Prior art keywords
frame
support frame
fixed pulley
wire rope
cantilever
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020450234.7U
Other languages
Chinese (zh)
Inventor
王龙刚
刘美虎
李江
王阿波
刘博涛
王玉玉
李军伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaanxi Construction Engineering Group Co Ltd
Original Assignee
Shaanxi Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shaanxi Construction Engineering Group Co Ltd filed Critical Shaanxi Construction Engineering Group Co Ltd
Priority to CN202020450234.7U priority Critical patent/CN211899582U/en
Application granted granted Critical
Publication of CN211899582U publication Critical patent/CN211899582U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Cultivation Receptacles Or Flower-Pots, Or Pots For Seedlings (AREA)

Abstract

The utility model discloses a hanging flower basket device is used in construction of roof steel structure platform glass curtain wall, including returning font frame, encorbelment the mechanism and with the hanging flower basket body that encorbelment the mechanism and be connected through work wire rope, the mechanism of encorbelmenting includes two supports of encorbelmenting of laying along the length direction of the length of side of returning font frame, the support of encorbelmenting includes the crossbeam of encorbelmenting, first support frame and second support frame, first support frame is located the one end of the crossbeam of encorbelmenting, the second support frame will encorbelment the crossbeam and split into linkage segment and cantilever section, first support frame is installed on the inner circle square frame who returns font frame, the second support frame is. The utility model discloses simple structure through setting up back font frame on roof steel structure platform top surface, plays the effect that supports the mechanism of encorbelmenting by back font frame to form the hanging flower basket device of no counter weight, after the hanging flower basket body is connected through work wire rope with the mechanism of encorbelmenting, can form complete and stable hanging flower basket device.

Description

Hanging flower basket device is used in construction of roof steel construction platform glass curtain wall
Technical Field
The utility model belongs to the technical field of the construction, concretely relates to hanging flower basket device is used in construction of roof steel construction platform glass curtain wall.
Background
The hanging basket is a construction machine for high-altitude operation in construction engineering, and is used for curtain wall installation and outer wall cleaning. The hanging basket is a novel high-altitude operation device which can replace a traditional scaffold, reduce labor intensity, improve working efficiency and be repeatedly used. The use of the construction hanging basket has gradually become a trend, and the construction hanging basket is widely accepted in high-rise and multi-storey high-rise building outer wall construction, curtain wall installation, heat preservation construction, maintenance and cleaning of outer walls and other high-rise operations, and can be used for the operation of large-scale tank bodies, bridges, dams and other projects. At present, roof steel structure platform's form is more and more, often appears because the particularity of roof steel structure platform engineering curtain, job site main part steel construction and curtain steelframe for the unable problem of adorning of conventional hanging flower basket suspension counter weight frame, consequently, should provide a hanging flower basket device that roof steel structure platform glass curtain wall construction used.
SUMMERY OF THE UTILITY MODEL
The utility model aims to solve the technical problem that not enough among the above-mentioned prior art is directed against, provide roof steel structure platform glass curtain wall construction with hanging flower basket device, its simple structure, reasonable in design, through set up back font frame on the roof steel structure platform top surface, play the effect that the mechanism was encorbelmented in the support by returning font frame to form the hanging flower basket device that does not have the counter weight, when the hanging flower basket body through work wire rope with after encorbelment the mechanism and be connected, can form complete and stable hanging flower basket device, construction convenience, convenient to popularize and apply.
In order to solve the technical problem, the utility model discloses a technical scheme is: the utility model provides a construction of roof steel construction platform glass curtain wall is with hanging flower basket device which characterized in that: comprises a square-back frame fixedly arranged on the top surface of a roof steel structure platform, an overhanging mechanism fixedly arranged on the square-back frame and a hanging basket body connected with the overhanging mechanism through a working steel wire rope, the cantilever mechanism comprises two cantilever brackets which are arranged along the length direction of the side length of the square-shaped frame, the cantilever support comprises a cantilever beam, a first support frame and a second support frame which are vertically arranged on the cantilever beam, the first support frame is positioned at one end of the cantilever beam, the second support frame divides the cantilever beam into a connecting section and a cantilever section, the top end of the second support frame is higher than the top end of the first support frame, the first support frame is arranged on the inner circle square frame of the square frame, the second support frame is arranged on the outer ring square frame, and the overhanging support and the hanging basket body are provided with a working steel wire rope fixed pulley block for winding the working steel wire rope.
Foretell roof steel structure platform hanging flower basket construction structures, its characterized in that: the working steel wire rope fixed pulley block comprises a first fixed pulley fixedly mounted at the top of the hanging basket body, a second fixed pulley mounted at the end part of the cantilever section, a third fixed pulley mounted at the top end of the second support frame and a fourth fixed pulley mounted at the top end of the first support frame.
Foretell roof steel structure platform hanging flower basket construction structures, its characterized in that: and a guide steel wire rope is arranged between the overhanging bracket and the hanging basket body, a guide rod is fixedly installed on the outer ring square frame, and a guide steel wire rope fixed pulley block for winding the guide steel wire rope is arranged on the hanging basket body, the guide rod and the overhanging bracket.
Foretell roof steel structure platform hanging flower basket construction structures, its characterized in that: the guide steel wire rope fixed pulley block comprises a fifth fixed pulley fixedly mounted on the hanging basket body, a sixth fixed pulley fixedly mounted at the end part of the guide rod and a seventh fixed pulley fixedly mounted at the end part of the cantilever section.
Foretell roof steel structure platform hanging flower basket construction structures, its characterized in that: the first support frame and the second support frame respectively comprise a horizontal rod and a vertical rod vertically installed on the horizontal rod, and the horizontal rod of the first support frame is fixedly connected with the inner ring square frame and the horizontal rod of the second support frame is fixedly connected with the outer ring square frame through U-shaped bolts.
Compared with the prior art, the utility model has the following advantage:
1. the utility model discloses a font frame is returned to fixed mounting on roof steel structure platform top surface, fixed mounting encorbelments the mechanism on returning the font frame, and be connected the hanging flower basket body through work wire rope with the mechanism of encorbelmenting, during the in-service use, the top surface when roof steel structure platform is special construction such as hollow out construction, cause the phenomenon that current hanging flower basket device can't erect easily, therefore, in order to guarantee the fixed connection of encorbelmenting mechanism and roof steel structure platform, need set up back font frame on roof steel structure platform top surface, play the effect that supports the mechanism of encorbelmenting by returning the font frame, thereby form the hanging flower basket device that does not have the counter weight, after the hanging flower basket body is connected with the mechanism of encorbelmenting through work wire rope, can form complete and stable hanging flower basket device, and.
2. The utility model discloses a mechanism of encorbelmenting includes the support of encorbelmenting that two length of side were laid along the length direction of returning font frame, the support of encorbelmenting is including encorbelmenting the crossbeam, first support frame and second support frame are all installed perpendicularly on the crossbeam of encorbelmenting, first support frame is located the one end of the crossbeam of encorbelmenting, the second support frame will encorbelment the crossbeam and split into linkage segment and cantilever section, during the actual installation, first support frame is installed on the inner circle square frame of returning font frame, the second support frame is installed on outer lane square frame, when installing work wire rope at the support of encorbelmenting, there is a safe distance in the cantilever section can make between the edge of work wire rope and roof steel structure platform, can avoid work wire rope and roof steel structure platform.
3. The utility model discloses a fixed mounting guide bar on outer lane square frame to at the sixth fixed pulley of tip fixed mounting of guide bar, the guide bar parallels with the crossbeam of encorbelmenting, utilize guide bar and sixth fixed pulley to lead and the tensioning to direction wire rope, utilize direction wire rope to make the hanging flower basket body constantly keep parallel with the construction face at the lift in-process, the hanging flower basket body removes under direction wire rope and the common effect of work wire rope, the operating personnel of being convenient for stands at the internal construction that carries out glass curtain of hanging flower basket.
4. The utility model has the advantages of simple structure and reasonable design, low in manufacturing cost, facilitate promotion is used.
To sum up, the utility model has the advantages of simple structure and reasonable design, through setting up back font frame on roof steel structure platform top surface, play the effect that supports the mechanism of encorbelmenting by back font frame to form the hanging flower basket device of no counter weight, after the hanging flower basket body is connected with the mechanism of encorbelmenting through work wire rope, can form complete and stable hanging flower basket device, construction convenience, facilitate promotion is used.
The present invention will be described in further detail with reference to the accompanying drawings and examples.
Drawings
Fig. 1 is a schematic structural diagram of the present invention.
Fig. 2 is an enlarged view of fig. 1 at a.
Description of reference numerals:
1-hanging basket body; 2-1-inner circle square frame; 2-outer ring square frame;
3, working steel wire ropes; 4, overhanging the bracket; 4-1-linking segment;
4-1-cantilever section; 4-2 — a first support frame; 4-3-a first support frame;
5-1-a first fixed pulley; 5-2 — a second fixed pulley; 5-3-third fixed pulley;
5-4-fourth fixed pulley; 6, guiding a steel wire rope; 7, a guide rod;
8-1-fifth fixed pulley; 8-2-sixth fixed pulley; 8-3-seventh fixed pulley;
9-U type bolt.
Detailed Description
As shown in fig. 1 and 2, the utility model comprises a frame shaped like a Chinese character 'hui' fixedly installed on the top surface of a roof steel structure platform, an overhanging mechanism fixedly installed on the frame shaped like a Chinese character 'hui' and a hanging basket body 1 connected with the overhanging mechanism through a working steel wire 3, wherein the overhanging mechanism comprises two overhanging brackets 4 arranged along the length direction of the side length of the frame shaped like a Chinese character 'hui', the overhanging brackets 4 comprise an overhanging beam, a first bracket 4-2 and a second bracket 4-3 vertically installed on the overhanging beam, the first bracket 4-2 is positioned at one end of the overhanging beam, the overhanging beam is divided into a connecting section 4-1-1 and an overhanging section 4-1-2 by the second bracket 4-3, the top end of the second bracket 4-3 is higher than the top end of the first bracket 4-2, the first support frame 4-2 is arranged on an inner ring square frame 2-1 of the square frame, the second support frame 4-3 is arranged on an outer ring square frame 2-2, and the overhanging support 4 and the hanging basket body 1 are provided with a working steel wire rope fixed pulley block for winding the working steel wire rope 3.
In this embodiment, through the font frame of returning of fixed mounting on roof steel structure platform top surface the mechanism of encorbelmenting of fixed mounting on the font frame to with the hanging flower basket body 1 through work wire rope 3 with the mechanism of encorbelmenting is connected, during the in-service use, when the top surface of roof steel structure platform is special construction such as hollow out construction, causes the unable phenomenon of erectting of current hanging flower basket device easily, consequently, in order to guarantee the fixed connection of the mechanism of encorbelmenting and roof steel structure platform, need set up font frame back on the roof steel structure platform top surface, play the effect of supporting the mechanism of encorbelmenting by font frame back to form the hanging flower basket device of no counter weight, after hanging flower basket body 1 through work wire rope 3 with the mechanism of encorbelmenting is connected, can form complete and stable hanging flower basket device, and construction convenience, convenient to.
In this embodiment, the cantilever mechanism includes two cantilever brackets 4 arranged along the length direction of the side length of the square frame, the cantilever brackets 4 include a cantilever beam, a first bracket 4-2 and a second bracket 4-3, the first bracket 4-2 and the second bracket 4-3 are both vertically installed on the cantilever beam, the first bracket 4-2 is located at one end of the cantilever beam, the cantilever beam is divided into a connecting section 4-1-1 and a cantilever section 4-1-2 by the second bracket 4-3, during actual installation, the first bracket 4-2 is installed on an inner ring square frame 2-1 of the square frame, the second bracket 4-3 is installed on an outer ring square frame 2-2, and the top end of the second bracket 4-3 is higher than the top end of the first bracket 4-2, therefore, when the working steel wire rope 3 is installed on the cantilever support 4, the cantilever section 4-1-2 enables a safe distance to exist between the working steel wire rope 3 and the edge of the roof steel structure platform, the working steel wire rope 3 can be prevented from rubbing against the edge of the roof steel structure platform, and the cantilever type steel wire rope lifting device is simple in structure and good in stability.
As shown in fig. 1 and 2, in this embodiment, the working cable fixed pulley set includes a first fixed pulley 5-1 fixedly mounted on the top of the basket body 1, a second fixed pulley 5-2 mounted on the end of the cantilever section 4-1-2, a third fixed pulley 5-3 mounted on the top of the second support frame 4-3, and a fourth fixed pulley 5-4 mounted on the top of the first support frame 4-2.
In this embodiment, the working steel wire rope 3 can move the hanging basket body 1 to the construction surface of the glass curtain wall through the chain block under the common guiding action of the first fixed pulley 5-1, the second fixed pulley 5-2, the third fixed pulley 5-3 and the fourth fixed pulley 5-4, so that an operator can stand in the hanging basket body 1 to construct the glass curtain wall, and the construction safety is high and the operation is convenient.
In this embodiment, a guide steel wire rope 6 is arranged between the overhanging bracket 4 and the hanging basket body 1, a guide rod 7 is fixedly installed on the outer ring square frame 2-2, and a guide steel wire rope fixed pulley block for winding the guide steel wire rope 6 is arranged on the hanging basket body 1, the guide rod 7 and the overhanging bracket 4.
As shown in fig. 1 and 2, in this embodiment, the guide wire rope fixed pulley set comprises a fifth fixed pulley 8-1 fixedly mounted on the basket body 1, a sixth fixed pulley 8-2 fixedly mounted on the end of the guide rod 7, and a seventh fixed pulley 8-3 fixedly mounted on the end of the cantilever segment 4-1-2.
In the embodiment, the guide rod 7 is fixedly installed on the outer ring square frame 2-2, the sixth fixed pulley 8-2 is fixedly installed at the end of the guide rod 7, the guide rod 7 is parallel to the cantilever beam, the guide rod 7 and the sixth fixed pulley 8-2 can be used for guiding and tensioning the guide steel wire rope 6, in practical use, the guide steel wire rope 6 is a steel wire rope with the diameter of 22mm, the guide steel wire rope 6 can enable the hanging basket body 1 to be parallel to a glass curtain wall construction surface constantly in the lifting process, and the hanging basket body 1 moves under the common action of the guide steel wire rope 6 and the working steel wire rope 3, so that an operator can conveniently stand in the hanging basket body 1 to construct the glass curtain wall.
In this embodiment, the first support frame 4-2 and the second support frame 4-3 both include a horizontal rod and a vertical rod vertically installed on the horizontal rod, and the horizontal rod of the first support frame 4-2 and the inner ring square frame 2-1, and the horizontal rod of the second support frame 4-3 and the outer ring square frame 2-2 are fixedly connected by U-shaped bolts 9.
In this embodiment, the second support frame 4-3 further includes two diagonal braces symmetrically disposed between the horizontal bar and the vertical bar, and during actual use, since the top end of the second support frame 4-3 is higher than the top end of the first support frame 4-2, that is, the height of the vertical bar of the second support frame 4-3 is greater than the height of the vertical bar of the first support frame 4-2, the stability of the second support frame 4-3 can be improved by disposing the two diagonal braces.
When the roof steel structure platform is actually used, firstly, after the roof steel structure platform is constructed, an inner ring square frame 2-1 and an outer ring square frame 2-2 are respectively and fixedly installed on the top surface of the roof steel structure platform, and the inner ring square frame 2-1 and the outer ring square frame 2-2 form a frame shaped like a Chinese character 'hui'; secondly, a plurality of supports 4 of encorbelmenting of fixed mounting in proper order on returning font frame, wherein every support 4 of encorbelmenting mounting means homogeneous phase is the same, and specific mounting means is: fixedly connecting the first support frame 4-2 with the inner ring square frame 2-1 and the second support frame 4-3 with the outer ring square frame 2-2 through U-shaped bolts 9; then, a working steel wire rope 3 is installed on the cantilever support 4, and the working steel wire rope 3 is wound on a working steel wire rope fixed pulley block; then, hoisting the hanging basket body 1, and fixedly connecting the hanging basket body 1 with a working steel wire rope 3; and finally, a guide steel wire rope 6 is arranged between the cantilever support 4 and the hanging basket body 1, so that the connection between the hanging basket body 1 and the cantilever support 4 is completed, and the whole construction structure is simple, high in construction safety and convenient to popularize and apply.
The above, only be the utility model discloses a preferred embodiment, it is not right the utility model discloses do any restriction, all according to the utility model discloses the technical entity all still belongs to any simple modification, change and the equivalent structure change of doing above embodiment the utility model discloses technical scheme's within the scope of protection.

Claims (5)

1. The utility model provides a construction of roof steel construction platform glass curtain wall is with hanging flower basket device which characterized in that: the cantilever type steel structure platform comprises a rectangular frame fixedly arranged on the top surface of a roof steel structure platform, a cantilever mechanism fixedly arranged on the rectangular frame and a hanging basket body (1) connected with the cantilever mechanism through a working steel wire rope (3), wherein the cantilever mechanism comprises two cantilever supports (4) arranged along the length direction of the side length of the rectangular frame, each cantilever support (4) comprises a cantilever beam, a first support frame (4-2) and a second support frame (4-3) which are vertically arranged on the cantilever beam, the first support frame (4-2) is positioned at one end of the cantilever beam, the second support frame (4-3) divides the cantilever beam into a connecting section (4-1-1) and a cantilever section (4-1-2), and the top end of the second support frame (4-3) is higher than the top end of the first support frame (4-2), the first support frame (4-2) is installed on an inner ring square frame (2-1) of the square frame in the shape of a Chinese character 'hui', the second support frame (4-3) is installed on an outer ring square frame (2-2), and a working steel wire rope fixed pulley block for winding the working steel wire rope (3) is arranged on the cantilever support (4) and the hanging basket body (1).
2. The hanging basket device for construction of the glass curtain wall of the roof steel structure platform as claimed in claim 1, wherein: the working steel wire rope fixed pulley group comprises a first fixed pulley (5-1) fixedly mounted at the top of the hanging basket body (1), a second fixed pulley (5-2) mounted at the end part of the cantilever section (4-1-2), a third fixed pulley (5-3) mounted at the top end of the second supporting frame (4-3) and a fourth fixed pulley (5-4) mounted at the top end of the first supporting frame (4-2).
3. The hanging basket device for construction of the glass curtain wall of the roof steel structure platform as claimed in claim 1, wherein: a guide steel wire rope (6) is arranged between the overhanging support (4) and the hanging basket body (1), a guide rod (7) is fixedly mounted on the outer ring square frame (2-2), and a guide steel wire rope fixed pulley block for winding the guide steel wire rope (6) is arranged on the hanging basket body (1), the guide rod (7) and the overhanging support (4).
4. The hanging basket device for construction of the glass curtain wall of the roof steel structure platform as claimed in claim 3, wherein: the guide steel wire rope fixed pulley block comprises a fifth fixed pulley (8-1) fixedly mounted on the hanging basket body (1), a sixth fixed pulley (8-2) fixedly mounted at the end part of the guide rod (7) and a seventh fixed pulley (8-3) fixedly mounted at the end part of the cantilever section (4-1-2).
5. The hanging basket device for construction of the glass curtain wall of the roof steel structure platform as claimed in claim 2, wherein: the first support frame (4-2) and the second support frame (4-3) respectively comprise a horizontal rod and a vertical rod vertically installed on the horizontal rod, and the horizontal rod of the first support frame (4-2) is fixedly connected with the inner ring square frame (2-1) and the horizontal rod of the second support frame (4-3) is fixedly connected with the outer ring square frame (2-2) through U-shaped bolts (9).
CN202020450234.7U 2020-03-31 2020-03-31 Hanging flower basket device is used in construction of roof steel construction platform glass curtain wall Expired - Fee Related CN211899582U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020450234.7U CN211899582U (en) 2020-03-31 2020-03-31 Hanging flower basket device is used in construction of roof steel construction platform glass curtain wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020450234.7U CN211899582U (en) 2020-03-31 2020-03-31 Hanging flower basket device is used in construction of roof steel construction platform glass curtain wall

Publications (1)

Publication Number Publication Date
CN211899582U true CN211899582U (en) 2020-11-10

Family

ID=73274135

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020450234.7U Expired - Fee Related CN211899582U (en) 2020-03-31 2020-03-31 Hanging flower basket device is used in construction of roof steel construction platform glass curtain wall

Country Status (1)

Country Link
CN (1) CN211899582U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112523488A (en) * 2020-12-08 2021-03-19 陈晓艳 Construction hanging basket with parking safety device for electric-based construction
CN113356556A (en) * 2021-05-31 2021-09-07 上海二十冶建设有限公司 Steel structure-based counterweight-free hanging basket installation method
CN115030477A (en) * 2022-06-22 2022-09-09 中国化学工程重型机械化有限公司 Keel hanging basket installation method based on steel structure

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112523488A (en) * 2020-12-08 2021-03-19 陈晓艳 Construction hanging basket with parking safety device for electric-based construction
CN113356556A (en) * 2021-05-31 2021-09-07 上海二十冶建设有限公司 Steel structure-based counterweight-free hanging basket installation method
CN115030477A (en) * 2022-06-22 2022-09-09 中国化学工程重型机械化有限公司 Keel hanging basket installation method based on steel structure
CN115030477B (en) * 2022-06-22 2024-05-28 中国化学工程重型机械化有限公司 Keel hanging basket installation method based on steel structure

Similar Documents

Publication Publication Date Title
CN211899582U (en) Hanging flower basket device is used in construction of roof steel construction platform glass curtain wall
CN200955259Y (en) Funnel-derrick moving type construction apparatus
CN211899163U (en) Construction structure of roof steel structure platform slope glass curtain wall
CN109881590A (en) Bridge steel box girder high altitude operation operating platform and building method
CN220376298U (en) Hanging basket lifting device
CN201786010U (en) Elevating platform for construction use
CN212866793U (en) Assembled construction elevator stops layer platform
CN201793330U (en) Gantry hanger frame device
CN211173007U (en) Novel tripod of encorbelmenting
CN210738053U (en) Turnover operation platform suitable for elevator counterweight installation
CN209873592U (en) Lifting type movable auxiliary tool for installing variable-section cantilever on steel box girder
CN209585576U (en) Overhanging scaffold
CN204983692U (en) Concrete panel's hoist device
CN111335172A (en) Movable pier column cross beam prestress tensioning hanging frame construction platform and construction method
CN111305433B (en) Construction structure and construction method of roof steel structure platform inclined glass curtain wall
CN212561213U (en) Railway pier top surrounding hanging basket safe operation platform
CN211285309U (en) Traveling type hanging basket for bridge construction
CN220265089U (en) Heavy pipeline mechanical lifting device
CN209874434U (en) Simple and easy scaffold frame of encorbelmenting of building high latitude
CN217203935U (en) Trash rack pier template hoisting device
CN207193654U (en) A kind of rope knitting machine frame
CN216471918U (en) Novel tower top structure of swing arm type tower crane
CN212076261U (en) Hoisting device convenient to move
CN210341680U (en) Door type corrugated steel web plate installation and overhanging type hanging bracket structure
CN212671130U (en) Elevator shaft template shaping supporting device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201110