CN208675884U - A kind of Ecological Road - Google Patents

A kind of Ecological Road Download PDF

Info

Publication number
CN208675884U
CN208675884U CN201821277347.0U CN201821277347U CN208675884U CN 208675884 U CN208675884 U CN 208675884U CN 201821277347 U CN201821277347 U CN 201821277347U CN 208675884 U CN208675884 U CN 208675884U
Authority
CN
China
Prior art keywords
water
road
greenbelt
ecological
main body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821277347.0U
Other languages
Chinese (zh)
Inventor
吴凤仪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Foshan Haoxinta Construction Engineering Co Ltd
Original Assignee
Foshan Haoxinta Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Foshan Haoxinta Construction Engineering Co Ltd filed Critical Foshan Haoxinta Construction Engineering Co Ltd
Priority to CN201821277347.0U priority Critical patent/CN208675884U/en
Application granted granted Critical
Publication of CN208675884U publication Critical patent/CN208675884U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A20/00Water conservation; Efficient water supply; Efficient water use
    • Y02A20/108Rainwater harvesting

Landscapes

  • Cultivation Of Plants (AREA)
  • Cultivation Receptacles Or Flower-Pots, Or Pots For Seedlings (AREA)

Abstract

The utility model discloses a kind of Ecological Roads, belong to technical field of road construction;The main points of its technical scheme are that including road main body, it is provided with greenbelt in the middle part of the road main body, the catch basin for collecting rainwater is offered in the road main body of the two sides of the greenbelt;Ecological Road further includes the water injector for extracting the water in catch basin and spraying water to the plant of greenbelt;Solve the problem of that existing road primarily now pours irrigation process to the plant of greenbelt using artificial or mobile waterwheel and is inconvenient and needs to expend a large amount of water resource;To improve the utilization rate of water resource, and can have the advantages that pouring is convenient in natural precipitation to being collected and irrigating using plant of the rainwater to greenbelt.

Description

A kind of Ecological Road
Technical field
The utility model relates to technical field of road construction more particularly to a kind of Ecological Roads.
Background technique
Ecological Road refers to that builder, can be by nature, people in On Road Planning And Design, process of construction and after the completion of construction It is organically combined with road, incorporates Ecological Design Method.The day that traffic trip is required with the development and people of society Benefit improves, and the road in city and rural construction is more and more.Ecological Road organically combines nature, people and road, The green coverage that environment can effectively be increased meets sustainable development sight, increasingly by the favor of road construction person.
Isolation strip can be arranged in the common centre in road main body, and the car lane of two sides is separated.Isolation strip Various ways are provided with, mostly use the mode of greening box or railing at present.Be isolated using greening box, by it is multiple greening every An isolation strip is afforested from case composition, the cultivated plant in greening box improves the green coverage of road, improves the ecology of road Environment.In the construction of Ecological Road, green isolation strip is widely used.
The greenbelt of existing Ecological Road can refer to the utility model patent that Authorization Notice No. is CN2144140Y File discloses ecologic road guard fence, including using the prefabricated component based on concrete, industrial residue.It is formed with groove, slot thereon The soil that interior filling has pole grass-seed, spends seed, natural gum and fertilizer.
The plant of the greenbelt of Ecological Road needs periodically to be poured, primarily now using artificial or mobile waterwheel The plant of greenbelt is poured, irrigation process is inconvenient, and needs to expend a large amount of water resource.
Utility model content
In view of the deficienciess of the prior art, the purpose of this utility model is to provide a kind of Ecological Road, it can be certainly To being collected and being irrigated using plant of the rainwater to greenbelt when right precipitation, to improve the utilization of water resource Rate, and have the advantages that pouring is convenient.
The above-mentioned technical purpose of the utility model has the technical scheme that a kind of Ecological Road, packet Road main body is included, greenbelt, the road main body of the two sides of the greenbelt are provided in the middle part of the road main body On offer collect rainwater catch basin;Ecological Road further includes that the water extracted in catch basin carries out the plant of greenbelt The water injector of water spray.
Through the above technical solutions, collecting catchmenting for rainwater by opening up in the road main body of the two sides of greenbelt Slot, in natural precipitation, can be collected rainwater by catch basin by the setting of catch basin, and then pass through water spray dress It sets the water extracted in catch basin and water spray pouring is carried out to the plant of greenbelt, realize to rain water reuse, water has been turned up The utilization rate of resource.
Preferably, the water injector includes the spray head for being located at greenbelt two sides, the water for being connected to spray head and catch basin The suction pump managed and be arranged on water pipe, the water in catch basin is extracted.
Through the above technical solutions, being extracted by suction pump to the water in catch basin, to pass through water pipe and spray head Water spray pouring is carried out to greenbelt.
Preferably, the water inlet of the water pipe is provided with the filter device for being filtered purification to the water of catch basin.
Purification is filtered to the water of catch basin through the above technical solutions, being provided with by the water inlet in water pipe Filter device;And then in pump process purification is filtered to the water flow of extraction, prevent the impurity contained in water flow to drawing water Pump and spray head result in blockage.
Preferably, the filter device includes Rose Box, the Rose Box is provided with inlet and outlet;The water inlet Mouth is sealedly and fixedly connected with water pipe;Filter screen is set in the Rose Box.
Through the above technical solutions, filter device includes Rose Box, Rose Box is provided with inlet and outlet;Water inlet It is sealedly and fixedly connected with water pipe;Filter screen is set in Rose Box;By the setting of Rose Box and filter screen to the water for entering water pipe Solid impurity in stream is filtered, to prevent the impurity in water flow from entering water pipe, is resulted in blockage to spray head and suction pump.
Preferably, the greenbelt includes the greening box for the planting plants being placed in road main body and is fixed on Multiple lattice of real things for placing plants are arranged on the supporter for supporter on greening box.
Through the above technical solutions, greenbelt include the planting plants being placed in road main body greening box and Multiple lattice of real things for placing plants are arranged on supporter for the supporter being fixed on greening box;It is planted by being transplanted in greening box Object forms isolation strip with green plants, road main body is isolated;By the setting of supporter, basin is placed in lattice of real thing Object is transplanted, plant and supporter form a unified entirety;Supporter has not only acted as buffer action, and improves to plant The space utilization rate of plant setting increases the space order of greening.
Preferably, the supporter, which is provided with, runs through the through hole of lattice of real thing in vertical direction.
Through the above technical solutions, by the way that the through hole that vertical direction runs through lattice of real thing is arranged in supporter, by passing through The setting of through-hole, when natural precipitation sprays water to the plant on supporter, water flow can penetrate the glove on upper layer every under The plant of layer is poured, to improve the pouring efficiency to plant on supporter, plays preferably to the plant on supporter Pour effect.
Preferably, Ecological Road further includes the pavement that road main body two sides are arranged in, the pavement, which is equipped with, plants Careless lattice.
Through the above technical solutions, by being laid with grass-planting grid on pavement, so as to by being planted in grass-planting grid Straw or like vegetable increases the green coverage to pavement, so that plant and pavement is formed a unified entirety, and then improve people's row Lateral road it is ecological.
It is additionally provided with water collection chamber below lateral road preferably, the people walks, connection water collection chamber is provided on the pavement Drain hole inside internal grass-planting grid.
It is additionally provided with water collection chamber below lateral road through the above technical solutions, people walks, connection is provided on pavement and catchments Drain hole inside intracavitary portion's grass-planting grid;To which when natural precipitation is more, extra moisture can be discharged to collection by drain hole In water cavity, so mitigate natural precipitation it is excessive when flood is flooded to plant in grass-planting grid.
Preferably, the suction hose inside connection water collection chamber and grass-planting grid is provided in the drain hole, the suction hose It is internally provided with absorbent wool.
Through the above technical solutions, by the way that the suction hose inside connection water collection chamber and grass-planting grid is arranged in drain hole, and And absorbent wool is set in the inside of suction hose, when the soil in grass-planting grid is more arid, by suction hose and suction hose Absorbent wool absorbs the moisture in water collection chamber, and then the soil into grass-planting grid is diffused, thus in grass-planting grid Carry out water replenishment.
In conclusion the utility model has the following beneficial effects:
1. collecting the catch basin of rainwater by opening up in the road main body of the two sides of greenbelt, pass through catch basin Setting, in natural precipitation, can be collected rainwater by catch basin, and then be extracted in catch basin by water injector Water carries out water spray pouring to the plant of greenbelt, realizes to rain water reuse, the utilization rate of water resource has been turned up;
2. greenbelt includes the greening box for the planting plants being placed in road main body and is fixed on greening box Supporter, multiple lattice of real things for placing plants are set on supporter;By the cultivated plant in greening box, with green plants shape At isolation strip, road main body is isolated;By the setting of supporter, place potted plant in lattice of real thing, plant with set Rack forms a unified entirety;Supporter has not only acted as buffer action, and improves the space benefit to plant setting With rate, the space order of greening is increased;
3. being provided with grass-planting grid inside connection water collection chamber on pavement by being additionally provided with water collection chamber below walking lateral road Internal drain hole, the interior setting connection water collection chamber of drain hole and the suction hose inside grass-planting grid, and set in the inside of suction hose Set absorbent wool;To which the moisture content of soil in grass-planting grid be adjusted, and then plant health in grass-planting grid is made to grow up.
Detailed description of the invention
Fig. 1 is a kind of structural schematic diagram of Ecological Road;
Fig. 2 is the partial enlarged view of A in Fig. 1;
Fig. 3 is the structural schematic diagram of water injector;
Fig. 4 is the cross-sectional view of filter device;
Fig. 5 is the cross-sectional view at grass-planting grid.
Appended drawing reference: 1, road main body;2, pavement;21, grass-planting grid;22, water collection chamber;23, drain hole;24, suction hose; 25, absorbent wool;3, greenbelt;31, greening box;32, supporter;321, lattice of real thing;322, through hole;4, catch basin;5, Water injector;51, suction pump;52, water pipe;53, spray head;6, filter device;61, Rose Box;611, water inlet;612, it is discharged Mouthful;62, filter screen.
Specific embodiment
Embodiment: including road main body 1 and 1 two sides of road main body are arranged in referring to Figures 1 and 2 in a kind of Ecological Road Pavement 2 is equipped with grass-planting grid 21 on pavement 2, and the middle part of road main body 1 is provided with greenbelt 3.It is planted in grass-planting grid 21 It is implanted with straw or like vegetable, greenbelt 3 forms unified entirety with building and green plants.By greenbelt 3 and plant The setting of careless lattice 21 increases the green coverage of whole road, and the organic unification for forming road and plant is whole.
Referring to Fig. 2, greenbelt 3 includes being placed on the greening box 31 of planting plants in road main body 1 and being fixed on Multiple lattice of real things 321 for placing plants are arranged on supporter 32 for supporter 32 on greening box 31.It plants and plants in greening box 31 Object, and by supporter 32, cultivated plant potting etc. is placed in lattice of real thing 321.By the setting of supporter 32, not only rise The effect of isolation has been arrived, and has increased the three-dimensional covering of plant, has increased the hierarchy of greening.
Referring to Fig. 2, supporter 32, which is provided with, runs through the through hole 322 of lattice of real thing 321 in vertical direction.By in through hole 322 setting, natural precipitation or to the plant on supporter 32 carry out water spray pour when, extra water flow can pass through upper layer The through hole 322 of lattice of real thing 321 is permeated downwards, to improve the utilization rate of water resource, is preferably set to every level-one Plant on object lattice 321 is poured.
Referring to Figure 1 and Figure 3, the catch basin 4 for collecting rainwater is offered in the road main body 1 of the two sides of greenbelt 3;It is raw State road further includes the water injector 5 for extracting the water in catch basin 4 and spraying water to the plant of greenbelt 3.Water injector 5 Including being located at the spray head 53 of 3 two sides of greenbelt, the water pipe 52 for being connected to spray head 53 and catch basin 4 and setting in water pipe 52 Suction pump 51 upper, that the water in catch basin 4 is extracted.Rainwater can be received in natural precipitation by catch basin 4 Collection to extract by suction pump 51 to the rainwater collected in catch basin 4, and then passes through water pipe 52 and 53 pairs of spray head greenings Plant on case 31 and supporter 32 carries out water spray pouring.By the setting of catch basin 4, rainwater is received in natural precipitation Collection utilizes, and improves the utilization rate of water resource, compound sustainable development view.
Referring to Fig. 3 and Fig. 4, the mistake that purification is filtered to the water of catch basin 4 is additionally provided at the water inlet 611 of water pipe 52 Filter device 6.Filter device 6 includes Rose Box 61, and Rose Box 61 is provided with water inlet 611 and water outlet 612;Water inlet 611 with Water pipe 52 is sealedly and fixedly connected;Filter screen 62 is set in Rose Box 61.Pass through filter screen 62 in Rose Box 61 and Rose Box 61 Setting, and then be filtered to the impurity of water flow in water pipe 52 is entered, to prevent the impurity present in the water flow due to cause to spray First 53 and suction pump 51 blocking, and then influence suction pump 51 and spray head 53 to the pouring function of plant.
Referring to Fig.1 and Fig. 5, the lower section on pavement 2 are additionally provided with water collection chamber 22, and connection water collection chamber 22 is provided on pavement 2 Drain hole 23 inside internal grass-planting grid 21.The suction hose being provided in drain hole 23 inside connection water collection chamber 22 and grass-planting grid 21 24, suction hose 24 is internally provided with absorbent wool 25.When carrying out natural precipitation, when precipitation is more, extra moisture can It is discharged in water collection chamber 22 to reduce and flood flood to plant in grass-planting grid 21 in precipitation by drain hole 23.Pass through suction hose 24 With the setting of the absorbent wool 25 in suction hose 24, thus in weather arid, by absorbent wool 25 to the moisture in water collection chamber 22 It is drawn, and then the soil into grass-planting grid 21 carries out moisture diffusion, to supply moisture to the plant in grass-planting grid 21.
Specifically used principle is as follows:
Greenbelt 3 carries out plant by greening box 31 and supporter 32 and places plant, in the base for playing buffer action On plinth, the building structure of plant and surrounding is set to form a unified ecology whole;By being laid with grass-planting grid 21 on pavement 2, And straw or like vegetable is transplanted in grass-planting grid 21, the green coverage of road entirety is further turned up.When carrying out natural precipitation, lead to It crosses catch basin 4 to be collected natural precipitation, and suction pump 51, water pipe 52, spray head by the way that 3 two sides of greenbelt are arranged in 53 realizations utilize the rainwater collected in catch basin 4 again, are carried out using the rainwater of collection to the plant of greenbelt 3 It pours, improves the utilization rate of water resource.Water collection chamber 22 is set by the lower section on pavement 2, and passes through 24 He of suction hose The setting of absorbent wool 25, adjusts the water balance of soil in grass-planting grid 21, thus make in grass-planting grid 21 plant more healthy at It is long.
This specific embodiment is only the explanation to the utility model, is not limitations of the present invention, ability Field technique personnel can according to need the modification that not creative contribution is made to the present embodiment after reading this specification, but As long as all by the protection of Patent Law in the scope of the claims of the utility model.

Claims (9)

1. a kind of Ecological Road, including road main body (1), greenbelt (3) are provided in the middle part of the road main body (1), It is characterized by: offering the catch basin (4) for collecting rainwater in the road main body (1) of the two sides of the greenbelt (3);It is raw State road further includes the water injector (5) for extracting the water in catch basin (4) and spraying water to the plant of greenbelt (3).
2. a kind of Ecological Road according to claim 1, it is characterised in that: the water injector (5) includes being located at greening The spray head (53) of isolation strip (3) two sides, the water pipe (52) of connection spray head (53) and catch basin (4) and setting are in water pipe (52) Suction pump (51) upper, that the water in catch basin (4) is extracted.
3. a kind of Ecological Road according to claim 2, it is characterised in that: the water inlet of the water pipe (52) is also set up There is the water to catch basin (4) to be filtered the filter device (6) of purification.
4. a kind of Ecological Road according to claim 3, it is characterised in that: the filter device includes Rose Box (61), The Rose Box is provided with water inlet (611) and water outlet (612);The water inlet (611) and the fixed company of water pipe (52) sealing It connects;Filter screen (62) are set in the Rose Box (61).
5. a kind of Ecological Road according to claim 1, it is characterised in that: the greenbelt (3) includes being placed on The greening box (31) of planting plants in road main body (1) and the supporter (32) being fixed on greening box (31), it is described to set Multiple lattice of real things (321) for placing plant are set in rack (32).
6. a kind of Ecological Road according to claim 5, it is characterised in that: the supporter (32) is provided in vertical side To the through hole (322) for running through lattice of real thing (321).
7. a kind of Ecological Road according to claim 1, it is characterised in that: Ecological Road further includes being arranged in road main body (1) pavement (2) of two sides is equipped with grass-planting grid (21) on the pavement (2).
8. a kind of Ecological Road according to claim 7, it is characterised in that: be additionally provided with collection below people's walking lateral road Water cavity (22) is provided with the internal drain hole (23) of the internal grass-planting grid (21) of connection water collection chamber (22) on the pavement (2).
9. a kind of Ecological Road according to claim 8, it is characterised in that: be provided with connected set in the drain hole (23) The suction hose (24) of water cavity (22) and grass-planting grid (21) inside, the suction hose (24) are internally provided with absorbent wool (25).
CN201821277347.0U 2018-08-08 2018-08-08 A kind of Ecological Road Active CN208675884U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821277347.0U CN208675884U (en) 2018-08-08 2018-08-08 A kind of Ecological Road

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821277347.0U CN208675884U (en) 2018-08-08 2018-08-08 A kind of Ecological Road

Publications (1)

Publication Number Publication Date
CN208675884U true CN208675884U (en) 2019-04-02

Family

ID=65884288

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821277347.0U Active CN208675884U (en) 2018-08-08 2018-08-08 A kind of Ecological Road

Country Status (1)

Country Link
CN (1) CN208675884U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113261446A (en) * 2021-05-17 2021-08-17 广东韩江工程总承包有限公司 Construction method of green isolation belt based on building engineering

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113261446A (en) * 2021-05-17 2021-08-17 广东韩江工程总承包有限公司 Construction method of green isolation belt based on building engineering

Similar Documents

Publication Publication Date Title
CN104695545B (en) Conveniently-constructed ecological building construction method
CN206274852U (en) Vertical greening decorative wall
CN101091448B (en) Irrigation and drainage pipes
CN207969440U (en) A kind of Green Roof
CN206090587U (en) School dropout's attitude system of watering is gathered to side slope
CN215254015U (en) Ecological roof greening circulating water structure for sponge city
CN109267772A (en) A kind of Ecological Landscape gallery and its workflow of intelligent three-dimensional rainwater reuse
CN112673930A (en) Road for building sponge city
CN206452786U (en) A kind of slope greening ground self-priming structure
CN206128181U (en) System that utilizes is collected to courtyard formula rainwater
CN209494139U (en) A kind of anti-roof afforestation structure of waterproof
CN208675884U (en) A kind of Ecological Road
CN106499033A (en) A kind of water drainage and the road green belt system of water conservation
KR101182722B1 (en) Water Supply Device for Roadside Tree
CN205934646U (en) Water conservancy system
CN208803519U (en) A kind of roof drainage structure
CN209330686U (en) A kind of plantation external wall structure of Collection utilization rainwater
CN209277257U (en) A kind of collection rainfall pattern road vegetation interacted system
CN109944294A (en) A kind of southwest knob hillside fields road band ditch rainwater-collecting and reutilization system
CN213061901U (en) Ecological slope wall of hydraulic engineering
CN109083250A (en) A kind of massif class greenery patches method of construction based on sponge city
CN205596693U (en) From flower bed that catchments
CN212835234U (en) Ecological environment-friendly water conservancy bank protection
CN211446456U (en) Multifunctional sponge structure under limited greenbelt condition
CN208701873U (en) A kind of open settlement integrated environment improvement greenbelt water-storing device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant