CN208701735U - A kind of foundation ring of wind generating set - Google Patents

A kind of foundation ring of wind generating set Download PDF

Info

Publication number
CN208701735U
CN208701735U CN201821393213.5U CN201821393213U CN208701735U CN 208701735 U CN208701735 U CN 208701735U CN 201821393213 U CN201821393213 U CN 201821393213U CN 208701735 U CN208701735 U CN 208701735U
Authority
CN
China
Prior art keywords
ring
concrete
steel base
high performance
foundation ring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821393213.5U
Other languages
Chinese (zh)
Inventor
吕伟荣
周卿祺
卢倍嵘
王功勋
袁深根
周志锦
廖继彪
姚帅
刘雪梅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan University of Science and Technology
Original Assignee
Hunan University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan University of Science and Technology filed Critical Hunan University of Science and Technology
Priority to CN201821393213.5U priority Critical patent/CN208701735U/en
Application granted granted Critical
Publication of CN208701735U publication Critical patent/CN208701735U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model discloses a kind of foundation ring of wind generating set, including steel base ring, foundation ring inside and outside wall is equipped with high performance concrete preform strip band, stack shell peg is set on steel base ring inside and outside wall, stack shell peg one end is weldingly fixed on steel base ring, the other end is attached through high performance concrete preform strip band and exposed with cast in situs normal concrete.The utility model is equipped with annular high performance concrete preform strip band on steel base ring inside and outside wall, by using the first prefabricated package foundation ring of high performance concrete, and it is arranged after stack shell peg and carries out live one-piece casting with normal concrete, it ensure that the concrete construction quality at interface between foundation ring and concrete, shear stiffness and anti-fatigue ability between interface are improved, blower foundation service life is extended.

Description

A kind of foundation ring of wind generating set
Technical field
The utility model relates to wind-powered electricity generation field, in particular to a kind of foundation ring of wind generating set.
Background technique
Currently, be to adapt to low wind speed power generation needs, long diameter, big blade new architecture continue to bring out, this directly results in wind Fatigue load is caused to dramatically increase, traditional basic ring type blower foundation causes because being unable to satisfy the increased demand of fatigue load Concrete prematurely fails with steel base interannular interface and loosens and wave, serious that tower is caused to tilt and can not normally make With causing great economic loss.
Traditional blower foundation ring wears annular distance up and down often by setting and wears ring reinforcing bar guarantee concrete and steel base The connection of plinth interannular, shear behavior is limited between interface, can still deal in the case where charming appearance and behaviour fatigue load is little, but with new machine The emergence of type, the increase of fatigue load, fatigue life then significantly reduce, and basic failure accidents continue to bring out, and are owner Biggish economic loss is caused, this shows that traditional foundation ring needs to improve.
Summary of the invention
In order to solve the above-mentioned technical problem, the utility model provides the wind-force that a kind of structure is simple, interface shearing-resistance performance is good Generating set foundation ring.
The technical solution that the utility model solves the above problems is: a kind of foundation ring of wind generating set, including steel base Plinth ring, foundation ring inside and outside wall are equipped with high performance concrete preform strip band, set stack shell peg, stack shell on steel base ring inside and outside wall Peg one end is weldingly fixed on steel base ring, and the other end is poured through high performance concrete preform strip band and exposed with scene Normal concrete is built to be attached.
Above-mentioned foundation ring of wind generating set, the stack shell peg are vertically uniformly distributed along the inside and outside wall of steel base ring.
Above-mentioned foundation ring of wind generating set, stack shell peg one end are welded on foundation ring, and the other end exposes high property The length of the concrete prefabricated band of energy is 100 ~ 200mm, and is attached with cast in situs normal concrete.
Above-mentioned foundation ring of wind generating set, the prefabricated strip width of high performance concrete are 100mm.
Above-mentioned foundation ring of wind generating set, the prefabricated swath height of high performance concrete and the embedment of steel base ring are mixed Height in solidifying soil is equal.
The utility model has the beneficial effects that: the utility model is equipped with the high property of annular on steel base ring inside and outside wall Can concrete prefabricated band, by using the first prefabricated package foundation ring of high performance concrete, and stack shell peg and common mixed is set Solidifying soil carries out live one-piece casting, can greatly increase the shear stiffness at interface between foundation ring and concrete in this way, reduces peak It is worth stress, improves anti-fatigue ability between interface, effectively increase blower fatigue life, extends blower service life.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model.
Fig. 2 is the secondary schematic diagram poured in the utility model scene.
Specific embodiment
The utility model is further described with reference to the accompanying drawings and examples.
As shown in Figure 1, a kind of foundation ring of wind generating set, including steel base ring 1, inside and outside the steel base ring 1 Wall, which is equipped with high performance concrete preform strip band 2, not only can effectively guarantee concrete construction quality because being prefabrication, and And can effectively increase the shear behavior between steel base ring 1 and concrete, anti-fatigue performance between interface is improved, and then effectively Avoid the charming appearance and behaviour fatigue damage of concrete.
2 width of high performance concrete preform strip band be 100mm, height in 1 Transducers Embedded in Concrete of steel base ring Height it is equal.
Vertical uniformly distributed stack shell peg 3 on 1 inside and outside wall of steel base ring, 3 one end of stack shell peg is welded on steel On foundation ring 1, the other end runs through the high performance concrete preform strip band 2 and exposed 100 ~ 200mm, with guarantee and cast in situs Normal concrete 4 effectively connects.
The setting of the stack shell peg 3 can increase between steel base ring 1 and high performance concrete preform strip band 2, is high Interfacial bond property between performance concrete preform strip band 2 and cast in situs normal concrete 4 improves anti-shear concrete fatigue energy Power increases service life of fan.It can also enhance between prefabricated high performance concrete and cast in situs normal concrete 4 simultaneously Switching performance guarantees the co-operation between new-old concrete, avoids disengaging between two kinds of materials.
1 periphery high performance concrete preform strip band 2 of steel base ring is transported again after wrapping up and conserve in advance to scene, The construction quality that can fully ensure that high performance concrete in this way, avoid cast-in-place concrete it is that may be present vibrate leakiness and Gradation equal construction quality problems not up to standard.
The work progress of the utility model is as follows: as shown in Fig. 2, first in 1 Transducers Embedded in Concrete section of steel base ring Stack shell peg 3 is evenly arranged according to calculating respectively on outer wall, 3 length requirement of stack shell peg runs through high performance concrete preform strip band Exposed 200mm or so after 2, to ensure the quality of connection between cast-in-site normal concrete.Then in factory by steel base 1 Transducers Embedded in Concrete section inside and outside wall of ring uses high performance concrete preform strip band 2 to wrap up in advance respectively, is transported to again after conserving 28 days Scene carries out second pouring;Finally pour at the scene, the normal concrete of after-pouring by stack shell peg 3 ensure with it is previous prefabricated 2 part of high performance concrete preform strip band carry out good connection, it is ensured that pouring quality.

