CN208561497U - A kind of Plug-in tower crane for following tower body to climb together is climbed frame apparatus - Google Patents

A kind of Plug-in tower crane for following tower body to climb together is climbed frame apparatus Download PDF

Info

Publication number
CN208561497U
CN208561497U CN201821062441.4U CN201821062441U CN208561497U CN 208561497 U CN208561497 U CN 208561497U CN 201821062441 U CN201821062441 U CN 201821062441U CN 208561497 U CN208561497 U CN 208561497U
Authority
CN
China
Prior art keywords
upper ledge
tower crane
tower body
tower
plug
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821062441.4U
Other languages
Chinese (zh)
Inventor
张宇
俞嫒妍
吴君
王军强
吴欣之
潘令誉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Mechanized Construction Group Co Ltd
Original Assignee
Shanghai Mechanized Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Mechanized Construction Group Co Ltd filed Critical Shanghai Mechanized Construction Group Co Ltd
Priority to CN201821062441.4U priority Critical patent/CN208561497U/en
Application granted granted Critical
Publication of CN208561497U publication Critical patent/CN208561497U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Jib Cranes (AREA)

Abstract

The Plug-in tower crane that tower body can be followed to climb together the utility model proposes one kind is climbed frame apparatus, the device includes: the first upper ledge, the second upper ledge, lower frame, hoist engine, wirerope, pull rod, wherein the lower frame bears tower crane vertical load, connecting building structure and tower body;Second upper ledge bears tower crane horizontal load, connecting building structure and tower body;The pull rod connects the lower frame and second upper ledge;First upper ledge is only connected with building structure, with tower body without connecting;The hoist engine is set at the top of tower crane, is connected to first upper ledge or the second upper ledge by wirerope.The utility model proposes the Plug-in tower crane for following tower body to climb together climb frame apparatus, during existing tower crane climbing can be efficiently solved, remove and installation climbed the complexity of frame, dangerous working condition, reduce the occupancy to resource, shorten the construction period.

Description

A kind of Plug-in tower crane for following tower body to climb together is climbed frame apparatus
Technical field
The utility model belongs to architectural engineering construction technique field, relate generally to it is a kind of can follow that tower body climbs together can The Plug-in tower crane for following tower body to climb together is climbed frame apparatus.
Background technique
The external-hanging structure of existing tower crane needs twice to climb frame (upper ledge and bottom frame) as supporting structure, holds at work By generated horizontal force, vertical force in tower crane lifting work etc..When tower crane climbs upwards, then need in addition to pacify again above Dress climbs frame (new upper ledge) together.Original twice bottom frame in frame that climbs will move out later work, and that newly installs climbs Upper ledge as the following tower crane is participated in work by frame.Each tower crane climbing all by along with new upper ledge is installed, removes old bottom The work of frame.Usual above-mentioned work is completed by adjacent tower crane, it means that the standard climbed in a tower crane Standby work and climb work when, itself cannot not only participate in site operation work, adjacent cooperation tower crane can not participate in scene Construction working greatly occupies resource, is affected to the duration.
Utility model content
The Plug-in tower crane that tower body can be followed to climb together the utility model proposes one kind is climbed frame apparatus, can be effectively During solving existing tower crane climbing, the complexity for the frame that climbs, dangerous working condition are removed and installed, the occupancy to resource is reduced, is shortened Duration.
In order to achieve the above object, the Plug-in tower crane that tower body can be followed to climb together the utility model proposes one kind is climbed Frame apparatus, comprising: the first upper ledge, the second upper ledge, lower frame, hoist engine, wirerope, pull rod,
Wherein the lower frame bears tower crane vertical load, connecting building structure and tower body;
Second upper ledge bears tower crane horizontal load, connecting building structure and tower body;
The pull rod connects the lower frame and second upper ledge;
First upper ledge is only connected with building structure, with tower body without connecting;
The hoist engine is set at the top of tower crane, is connected to first upper ledge or the second upper ledge by wirerope.
Further, first upper ledge and building structure are dismountable connection type.
Further, second upper ledge and building structure and the connection of tower body are dismountable connection type.
Further, the connection of the pull rod and the lower frame and second upper ledge is dismountable connection type.
Further, the connection of the hoist engine and first upper ledge and the second upper ledge is dismountable connection type.
The utility model proposes the Plug-in tower crane for following tower body to climb together climb frame apparatus, can not be by other Tower crane completes the installation that follows of frame of climbing, meanwhile, also complete the work of climbing of tower crane itself.The utility model can be effectively During solving existing tower crane climbing, the complexity for the frame that climbs, dangerous working condition are removed and installed, the occupancy to resource is reduced, is shortened Duration.
Detailed description of the invention
The Plug-in tower crane that Fig. 1 show the utility model preferred embodiment is climbed frame apparatus structural schematic diagram.
The Plug-in tower crane that Fig. 2~Fig. 8 show the utility model preferred embodiment climb frame apparatus application method signal Figure.
Specific embodiment
Specific embodiment of the present utility model, but the utility model implementation not limited to the following are provided below in conjunction with attached drawing Mode.According to following explanation and claims, will be become apparent from feature the advantages of the utility model.It should be noted that attached drawing It is all made of very simplified form and uses non-accurate ratio, be only used for convenience, lucidly aid in illustrating the utility model The purpose of embodiment.
The frame apparatus structural representation referring to FIG. 1, the Plug-in tower crane that Fig. 1 show the utility model preferred embodiment is climbed Figure.It climbs frame apparatus the utility model proposes a kind of Plug-in tower crane, comprising: the first upper ledge 100, the second upper ledge 200, lower frame 300, hoist engine 400, wirerope 500, pull rod 600, wherein the lower frame 300 bears tower crane vertical load, connecting building structure 10 and tower body 20;Second upper ledge 200 bears tower crane horizontal load, connecting building structure 10 and tower body 20;The pull rod 600 Connect the lower frame 300 and second upper ledge 200;First upper ledge 100 is only connected with building structure 10, not with tower body 20 It is attached;The hoist engine 400 is set at the top of tower crane, is connected to first upper ledge 100 or the by wirerope 500 Two upper ledges 200.
According to the utility model preferred embodiment, first upper ledge 100 is dismountable connection side with building structure 10 Formula.Second upper ledge 200 is dismountable connection type with building structure 10 and the connection of tower body 20.The pull rod 600 with The connection of the lower frame 300 and second upper ledge 200 is dismountable connection type.The hoist engine 400 and described first The connection of upper ledge 100 and the second upper ledge 200 is dismountable connection type.
In order to achieve the above object, the utility model also proposes that a kind of Plug-in tower crane is climbed frame apparatus application method, packet Include the following steps:
As shown in Fig. 2, releasing the connection of the first upper ledge and building structure, the first upper ledge is mentioned by hoist engine and wirerope The respective heights after the completion of climbing are risen to, then it is connect with building structure, the first upper ledge is withstood into plug-in tower crane tower body, makes it Horizontal load is born, meanwhile, contacting for the second upper ledge and tower body is released, it is made to be not subjected to horizontal load;
As shown in figure 3, hoist engine is connected by wirerope with the second upper ledge;
As shown in figure 4, release contacting for the second upper ledge and building structure, it is promoted to next operating position, then with Building structure connection;
As shown in figure 5, releasing steel wire rope of windlass, pull rod is installed on the second upper ledge, vertical load can be born, Meanwhile the pull rod on lower frame is released, not in the vertical load for bearing tower crane;
As shown in fig. 6, releasing contacting for lower frame and building structure, but tower body is kept to be connected thereto, tower crane is opened by climbing band Beginning climbs work, rises together with lower frame;
Band is climbed in the work as shown in fig. 7, tower crane completion is climbed, releasing, and lower frame is reliably connected with building structure;
As shown in figure 8, installing pull rod on lower frame, it is made to bear tower crane vertical load, the second upper ledge and tower body is reliable Connection makes its bear tower crane horizontal loading, releases contacting for the first upper ledge and tower crane, makes it not by load.
In conclusion the utility model proposes the Plug-in tower crane for following tower body to climb together climb frame apparatus, can The installation that follows of frame of climbing is not completed by other tower cranes, meanwhile, also complete the work of climbing of tower crane itself.The utility model During existing tower crane climbing can be efficiently solved, the complexity for the frame that climbs, dangerous working condition are removed and installed, is reduced to resource It occupies, shortens the construction period.
Although the utility model has been disclosed with preferred embodiment as above, so it is not intended to limit the utility model.This reality It is without departing from the spirit and scope of the utility model, each when that can make with novel those of ordinary skill in the art Kind changes and retouches.Therefore, the protection scope of the utility model is subject to view those as defined in claim.

Claims (5)

  1. The frame apparatus 1. Plug-in tower crane that one kind can follow tower body to climb together is climbed characterized by comprising the first upper ledge, Second upper ledge, lower frame, hoist engine, wirerope, pull rod,
    Wherein the lower frame bears tower crane vertical load, connecting building structure and tower body;
    Second upper ledge bears tower crane horizontal load, connecting building structure and tower body;
    The pull rod connects the lower frame and second upper ledge;
    First upper ledge is only connected with building structure, with tower body without connecting;
    The hoist engine is set at the top of tower crane, is connected to first upper ledge or the second upper ledge by wirerope.
  2. The frame apparatus 2. Plug-in tower crane according to claim 1 for following tower body to climb together is climbed, which is characterized in that First upper ledge and building structure are dismountable connection type.
  3. The frame apparatus 3. Plug-in tower crane according to claim 1 for following tower body to climb together is climbed, which is characterized in that Second upper ledge and building structure and the connection of tower body are dismountable connection type.
  4. The frame apparatus 4. Plug-in tower crane according to claim 1 for following tower body to climb together is climbed, which is characterized in that The connection of the pull rod and the lower frame and second upper ledge is dismountable connection type.
  5. The frame apparatus 5. Plug-in tower crane according to claim 1 for following tower body to climb together is climbed, which is characterized in that The connection of the hoist engine and first upper ledge and the second upper ledge is dismountable connection type.
CN201821062441.4U 2018-07-05 2018-07-05 A kind of Plug-in tower crane for following tower body to climb together is climbed frame apparatus Active CN208561497U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821062441.4U CN208561497U (en) 2018-07-05 2018-07-05 A kind of Plug-in tower crane for following tower body to climb together is climbed frame apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821062441.4U CN208561497U (en) 2018-07-05 2018-07-05 A kind of Plug-in tower crane for following tower body to climb together is climbed frame apparatus

Publications (1)

Publication Number Publication Date
CN208561497U true CN208561497U (en) 2019-03-01

Family

ID=65490496

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821062441.4U Active CN208561497U (en) 2018-07-05 2018-07-05 A kind of Plug-in tower crane for following tower body to climb together is climbed frame apparatus

Country Status (1)

Country Link
CN (1) CN208561497U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108792962A (en) * 2018-07-05 2018-11-13 上海市机械施工集团有限公司 A kind of Plug-in tower crane is climbed frame apparatus and its application method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108792962A (en) * 2018-07-05 2018-11-13 上海市机械施工集团有限公司 A kind of Plug-in tower crane is climbed frame apparatus and its application method

Similar Documents

Publication Publication Date Title
CN101787792B (en) Building protection screen system
CN201221193Y (en) High altitude packway ceiling construction operating platform
CN209052240U (en) A kind of tool for super high-rise building duplex elevator vertical transport
CN105971271A (en) Single-side self-climbing cantilever formwork and construction method thereof
CN107190964A (en) A kind of construction method of prefabricated hoistway operation platform
CN105201195A (en) Liftable supporting leg type elevator shaft construction platform and method
CN109138454A (en) A kind of installation method of super high-rise building outline border bandy truss
CN208561497U (en) A kind of Plug-in tower crane for following tower body to climb together is climbed frame apparatus
CN105672665A (en) Installation method for large-span double-layer cylindrical surface net shell
CN102493666A (en) High-altitude translation installation and construction method for super-large super-heavy member
CN106567542A (en) Super high-rise double tower building steel structure corridor assembling method
CN104032966A (en) Partitioning, hoisting, overhead closing and mounting method for arc-shaped double-layer net racks
CN107502690A (en) A kind of point of device and replacing options with integral replacing last furnace shell
CN107130517B (en) It is a kind of fine-tuning from promotion closure mould bases base apparatus and its operating method
CN108792962A (en) A kind of Plug-in tower crane is climbed frame apparatus and its application method
CN108118885B (en) vertical moving type protection platform and application thereof in steel structure column butt joint construction
CN203452375U (en) Hydraulic self-jacking oblique creeping formwork
CN204456816U (en) One can promote supporting leg type elevator hoistway construction platform
CN205421928U (en) From upset strutting arrangement
CN202544379U (en) Automatic climbing device
CN204474202U (en) Large-tonnage steel member integrated hoisting fixture
CN104030176B (en) The equalizer bar of hoisting platform truss and hanging method thereof
CN205134921U (en) Building outer wall concrete constructional column hangs construction platform
CN206784891U (en) A kind of prefabricated hoistway operation platform
CN205500626U (en) Climbing mechanism in tower crane

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant