CN208502210U - Wall elevation construction operating platform - Google Patents
Wall elevation construction operating platform Download PDFInfo
- Publication number
- CN208502210U CN208502210U CN201820768859.0U CN201820768859U CN208502210U CN 208502210 U CN208502210 U CN 208502210U CN 201820768859 U CN201820768859 U CN 201820768859U CN 208502210 U CN208502210 U CN 208502210U
- Authority
- CN
- China
- Prior art keywords
- operating platform
- ladder
- protect
- construction
- frame structure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Ladders (AREA)
Abstract
The utility model provides a kind of wall elevation construction operating platform; belong to field of steel structure construction; including ladder and the operating platform being arranged on the ladder; the ladder is vertical ladder; top is provided with for hanging over the suspension part on wall purlins or girder steel; the operating platform includes protect-ing frame structure and the bottom plate that the protect-ing frame structure bottom is arranged in, and the protect-ing frame structure and the ladder are fixedly installed.Wall elevation construction operating platform provided by the utility model can provide protective platform safely, conveniently, stable in construction, easy for construction, time saving and energy saving, substantially increase work task efficiency, eliminate security risk, achieved the purpose that safety in production.Have the characteristics that easy to operate, dismounting is convenient, be used in turn, it is both beautiful and practical, very big help is played to safety construction.
Description
Technical field
The utility model belongs to steel structure construction technology field, is to be related to a kind of wall elevation construction operation more specifically
Platform.
Background technique
Steel-structure factory building is in daily construction, and people stands on girder steel or wall purlins only by a peace when wall elevation construction
Full band guarantees safety, and there are larger security risks, and while constructing is inconvenient.Especially shingle nail, wall purlins etc. were installed
Cheng Zhong, material shakes larger when lifting, and construction personnel is easy to be led to itself unstability by Effect of Materials is shaken, and there is the wind that falls greatly very much
Danger.
Utility model content
It is existing in the prior art to solve the purpose of this utility model is to provide a kind of wall elevation construction operating platform
It is inconvenient and there is the technical issues of security risk when wall elevation construction.
In order to achieve the above purposes, the technical solution adopted by the utility model is: provides a kind of wall elevation construction operating platform,
The operating platform for including: ladder and being arranged on the ladder, the ladder are vertical ladder, and top is provided with for hanging over wall
Suspension part on face purlin or girder steel, the operating platform include protect-ing frame structure and the bottom that the protect-ing frame structure bottom is arranged in
Plate, the protect-ing frame structure and ladder fixed setting.
Further, the bottom plate of the operating platform is hingedly arranged with the protect-ing frame structure.
Further, the operating platform is one or more.
Further, the interconnecting piece with ladder cooperation is provided in the protect-ing frame structure, the interconnecting piece passes through spiral shell
Bolt is fixedly connected with the ladder.
Further, the width of the ladder is 600mm, and ladder step spacing is 450mm.
Further, the bottom plate is the steel plate of 3mm thickness, and the size of the bottom plate is 600*600*900mm.
Further, the ladder and the protect-ing frame structure pass through 30mm square steel and are welded.
The beneficial effect of wall elevation construction operating platform provided by the utility model is:
Compared with prior art, the utility model wall elevation construction operating platform can provide safely, just in construction
Prompt, stable protective platform, it is easy for construction, time saving and energy saving, it substantially increases work task efficiency, eliminate security risk,
Safety in production is achieved the purpose that.Have the characteristics that easy to operate, dismounting is convenient, be used in turn, it is both beautiful and practical, to safety
Civilized construction plays very big help.
Detailed description of the invention
It, below will be to embodiment or the prior art in order to illustrate more clearly of the technical scheme in the embodiment of the utility model
Attached drawing needed in description is briefly described, it should be apparent that, the accompanying drawings in the following description is only that this is practical new
Some embodiments of type for those of ordinary skill in the art without any creative labor, can be with
It obtains other drawings based on these drawings.
Fig. 1 is the structural schematic diagram of wall elevation construction operating platform provided by the embodiment of the utility model.
Wherein, each appended drawing reference in figure:
1- ladder;The suspension part 11-;2- operating platform;21- protect-ing frame structure;22- bottom plate.
Specific embodiment
In order to which technical problem to be solved in the utility model, technical solution and beneficial effect is more clearly understood, with
Lower combination accompanying drawings and embodiments, the present invention will be further described in detail.It should be appreciated that specific reality described herein
It applies example to be only used to explain the utility model, is not used to limit the utility model.
It should be noted that it can be directly another when element is referred to as " being fixed on " or " being set to " another element
On one element or indirectly on another element.When an element is known as " being connected to " another element, it can
To be directly to another element or be indirectly connected on another element.
It is to be appreciated that term " length ", " width ", "upper", "lower", "front", "rear", "left", "right", "vertical",
The orientation or positional relationship of the instructions such as "horizontal", "top", "bottom" "inner", "outside" is that orientation based on the figure or position are closed
System, is merely for convenience of describing the present invention and simplifying the description, rather than the device or element of indication or suggestion meaning are necessary
It with specific orientation, is constructed and operated in a specific orientation, therefore should not be understood as limiting the present invention.
In addition, term " first ", " second " are used for descriptive purposes only and cannot be understood as indicating or suggesting relative importance
Or implicitly indicate the quantity of indicated technical characteristic.Define " first " as a result, the feature of " second " can be expressed or
Implicitly include one or more of the features." multiple ", " several " are meant that two in the description of the present invention,
It is a or more than two, unless otherwise specifically defined.
Referring to Fig. 1, existing be illustrated wall elevation construction operating platform provided by the utility model.The wall facade is applied
Work operating platform, including ladder 1 and the operating platform 2 being arranged on the ladder 1, the ladder 1 is vertical ladder, and top is set
It is equipped with for hanging over the suspension part 11 on wall purlins or girder steel, the operating platform 2 includes protect-ing frame structure 21 and is arranged in institute
The bottom plate 22 of 21 bottom of protect-ing frame structure is stated, the protect-ing frame structure 21 and the ladder 1 are fixedly installed.
Wall elevation construction operating platform provided by the utility model is used for the various constructing operations of steel-structure factory building wall facade,
The utility model is directly hung to construction part with crane when use, 1 upper end of ladder by suspension part 11 be hung on wall purlins or
On girder steel, top and bottom can be fixed with iron wire to prevent from shaking, and construction personnel is climbed from top or lower part to behaviour by ladder 1
Make on the bottom plate 22 of platform 2, constructing operation is carried out inside protect-ing frame structure 21.
Wall elevation construction operating platform provided by the utility model, can be provided in construction safely, conveniently, it is stable anti-
Platform is protected, it is easy for construction, time saving and energy saving, it substantially increases work task efficiency, eliminate security risk, reached safe life
The purpose of production.Have the characteristics that easy to operate, dismounting is convenient, be used in turn, it is both beautiful and practical, safety construction is played
Very big help.
Further, referring to Fig. 1, a kind of specific reality as wall elevation construction operating platform provided by the utility model
Apply mode, the bottom plate 22 of the operating platform 2 and the hingedly setting of the protect-ing frame structure 21.So that bottom plate 22 forms protect-ing frame structure 21
Gate-type dump bottom, convenient for construction personnel from 1 lower part of ladder enter the operating platform 2 inside.
Further, referring to Fig. 1, a kind of specific reality as wall elevation construction operating platform provided by the utility model
Mode is applied, the operating platform 2 is one or more.I.e. in the utility model, the quantity of operating platform 2, position are not limited to,
It can be adjusted according to actual condition.
Further, referring to Fig. 1, a kind of specific reality as wall elevation construction operating platform provided by the utility model
Apply mode, be provided in the protect-ing frame structure 21 with the ladder 1 cooperation interconnecting piece, the interconnecting piece by bolt with it is described
Ladder 1 is fixedly connected.
Further, referring to Fig. 1, a kind of specific reality as wall elevation construction operating platform provided by the utility model
Mode is applied, the width of the ladder 1 is 600mm, and ladder step spacing is 450mm.The length of ladder 1 can be according to live practical determining.
Further, referring to Fig. 1, a kind of specific reality as wall elevation construction operating platform provided by the utility model
Mode is applied, the bottom plate 22 is the steel plate of 3mm thickness, and the size of the bottom plate 22 is 600*600*900mm.
Further, referring to Fig. 1, a kind of specific reality as wall elevation construction operating platform provided by the utility model
Mode is applied, the ladder 1 and the protect-ing frame structure 21 are welded by 30mm square steel.
The above is only the preferred embodiment of the utility model only, is not intended to limit the utility model, all at this
Made any modifications, equivalent replacements, and improvements etc., should be included in the utility model within the spirit and principle of utility model
Protection scope within.
Claims (7)
1. wall elevation construction operating platform, it is characterised in that: described including ladder and the operating platform being arranged on the ladder
Ladder is vertical ladder, and top is provided with for hanging over the suspension part on wall purlins or girder steel, and the operating platform includes protecting
Shield frame and the bottom plate that the protect-ing frame structure bottom is set, the protect-ing frame structure and ladder fixed setting.
2. wall elevation construction operating platform as described in claim 1, it is characterised in that: the bottom plate of the operating platform with it is described
Protect-ing frame structure is hingedly arranged.
3. wall elevation construction operating platform as described in claim 1, it is characterised in that: the operating platform is one or more
It is a.
4. wall elevation construction operating platform as described in claim 1, it is characterised in that: be provided in the protect-ing frame structure and institute
The interconnecting piece of ladder cooperation is stated, the interconnecting piece is fixedly connected by bolt with the ladder.
5. wall elevation construction operating platform as described in claim 1, it is characterised in that: the width of the ladder is 600mm, ladder
Step spacing is 450mm.
6. wall elevation construction operating platform as described in claim 1, it is characterised in that: the bottom plate is the steel plate of 3mm thickness, institute
The size for stating bottom plate is 600*600*900mm.
7. wall elevation construction operating platform as described in claim 1, it is characterised in that: the ladder and the protect-ing frame structure are equal
It is welded by 30mm square steel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820768859.0U CN208502210U (en) | 2018-05-22 | 2018-05-22 | Wall elevation construction operating platform |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820768859.0U CN208502210U (en) | 2018-05-22 | 2018-05-22 | Wall elevation construction operating platform |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208502210U true CN208502210U (en) | 2019-02-15 |
Family
ID=65293115
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820768859.0U Expired - Fee Related CN208502210U (en) | 2018-05-22 | 2018-05-22 | Wall elevation construction operating platform |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208502210U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112127611A (en) * | 2020-09-23 | 2020-12-25 | 中国五冶集团有限公司 | Assembly type high-altitude corbel construction operation platform device |
CN112716350A (en) * | 2020-12-31 | 2021-04-30 | 福建省闽南建筑工程有限公司 | Improved suspension support frame for cleaning building outer wall glass |
CN113802825A (en) * | 2021-09-24 | 2021-12-17 | 上海宝冶集团有限公司 | Hanging scaffold |
-
2018
- 2018-05-22 CN CN201820768859.0U patent/CN208502210U/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112127611A (en) * | 2020-09-23 | 2020-12-25 | 中国五冶集团有限公司 | Assembly type high-altitude corbel construction operation platform device |
CN112716350A (en) * | 2020-12-31 | 2021-04-30 | 福建省闽南建筑工程有限公司 | Improved suspension support frame for cleaning building outer wall glass |
CN112716350B (en) * | 2020-12-31 | 2022-10-28 | 福建省闽南建筑工程有限公司 | Improved suspension support frame for cleaning building outer wall glass |
CN113802825A (en) * | 2021-09-24 | 2021-12-17 | 上海宝冶集团有限公司 | Hanging scaffold |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208502210U (en) | Wall elevation construction operating platform | |
CN206873896U (en) | Cage for the construction of oil gas storage tank outer wall pipe support | |
CN207245138U (en) | Boat scaffold adjustable in pitch | |
CN109024896A (en) | A kind of bilayer anticollision assembling type steel structure truss bars processing is anti-to pound canopy | |
CN208518306U (en) | Horizontal operation platform for daylighting roof construction | |
CN206219988U (en) | Foldable hanging basket | |
CN105735624A (en) | Cage for installing roof ceiling sheet | |
CN207160249U (en) | Structure is built in a kind of interim room in quick detachable building site | |
CN104860245B (en) | A kind of two grades of inspection platforms of energy-saving appliance of boiler | |
CN206487178U (en) | Distribution box protection canopy is used in one kind construction | |
CN108756721B (en) | A kind of cement shaft tower Anti-drop ladder structure | |
CN202731270U (en) | Movable platform for aerial installation operation of space steel structure | |
CN207332341U (en) | Protective shed structure of reserved hole of tower crane | |
CN202913679U (en) | Double-function construction operation protection derrick in elevator shaft way | |
CN206667721U (en) | The construction integrated system of operating platform on a kind of wide-angle Sloping roof | |
CN205421955U (en) | Cage that installation roofing furred ceiling board was used | |
CN206987720U (en) | A kind of double shield cage cat ladders | |
CN208856819U (en) | People channel on setting tower crane | |
CN203961405U (en) | Yi Zhong sightseeing tower | |
CN206091013U (en) | Novel convertible canopy steel construction | |
CN206956739U (en) | A kind of portable edge protection device | |
CN208039796U (en) | A kind of safety-type hanging basket of construction | |
CN207073209U (en) | A kind of fireproof steel structure | |
CN206800974U (en) | Lower-hanging type outer wall moving cantilever operation frame | |
CN207277207U (en) | A kind of bridge top construction safety protection column |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190215 |
|