Claims (5)

1. a kind of foundation ring of wind generating set, it is characterised in that: including steel base ring, foundation ring inside and outside wall is equipped with high property Can concrete prefabricated band, set stack shell peg on steel base ring inside and outside wall, stack shell peg one end is weldingly fixed on steel base On ring, the other end is attached through high performance concrete preform strip band and exposed with cast in situs normal concrete.
2. foundation ring of wind generating set according to claim 1, it is characterised in that: the stack shell peg is along steel base The inside and outside wall of ring is vertically uniformly distributed.
3. foundation ring of wind generating set according to claim 1, it is characterised in that: stack shell peg one end is welded on On foundation ring, the other end expose high performance concrete preform strip band length be 100 ~ 200mm, and with the common coagulation of cast in situs Soil is attached.
4. foundation ring of wind generating set according to claim 1, it is characterised in that: the high performance concrete preform strip Bandwidth is 100mm.
5. foundation ring of wind generating set according to claim 1, it is characterised in that: the high performance concrete preform strip It is equal with the height in steel base ring Transducers Embedded in Concrete with height.
CN201821393213.5U 2018-08-28 2018-08-28 A kind of foundation ring of wind generating set Active CN208701735U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821393213.5U CN208701735U (en) 2018-08-28 2018-08-28 A kind of foundation ring of wind generating set

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821393213.5U CN208701735U (en) 2018-08-28 2018-08-28 A kind of foundation ring of wind generating set

Publications (1)

Publication Number Publication Date
CN208701735U true CN208701735U (en) 2019-04-05

Family

ID=65944503

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821393213.5U Active CN208701735U (en) 2018-08-28 2018-08-28 A kind of foundation ring of wind generating set

Country Status (1)

Country Link
CN (1) CN208701735U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108755739A (en) * 2018-08-28 2018-11-06 湖南科技大学 A kind of foundation ring of wind generating set
CN113684873A (en) * 2020-05-19 2021-11-23 北京金风科创风电设备有限公司 Reinforcing system, tower system and reinforcing method for foundation of wind generating set

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108755739A (en) * 2018-08-28 2018-11-06 湖南科技大学 A kind of foundation ring of wind generating set
CN108755739B (en) * 2018-08-28 2024-03-15 湖南科技大学 Wind generating set foundation ring
CN113684873A (en) * 2020-05-19 2021-11-23 北京金风科创风电设备有限公司 Reinforcing system, tower system and reinforcing method for foundation of wind generating set

Similar Documents

Publication Publication Date Title
CN208701735U (en) A kind of foundation ring of wind generating set
CN215715494U (en) Partially prefabricated offshore high pile cap
US10851513B1 (en) Combined offshore wind power foundation with duct piles and a bucket
CN108755739A (en) A kind of foundation ring of wind generating set
CN109024661B (en) Wind generating set foundation reinforcing system
CN112412707A (en) Assembled wind turbine generator system circle cross section concrete bearing structure
CN108824475A (en) A kind of transmission line of electricity equilateral triangle cushion cap stake assembling type base
CN209703838U (en) Steel bar connecting structure between reinforcing bar connector and precast concrete
CN205638802U (en) Formula precast concrete pylon structure is made up in segmentation
CN209703418U (en) Assembled flood-control wall
CN111197319A (en) Multidirectional prestress prefabricated assembled beam slab foundation of wind power generation tower
CN204491567U (en) Pre-manufactured steel pile tube wind power generation platform
CN208293604U (en) Prefabrication type High-Rise Pile Cap Foundation
CN217325391U (en) Construction tool for high-speed rail line deep foundation pit secant pile
CN109457868A (en) A kind of steel tube concrete column feet node and its construction method
CN211250565U (en) Pouring die for beam
CN208430851U (en) A kind of steel tube concrete column feet node
CN208792364U (en) Foundation of wind-driven generator unit hardened system
CN110397067A (en) A kind of more steel reinforced concrete combination foundation structures and its construction method with support construction
CN206829175U (en) A kind of foundation ring of wind generating set local stiffening device
CN207047887U (en) A kind of blower foundation ring anchor structure
CN112211219A (en) Novel thin-wall large-diameter single pile-barrel composite pile foundation and installation method thereof
CN218622304U (en) Land wind self-response fan foundation device
CN216041288U (en) Spiral anchor foundation
CN105735338A (en) Prestress assembled-type fan foundation

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant