CN208518306U - A kind of levels operation platform for lighting roof construction - Google Patents

A kind of levels operation platform for lighting roof construction Download PDF

Info

Publication number
CN208518306U
CN208518306U CN201820885475.7U CN201820885475U CN208518306U CN 208518306 U CN208518306 U CN 208518306U CN 201820885475 U CN201820885475 U CN 201820885475U CN 208518306 U CN208518306 U CN 208518306U
Authority
CN
China
Prior art keywords
steel wire
wire rope
inhaul cable
cable steel
main
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820885475.7U
Other languages
Chinese (zh)
Inventor
袁鹏智
赵娜
任晓
张帆
张一帆
任淑华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction First Group Corp Ltd
China Construction First Division Steel Structure Engineering Co Ltd
Original Assignee
China Construction First Group Corp Ltd
China Construction First Division Steel Structure Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction First Group Corp Ltd, China Construction First Division Steel Structure Engineering Co Ltd filed Critical China Construction First Group Corp Ltd
Priority to CN201820885475.7U priority Critical patent/CN208518306U/en
Application granted granted Critical
Publication of CN208518306U publication Critical patent/CN208518306U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of levels operation platforms for lighting roof construction, it includes main inhaul cable steel wire rope, secondary inhaul cable steel wire rope and vertical hanger wirerope, the main inhaul cable steel wire rope and time inhaul cable steel wire rope vertical interlaced form a steel wire, and scaffold board is arranged on steel wire;The main inhaul cable steel wire rope is connected and fixed by steel wire rope card and the horizontal fixed point of main inhaul cable steel wire rope on building, and secondary inhaul cable steel wire rope is connected and fixed by steel wire rope card and the horizontal fixed point of secondary inhaul cable steel wire rope on building;The vertical hanger wirerope is vertically set between main inhaul cable steel wire rope and building;The main inhaul cable steel wire rope and time inhaul cable steel wire rope staggered place are provided with fixed plate, and a pair of of fixed plate is mutually fastened on staggered place and is locked by bolt.The levels operation platform that the utility model mentions, structurally reasonable, wirerope vertical interlaced forms, and setting fixed plate snapping is fixed, and is effectively prevent steel cable sliding, is improved fixed reliability, guarantees the safety of construction.

Description

A kind of levels operation platform for lighting roof construction
Technical field
The utility model belongs to technical field of building construction, is related to a kind of levels operation platform for lighting roof construction.
Background technique
In construction, operating platform is indispensable interim setting, provides safety, steady for construction personnel Solid operation supporting surface.But in the construction of some lighting roofs, since lighting roof is higher apart from ground, set up steel pipe scaffold i.e. It is uneconomical, but it is larger to take up space, and is unable to satisfy site operation requirement.
Therefore, it needs to design a kind of levels operation platform for lighting roof construction, solve.
Utility model content
The purpose of this utility model is a kind of levels operation for lighting roof construction provided in view of the above technical problems Platform, structurally reasonable, wirerope vertical interlaced forms, and setting fixed plate snapping is fixed, and steel cable sliding is effectively prevent, and improves Fixed reliability guarantees the safety of construction, is suitable for a wide range of promote the use of.
In order to solve the above technical problems, a kind of levels operation platform for lighting roof construction provided by the utility model, It specifically includes main inhaul cable steel wire rope, secondary inhaul cable steel wire rope and vertical hanger wirerope, the main inhaul cable steel wire rope and time drag-line Wirerope vertical interlaced forms a steel wire, and scaffold board is arranged on steel wire;The main inhaul cable steel wire rope passes through steel wire rope Card is connected and fixed with the horizontal fixed point of main inhaul cable steel wire rope on building, and secondary inhaul cable steel wire rope passes through steel wire rope card and building The horizontal fixed point of secondary inhaul cable steel wire rope on object is connected and fixed;The vertical hanger wirerope is vertically set on main inhaul cable steel wire rope Between building;The main inhaul cable steel wire rope and time inhaul cable steel wire rope staggered place are provided with fixed plate, and a pair of of fixed plate is mutual It is fastened on staggered place and is locked by bolt;The shape of the fixed plate be it is rectangular, be provided with card slot, the card slot perforation is set It sets at the middle part of fixed plate, the two sides of card slot are provided with locking hole.
In some embodiments, the diameter matches of the card slot and main inhaul cable steel wire rope and secondary inhaul cable steel wire rope are arranged.
In some embodiments, the vertical hanger wirerope is solid by the vertical hanger on steel wire rope card and building Fixed point is connected and fixed.
In some embodiments, the horizontal fixed point of the main inhaul cable steel wire rope, the horizontal fixed point of secondary inhaul cable steel wire rope and perpendicular It is concrete structure, steel construction or key keel of curtain wall to hoist cable fixed point.
The utility model the utility model has the advantages that
A kind of levels operation platform for lighting roof construction provided by the utility model, it is structurally reasonable, have following Technical effect:
(1) wirerope vertical interlaced forms a steel wire, and setting fixed plate snapping is fixed, and wirerope is arranged in fixed plate Card slot in, effectively prevent steel cable sliding, improve fixed reliability, guarantee construction safety;
(2) construction is saved without setting up steel pipe scaffold operating platform using levels operation platform described herein Space, control the cost of construction.
Detailed description of the invention
It will be apparent and more hold by made detailed description, the above-mentioned advantage of the utility model in conjunction with the following drawings Readily understood, these attached drawings are only schematical, are not intended to limit the utility model, in which:
Fig. 1 is a kind of structural schematic diagram of levels operation platform for lighting roof construction described in the utility model;
Fig. 2 is the sectional view of Fig. 1;
Fig. 3 is the fixation schematic diagram of the main inhaul cable steel wire rope of the utility model;
Fig. 4 is the fixation schematic diagram of the vertical hanger wirerope of the utility model;
Fig. 5 is the structural schematic diagram of the fixed plate of the utility model;
Fig. 6 is the main inhaul cable steel wire rope of the utility model and the fixation schematic diagram of time inhaul cable steel wire rope.
In attached drawing, component representated by each label is as follows:
1. main inhaul cable steel wire rope;2. time inhaul cable steel wire rope;3. the main horizontal fixed point of inhaul cable steel wire rope;4. time inhaul cable steel wire rope Horizontal fixed point;5. vertical hanger wirerope;6. vertical hanger fixed point;7. fixed plate, 7-1. card slot, 7-2. locking hole;8. Steel wire rope card.
Specific embodiment
Fig. 1 to Fig. 6 is a kind of accompanying drawings of herein described levels operation platform for lighting roof construction, below The utility model is described in detail in specific embodiments and the drawings.
The embodiment recorded herein is the specific specific embodiment of the utility model, for illustrating the utility model Design, be it is explanatory and illustrative, should not be construed as the limit to the utility model embodiment and the scope of the utility model System.In addition to the embodiment recorded herein, those skilled in the art can also be public based on the claim of this application book and specification institute For the content opened using obvious other technical solutions, these technical solutions include using doing to the embodiment recorded herein The technical solution of any obvious substitutions and modifications out.
The attached drawing of this specification is schematic diagram, aids in illustrating the design of the utility model, it is schematically indicated each section Shape and its correlation.It note that for the ease of clearly showing the structure of each component of the utility model embodiment, respectively It is not drawn according to identical ratio between attached drawing.Identical reference marker is for indicating identical part.
The structural schematic diagram of herein described a kind of levels operation platform for lighting roof construction, such as Fig. 1 and Fig. 2 institute Show, specifically includes main inhaul cable steel wire rope 1, secondary inhaul cable steel wire rope 2 and vertical hanger wirerope 5.
The main inhaul cable steel wire rope 1 forms a steel wire with time 2 vertical interlaced of inhaul cable steel wire rope, and scaffold board is arranged in steel wire On the net;The main inhaul cable steel wire rope 1 is connect by steel wire rope card 8 with the horizontal fixed point 3 of the main inhaul cable steel wire rope on building It is fixed, as shown in Figure 3;Secondary inhaul cable steel wire rope 2 passes through the horizontal fixed point of secondary inhaul cable steel wire rope on steel wire rope card 8 and building 4 are connected and fixed.
The vertical hanger wirerope 5 is vertically set between main inhaul cable steel wire rope 1 and building, the vertical hanger steel Cord 5 is connected and fixed by steel wire rope card 8 with the vertical hanger fixed point 6 on building, as shown in Figure 4.
In the embodiment shown in fig. 1, the diameter of main inhaul cable steel wire rope 1 is greater than the diameter of time inhaul cable steel wire rope 2, vertical lifting The diameter of rope wirerope 5 is equal with time diameter of diameter of inhaul cable steel wire rope 2.Main inhaul cable steel wire rope 1 hangs down with time inhaul cable steel wire rope 2 Straight staggeredly vertical hanger wirerope 5 is vertically set between main inhaul cable steel wire rope 1 and building in addition, and it is flat to form levels operation Platform, construction personnel carry out the construction of lighting roof on levels operation platform.
The main inhaul cable steel wire rope 1 is provided with fixed plate 7, a pair of of fixed plate 7 mutually button with time 2 staggered place of inhaul cable steel wire rope It is locked together in staggered place and by bolt.In this way, forming a horizontally disposed steel wire on building, set above steel wire Scaffold board is set, operator can carry out the construction operation of reflective roof on the top of scaffold board.
In the embodiment shown in fig. 1, the shape of the levels operation platform of formation is circle, 6 edge of vertical hanger fixed point The fixed reliability of levels operation platform is effectively ensured, it is ensured that the safety of construction in the setting of " well " word.Also, use the application institute The levels operation platform stated saves the space of construction without setting up steel pipe scaffold operating platform, control construction at This.
In the application, the shape of the fixed plate 7 be it is rectangular, be provided with card slot 7-1, as shown in Figure 5.The card slot 7-1 penetrates through the middle part that fixed plate 7 is arranged in, and the two sides of card slot 7-1 are provided with locking hole 7-2;The card slot 7-1 and main drag-line steel The setting of the diameter matches of cord 1 and secondary inhaul cable steel wire rope 2.
The horizontal fixed point 3 of the main inhaul cable steel wire rope, the horizontal fixed point 4 of secondary inhaul cable steel wire rope and vertical hanger fixed point 6 For concrete structure, steel construction or key keel of curtain wall.In the embodiment shown in Figure 2, the horizontal fixed point 3 of main inhaul cable steel wire rope, The secondary horizontal fixed point 4 of inhaul cable steel wire rope is concrete structure, and vertical hanger fixed point 6 is steel construction.
Fig. 6 is the main inhaul cable steel wire rope of the utility model and the fixation schematic diagram of time inhaul cable steel wire rope, a pair of of 7 phase of fixed plate It mutually is fastened on staggered place, main inhaul cable steel wire rope 1 and secondary inhaul cable steel wire rope 2 are arranged in the card slot 7-1 in fixed plate 7, use spiral shell Bolt locks a pair of of fixed plate 7.Card slot 7-1 and main inhaul cable steel wire rope 1 and secondary inhaul cable steel wire rope 2 in the application, in fixed plate 7 Diameter matches setting, wirerope can be effectively prevent to skid off in this way, it is ensured that main inhaul cable steel wire rope is fixed with secondary inhaul cable steel wire rope Reliability.
Compared with the prior art the shortcomings that and deficiency, the levels operation platform that the utility model mentions are applied for lighting roof Work, structurally reasonable, wirerope vertical interlaced forms a steel wire, and setting fixed plate snapping is fixed, and effectively prevent wirerope sliding It is dynamic, fixed reliability is improved, guarantees the safety of construction;Also, it without setting up steel pipe scaffold operating platform, saves and applies The space of work controls the cost of construction.
The utility model is not limited to above embodiment, anyone can obtain other under the enlightenment of the utility model Various forms of products, however, make any variation in its shape or structure, it is all with identical or similar to the present application Technical solution, all fall within the protection scope of the utility model.

Claims (4)

1. a kind of levels operation platform for lighting roof construction, which is characterized in that including main inhaul cable steel wire rope (1), secondary drag-line Wirerope (2) and vertical hanger wirerope (5), the main inhaul cable steel wire rope (1) are formed with time inhaul cable steel wire rope (2) vertical interlaced One steel wire, scaffold board are arranged on steel wire;The main inhaul cable steel wire rope (1) passes through on steel wire rope card (8) and building The horizontal fixed point of main inhaul cable steel wire rope (3) be connected and fixed, secondary inhaul cable steel wire rope (2) pass through steel wire rope card (8) and building On the horizontal fixed point of secondary inhaul cable steel wire rope (4) be connected and fixed;The vertical hanger wirerope (5) is vertically set on main drag-line steel Between cord (1) and building;The main inhaul cable steel wire rope (1) and time inhaul cable steel wire rope (2) staggered place are provided with fixed plate (7), a pair of of fixed plate (7) is mutually fastened on staggered place and is locked by bolt;The shape of the fixed plate (7) be it is rectangular, thereon It is provided with card slot (7-1), card slot (7-1) perforation is arranged at the middle part of fixed plate (7), and the two sides of card slot (7-1) are provided with Locking hole (7-2).
2. a kind of levels operation platform for lighting roof construction according to claim 1, which is characterized in that the card slot The diameter matches of (7-1) and main inhaul cable steel wire rope (1) and secondary inhaul cable steel wire rope (2) are arranged.
3. a kind of levels operation platform for lighting roof construction according to claim 1, which is characterized in that described vertical Sling cable (5) is connected and fixed by steel wire rope card (8) with the vertical hanger fixed point (6) on building.
4. a kind of levels operation platform for lighting roof construction according to claim 1, which is characterized in that the main drawing The horizontal fixed point of rope wirerope (3), the horizontal fixed point of secondary inhaul cable steel wire rope (4) and vertical hanger fixed point (6) are concrete knot Structure, steel construction or key keel of curtain wall.
CN201820885475.7U 2018-06-08 2018-06-08 A kind of levels operation platform for lighting roof construction Expired - Fee Related CN208518306U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820885475.7U CN208518306U (en) 2018-06-08 2018-06-08 A kind of levels operation platform for lighting roof construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820885475.7U CN208518306U (en) 2018-06-08 2018-06-08 A kind of levels operation platform for lighting roof construction

Publications (1)

Publication Number Publication Date
CN208518306U true CN208518306U (en) 2019-02-19

Family

ID=65326508

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820885475.7U Expired - Fee Related CN208518306U (en) 2018-06-08 2018-06-08 A kind of levels operation platform for lighting roof construction

Country Status (1)

Country Link
CN (1) CN208518306U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110528849A (en) * 2019-09-05 2019-12-03 北京天润建设有限公司 A kind of aerial operation Platforms Construct Method of Super
CN110778094A (en) * 2019-11-06 2020-02-11 江苏中南建筑产业集团有限责任公司 High-altitude large-span dragline net operating platform and construction method
CN114991450A (en) * 2022-05-17 2022-09-02 中建二局第三建筑工程有限公司 Prestress reverse-pulling soft platform and construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110528849A (en) * 2019-09-05 2019-12-03 北京天润建设有限公司 A kind of aerial operation Platforms Construct Method of Super
CN110778094A (en) * 2019-11-06 2020-02-11 江苏中南建筑产业集团有限责任公司 High-altitude large-span dragline net operating platform and construction method
CN114991450A (en) * 2022-05-17 2022-09-02 中建二局第三建筑工程有限公司 Prestress reverse-pulling soft platform and construction method

Similar Documents

Publication Publication Date Title
CN208518306U (en) A kind of levels operation platform for lighting roof construction
CN205296803U (en) Elevator automatic lifting operation panel
CN105926918B (en) A kind of collapsible hoistway operation steel platform device and erection method
CN208502210U (en) Wall elevation construction operating platform
CN208830690U (en) A kind of lighting roof operating platform
CN209011528U (en) A kind of all steel attachment type raise scaffold
CN207776405U (en) Prefabricated outer wall panel safety protection frame
CN205743207U (en) The typhoon protection ruggedized construction built is faced in a kind of construction
CN205955160U (en) Antiskid lattice formula elevartor shaft removes operation platform
CN213326459U (en) Tower crane anti-climb safety device
CN204778496U (en) Platform sling structure of tower crane
CN107288361B (en) High-rise falling-prevention backward anchoring self-hanging double-layer horizontal safety net device and construction method thereof
CN206987720U (en) A kind of double shield cage cat ladders
CN202788017U (en) Horizontally-overhung rigid hermetic section steel protective shed for high-rise buildings
CN106869486A (en) The reinforcement type building for possessing illumination and drain function builds frame pedal
CN207348787U (en) One kind maintenance cat ladder platform
CN208173343U (en) A kind of novel transformer substation Transformer Emergency Oil Pond grid device
CN206636188U (en) The reinforcement type building for possessing illumination and drain function builds frame pedal
CN108550453A (en) A kind of novel transformer substation Transformer Emergency Oil Pond grid device
KR100777370B1 (en) Glass panel construction apparatus of building
CN220451375U (en) Auxiliary operation platform for high-altitude suspended ceiling construction
CN205134785U (en) Prevent structure that cornices that ftractures
CN219862199U (en) Steel suspended pavement applied to site exhibition hall
CN205558305U (en) Steel gallery promotes reinforcing apparatus
CN215368651U (en) Lifting scaffold faces limit protection platform

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190219

CF01 Termination of patent right due to non-payment of annual fee