagram of each electrical part part in the utility model.
In figure: pillar 1, support frame 2, spraying rack 3, guiding device 4, hanging beam 5, connecting rod 6, twin drum winch 7, solenoid valve 8,
Second lantern ring 22, third lantern ring 23, the 4th lantern ring 24, gib block 25, the first lantern ring 31, spray tube 32, idler wheel 33, connection strap
34, water inlet pipe 35, the first sheave 41, the second sheave 42, third sheave 43, the 4th sheave 44, wirerope 71.
Specific embodiment
As shown in Fig. 1 to 5, a kind of Double Column Piers curing means, including 7, two groups of spraying racks 3 of twin drum winch and two groups of branch
Support 2, outside Double Column Piers pillar 1, support frame 2 is arranged in 1 top of Double Column Piers pillar, two groups of spraying racks 33 housing of spraying rack
It is connected by more connecting rods 6, two groups of support frames 2 are connected by two hanging beams 5, and two groups of guiding dresses are equipped on two hanging beams 5
4 are set, two wirerope 71 are connect with two groups of spraying racks 3 respectively after bypassing two assembly guidances 4 on twin drum winch 7;
The spraying rack 3 includes the circular ring shape spray tube 32 and multiple first lantern rings 31 sequentially coaxially arranged from top to bottom,
It is fixedly connected by more connection straps 34 between each first lantern ring 31 between spray tube 32 and the first lantern ring 31, each first
Multiple idler wheels 33 are mounted on the inside of lantern ring 31, each idler wheel 33 is uniformly distributed around 31 axis of the first lantern ring, circular ring shape spray
Outside Double Column Piers pillar 1, each 33 one end of idler wheel is resisted against in 1 outside wall surface of pillar for pipe 32 and the equal housing of multiple first lantern rings 31,
Spray tube 32 includes circulating line, multiple nozzles is equipped on circulating line, each nozzle is uniform around circulating line axis
It is distributed, the injection direction of each nozzle is communicated with water inlet pipe in 32 one end of spray tube towards 32 center of spray tube on spray tube 32
35, water inlet pipe 35 is connected to by hose with running water pipe, is not shown in hose figure;Wherein the effect of idler wheel 33 is: can
The position of spray tube 32 is limited, making each nozzle on spray tube 32 is equal, raising spray to the distance of 1 outside wall surface of pillar
In addition the uniformity of leaching also can prevent spray tube 32 from rubbing on pillar 1;
Support frame as described above 2 includes that an internal diameter is small greater than the second lantern ring 22 of 1 outer diameter of Double Column Piers pillar and an internal diameter
In the third lantern ring 23 of Double Column Piers outer diameter, third lantern ring 23 is co-axially located at the top of the second lantern ring 22, the second lantern ring 22 and the
It is connected between three lantern rings 23 by more gib blocks 25, is enclosed jointly by the second lantern ring 22, third lantern ring 23 and Ge Gen gib block 25
It closes a long up-thin-low-thick flared structure and utilizes branch when the support frame 2 of lid flared structure to be lifted on pillar 1
The guiding role of 2 flared structure of support can be convenient, support frame 2 is quickly placed to 1 top of pillar;
Guiding device 4 includes the first sheave 41 and the second sheave 42 being mounted between two hanging beams 5,41 He of the first sheave
Second sheave 42 is located at 5 middle part of 5 one end of hanging beam and hanging beam, and 71 one end of wirerope bypasses the second sheave 42 and the first sheave 41
It is connect afterwards with spraying rack 3.
The application method of the utility model are as follows:
The first step, steel wire rope of windlass 71 lengthen, and then two spraying racks 3 are set to Double Column Piers two by truck crane outside respectively
Outside root pillar 1, then slowly spraying rack 3 is put down;In lifting, rope, worker can be fastened respectively on two spraying racks 3
Two ropes are pulled to be finely adjusted the position of two spraying racks 3 on the ground, Double Column Piers branch will be set to by facilitating outside spraying rack 3
Outside column 1.
Two groups of support frames 2 are hung two 1 tops of pillar of Double Column Piers by second step, truck crane.
Third step, steel wire rope of windlass 71 are wound, and wirerope 71 is tightened.
Tap water is passed into spray tube 32 by the 4th step, and hoist engine winds wirerope 71 or unclasps wirerope 71, benefit
It pulls spraying rack 3 to move up and down with wirerope 71, spray tube 32 is allowed to spray two pillars 1.
Guiding device 4 further includes the third sheave 43 and the 4th sheave 44 being mounted between two hanging beams 5, third sheave 43
Setting is arranged in 41 side of the first sheave, the 4th sheave 44 in 42 side of the second sheave, and 71 one end of wirerope sequentially passes through second
It is connect behind the gap between gap, third sheave 43 and the first sheave 41 between sheave 42 and the 4th sheave 44 with spraying rack 3.
Third sheave 43 and the 4th sheave 44 can limit wirerope 71, when avoiding lifting support frame 2, wirerope 71 from first
Deviate from sheave 41 and the second sheave 42.
Support frame as described above 2 further includes the 4th lantern ring 24 being arranged between the second lantern ring 22 and third lantern ring 23, and the 4th set
24 surrounding of ring is fixedly connected with each to gib block 25, and 24 outer diameter of the 4th lantern ring is equal to 1 outer diameter of Double Column Piers pillar.When will support
After frame 2 is installed on 1 top of pillar, the 4th lantern ring 24 is shelved on 1 end face of pillar, is carried out by the 4th lantern ring 24 to support frame 2
Planar support improves the stability after support frame 2 is installed.
Further include PLC controller and be mounted on 35 solenoid 8 of each water inlet pipe, PLC controller controls twin drum winch
7 and solenoid valve 8.PLC controller is by the control of the opening and closing time to driving motor and solenoid valve 8, to realize timing, quantitative
Spray maintenance is carried out to pillar 1, reduces the labor intensity of worker.
The course of work of PLC control are as follows: worker manually controls twin drum winch 7 and spraying rack 3 is moved under pillar 1 first
End, then spraying rack 3 is drawn to 1 upper end of pillar again by twin drum winch 7, is recorded spraying rack 3 from 1 lower end of pillar and is moved to pillar
Time T, is then input in PLC controller by the time T of 1 upper end;Then worker is converted to PLC controller control bitubular elevator
Machine 7 and solenoid valve 8, when initial, for spraying rack 3 at 1 upper end of pillar, PLC controller control twin drum winch 7 puts spraying rack 3
Under, after time T, spraying rack 3 is moved to 1 lower end of pillar;The commutation of then PLC controller control twin drum winch 7 will spray
Frame 3 is promoted, and after time T, spraying rack 3 is moved to 1 upper end of pillar, and both every after time T, PLC controller just controls
Twin drum winch 7 commutates, and recycles repeatedly, realizes up and down reciprocatingly spraying automatically for automatic spray frame 3;Furthermore it is possible to utilize
Time module in PLC controller, setting spray interval time, timing, quantitative spray with realization to concrete pillar 1.
Claims (4)
1. a kind of Double Column Piers curing means, it is characterised in that: including twin drum winch (7), two groups of spraying racks (3) and two groups of branch
Support (2), spraying rack (3) housing Double Column Piers pillar (1) outside, support frame (2) setting on Double Column Piers pillar (1) top,
Two groups of spraying racks (3) are by more connecting rod (6) connections, and two groups of support frames (2) are by two hanging beam (5) connections, in two hanging beams
(5) it is equipped on two assembly guidances (4), after upper two wirerope (71) of twin drum winch (7) bypass two assembly guidances (4)
It is connect respectively with two groups of spraying racks (3);
The spraying rack (3) includes the circular ring shape spray tube (32) and multiple first lantern rings sequentially coaxially arranged from top to bottom
(31), fixed by more connection straps (34) between each first lantern ring (31) between spray tube (32) and the first lantern ring (31)
Connection is mounted on multiple idler wheels (33), circular ring shape spray tube (32) and multiple first lantern rings on the inside of each first lantern ring (31)
(31) housing Double Column Piers pillar (1) outside, each idler wheel (33) one end is resisted against in pillar (1) outside wall surface, spray tube (32)
The injection direction of upper each nozzle is communicated with water inlet pipe (35) in spray tube (32) one end towards spray tube (32) center;
Support frame as described above (2) includes the second lantern ring (22) and an internal diameter that an internal diameter is greater than Double Column Piers pillar (1) outer diameter
Less than the third lantern ring (23) of Double Column Piers outer diameter, third lantern ring (23) is co-axially located above the second lantern ring (22), and second set
It is connect between ring (22) and third lantern ring (23) by more gib blocks (25);
Guiding device (4) includes the first sheave (41) and the second sheave (42) being mounted between two hanging beams (5), the first sheave
(41) it is located in the middle part of hanging beam (5) one end and hanging beam (5) with the second sheave (42), wirerope (71) one end bypasses the second sheave
(42) it is connect afterwards with spraying rack (3) with the first sheave (41).
2. a kind of Double Column Piers curing means according to claim 1, it is characterised in that: guiding device (4) further includes peace
Third sheave (43) and the 4th sheave (44) between two hanging beams (5), third sheave (43) are arranged in the first sheave
(41) side, the 4th sheave (44) are arranged in the second sheave (42) side, and wirerope (71) one end sequentially passes through the second sheave
(42) behind the gap between the gap between the 4th sheave (44), third sheave (43) and the first sheave (41) with spraying rack
(3) it connects.
3. a kind of Double Column Piers curing means according to claim 1, it is characterised in that: support frame as described above (2) further includes
The 4th lantern ring (24) being arranged between the second lantern ring (22) and third lantern ring (23), the 4th lantern ring (24) surrounding is with each to leading
It is fixedly connected to item (25), the 4th lantern ring (24) outer diameter is equal to Double Column Piers pillar (1) outer diameter.
4. a kind of Double Column Piers curing means according to claim 1 or 2, it is characterised in that: further include PLC controller and
It is mounted on each water inlet pipe (35) solenoid (8), PLC controller controls twin drum winch (7) and solenoid valve (8).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820999975.3U CN208792158U (en) | 2018-06-27 | 2018-06-27 | A kind of Double Column Piers curing means |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820999975.3U CN208792158U (en) | 2018-06-27 | 2018-06-27 | A kind of Double Column Piers curing means |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208792158U true CN208792158U (en) | 2019-04-26 |
Family
ID=66201518
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820999975.3U Expired - Fee Related CN208792158U (en) | 2018-06-27 | 2018-06-27 | A kind of Double Column Piers curing means |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208792158U (en) |
-
2018
- 2018-06-27 CN CN201820999975.3U patent/CN208792158U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203654702U (en) | Operating platform for construction of reinforced concrete chimney | |
CN109881590A (en) | Bridge steel box girder high altitude operation operating platform and building method | |
CN211899582U (en) | Hanging flower basket device is used in construction of roof steel construction platform glass curtain wall | |
CN207277204U (en) | A kind of pier stud automatic spray curing means | |
CN208792158U (en) | A kind of Double Column Piers curing means | |
CN101818563B (en) | Jack-up integral lifting mobile platform and using method | |
CN110273039B (en) | Blast furnace surrounding pipe hoisting structure and installation method thereof | |
CN211171635U (en) | Automatic maintenance device for bridge pier column | |
CN209873572U (en) | Interim navigation lifting station of adjustable vertical lift height | |
CN111335172A (en) | Movable pier column cross beam prestress tensioning hanging frame construction platform and construction method | |
CN208981895U (en) | A kind of lifting set up for power transmission tower and the combined mechanism that climbs certainly | |
CN110130644A (en) | A kind of construction method of high-altitude steel structure bottom metal curtain wall | |
CN203486787U (en) | Integral lifting device for cabinet top of Wiggins coal gas cabinet | |
CN107010551B (en) | A kind of restricted clearance construction method for hanging | |
CN101318617A (en) | Hydraulic hoisting hanging apparatus with steering and horizontally moving functions | |
CN204508629U (en) | A kind of light type agricultural lifting appliance | |
CN204198306U (en) | A kind of device for purlin lifting in building operation | |
CN209816682U (en) | Bridge steel box girder aerial working operation platform | |
CN207522813U (en) | A kind of curing means of precast concrete decorative panel | |
CN106984474B (en) | Steel structural bridge beam bridge floor spray-painting plant and its construction method | |
CN206156638U (en) | Swing arm tower crane top ping lift prevents kinking device | |
CN110255331A (en) | A kind of building hoist testing stand | |
CN201857225U (en) | Hoisting device for bridge crane frame | |
CN220452389U (en) | Frock is dismantled to LNG unloading arm front and back drive hydraulic cylinder | |
CN210366676U (en) | Pipeline installation lifting machine |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190426 Termination date: 20190627 |
|
CF01 | Termination of patent right due to non-payment of annual fee |